465 judgments, latest first, from 2018 to 2026. Listed when the Supreme Court Reports file the judgment's headnote under Section 34 of this Act, as printed at the start of the headnote, or, for a judgment with no such headnote, when its own text names Section 34 with this Act as the provision it is brought under, or at its start and again later, or at least three times. Judgments that only mention it in passing are not listed.

Rakhal Ch. Ghosh vs The Union of India and 3 Ors
Tripura HC · 26 September 2019
From the judgment…copy of the arbitral award is the date of commencement for purpose of limitation for filing the application under Section 34 of the Arbitration and Conciliation Act, 1996 challenging the award within the parameters as prescribed under Section 34 of the Arbitration and Conciliation Act, 1996.
Vinod Bhaiyalal Jain & Ors. vs Wadhwani Parmeshwari Cold Storage Pvt. Ltd.Through Its Director & Anr.
SC · 24 July 2019
[2019] 9 S.C.R. 1080 : 2019 INSC 800
Arbitration and Conciliation Act, 1996 – ss.34, 37(1)(b) – Appellant utilized the services of respondent No.1 for keeping an agricultural product – According to appellants, the respondent no.1 caused damage to the produc…
North Eastern Electric Power Corporation Ltd. (Neepco) vs M/S Patel Engineering Ltd. Unity Infra Projects (Jv)
Meghalaya HC · 26 February 2019
From the judgment…passed by the Court of the learned Additional Deputy Commissioner (Judicial), Shillong on applications under Sec.
Mmtc Ltd. vs M/s Vedanta Ltd.
SC · 18 February 2019
[2019] 3 S.C.R. 1023 : 2019 INSC 218
Arbitration and Conciliation Act, 1996: s.34, 37 – Scope of interference with an arbitral award in India – Pre and Post amendment made to s.34 in 2015, position explained. Arbitration and Conciliation Act, 1996: s.34, 37…
Nhpc Limited vs M/s Patel Engineering Limited
SC · 30 November 2018
[2018] 14 S.C.R. 1101 : 2018 INSC 1124
Arbitration and Conciliation Act, 1996: ss. 9 and 34 – Postaward application u/s. 9 - Application allowed and the appellant called upon to release the amount covered by the arbitral award – Challenge to, on the ground th…
Vedanta Ltd. vs Shenzen Shandong Nuclear Power Construction Co. Ltd.
SC · 11 October 2018
[2018] 12 S.C.R. 829 : 2018 INSC 959
Arbitration and Conciliation Act, 1996 – ss.34 and 37 – Appellant and the Respondent-Company entered into four interrelated contracts for construction of a Co-Generation Power Plant – Dispute arose between the parties –…
Union of India vs Hardy Exploration and Production (India) Inc
SC · 25 September 2018
[2018] 13 S.C.R. 379 : 2018 INSC 865
Arbitration and Conciliation Act, 1996 – s.34 – “seat” and “venue” for holding arbitration proceedings under the Arbitration agreement – Arbitrator held meeting at Kuala Lumpur and signed the arbitral award in favour of…
The Chairman-Cum-Md, Tsec Ltd and Anr vs M/S Horizon Hi-Tech Engicon Ltd and Anr
Tripura HC · 11 September 2018
From the judgment…Judge, West Tripura, Agartala rejecting the application filed by the appellant u/S.34(3) of the Arbitration & Conciliation Act 1996 read with S.14 of the Limitation Act 1963 praying for condoning the purported delay of 16 days in filing the application u/S.34 for setting aside the arbitral award dt
The Principal Secretary, Department of Commerce and Industries, Government of Sikkim vs M/s Snowlion Automobile Pvt. Ltd.
Sikkim HC · 28 August 2018
From the judgment…the arbitral award the Appellant preferred an application under Section 34 of the Arbitration and Conciliation Act, 1996 (the said Act).
M/s Emkay Global Financial Services Ltd. vs Girdhar Sondhi
SC · 20 August 2018
[2018] 10 S.C.R. 937 : 2018 INSC 724
Arbitration and Conciliation Act, 1996: s.34 – Territorial jurisdiction – Dispute arose between the registered broker of the National Stock Exchange (NSE) and its client regarding certain transactions in securities and s…
M/s Patel Unity Joint Venture (pujv) vs North Eastern Electric Power Corporation Ltd.
Meghalaya HC · 5 June 2018
From the judgment…whereof, respondent-North Eastern Electric Power Corporation Limited, filed an application under Section 34 of the Arbitration and Conciliation Act (AC MC (ARB.A) No.3/2017 Act) for setting aside the Arbitral Award before the Additional Deputy Commissioner (Judicial), Shillong.
M/s Lion Engineering Consultants vs State of M.P. & Ors.
SC · 22 March 2018
[2018] 6 S.C.R. 683
Arbitration and Conciliation Act, 1996 – ss.16 and 34 – Arbitrator passed award in favour of the Appellant – Award was challenged by respondent-State u/s.34 of the Act before the trial Court – Respondent sought to amend…
The Principal Secretary.department Of Commerce & Industries, Government Of Sikkim,gangtok,east Sikki vs Ms. Snowlion Automobile Pvt. Ltd.
Sikkim HC · 26 February 2018
From the judgment…dismissal Order dated 10.06.2016 passed by the District Judge, East Sikkim at Gangtok, in application under Section 34 of the Arbitration and Conciliation Act, 1996 (in short, the Act, 1996), on stated grounds that there was palpable, manifest error causing miscarriage of justice.
M/s. Indian Farmers Fertilizer Co-Operative Limited vs M/s Bhadra Products
SC · 23 January 2018
[2018] 1 S.C.R. 848 : 2018 INSC 53
Arbitration and Conciliation Act, 1996 – ss. 2(c), 31(6), 32 and 34 – Interim Arbitral Award – Whether an award delivered by an Arbitrator, which decides the issue of limitation, can be said to be an interim award and wh…
Maharashtra State Electricity Distribution Company Ltd. vs M/s. Datar Switchgear Limited & Ors.
SC · 18 January 2018
[2018] 1 S.C.R. 733 : 2018 INSC 33
Arbitration and Conciliation Act, 1996 – s.34 – Contract between parties – Termination of, on ground of fundamental breach – Propriety of – Respondent no.2 awarded tender/contract by appellant, in 1993-1994, for installa…

All judgments on the Arbitration and Conciliation Act, 1996 · All Acts · Topics · Judges