Serial No. 09 to 11
Regular List
HIGH COURT OF MEGHALAYA
AT SHILLONG
Arb. A. No. 3 of 2018 with
Arb. A. No. 4 of 2018
Arb. A. No. 5 of 2018
Date of Decision: 26.02.2019
North Eastern Electric Power
Corporation Ltd. (NEEPCO)
Vs M/S Patel Engineering Ltd.
Unity Infra Projects (JV)
North Eastern Electric Power
Corporation Ltd. (NEEPCO)
Vs M/S Patel Engineering
Limited
North Eastern Electric Power
Corporation Ltd. (NEEPCO)
Vs M/S Patel Engineering
Limited
Coram:
Hon’ble Mr. Justice Mohammad Yaqoob Mir, Chief Justice
Hon’ble Mr. Justice H.S. Thangkhiew, Judge
Appearance:
For the Petitioner(s)/Appellant(s):
For the Respondent(s)
Mr. H.A. Ahmadi, Sr. Adv.
Mr. V.K. Jindal, Sr. Adv. with
Mr. K. Laheri, Adv.
Ms. P. Biswakarma, Adv.
:
Mr. A. Bhan, Sr. Adv. with
Mr. A. Bhan, Adv.
i)
Whether approved for reporting in
Law journals etc.:
ii)
Whether approved for publication
in press:
Yes/No
Yes/No
1. These three Arbitration Appeals have been filed by the appellant North
Eastern Electric Power Corporation (for short “NEEPCO”) under Sec.
37 of the Arbitration and Conciliation Act, 1996, challenging the
common order dated 27.04.2018 passed by the Court of the learned
Additional Deputy Commissioner (Judicial), Shillong on applications
under Sec. 34 of the Arbitration and Conciliation Act, 1996 filed by
NEEPCO which were registered as Arbitration Case No. 5 (T) 2016,
Arbitration Case No. 6 (T) 2016 and Arbitration Case No. 7 (T) 2016.
The learned Additional Deputy Commissioner (Judicial), Shillong vide
the aforesaid common order dated 27.04.2018 has dismissed the
aforesaid Sec. 34 applications filed by NEEPCO and upheld the 3
(three) Arbitral Awards dated 29.03.2016.
2. The facts leading to filing of the batch of these three Arbitration
Appeals are that in the year 2000, NEEPCO had acquired 710 hectares
of land in Kameng, Arunachal Pradesh had also obtained clearances
from the Ministry of Environment and Forests for setting up Kameng
Hydro Electric Project (for short “KaHEP”).
3. On 23.04.2003, NEEPCO issued Invitation for Bids for civil work of
the said project under three separate Packages as follows:
Package-I: Contract for civil works for Bichom Dam, River Diversion,
Bichom Intake and Head Race Tunnel from RD 0 m to 4400m (+/500m) on either side (i.e. 1st half of the Bichom-Tenga Portion).
Package-II: Contract for civil works for Bichom Dam, River
Diversion, Bichom Intake and Head Race Tunnel from RD 4400 m to
11600m (+/- 500m) on either side (i.e. 2nd half of the Bichom-Tenga
Portion and 1st half of Tenga-Kimi portion).
Package-III: Contract for civil works for Head Race Tunnel from RD
11600m (+/- 500m) up to surge shaft (i.e. 2nd half of Tenga-Kimi
portion), surge shaft, Pressure Tunnels, Power House and Tail Race
Tunnel.
4. On 8.12.2003 a corrigendum was issued by NEEPCO to the Bid
Documents and a location map was issued showing the distance of the
designated quarries for sand and boulders for Package-I at a distance of
500 Mtrs from the dam axis of Bichom Dam, for Package-II at a
distance of 1200/1300 Mtrs from the dam axis of Tenga Dam, and for
Package-III at a very short distance from Kimi Power House.
5. On 03.12.2004 the bids of the respondents were accepted by NEEPCO
and Letters of Intent were issued to them as follows:
Package-I: Contract Amount Rs. 1,43,81,03,498/Contract awarded to Patel Engineering Ltd.-Unity Infra Projects JV
Package-II:
Contract Amount Rs. 1,16,39,65,649/-
Contract awarded to Patel Engineering Ltd.
Package-III: Contract Amount Rs. 1,31,65,12,797/Contract awarded to Patel Engineering Ltd.
This was followed by issuance of detailed Work Order by NEEPCO on
08.12.2004 in favour of Patel Engineering Ltd.-Unity Infra Projects JV,
Patel Engineering Ltd. and Patel Engineering Ltd. in respect of
Packages-I, II and III respectively and signing of formal Contract
Agreements on 17.12.2004. The documents which would form part of
the Contract are mentioned in the said Contract Agreement dated
17.12.2004.
6. On 29.03.2007, the Deputy Commissioner, West Kameng District
issued letter to NEEPCO informing that the designated stone/boulder
quarries as indicated in the project location map had been leased by the
local people in favour of a third party for a period of 15 years and
hence there was objection to acquisition of the said quarry land.
Thereafter, in the year 2010, NEEPCO acquired additional 42 hectares
of land at a cost of Rs. 3.20 Crores for the purpose of quarrying of sand
and boulders. However, the Chief Conservator of Forests, by his letter
dated 01.09.2011 declined permission for operation of stone quarry in
the said 42 Hectares of land. The said letter stated as follows:
“The construction activities of Kameng HEP has already
caused serious interference to the pristine and serene
environment of the area. Under the circumstances it is not
possible to allow open cast mining which will require heavy
blasting by using explosives or use of heavy machineries for
collection and transportation of the mined boulders, sand and
shingles to the tune of 6 (six) Lakh Cubic Mtrs. Further open cast
mining is also prohibited by the Hon‟ble Supreme Court of India.
Therefore, the User Agency may be advised to collect the
required sand, shingles and boulders from the Government
approves quarries in the adjoining areas. Further, the proposal
submitted by you vide your letter under reference is also returned
herewith as it is not possible to allow open cast mining in the
area.”
7. The result of the above was that the construction material viz. sand,
shingles and boulders for the project was required to be procured from
State Government approved quarries located at places far away from
the project sites. The State Government approved quarries were
situated at following distances from the project sites:
Package-I: 78 Km
Package-II: 53 Km
Package-III: 36.50 Km
8. This new dimension of transportation of construction material like
sand, shingles and boulders from Government approved quarries
located at a distance of 36.5 to 78 Kms from the project site
necessitated a meeting between NEEPCO and the Contractors to
resolve the issue relating to extra lead for transportation of quarried
sand, shingles and boulders. The meeting was held on 19.04.2012 and
the record of the meeting are as follows:
“M/S PEL expressed that in wake of restrictions imposed
by Forest department, Project Authorities of Package-II and III
have instructed M/S PEL to fetch sand and boulders from
quarries as far as 50 to 100 KM from project site to suffice the
requirement of aggregates required for concreting works. M/S
PEL insisted that payment for the lead in handling of common
excavated materials from the far away quarries shall be made in
terms of respective BOQ items under Package-II and PackageIII. NEEPCO opined that payment of extra lead is payable and
the rate for the same will be decided on mutual discussions.
CMD, NEEPCO agreed to resolve the issue within 7 (seven) days
i.e. by 26th April 2012 in the best interest of the progress of the
project citing necessity of an internal meeting with finance wing.
9. On 01.05.2012, NEEPCO conveyed its decision that Clause 33(iii) of
the Conditions of Contract would be applicable in calculating extra lead
and this would be based on a detailed rate analysis in terms of the
Conditions of Contract. Thereafter in the meeting held between the
parties on 06.08.2012 NEEPCO conveyed its decision to the
Contractors that (i) existing BOQ rates cannot be considered as
analogous item due to certain major dissimilarities, (ii) the rates shall
be firmed up on actual basis, (iii) till such time payment on provisional
basis may be affected, (iv) in order to facilitate continuance of the
project work unhindered, 80% of the approved analyzed rate for similar
contract may be considered provisionally against extra lead from the
govt approved quarries, and (v) the provisional payment would be
subject to adjustment on finalization of the rates.
10.Thereafter meetings were held between the parties on 07.12.2012 and
08.12.2012 wherein the Contractors reiterated their stand that the rates
of similar items available in the BOQ for open excavation and
underground excavation as per Clause 33(ii)(a) of the Conditions of
Contract be made applicable. On the other hand, NEEPCO reiterated
that the rates should be decided in terms of Clause 33(iii) of the
Conditions of Contract. Finally, Patel Engineering Ltd. requested that
since a dispute has arisen, the matter may be referred to arbitration
panel appointed by NEEPCO to resolve the dispute. It was finally
decided that HoP, KaHEP will forward the matter to NEEPCO
Headquarters for further necessary action to start the process of
arbitration. It was also agreed that till the arbitral award, the payment
would be made as per the prevailing provisional rate without any
escalation and that final rate payable for transportation of sand and
boulder shall be done on implementation of the arbitral award.
11.In the meantime, on 11.10.2013 NEEPCO issued Invitation for Bids for
transportation of boulders, sand from the government approved quarries
to the project site. The respondents challenged the said Notice Inviting
Bids before this Court by way of W.P. (C)’sNos 306,307and 308 of
2013. This Court vide separate orders dated 29.10.2013 dismissed the
said three writ petitions. The respondent herein, then filed three writ
appeals being W.A. Nos.39,40 and 41 of 2013. This Court then vide
order dated 01.11.2013 granted an interim stay on the Notice Inviting
Bids and the order dated 29.10.2013 passed by the learned Single
Judge. NEEPCO preferred SLP’s before the Hon’ble Supreme Court
against the order dated 01.11.2013. The said SLP’s later numbered as
Civil Appeal No. 11224 of 2013 arising from SLP 36587 of 2013, Civil
Appeal No. 11225 of 2013 arising from SLP 36684 of 2013, and Civil
Appeal No. 11226 of 2013 arising from SLP 36756 of 2013, were
disposed of vide consent order dated 13.12.2013 with a direction that
NEEPCO would be free to invite fresh bids, but the finalization of the
bid would be subject to outcome of the writ appeal pending before this
Court. It was alsoprovided that in the meantime, the respondents herein
would be free to collect sand and boulders for use at the three sites
from the approved quarries. NEEPCO then issued fresh Notice Inviting
Bids which was again challenged by the respondents before this Court
in W.P. (C) No76 of 2014. The said writ petition was dismissed vide
order dated 19.03.2014 on the ground that an appeal was already
pending before the Division bench of this Court.
The three Writ
Appeals, W.A.s No. 39, 40 and 41 of 2013,then came up for
consideration on 05.05.2014 and NEEPCO made a statement that “as
the lowest bids quoted by the contractor is 100 times higher than the
estimated cost, it will not be continued to finalize the tender in the
interest of public at large. Therefore, the respondent has already
cancelled the newNIB”. The said writ appeals were as such disposed of
vide order dated 05.05.2014 as being infructuous.
12.On 16.06.2014 the dispute between NEEPCO and the respondents was
referred to arbitration. Three identical but separate arbitration
references were made to the learned Sole Arbitrator in connection with
three
separate
work
contracts
i.e.
Package-I
(Contract
No.
NEEPCO/ED/QP/ C&P/R/C/KaHEP/560 dated 17.12.2004), PackageII (Contract No. NEEPCO/ED/QP/C&P/R/C/ KaHEP/ 561 dated
17.12.2004), and
Package-III
(Contract
No.
NEEPCO/ED/QP/
C&P/R/C/KaHEP/562 dated 17.12.2004) of the Kameng HE Project.
The term of arbitration reference under Package-I was as follows:
“Whether the rate for extra lead for transportation of sand and
boulder from Government approved quarries to work site for
Package-I under KaHEP shall be decided in terms of Clause
33(ii)(a) or Clause 33(iii) of Part-III, Vol. I, Conditions of
Contract
of
Book-II
of
Contract
Agreement
No.
NEEPCO/ED/QP/C&P/R/C/ KaHEP/560 of 2004-05 dated
17.12.2004.”
There were similar terms of arbitration reference in respect of PackageII and Package-III.
13.The learned Sole Arbitrator held the arbitration proceedings in several
sittings and finally passed the declaratory Arbitral Award dated
29.03.2016 in respect of Package-I holding as follows:
“Based on my findings above, I have no hesitation in
coming to the considered finding that the contract itself provides
rate(s) for payment of extra lead in items Nos. 2.7 and 3.4 of the
BOQ for surface and underground structures respectively.
Admittedly material had been transported from a lead much
longer than that envisaged at the time of award of work in favour
of the claimant. It is also an admitted case of the parties that the
claimant is entitled to extra payment for the extra lead. The only
point at issue is whether Clause 33(ii)(a) or Clause 33(iii) would
be applicable for working out the rate payable for transportation.
In view of my findings, I have no hesitation in holding that the
payment of extra lead is to be determined in accordance with
Clause 33(ii)(a) for the item which has deviated being already
available in the contract.
I, therefore, answer the reference as follows:
The rate for extra lead for transportation of sand and
boulders from Government approved quarries to the work site for
package-I works under KaHEP shall be decided in terms of
Clause 33(ii)(a) of Part-III, Volume-I, Conditions of Contract of
Book-II
of
Contract
Agreement
NEEPCO/ED/QP/C&P/R/C/KaHEP/560
of
2004-05
No.
dated
17.12.2004.”
Similar Declaratory Arbitral Awards dated 29.03.2016 were passed by
the learned Sole Arbitrator in respect of the other two Arbitral
References in respect of contracts pertaining to Package-II and
Package-III of the project.
14.The appellant NEEPCO then filed three separate applications under
Sec. 34 of the Arbitration and Conciliation Act, 1996 before the learned
Additional Deputy Commissioner (Judicial), Shillong challenging the
three Arbitral Awards dated 29.03.2016 in respect of Packages-I, II and
III and the same were registered as Arbitration Case No. 5 (T) 2016,
Arbitration Case No. 6 (T) 2016 and Arbitration Case No. 7 (T) 2016
respectively.
The
Court
Commissioner
(Judicial),
of
the
Shillong
learned
vide
Additional
common
order
Deputy
dated
27.04.2018 declined to interfere and dismissed the aforesaid Sec. 34
applications filed by NEEPCO and upheld the 3 (three) Arbitral Awards
dated 29.03.2016.
15.The appellant NEEPCO has filed these 3 (three) Arbitration Appeals
under Sec. 37 of the Arbitration and Conciliation Act, 1996 challenging
the common order dated 27.04.2018 passed by the Court of the learned
Additional Deputy Commissioner (Judicial), Shillong in Arbitration
Case No. 5 (T) 2016, Arbitration Case No. 6 (T) 2016 and Arbitration
Case No. 7 (T) 2016.
16.Heard learned Senior Counsels Shri. H.A. Ahmadi and Shri. V.K. Jindal
appearing for the appellant and Senior Counsel Shri. A. Bhan appearing
for the respondents.
17.Shri. H.A. Ahmadi, the learned Senior Counsel appearing for the
appellant submits that the instant case primarily involves interpretation
of Clause 33 of the Conditions of Contract and the issue before the
learned Arbitrator was as to whether the rate for extra lead for
transportation of sand and boulder from government approved quarries
to work site was to be decided in terms of Clause 33(ii)(a) or in terms of
Clause 33(iii) of the Conditions of Contract. Clause 33 of the
Conditions of Contract reads as follows:
“33. DEVIATIONS
(I) The Engineer-in-Charge shall have power to make any
deviations in the original specifications or drawings or
designs of the works or any part thereof that are in his
opinion, necessary at the time of or during the course of
execution of work. In the aforesaid purpose or for any other
reason, if it shall in the opinion of the Engineer-in-Charge
be desirable he will also have the powers to make
deviations, such as:
(a) variations,
(b) extra item,
(c) additions/omissions,
(d) alterations or substitutions of any kind.
No such deviations in the specifications or drawings or
designs or Bill of Quantities, as aforesaid shall in any way
vitiate or invalidate the contract and any such deviations
which the contractor may be directed to do shall form
integral part of the contract as if originally provided therein
and the contractor shall carry out the same on the same
conditions in all respect on which he agreed to do the works
under the contract.
(II) The rates for such items of works as are required to be
executed due to deviations as stated in sub-clause shall be
payable in the manner as stated hereunder:
(a) The rates already provided in the Bill of Quantities and
as per the procedure mentioned above under sub-clause
33 of this part shall apply in respect of the same item(s)
of work to be executed due to variations.
(b) In case some items are not available in the Bill of
Quantities, the rates of such items, as far as practicable,
shall be derived from the contracted rates of analogous
item(s) in the Bill of Quantities after actual observation
at Site. The decision to select analogous item(s) shall be
taken by the Engineer-in-Charge which shall be
conclusive and binding on the Contractor.
(III) If the rates for such items of work cannot be determined in
the manner as specified in Clause 33(ii), the rates for such
items to be executed shall be determined by the Engineer-inCharge on the basis of actual analysed cost taking the
following into consideration the rates for such items of
works as are required to be executed due to deviations as
stated in sub-clause shall be payable in the manner as stated
hereunder:
(a) Cost of material including taxes
(b) Cost of transportation to site
(c) Cost of direct wages (excluding fringe benefit) for
workers, gangers and working foreman (exclusing
supervisors) and direct equipment charges as set out in
the Central Water Commission guidelines.
(d) Cost of facilities like electricity
(e) Supervision and overhead profit @ 20% of the sum of (a)
to (d).
Note:
In case material in (a) above is supplied by the Corporation,
there will be no overhead and profit on the cost of material.The
decision of the Engineer-in-Charge, if any, in deriving rates as
aforesaid shall be conclusive and binding on the Contractor.
(IV) Under no circumstances, the Contractor shall at any stage
suspend the work on account of non-settlement of rates of
such deviated items.
18.The learned Senior Counsel Shri. H.A. Ahmadi further submits that
Clause 33(ii)(a) would apply only when the rates for similar item is
already provided in the Bill of Quantities and not otherwise. The
learned Senior Counsel submits that Clauses 2.7 and 3.4 of the Bill of
Quantities (of Packages-I and II) require to be examined as to whether
these clauses provide rates for similar item as “transportation of sand
and boulders from government approved quarries to work site”. Clauses
2 and 3 of the Bill of Quantities, which include clauses 2.7 and 3.4, read
as follows:
BILL OF QUANTITIES/SCHEDULE OF ITEMS
PACKAGE-I
Item
Description
Unit Qty
Rate
Amount
(Rs.)
(Rs.)
SURFACE EXCAVATION
AND BACKFILL
2.1
2.2
2.3
2.4
Surface excavation including
loading, transport, all lift and
lead up to 3.0 km from the
excavation area/working site,
unloading at disposal site or
stockpiles and maintenance of
the disposal sites or stockpiles,
construction of haul roads (if
any) and its maintenance,
complete in all respects as per
technical
specifications,
drawings and as directed by
Engineer-in-Charge.
Clearing of excavation areas, M2 38300
disposal areas and stockpiles
Excavation in soil including M3 20500
stripping of top soil
Excavation
in
soft
and M3 120000
disintegrated rock
Excavation in hard rock
2.4.1 Drilling and blasting
M3
60000
957500
2665000
24000000
19200000
2.4.2 Line drilling
2.5
2.6
2.7
2.8
M
50000
Additional excavation (in open M3
cuts,
for
foundation
of
structures, in faults and seams
etc.)
Loading,
transportation M3
including all lift and lead upto
3.0 km and unloading of
accepted geological overbreak
at disposal areas or stockpiles
Handling excavated material M3
for extra lead beyond initial
/KM
lead of 3.0 km
Backfilling
17600
54450
39600
2.8.1 Random backfill
M3
30000
2.8.2 Selected backfill
M3
15000
2.8.3 Free-draining backfill
M3
50000
2.8.4 Sand-gravel backfill
M3
50000
2.8.5 Backfilling with M10 concrete
M3
118800
2.8.6 Backfilling with M15 concrete
M3
89100
2.8.7 Backfilling with M20 concrete
M3
49500
UNDERGROUND
EXCAVATION
Underground excavation of
Head Race Tunnel and
Construction Adit including
excavation by drill and blast,
mechanical,
manual
or
conventional
methods;
including all survey and setting
out, all lifts and transportation
and unloading at disposal sites
upto 3.0 km from the nearest
portal
and
including
maintenance of the disposal
sites. Stockpiles, construction
of haul roads (if any) and its
maintenance, complete in all
respects as per technical
specifications, drawings and as
directed
by
Engineer-inCharge.
3.1
Head Race Tunnel excluding
handling of excavated materials
upto 3.0 km from the nearest
portal
3.1.1 Excavation in Class I
M3
62000
62000000
3.1.2 Excavation in Class 2
M3
82000
84460000
3.1.3 Excavation in Class 3
M3
46500
61845000
3.1.4 Excavation in Class 4A & 4B
M3
24000
49200000
Construction Adit including
handling of excavated materials
upto 3.0 km from the nearest
portal
3.2.1 Excavation in Class 3
M3
5453000
M3
8405000
Loading, transport including all M3
lift and lead up to 3.0 km and
unloading
of
accepted
geological
overbreak
at
disposal areas or stockpiles
Handling of excavated material M3
for extra lead beyond initial
/KM
lead of 3.0 km
Backfilling
of
accepted M3
geological overbreak with M10
concrete
Backfilling
of
accepted M3
geological overbreak with M15
concrete
Backfilling
of
accepted M3
geological overbreak with M20
concrete
1584000
396000
519750
556975
420750
3.2
3.2.2 Excavation in Class 4
3.3
3.4
3.5
3.6
3.7
The Bill of Quantities in respect of Surface Excavation and Backfill
Underground Excavation under Package-III is also similarly worded
except that clauses are numbered differently and are numbered as 2.7
and 3.5 instead of Clause 2.7 and 3.4.
19.The further submission of the learned Senior Counsel for the appellant
is that the appellant’s case before the learned Arbitrator was that that
the work “extra lead for transportation of sand and boulder from
Government approved quarries to work sites” is not the same as or
identical to any of the items in the BoQ and since, the work is not
identical to any of the items in the BoQ, Clause 33(iii) of the Conditions
of Contract was applicable which provides that “If the rates for such
items of work cannot be determined in the manner as specified in
Clause 33(ii), the rates for such items to be executed shall be
determined by the Engineer-in-Charge on the basis of actual analysed
cost taking the following into consideration the rates for such items of
works as are required to be executed due to deviations as stated in subclause shall be payable in the manner as stated hereunder: (a) Cost of
material including taxes, (b) Cost of transportation to site, (c) Cost of
direct wages (excluding fringe benefit) for workers, gangers and
working foreman (excluding supervisors) and direct equipment charges
as set out in the Central Water Commission guidelines, (d) Cost of
facilities like electricity, (e) Supervision and overhead profit @ 20% of
the sum of (a)to (d).” As such the rates in respect of the work of“extra
lead for transportation of sand and boulder from Government approved
quarries to work sites” was required to be determined by the Engineerin-Charge in terms of the provisions of Clause 33(iii) of the Conditions
of Contract.
20.The learned Senior Counsel further submits that Clause 33(ii)(a) can be
resorted to for fixing the rates for the work of “extra lead for
transportation of sand and boulder from Government approved quarries
to work sites” in terms of Clause 2.7 (Handling Excavated Materials
for extra lead beyond initial lead of 3.0 km at the rate of Rs. 198 per
Cubic Mtr/Km) and in terms of Clause 3.4 (Handling Excavated
Materials for extra lead beyond initial lead of 3.0 km at the rate of
Rs. 198 per Cubic Mtr/Km) only if the said work of“extra lead for
transportation of sand and boulder from Government approved
quarries to work sites” was same as or identical to the work
“Handling Excavated Materials for extra lead beyond initial lead of
3.0 km”. This is apparent from the very wording of Clause 33(ii)(a)
which states that, “The rates already provided in the Bill of Quantities
and as per the procedure mentioned above under sub-clause 33 of this
part shall apply in respect of the same item(s) of work to be executed
due to variations”.
21.The learned Senior Counsel for the appellant further referred to various
other clauses viz. Clause 2.1 of one of the contract documents namely
“Particular Technical Specifications”, Vol. 2, Part II. Clause 2.15 of the
aforesaid document
provides for mode and manner of disposal of
excavated materials from surface excavation as follows:
“2.15. Disposal of Excavated Materials
i) All materials from surface excavation suitable for use as
backfill, concrete aggregates or for other purposes shall be
stockpiled on the site within a radius of 3.0 km, as directed or
approved by the Engineer-in-Charge, if the immediate placement
in the final location in permanent works is not possible.
ii) Excavated materials which is not suitable for or is in excess of
the permanent construction requirements, shall be disposed of
within a radius of 3.0 km from the excavation place in the waste
disposal areas shown on the drawings or in areas designated as
such by the Engineer-in-Charge in the course of the work.
22.The learned Senior Counsel further referred to Clause 2.17.2(vii) of the
aforesaid document which provides for extra payment for handling of
excavated material from surface excavation beyond initial lead of 3.0
km and provides that extra payment will be made for handling of
excavated material beyond initial lead of 3.0 km and the measurement
of the same would be based on the hauled volume which will be
measured during hauling operation by counting the number of return
truck loads. The learned Senior Counsel further referred to Clause
3.10.1(iv) which provides for extra payment for handling of excavated
material from underground excavation beyond initial lead of 3.0 km and
provides for similar method of measurement as in the case of handling
of excavated material for surface excavation.
23.It is the submission of the learned counsel for the appellant that the
contract documents have to be read as a whole and Clauses 2.7 and 3.4
of the BoQ cannot be read in isolation. To support this contention
reliance has been placed on CHITTTY ON CONTRACTS, Vol. I (26th
Edition), pg 520-521, ODGER’s CONSTRUCTION OF DEEDS AND
STATUTES (5thEdn) Pg 55-56, The House of Lords decision in North
Eastern Railway Company vs. Lord Hastings, [1900] AC 260, the
Hon’ble Apex Court decisions in Bank of India vs. K. Mohandas,
(2009) 5 SCC 313 and Mahanadi Coalfields Ltd. Vs. DhansarEngg Co.
(P) Ltd., (2016) 10 SCC 571.
24.The learned Senior Counsel for the appellant submits that (a) if the
contract is read as a whole, it is evident that the provisions thereof have,
in the ordinary course, only provided for dumping of the excavated
material from the project site at designated locations which are
otherwise within a lead of 3.0 km, (b) however, clauses 2.7 and 3.4
have been added by way of abundant caution to factor in a contingency
when such excavated material is dumped beyond the distance of 3.0 km
instead of the designated dumping areas, (c) Clauses 2.7 and 3.4 are part
of a composite sequence of activities undertaken in the course of
“Surface Excavation and Backfill” and “Underground Excavation”. The
work in question “extra lead for transportation of sand and boulders
from Government Approved quarries” does not form part of the
sequence of activities contemplated under Chapter 2 and 3 of the
Particular Technical Specifications, (d) When the respondent loaded
and transported sand and boulders from the Government Approved
quarries, there was no excavation involved, (e) Therefore, the work in
question ““extra lead for transportation of sand and boulders from
Government Approved quarries” cannot be considered as the item of
work “same as’ the item of work under Clause 2.7 and 3.4 of the BoQ,
and (e) as evident from Clause 33(ii)(a), the clause only applies in
respect of the “same item(s) of works to be executed due to variations”,
that is when there is a variation in the quantity with respect to the same
item already in BoQ. As this is not the case in the instant case, Clause
33(ii)(a) has no relevance and the appropriate clause for arriving at the
rate would be Clause 33(iii) of the Conditions of Contract.
25.The second submission of the learned senior Counsel for the appellant
is that Clauses 2.7 and 3.4 of the BoQ contemplate “Handling” of
excavated material which encompasses a plethora of activities far wider
than mere “transportation” of boulder and sand. In this regard,
references have been made of clauses 2.15(iii), 2.17.2(vi)(b), 3.6.8(iii),
3.10.1(iii)(b) of the Particular technical Specifications to substantiate
that “handling” as envisaged in the contract involves a plethora of
activities like shaping and trimming of disposal areas to the lines and
grades, stripping of vegetation, compacting by movement of dumping
vehicles, grading in layers, loading, hauling, dumping, formation and
maintenance of stockpiles, recultivation of disposal areas and stockpile
areas etc. This plethora of activities is not involved in the work of
“transportation of sand and boulders from Government Approved
quarries”.
26.The learned Senior Counsel for the appellant further submits that the
type and nature of road surface has an impact on determining the rate as
it impacts fuel consumption and also the types of vehicles being used.
Moving the material within the project site under Clauses 2.7 and 3.4
would involve vehicles traversing haulage roads which are freshly cut
and which are not paved. On the other hand, transport of sand and
boulder from the Government Approved quarries from the distance of
78 km, 53 km and 36.5 km involved transportation over paved roads.
Further, moving the material within the project site under Clauses 2.7
and 3.4 involved hauling equipment which are different from tipper
trucks used for transportation of sand and boulders.
27.The further submission of the appellant is that the cost of material,
including aggregate, was already factored in the existing items of BoQ
which also includes “lead” in respect of all materials used in concrete.
Clause 33 provides that, “The Corporation will not issue any material
like reinforcement and/or structural steel, cement, POL etc. except
explosives for this package. The Contractor has to make his own
arrangements for all materials, consumables etc for incorporation and
for completion of the works, within his quoted rates”. Additionally, the
learned Senior Counsel for the appellant submits that the award is an
inchoate award, lacking in certainty and ought to set aside on this
ground alone.
28.The further submission of the appellant is that the learned Arbitrator has
exceeded his jurisdiction and has ruled on an “excepted matter”. As per
Clause 33 of the Conditions of Contract, “the decision of the Engineerin-Charge, if any, in deriving rates as aforesaid shall be conclusive and
binding on the Contractor” and therefore, arriving at a rate under Clause
33(iii) was the exclusive domain of the engineer-in-Charge and the
learned Arbitrator has essentially impinged on the exclusive domain of
the Engineer-in-Charge. Reliance has been placed on the Hon’ble Apex
Court decision in Vishwanath Sood vs. Union of India, (1989) 1 SCC
657 wherein the Hon’ble Apex Court observed:
“8. We have gone through the judgment of the Division Bench of the
High Court and we have also considered the arguments advanced on
both sides. With great respect, we find our- selves unable to agree with
the interpretation placed by the Division Bench on the terms of the
contract. Clause 2 of the contract makes the time specified for the
performance of the contract a matter of essence and emphasises the
need on the part of the contractor to scrupulously adhere to the time
schedule approved by the Engineer-in charge. With a view to compel
the contractor to adhere to this time schedule, this clause provides a
kind of penalty in the form of a compensation to the Department for
default in adhering to the time schedule. The clause envisages an
amount of compensation calculated as a percentage of the estimated
cost of the whole work on the basis of the number of days for which the
work remains uncommenced or unfinished to the prescribed extent on
the relevant dates. We do not agree with the counsel for the respondent
that this is in the nature of an automatic levy to be made by the
Engineer-in charge based on the number of days of delay and the
estimated amount of work. Firstly, the reference in the clause to the
requirement that the work shall throughout the stipulated period of the
contract be proceeded with due diligence and the reference in the latter
part of the clause that the compensation has to be paid "in the event of
the contractor failing to comply with" the prescribed time schedule
make it clear that the levy of compensation is conditioned on some
default or negligence on the part of the contractor. Secondly, while the
clause fixes the rate of compensation at 1 per cent for every day of
default it takes care to prescribe the maximum compensation of 10 per
cent on this ground and it also provides for a discretion to the
Superintending Engineer to reduce the rate of penalty from 1 per cent.
Though the clause does not specifically say so, it is clear that any
moderation that may be done by the Super- intending Engineer would
depend upon the circumstances, the nature and period of default and
the degree of negligence or default that could be attributed to the
contractor. This means that the Superintending Engineer, in
determining the rate of compensation chargeable, will have to go into
all the aspects and determine whether there is any negligence on the
part of the contractor or not. Where there has been no negligence on
the part of the contractor or where on account of various extraneous
circumstances referred to by the Division Bench such as vis major or
default on the part of the Government or some other unexpected
circumstance which does not justify penalising the contractor, the
Superintending Engineer will be entitled and bound to reduce or even
waive the compensation. It is true that the clause does not in terms
provide for any notice to the contractor by the Superintending
Engineer. But it will be appreciated that in practice the amount of
compensation will be initially levied by the Engineer-in-charge and the
Superintending Engineer comes into the picture only as some sort of
revisional or appellate authority to whom the contractor appeals for
redress. As we see it, clause 2 contains a complete machinery for
determination of the compensation which can be claimed by the
Government on the ground of delay on the part of the contractor in
completing the contract as per the time schedule agreed to between the
parties. The decision of the Superintending Engineer, it seems to us, is
in the nature of a considered decision which he has to arrive at after
considering the various mitigating circumstances that may be pleaded
by the contractor or his plea that he is not liable to pay compensation
at all under this clause. In our opinion the question regarding the
amount of compensation leviable under clause 2 has to be decided only
by the Superintending Engineer and no one else.
9. The Division Bench has construed the expression in clause 2 in
parenthesis that "the Superintending Engineer's decision shall be final"
as referring only to a finality qua the department; in other words, that
it only constitutes a declaration that no officer in the department can
determine the quantification and that the quantum of compensation
levied by the Superintending Engineer shall not be changed without the
approval of the Government. After refer- ring to certain judicial
decisions regarding the meaning of the word "final" in various statutes,
the Division Bench concluded that the finality cannot be construed as
excluding the jurisdiction of the arbitrator under clause 25. We are
unable to accept this view. Clause 25 which is the arbitration clause
starts with an opening phrase excluding certain matters and disputes
from arbitration and these are matters or disputes in respect of which
provision has been made elsewhere or otherwise in the contract. These
words in our opinion can have reference only to provisions such as the
one in parenthesis in clause 2 by which certain types of determinations
are left to the administrative authorities concerned. If that be not so,
the words "except where other- wise provided in the contract" would
become meaningless. We are therefore inclined to hold that the opening
part of clause 25 clearly excludes matters like those mentioned in
clause 2 in respect of which any dispute is left to be decided by a higher
official of the Department. Our conclusion, therefore, is that the
question of awarding compensation under clause 2 is outside the
purview of the arbitrator and that the compensation, determined under
clause 2 either by the Engineer-in-charge or on further reference by the
Superintending Engineer will not be capable of being called in question
before the arbitrator.
10. We may confess that we had some hesitation in coming to this
conclusion. As pointed out by the Division Bench, the question of any
negligence or default on the part of the contractor has many facets and
to say that such an important aspect of the contract cannot be settled by
arbitration but should be left to one of the contracting parties might
appear to have far reaching effects. In fact, although the contractor in
this case might object to the process of arbitration because it has gone
against him, contractors generally might very well prefer to have the
question of such compensation decided by the arbitrator rather than by
the Superintending Engineer. But we should like to make it clear that
our decision regarding non arbitrability is only on the question of any
compensation which the Government might claim in terms of clause 2
of the contract. We have already pointed out that this is a penalty
clause introduced under the contract to ensure that the time schedule is
strictly adhered to. It is something which the Engineer- in-Charge
enforces from time to time when he finds that the contractor is being
recalcitrant, in order to ensure speedy and proper observance of the
terms of the contract. This is not an undefined power. The amount of
compensation is strictly limited to a maximum of 10% and with a wide
margin of discretion to the Superintending Engineer, who might not
only reduce the percentage but who, we think, can even reduce it to nil,
if the circumstances so warrant. It is this power that is kept outside the
scope of arbitration. We would like to clarify that this decision of ours
will not have any application to the claims, if any, for loss or damage
which it may be open to the Government to lay against the contractor,
not in terms of clause 2 but under the general law or under the
Contract Act. As we have pointed out at the very outset so far as this
case is concerned the claim of the Government has obviously
proceeded in terms of clause 2 and that is the way in which both the
learned single Judge as well as the Division Bench have also
approached the question. Reading clauses 2 and 25 together we think
that the conclusion is irresistible that the amount of compensation
chargeable under clause 2 is a matter which has to be adjudicated in
accordance with that clause and which cannot be referred to
arbitration under clause 25.”
29.The further submission of the learned counsel for the appellant is that
the errors in the Award are not trivial and the potential effect on the
public exchequer is massive. Although, no crystallized sum is
mentioned in the Award and the Award is only a declaratory award, the
appellants have, on processing of the bills have tentatively calculated
that they might have to pay an amount of Rs. 3.56 lakh for every truck
of which has travelled 100 km carrying 10 cubic Metre of sand or
boulder. The Arbitral Award would allow the respondents to unjustly
enrich itself ultimately driving up the cost of project by over Rs. 1,000
Crores. The learned Counsel refers to the decisions of the Bombay High
Court in Angerlehner Structural and Civil Engineering co. vs.
Municipal Corporation of Greater Mumbai, MANU/MH/0554/2017.
30.Per contra, the learned senior counsel for the respondents submits that
the scope of appeal under Sec. 37 of the Arbitration and Conciliation
Act, 1996 is limited and that it is now settled law that the court while
deciding an appeal under Sec. 37 of the Arbitration and Conciliation
Act, 1996 must not interfere with the decision of the lower court unless
it is shown to be palpably erroneous in facts or in law, or it is manifestly
perverse. Reliance has been placed on the decision of the Delhi High
Court in NHAI vs BSC-RBM-Pati JV, 2018 SCC Online Del 6780
wherein it has been held at para 66, as follows:
“The position that emerges from the law, as it stands crystallized
today, is, clearly, that findings, of fact as well as of law, of the
arbitrator/Arbitral Tribunal are ordinarily not amenable to
interference either under Sections 34 or Section 37 of the Act. It
is only where the finding is either contrary to the terms of the
contract between the parties, or, ex facie, perverse, that
interference, by this Court, is necessary. The arbitrator/Arbitral
Tribunal is the final arbiter on facts as well as in law, and even
errors, factual or legal, which stop short of perversity, do not
merit interference under Sections 34or 37 of the Act. Insofar as
the ultimate view of the learned arbitrator/ Arbitral Tribunal, on
any issue is concerned, so long as the view is plausible, and not
merely possible, this Court would be loath to interfere
therewith.”
31.In this regard the learned senior counsel for the respondents places
further reliance on the decision of the Hon’ble Apex Court in
Associated Builders vs. Delhi Development Authority, (2015) 3 SCC 49,
wherein the Hon’ble Apex Court held as follows:
“It must clearly be understood that when a court is applying the
"public policy" test to an arbitration award, it does not act as a
court of appeal and consequently errors of fact cannot be
corrected. A possible view by the arbitrator on facts has
necessarily to pass muster as the arbitrator is the ultimate master
of the quantity and quality of evidence to be relied upon when he
delivers his arbitral award.
“Construction of the terms of a contract is primarily for an
arbitrator to decide unless the arbitrator construes the contract
in such a way that it could be said to be something that no fair
minded or reasonable person could do.”
32.The learned senior counsel for the respondents places further reliance
on the Delhi High Court decision in NTPC vs. Marathon Electric
motors, (2012) 194 DLT 404 (DB) wherein it has been held as follows:
“17. We have gone through the pleading as well as all the orders
passed by trial Court in the above matter and considered the
rival submissions of both sides. The present matter has been filed
by the appellant under Section 31(1)(b) of the Act. It is settled
law that the Appellate Court should not interfere with the
exercise of the discretion under appeal solely on the ground that
if it had considered the matter at the trial stage, it may have
come to a contrary conclusion. In case, the discretion has been
exercised by the trial Court reasonably and in judicial matter, the
Appellate Court would not take different view by interfering with
the Trial Court's exercise of discretion, unless, it is found that in
exercising its discretion, the trial Court has acted unreasonably
and capriciously or has ignored relevant facts, then it could be
open to the Appellate Court to interfere with the trial Court's
exercise of discretion. Reliance can be placed upon the case
reported in AIR 1967 SC 209, Uttar Pradesh Co-operative
Society vs. Sundar Bros.
18. The scope of judicial interference against the arbitral award
which has time and again came up before the courts for
consideration, wherein the view of the Courts including this
Court are consistent that the Court while deciding Section 34
objection cannot culminate into the appellate Court to decide
every legal and factual issue. It is only those errors of patent
illegality, without jurisdiction or biasness or against the public
policy where in the awards seems to be unsustainable, the Courts
are empowered to interfere and not in all other cases to correct
errors committed by the Arbitrator.”
33.The learned senior counsel for the respondents next submits that the
work of “extra lead for transportation of sand and boulder from
Government Approves quarries to work sites” is identical to and is the
same item of work as specified under Clauses 2.7 and 3.4 of the BoQ
and that quarry excavation is the same as surface excavation. The term
“surface excavation” includes within its ambit excavated material
obtained from excavation in quarry areas. Clause 2.8 of the Particular
technical Specifications, Vol. 2, Part II mentions about Quarry
Excavation under Chapter 2 (SURFACE EXCAVATION AND
BACKFILL) and therefore surface excavation includes within its ambit
excavated material obtained from excavation in quarry. Therefore, it is
abundantly clear that excavation activities mentioned in Items No. 2.1
to 2.5 of the BoQ read with Chapter 2 of the PTS for surface excavation
are the same excavation activities that were undertaken by the
respondent for quarry excavation in the Government Approved quarries.
The works mentioned in items No. 2.2. to 2.5 of the BoQ have been
undertaken by the respondents with respect to sand and boulder during
quarry excavation which is to be done in the same manner as surface
excavation. The term “excavated material” as used in Clause 2.7 of the
BoQ is nothing but the material that are excavated during quarry
excavation which in this case is sand and boulder. The payment of these
activities within the distance of 3.0 km has been included in the rate of
concrete under the BoQ and, therefore, the cost with respect to
excavation of sand and boulders from the Government Approved
quarries including transportation upto a distance of 3.0 km has already
been paid for to the respondent in the price of concrete. The only cost
that remains unpaid is the cost of transportation of sand and boulders
beyond the intial lead of 3.0 km which is to be paid by the appellant
under Clauses 2.7 and 3.4 of the BoQ.
34.It is further submitted on behalf of the respondents that a commercial
contract of the present nature ought to be interpreted so as to give effect
to the commercial intent of the parties and an ambiguity, if any, ought
to be read against the draftsman. The learned Senior Counsel places
reliance on Bombay High Court decision in Mumbai Metropolitan
Region Development Authority vs Unity Infraprojects Ltd, (2008) 5
Bom CR 196 wherein it has been held as follows:
“5. A business like interpretation of contractual provisions must
be adopted in construing contracts entered into by persons of
business to govern business dealings. The Court must ensure that
interpretation of law in commercial cases must not be disjointed
from the intent and object which those having business dealings
seek to subserve. Unless interpretation of contracts effectuates a
business meaning for persons of business, the law will not fulfill
its purpose and object of being a facilitator for business and
providing a structure of ordered certainty to those who carry on
business here. The legal system must innovate constantly to keep
abreast with rapid changes in technology and business.
Further reliance has been placed on the Supreme Court decision
inGodhra Electricity Co, Ltd. vs. State of Gujarat, (1975) 1 SCC 199
wherein it has been held as follows:
“16. We are not certain that if evidence of subsequent acting
under a document is admissible, it might have the result that a
contract would mean one thing on the day it is signed but by
reason of subsequent event it would mean something a month or
year later. Subsequent 'interpreting' statements might not always
change the meaning of a word or a phrase. A word or a phrase,
is not always crystal clear. When both parties subsequently say
that by the word or phrase which, in the context, is ambiguous,
they meant this, it only supplies a glossary as to the meaning of
the word or phrase. After all, the inquiry is as to, what the
intention of the parties was from the language used. And, why is
it that parties cannot clear the latent ambiguity in the language
by a subsequent interpreting statement?
If the meaning of the
word or phrase or sentence is clear, extrinsic evidence is not
admissible. It is only when there is latent ambiguity that extrinsic
evidence in the shape of interpreting statement in which both
parties have concurred should be admissible. The parties
themselves might not have been clear as to the meaning of the
word or phrase when they entered into the contract.
Unanticipated situations might arise or come into the
contemplation of the parties subsequently which would sharpen
their focus and any statement by them which would illuminate the
darkness arising out of the ambiguity of the language should not
be shut out. In the case of an ambiguous instrument, there is no
reason why subsequent interpreting statement should be
inadmissible.”
35.It is additionally submitted on behalf of the respondents that even if
there was some ambiguity in the meaning of the terms used in the BoQ
items, in such case the principle of verba chartarum forties accipiuntur
contra proferentem should be applied. This is a principle of
construction where under if words of a contract are ambiguous, of two
equally possible meanings, they should be interpreted against the
author, drafter or writer of the contract and not against the other party.
The counsel places reliance on Bank of India vs. K. Mohandas, (2009) 5
SCC 313, para 32, wherein it has been held as follows:
“The fundamental position is that it is the banks who were
responsible for formulation of the terms in the contractual
Scheme that the optees of voluntary retirement under that Scheme
will be eligible to pension under Pension Regulations, 1995, and,
therefore, they bear the risk of lack of clarity, if any. It is a wellknown principle of construction of contract that if the terms
applied by one party are unclear, an interpretation against that
party is preferred.” (verba chartarum forties accipiuntur contra
proferentem)
36.The next submission on behalf of the respondents is that the terms of
reference as referred to the learned Arbitrator is within the scope of his
jurisdiction and does not amount to an “excepted matter”. The learned
Senior Counsel raises the point that the above ground has been raised
for the first time before this Court in the instant appeal. This ground
was not raised either before the learned Arbitrator or before the learned
Additional Deputy Commissioner (Judicial), Shillong at the stage of
hearing on Sec. 34 application and as such this ground cannot be raised
at the appellate stage. The learned Senior Counsel further submits that it
is incorrect to aver that the learned Arbitrator exceeded his jurisdiction
and usurped the power of the Engineer-in-Charge because the present
dispute is with regard to whether the payment for the works in question
is to be made in terms of Clause 33(ii)(a) or Clause 33(iii) of the
Conditions of Contract which would constitute a condition precedent
before the Engineer-in-Charge can determine the appropriate rate under
Clause 33(iii). In this regard reliance has been placed on the Hon’ble
Supreme Court decision in BSNL vs. Motorola India (P) Ltd., 92009) 2
SCC 337.
37.The additional submissions of the respondents are that the award is well
reasoned, considered and unambiguous award and there is no legal
infirmity in the award on this count and that though appellant NEEPCO
is a public sector undertaking, but mere loss to the public exchequer
will not be a ground to set aside an award on ground of public policy.
Reliance in this regard is placed on Bombay High Court decision in
Union of India vs. India Proofing and General Industries, AIR 2000
Bom 292.
38.We have heard the submissions of the learned senior counsel for the
parties.
39.The present appeals are appeals under Sec. 37 of the Arbitration and
Conciliation Act, 1996. We are conscious of the scope of judicial
interference with an Arbitral Award under Sec. 34 or under Sec. 37 of
the Arbitration and Conciliation Act, 1996. The above provisions of the
Arbitration and Conciliation Act, 1996 read as follows:
34. Application for Setting Aside Arbitral Award.(1) Recourse to a Court against an arbitral award may be made
only by an application for setting aside such award in
accordance with sub-section (2) and sub-section (3).
(2) An arbitral award may be set aside by the Court only if(a) the party making the application furnishes proof that(i) a party was under some incapacity; or
(ii) the arbitration agreement is not valid under the law to which
the parties have subjected it or, failing any indication thereon,
under the law for the time being in force; or
(iii) the party making the application was not given proper notice
of the appointment of an arbitrator or of the arbitral proceedings
or was otherwise unable to present his case; or
(iv) the arbitral award deals with a dispute not contemplated by
or not falling within the terms of the submission to arbitration, or
it contains decisions on matters beyond the scope of the
submission to arbitration:
Provided that, if the decisions on matters submitted to arbitration
can be separated from those not so submitted, only that part of
the arbitral award which contains decisions on matters not
submitted to arbitration may be set aside; or
(v)
the composition of the arbitral tribunal or the arbitral
procedure was not in accordance with the agreement of the
parties, unless such agreement was in conflict with a provision of
this Part from which the parties cannot derogate, or, failing such
agreement, was not in accordance with this Part; or
(b) the Court finds that(i)
the subject-matter of the dispute is not capable of
settlement by arbitration under the law for the time being in
force, or
(ii)
the arbitral award is in conflict with the public policy
of
India.
Explanation.-Without prejudice to the generality of sub-clause
(ii), it is hereby declared, for the avoidance of any doubt, that an
award is in conflict with the public policy of India if the making
of the award was induced or affected by fraud or corruption or
was in violation of Section 75 or Section 81.
(3) An application for setting aside may not be made after three
months have elapsed from the date on which the party making
that application had received the arbitral award or, if a request
had been made under Section 33, from the date on which that
request had been disposed of by the arbitral tribunal:
Provided that if the Court is satisfied that the applicant was
prevented by sufficient cause from making the application within
the said period of three months it may entertain the application
within a further period of thirty days, but not thereafter.
(4) On receipt of an application under sub-section (1), the Court
may, where it is appropriate and it is so requested by a party,
adjourn the proceedings for a period of time determined by it in
order to give the arbitral tribunal an opportunity to resume the
arbitral proceedings or to take such other action as in the
opinion of arbitral tribunal will eliminate the grounds for setting
aside the arbitral award."
Sec. 5 of the Act categorically provides that, “Extent of judicial
intervention.-Notwithstanding anything contained in any other law for
the time being in force, in matters governed by this Part, no judicial
authority shall intervene except where so provided in this Part." Thus
Section 34 of the Arbitration and Conciliation Act, 1996 when read
with Section 5 of the said Act, makes it abundantly clear that an arbitral
award which is governed by Part I of the Act can be set aside only on
the grounds mentioned in Sec. 34(2) of the Act and not on any other
grounds.
Section 37 of the Arbitration and Conciliation Act, 1996 reads as
follows:
37. Appealable orders.— (1) An appeal shall lie from the
following orders (and from no others) to the Court authorised by
law to hear appeals from original decrees of the Court passing
the order, namely:—
(a) granting or refusing to grant any measure under section 9;
(b) setting aside or refusing to set aside an arbitral award under
section 34.
(2) An appeal shall also lie to a Court from an order granting of
the arbitral tribunal.—
(a) accepting the plea referred in sub-section (2) or sub-section
(3) of section 16; or
(b) granting or refusing to grant an interim measure under
section 17.
(3) No second appeal shall lie from an order passed in appeal
under this section, but nothing in this section shall affect or take
away any right to appeal to the Supreme Court.
This is also a settled proposition that none of the grounds contained in
sub- clause 2(a) of Sec. 34 deal with the merits of the decision rendered
by an arbitral tribunal. It is only when we come to sub-clause 2(b)(ii)
that is “the award being in conflict with the public policy of India” that
the merits of an arbitral award can be looked into by a Court under
certain specified circumstances. Associated Builders vs. Delhi
Development Authority, (2015) 3 SCC 49
40.While construing the expression "the public policy of India" as
contained in Section 34 (2)(b)(ii) of the Arbitration and Conciliation
Act, 1996, the Hon’ble Apex Court in ONGC v. Saw Pipes, 2003 (5)
SCC 705, held as follows:
"31. Therefore, in our view, the phrase "public policy of India"
used in Section 34 in context is required to be given a wider
meaning. It can be stated that the concept of public policy
connotes some matter which concerns public good and the public
interest. What is for public good or in public interest or what
would be injurious or harmful to the public good or public
interest has varied from time to time. However, the award which
is, on the face of it, patently in violation of statutory provisions
cannot
be
said
to
be
in
public
interest.
Such
award/judgment/decision is likely to adversely affect the
administration of justice. Hence, in our view in addition to
narrower meaning given to the term "public policy" in
Renusagar case [1994 Supp (1) SCC 644] it is required to be
held that the award could be set aside if it is patently illegal. The
result would be - award could be set aside if it is contrary to:
(a) Fundamental policy of Indian law; or
(b) The interest of India; or
(c) Justice or morality, or
(d) in addition, if it is patently illegal.
Illegality must go to the root of the matter and if the illegality is
of trivial nature it cannot be held that award is against the public
policy. Award could also be set aside if it is so unfair and
unreasonable that it shocks the conscience of the court. Such
award is opposed to public policy and is required to be adjudged
void.”
41.The Hon’ble Apex Court in ONGC vs. Western Geco International Ltd.,
(2014) 9 SCC 263 held as follows:
35. What then would constitute the „Fundamental policy of
Indian Law‟ is the question. The decision in Saw Pipes Ltd. does
not elaborate that aspect. Even so, the expression must, in our
opinion, include all such fundamental principles as providing a
basis for administration of justice and enforcement of law in this
country. Without meaning to exhaustively enumerate the purport
of the expression “Fundamental Policy of Indian Law”, we may
refer to three distinct and fundamental juristic principles that
must necessarily be understood as a part and parcel of the
Fundamental Policy of Indian law. The first and foremost is the
principle that in every determination whether by a Court or other
authority that affects the rights of a citizen or leads to any civil
consequences, the Court or authority concerned is bound to
adopt what is in legal parlance called a „judicial approach‟ in
the matter. The duty to adopt a judicial approach arises from the
very nature of the power exercised by the Court or the authority
does not have to be separately or additionally enjoined upon the
fora concerned. What must be remembered is that the importance
of Judicial approach in judicial and quasi judicial determination
lies in the fact so long as the Court, Tribunal or the authority
exercising powers that affect the rights or obligations of the
parties before them shows fidelity to judicial approach, they
cannot act in an arbitrary, capricious or whimsical manner.
Judicial approach ensures that the authority acts bonafide and
deals with the subject in a fair, reasonable and objective manner
and that its decision is not actuated by any extraneous
consideration. Judicial approach in that sense acts as a check
against flaws and faults that can render the decision of a Court,
Tribunal or Authority vulnerable to challenge.
38. Equally important and indeed fundamental to the policy of
Indian law is the principle that a Court and so also a quasijudicial authority must, while determining the rights and
obligations of parties before it, do so in accordance with the
principles of natural justice. Besides the celebrated „audi alteram
partem‟ rule one of the facets of the principles of natural justice
is that the Court/authority deciding the matter must apply its
mind to the attendant facts and circumstances while taking a
view one way or the other. Non-application of mind is a defect
that is fatal to any adjudication. Application of mind is best
demonstrated by disclosure of the mind and disclosure of mind is
best done by recording reasons in support of the decision which
the Court or authority is taking. The requirement that an
adjudicatory authority must apply its mind is, in that view, so
deeply embedded in our jurisprudence that it can be described as
a fundamental policy of Indian Law.
39. No less important is the principle now recognised as a
salutary juristic fundamental in administrative law that a
decision which is perverse or so irrational that no reasonable
person would have arrived at the same will not be sustained in a
Court of law. Perversity or irrationality of decisions is tested on
the touchstone of Wednesbury‟s principle of reasonableness.
Decisions that fall short of the standards of reasonableness are
open to challenge in a Court of law often in writ jurisdiction of
the Superior courts but no less in statutory processes where ever
the same are available.
40. It is neither necessary nor proper for us to attempt an
exhaustive enumeration of what would constitute the fundamental
policy of Indian law nor is it possible to place the expression in
the straitjacket of a definition. What is important in the context of
the case at hand is that if on facts proved before them the
arbitrators fail to draw an inference which ought to have been
drawn or if they have drawn an inference which is on the face of
it, untenable resulting in miscarriage of justice, the adjudication
even when made by an arbitral tribunal that enjoys considerable
latitude and play at the joints in making awards will be open to
challenge and may be cast away or modified depending upon
whether the offending part is or is not severable from the rest.
42. The Hon’ble Apex Court in Associated Builders vs. DDA, (2015)
3 SCC 49 further held as follows:
31. The third juristic principle is that a decision which is
perverse or so irrational that no reasonable person would have
arrived at the same is important and requires some degree of
explanation. It is settled law that where(i)
a finding is based on no evidence,
(ii)
an arbitral tribunal takes into account something
irrelevant to the decision which it arrives at;
(iii) ignores vital evidence in arriving at its decision, such
decision would necessarily be perverse.
32. A good working test of perversity is contained in two
judgments. In H.B. Gandhi, Excise and Taxation Officer-cumAssessing Authority v. GopiNath & Sons, 1992 Supp (2) SCC 312
at p. 317, it was held:
"7. ...................It is, no doubt, true that if a finding of fact is
arrived at by ignoring or excluding relevant material or by
taking into consideration irrelevant material or if the finding
so outrageously defies logic as to suffer from the vice of
irrationality incurring the blame of being perverse, then, the
finding is rendered infirm in law."
In Kuldeep Singh v. Commr. of Police, (1999) 2 SCC 10, at para
10, it was held:
"10. A broad distinction has, therefore, to be maintained
between the decisions which are perverse and those which are
not. If a decision is arrived at on no evidence or evidence
which is thoroughly unreliable and no reasonable person
would act upon it, the order would be perverse. But if there is
some evidence on record which is acceptable and which could
be relied upon, howsoever compendious it may be, the
conclusions would not be treated as perverse and the findings
would not be interfered with."
33. It must clearly be understood that when a court is applying
the "public policy" test to an arbitration award, it does not act as
a court of appeal and consequently errors of fact cannot be
corrected. A possible view by the arbitrator on facts has
necessarily to pass muster as the arbitrator is the ultimate master
of the quantity and quality of evidence to be relied upon when he
delivers his arbitral award. Thus an award based on little
evidence or on evidence which does not measure up in quality to
a trained legal mind would not be held to be invalid on this
score[1]. Once it is found that the arbitrators approach is not
arbitrary or capricious, then he is the last word on facts. In P.R.
Shah, Shares & Stock Brokers (P) Ltd. v. B.H.H. Securities (P)
Ltd., (2012) 1 SCC 594, this Court held:
"21. A court does not sit in appeal over the award of an
Arbitral Tribunal by reassessing or reappreciating the
evidence. An award can be challenged only under the grounds
mentioned in Section 34(2) of the Act. The Arbitral Tribunal
has examined the facts and held that both the second
respondent and the appellant are liable. The case as put
forward by the first respondent has been accepted. Even the
minority view was that the second respondent was liable as
claimed by the first respondent, but the appellant was not
liable only on the ground that the arbitrators appointed by the
Stock Exchange under Bye-law 248, in a claim against a nonmember, had no jurisdiction to decide a claim against another
member. The finding of the majority is that the appellant did
the transaction in the name of the second respondent and is
therefore, liable along with the second respondent. Therefore,
in the absence of any ground under Section 34(2) of the Act, it
is not possible to re-examine the facts to find out whether a
different decision can be arrived at."
34. It is with this very important caveat that the two fundamental
principles which form part of the fundamental policy of Indian
law (that the arbitrator must have a judicial approach and that
he must not act perversely) are to be understood.
43.The legal proposition that emerges from the above is that an arbitral
award can be set aside under Sec. 34 of the Arbitration and Conciliation
Act, 1996 if it is contrary to:
(a) The fundamental policy of Indian law
The three aspects of “the fundamental policy of Indian law” that
have been elucidated are that:
(i) The Court or the authority must adopt a judicial approach in
deciding the matter
(ii) The Court or the authority must determine the rights and
obligations of the parties in accordance with the principles of
natural justice.
(iii) The decision must not be so irrational or perverse that no
reasonable person would have arrived at such decision.
(b) The interest of India
(c) Justice or morality
(d) If it is patently illegal, that is if it is patently in violation of
statutory provisions
44.Coming to the test that “the decision must be so irrational or perverse
that no reasonable person would have arrived at such decision”, the
Hon’ble Apex Court further elucidated that if a finding is based on no
evidence, or an arbitral tribunal takes into account something irrelevant
to the decision which it arrives at, or an arbitral tribunal ignores vital
evidence in arriving at its decision, such decision would necessarily be
perverse (Associated Builders case). If a finding of fact is arrived at by
ignoring or excluding relevant material or by taking into consideration
irrelevant material or if the finding so outrageously defies logic as to
suffer from the vice of irrationality incurring the blame of being
perverse, then, the finding is rendered infirm in law (H.B. Gandhi case).
A decision which is perverse or so irrational that no reasonable person
would have arrived at the same will not be sustained in a Court of law.
Perversity or irrationality of decisions is tested on the touchstone of
Wednesbury’s principle of reasonableness. Decisions that fall short of
the standards of reasonableness are open to challenge in a Court of law
often in writ jurisdiction of the Superior courts but no less in statutory
processes where ever the same are available (Western Geco Case).
45.Turning to the case in hand, it is a settled law that a contract has to be
read as a whole and individual clauses cannot be read in isolation. In
CHITTY ON CONTRACTS, VOL.I (26th Edition), Pg 520-52, it is
stated, “The whole contract is to be considered. Every contract is to be
construed with reference to its object and the whole of its terms, and
accordingly, the whole contract must be considered in endeavoring to
collect the intention of the parties, even though the immediate object of
inquiry is the meaning of an isolated clause.” In Bank of India vs. K.
Mohandas, (2009) 5 SCC 313, the Hon’ble Apex Court cited with
approval the passage from the decision of the House of Lords in North
Eastern Railway Company vs. Lord Hastings, [1900] AC 260 and held
as follows:
28. The true construction of a contract must depend upon the
import of the words used and not upon what the parties choose to
say afterwards. Nor does subsequent conduct of the parties in the
performance of the contract affect the true effect of the clear and
unambiguous words used in the contract. The intention of the
parties must be ascertained from the language they have used,
considered in the light of the surrounding circumstances and the
object of the contract. The nature and purpose of the contract is
an important guide in ascertaining the intention of the parties.
31. It is also a well-recognized principle of construction of a
contract that it must be read as a whole in order to ascertain the
true meaning of its several clauses and the words of each clause
should be interpreted so as to bring them into harmony with the
other provisions if that interpretation does no violence to the
meaning of which they are naturally susceptible. [The North
Eastern Railway Company vs. Lord Hastings, (1900) AC 260].
46.In the instant case also, Clauses 2.7 and 3.4 of the BoQ cannot be read
in isolation and have to be read along with other provisions of the
Contract. In the instant case, Clause 2.7 forms part of main Clause 2
which has the following heading-“SURFACE EXCAVATION AND
BACKFILL-Surface excavation including loading, transport, all lift and
lead up to 3.0 km from the excavation area/working site, unloading at
disposal site or stockpiles and maintenance of the disposal sites or
stockpiles, construction of haul roads (if any) and its maintenance,
complete in all respects…”. The various works under the heading of
SURFACE EXCAVATION AND BACKFILL are mentioned as
separate items under clauses 2.1 to 2.8.7. This essentially means that
these items and rates are pertaining to clearing to surface excavation
areas, excavation of soil, excavation of soft rock, excavation of hard
rock, drilling and blasting, loading and transport of excavated material
to upto initial lead of 3 km, handling excavated materials for extra lead
beyond 3 km, backfilling and backfilling with concrete. A close reading
of Clause 2 and its various sub-clauses from 2.1 to of the BoQ clearly
indicates that all the items mentioned therein are with regard to material
excavated at the project site in the course of surface excavation. Clause
2.6 therefore pertains to loading, transport including all lift and lead
upto 3.0 km and unloading of materials excavated at the project site
from the surface. Similarly Clause 2.7 pertains to handling of materials
for extra lead beyond initial lead of 3,.0 km of the materials excavated
at the project site from the surface.
47.Clause 2.1 of the contract document namely “Particular Technical
Specifications”, Vol. 2, Part II broadly defines the scope of the work of
“SURFACE
EXCAVATION
AND
BACKFILL”
as
“The
Specifications described herein cover the surface excavation and
backfilling in and around structures, buildings, pipes, foundations,
trenches, pits, channel, cable ducts, underground facilities & similar
works and shall include all labour materials, plant and equipment
necessary to carry out the excavation in all materials, the transportation
and stockpiling or disposal of all excavated material into stockpiles or
disposal areas including all leads and lifts as shown on the drawings or
as approved by the Engineer-in-Charge.” Clause 2.15 of the aforesaid
contract document provides for mode and manner of disposal of
excavated materials from surface excavation as follows:
“2.15. Disposal of Excavated Materials
i) All materials from surface excavation suitable for use as
backfill, concrete aggregates or for other purposes shall be
stockpiled on the site within a radius of 3.0 km, as directed or
approved by the Engineer-in-Charge, if the immediate placement
in the final location in permanent works is not possible.
ii) Excavated materials which is not suitable for or is in excess of
the permanent construction requirements, shall be disposed of
within a radius of 3.0 km from the excavation place in the waste
disposal areas shown on the drawings or in areas designated as
such by the Engineer-in-Charge in the course of the work.
iii)…..
iv)…..
v) ….
vi) …
vi)…..
48.Clause 2.17.2(vii) provides for extra payment for handling of excavated
material from surface excavation beyond initial lead of 3.0 km and
provides as follows:
“Extra payment will be made for handling the excavated material
beyond 3.0 km. Payment for handling of excavated material will
be made at the Unit Price per cubic meter per km and the same
will be applicable for all leads beyond initial 3.0 km.
Measurement will be based on the hauled volume. The volume of
the material will be measured during hauling operations by
counting the number of return truck loads and will be calculated
by applying the following bulk factor……..”
49.Clause 3.4 of the BoQ which provides for “Handling Excavated
Materials for extra lead beyond initial lead of 3.0 km” at the rate of Rs.
198 per Cubic Mtr/Km, forms part of the main Clause 3 which has the
following heading-“UNDERGROUND EXCAVATION-Underground
excavation of Head Race Tunnel and Construction Adit including
excavation by drill and blast, mechanical, manual or conventional
methods; including all survey and setting out, all lifts and transportation
and unloading at disposal sites upto 3.0 km from the nearest portal and
including maintenance of the disposal sites. Stockpiles, construction of
haul roads (if any) and its maintenance, complete in all respects ….”.
Similarly, a closer scrutiny of Clause 3 and its various sub-clauses from
3.1 to 3.7 of the BoQ clearly shows that all the items mentioned therein
are with regard to material excavated at the project site in the course of
underground excavation. Clause 3.4 therefore pertains to loading,
transport including all lift and lead upto 3.0 km and unloading of
materials excavated at the project site by way of underground
excavation. Similarly Clause 3.4 pertains to handling of materials for
extra lead beyond initial lead of 3.0 km of the materials excavated at the
project site by way of underground excavation.
50.Clause 3.1 of “Particular Technical Specifications”, Vol. 2, Part II
outlines the scope of the work of “UNDERGOUND EXCAVATION”
as, “This chapter covers all excavation work for underground structures
to be carried out by the Contractor under this contract and shall include
all labour, materials, plant and equipment, all survey and setting out, all
excavation, loading, transportation and disposal of materials to disposal
or stockpile areas as well as the cleaning of excavated surfaces.” Clause
3.10.1(iv) provides for extra payment for handling of excavated
material from underground excavation beyond initial lead of 3.0 km and
provides as follows:
“Extra payment will be made for handling the excavated
material beyond 3.0 km from the portal/working site as
applicable. Payment for handling of excavated material will be
made at the Unit Price per cubic meter per km and the same will
be applicable for all leads beyond initial 3.0 km. Measurement
will be based on the hauled volume. The volume of the material
will be measured during hauling operations by counting the
number of return truck loads and will be calculated by applying
the following bulk factors….”
51.A reading of the contract document as a whole including Clauses 2.7
and 3.4 of the BoQ leaves no room for doubt that the item “Handling
Excavated Materials for extra lead beyond initial lead of 3.0 km” at the
rate of Rs. 198 per Cubic Mtr/Km as mentioned in Clauses 2.7 and 3.4
of the BoQ pertains to handling of excavated materials excavated
from the work site by way of surface excavation or underground
excavation for the purpose of its disposal in the waste disposal areas, if
such waste disposal areas are beyond the initial lead of 3.0 km. As
Clause 2.6 and 3.3 of the BoQ make it amply clear, the originally
envisaged position in the contract is that such excavated material will
be disposed of within the initial lead of radius of 3.0 km from the
working site/portal at the rate of Rs. 495 per Cubic Metre (Surface
excavation) and Rs. 7920 (underground excavation). However, any
unforeseen eventuality has been taken care of by Clauses 2.7 and 3.4
that in case such waste disposal is not possible within the initial lead of
radius of 3.0 km from the working site/portal, extra payment would be
made at the rate of Rs. 198 per Cubic Mtr for every extra km. Thus, a
reading of Clause 2.7 and 3.4 along with the contract document as a
whole makes it abundantly clear that Clauses 2.7 and 3.4 pertain to
handling of outbound excavated material which have been excavated
from the project site by way of either surface excavation or
underground excavation for its disposal in the designated waste disposal
areas. Thus, it is abundantly clear, and leaves absolutely no room for
doubt that the work “handling Excavated Materials for extra lead
beyond initial lead of 3.0 km” at the rate of Rs. 198 per Cubic Mtr/Km
as mentioned in Clauses 2.7 and 3.4 of the BoQ is not the same, similar
or identical work as “extra lead for transportation of sand and
boulder from Government approved quarries to work sites” which
apparently is handling of inbound construction material like sand,
shingles and boulders from the government approved quarries located at
a distance of 78 km from the project site of Package-I, 53 km from the
project site of Package-II and 36.50 km from the project site of
Package-III. As this is our categorical conclusion that the work
“Handling Excavated Materials for extra lead beyond initial lead of 3.0
km” at the rate of Rs. 198 per Cubic Mtr/Km as mentioned in Clauses
2.7 and 3.4 of the BoQ is not the work “same” as the work “extra lead
for transportation of sand and boulder from Government approved
quarries to work sites”, there is absolutely no scope for invoking Clause
33(ii)(a) of the Conditions of Contract. Clause 33(ii)(a) can be invoked
only when the work executed is the “same” as the one provided in the
BoQ. This is apparent from the very wording of Clause 33(ii)(a) which
states that, “The rates already provided in the Bill of Quantities and as
per the procedure mentioned above under sub-clause 33 of this part
shall apply in respect of the same item(s) of work to be executed due
to variations”. The necessary corollary of the above is that since the
item is not the same as mentioned in BoQ, the rate cannot be
determined in terms of Clause 33(ii)(a) and hence the rates have to be
determined in terms of Clause 33(iii) of the Conditions of Contract.
Clause 33(iii) specifically provides that “If the rates for such items of
work cannot be determined in the manner as specified in Clause
33(ii), the rates for such items to be executed shall be determined by
the Engineer-in-Charge on the basis of actual analysed cost taking
the following into consideration the rates for such items of works as
are required to be executed due to deviations as stated in sub-clause
shall be payable in the manner as stated hereunder…..”. We are of the
firm view that this is the only possible interpretation of Clauses 2.7 and
3.4 of the BoQ and Clauses 32(ii)(a) and 33(iii) of the Conditions of
Contract. No reasonable person would arrive at a different conclusion
while interpreting Clauses 2.7 and 3.4 of the BoQ and Clauses 32(ii)(a)
and 33(iii) of the Conditions of Contract. Any other interpretation of the
above clauses would definitely be irrational and in defiance of all logic.
52.The Arbitral Awards and the findings of the learned Arbitrator suffer
from the vice of perversity. The learned Arbitrator has taken into
account various factors irrelevant in coming to the decision and has
ignored vital clauses of the tender documents like Clause 2 and various
Sub-clauses i.e. Sub-clauses 2.1 to 2.8.7 under Clause 2 and Clause 3
and various Sub-Clauses i.e. Sub-clauses 3.1 to 3.7 under Clause 3 of
the BoQ, Clause 2 and various Sub-clauses i.e. Sub-clause 2.1 to 2.17.7
under Clause 2 and Clause 3 and various Sub-clauses i.e. Sub-clause 3.1
to 3.10.5 under Clause 3 of “Particular Technical Specifications”, Vol.
2, Part II. The learned Arbitrator has taken into consideration an
irrelevant fact that while making provisional payment, the initial lead of
3.0 km has been deducted and that this shows that Clause 2.7 and 3.4 of
the BoQ are applicable. The provisional payment was an interim
arrangement and was preceded by meetings dated 07.12.2012 and
08.12.2012 wherein it was specifically agreed between the parties that
HoP, NEEPCO would take steps for referring the dispute to arbitration
and that till the arbitral award, the payment would be made as per the
prevailing provisional rate without any escalation and that final rate
payable for transportation of sand and boulder shall be done on
implementation of the arbitral award. As such the fact that provisional
payment was made by deducting initial lead of 3.0 km was an irrelevant
fact for deciding the issue. The findings of the learned Arbitrator having
been arrived at by taking into account irrelevant factors and by ignoring
vital clauses, the same suffers from vice of irrationality and perversity.
It must be borne in mind that the Arbitral Awards in question are
Declaratory Arbitral Awards and involved interpretation of Clauses 2.7
and 3.4 of the BoQ and Clauses 32(ii)(a) and 33(iii) of the Conditions
of Contract and the learned arbitrator was required to interpret the same
in accordance with the established rules of interpretation. The findings
of the learned Additional Deputy Commissioner (Judicial), Shillong
while upholding the arbitral awards of the learned Arbitrator also suffer
from the similar vice. We are, therefore, of the considered view that that
the common order dated 27.04.2018 passed by the learned Additional
Deputy Commissioner (Judicial), Shillong in Arbitration Case No. 5 (T)
2016, Arbitration Case No. 6 (T) 2016 and Arbitration Case No. 7 (T)
2016 as well as the 3 (three) Arbitral Awards dated 29.03.2016 passed
by the learned Arbitrator warrant interference in these appeals under
Sec. 37 of the Arbitration and Conciliation Act, 1996.
53.There are additional reasons for interfering with order dated 27.04.2018
passed by the learned Additional Deputy Commissioner (Judicial),
Shillong and the Arbitral Awards dated 29.03.2016 passed by the
learned Arbitrator. As the learned counsel for the appellant has
submitted, the potential effect of the Arbitral Award on public
exchequer is that the appellant, which is a public sector undertaking,
will have to pay a sum of about Rs. 3.56 Lakh for every truckload of 10
cubic metre of sand or boulder (travelling for 100 km) and the total
potential effect would be about Rs. 1,000 Crore. We are of the
considered view that payment of Rs. 3.56 Lakh per truck (10 Cubic
Metre) of sand or boulder (100 km distance) is definitely a case of
unjust enrichment which is contrary to the Fundamental Policy of
Indian Law. Unjust enrichment being contrary to the Fundamental
Policy of Indian Law is a ground for interference with an Arbitral
Award under Sec. 34(2) of the Act. The Bombay High Court in
Angerlehner Structural and Civil Engineering co. vs. Municipal
Corporation
of
Greater
Mumbai,
MANU/MH/0554/2017
has
recognized unjust enrichment of a party at the cost of public exchequer
as being against the fundamental policy of Indian law. The Bombay
High Court has held:
“If the argument of the Contractors is accepted, it lead to them
blatantly enriching themselves over and above what they are
entitled. Such completely unjust enrichment, that too at the cost
of public funds, is abhorrent under the fundamental policy of
Indian Law. The award in AJECT, which permits such blatant
enrichment is therefore is also vitiated on the ground that it is
against the fundamental policy of Indian Law.”
We are also of the considered view that the Arbitral Award which
would potentially result in unjust enrichment of the respondent to the
extent of about Rs. 1,000 Crores is against the fundamental policy of
Indian law and, therefore, warrant interference on this count as well.
Though this court is not sitting in appeal over the award of the
arbitral tribunal, the presence of grounds under Section 34[2] of the Act
and the satisfaction arrived at by this Court in this regard, warrants
interference more so, as the Arbitral Awards in question are Declaratory
Arbitral Awards and involved interpretation of Clauses 2.7 and 3.4 of
the BoQ and Clauses 32(ii)(a) and 33(iii) of the Conditions of Contract
and the learned arbitrator was required to interpret the same in
accordance with the established rules of interpretation and in line with
the fundamental policy of Indian law.
54.The result of the above is that the common order dated 27.04.2018
passed by the learned Additional Deputy Commissioner (Judicial),
Shillong in Arbitration Case No. 5 (T) 2016, Arbitration Case No. 6 (T)
2016 and Arbitration Case No. 7 (T) 2016 as well as the 3 (three)
Arbitral Awards dated 29.03.2016 passed by the learned Arbitrator are
hereby set aside. Further, it is hereby declared that the rates for “extra
lead for transportation of sand and boulders from Government approved
quarries to the work site” shall be determined by the Engineer-inCharge in accordance with Clause 33(iii) of the Conditions of contract
in the manner as provided therein.
No order as to costs.
(H.S. Thangkhiew)
Judge
(Mohammad Yaqoob Mir)
Chief Justice
Meghalaya
D.Thabah, PS
26.02.2019
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review