Free legal tools
RERA interest calculator
The interest a builder owes you under section 18 of the RERA Act when the flat is late: on a full refund, or for every month you wait. Enter each payment you made with its date.
Read against the Act and State rules on 15 November 2026.
Interest the builder owes
What the law gives you
Section 18(1) of the Real Estate (Regulation and Development) Act, 2016: if the builder fails to give possession as the agreement for sale says, you may
- leave the project and get back every amount you paid, with interest at the prescribed rate, and compensation; or
- stay and get interest for every month of delay until possession is handed over, at the prescribed rate.
The Supreme Court held in Newtech Promoters and Developers v. State of Uttar Pradesh (2021) that the right to a refund on delay is unconditional. The rate is the same both ways: you pay the builder the same interest on a late instalment (section 2(za)).
The prescribed rate
Each State's RERA rules prescribe it. Most say the State Bank of India's highest marginal cost of lending rate plus 2% (for example rule 18 of the Maharashtra rules, and rule 15 in the rules of Delhi, Chandigarh and Haryana). Authorities apply it as simple interest at the rate on the date of their order, so the figure here moves when SBI changes its MCLR.
Compensation is separate
Compensation for loss, harassment and the cost of the case is decided by the adjudicating officer under section 71. It is not in this calculator. You can also go to the consumer commission instead of RERA; see complaint against a builder.
Questions people ask
What interest does RERA give for a delayed flat?
Section 18 of the RERA Act gives interest at the rate the State rules prescribe. Most States prescribe the State Bank of India's highest marginal cost of lending rate (MCLR) plus 2%. If you stay in the project it runs for every month of delay until possession; if you leave, it runs on each payment from the day you paid until the refund.
Refund or stay: which should I ask for?
If possession is not given as agreed, you can choose. The Supreme Court held in Newtech Promoters (2021) that the right to a refund is unconditional. Staying keeps the flat and gives delay interest; leaving returns the money with interest and lets you claim compensation from the adjudicating officer.
Which date does the delay interest run from?
From the date of possession promised in the agreement for sale (or the extended date the authority accepts), until the builder actually offers possession with an occupancy or completion certificate.
Do I also pay the same interest if I am late with an instalment?
Yes. Section 2(za) of the Act makes the rate the same both ways: what the builder pays you for delay and what you pay the builder for a late instalment.
Where do I file?
With the Real Estate Regulatory Authority of your State or UT. See how to file a RERA complaint and the notice to a builder for late possession.
What this calculator follows
- Real Estate (Regulation and Development) Act, 2016, sections 2(za), 18 and 71
- State RERA rules on the rate of interest, e.g. Maharashtra rule 18; rule 15 in the Delhi, Chandigarh and Haryana rules
- Newtech Promoters and Developers Pvt. Ltd. v. State of Uttar Pradesh, Supreme Court, 2021
- State Bank of India, MCLR effective 15 November 2026 (three years: 8.95%)
- How to file a RERA complaint
Read on 15 November 2026. This is an estimate to help you prepare, not legal advice; the tribunal, authority or court decides the figure on the facts it finds. Nothing you type is saved or sent anywhere.