IN THE HIGH COURT OF MADHYA PRADESH
AT JABALPUR
BEFORE
HON'BLE SHRI JUSTICE GURPAL SINGH AHLUWALIA
ON THE 12th OF JANUARY, 2024
WRIT PETITION No. 1082 of 2024
BETWEEN:V.M. UPADHYAY S/O AN UPADHYAY, AGED
ABOUT 70 YEARS, OCCUPATION: RETIRED ADDCL -4 SAGAR PREMIUM TOWERS DAM KHEDA
KOLAR ROAD BHOPAL (MADHYA PRADESH)
.....PETITIONER
(BY SHRI MANOJ KUMAR SHARMA – SENIOR ADVOCATE WITH SHRI
QUAZI FAKHRUDDIN - ADVOCATE)
AND
1.
MUNICIPALCORPORATION
BHOPAL
THROUGH ITS COMMISSIONER ADD
MUKHYALAYA
BHAVAN
ANUGYA
SHAHPURA BHOPAL (MADHYA PRADESH)
2.
THE ASSISTANT ENGINEER MUNICIPAL
CORPORATION BHOPAL MUKHYALAYA
BHAVAN ANUGYA SHAHPURA BHOPAL
(MADHYA PRADESH)
3.
STATE OF M.P. THROUGH THE ENGINEER
IN
CHIEF
WATER
RESOURCES
DEPARTMENT JAL SANSADHAN BHAWAN
BHOPAL (MADHYA PRADESH)
.....RESPONDENTS
(BY SHRI GAJENDRA PARASHAR – PANEL LAWYER)
This petition coming on for admission this day, the court passed
the following:
ORDER
1. This petition under Article 226 of Constitution of India has been filed
against the order dated 23.12.2023 passed by the Assistant Engineer,
Municipal Corporation, Bhopal, by which the petitioner has been
directed to remove his construction falling within the area of 33 meters
from the river, failing which action shall be taken for removal of the
construction. It has also been mentioned that petitioner has constructed
Sagar Premium Tower, Block C-1, and area approximately 1055
square meter on the ground floor and area approximately 6352 square
meter up to the seventh floor is coming under the encroachment zone
and, therefore, the same is to be removed.
2. It is submitted by counsel for petitioner that before issuing such an
order no opportunity of hearing was given to the petitioner. It is further
submitted that a coordinate Bench of this Court by order dated
22.09.2023 passed in the cases of Avdesh Agrawal Vs. Municipal
Corporation and others and Vinit Ajmani Vs. Municipal
Corporation and others in W.P. No.24093/2023 and W.P.
No.24059/2023 have issued notices and have also stayed the
demolition of the alleged construction.
3. It is further submitted that a complaint was pending before the National
Green Tribunal, Bhopal Bench (hereinafter referred to as ‘the NGT’)
and a stand was taken by the respondents that with a permission of
respondents certain constructions have been raised and accordingly, the
NGT had accepted that report and had directed to take action only in
respect of 172 constructions. It is submitted that in fact the order under
challenge is nothing but it is an eyewash because the respondents have
to file their reply before the NGT by 15.01.2024 and in order to save
the skin, they are issuing such notices. It is further submitted that
petitioner’s right under Article 300-A of the Constitution of India
cannot be taken away without even giving an opportunity of hearing. It
is further submitted that earlier the stand of the State Government was
that the area of 33 meters shall be measured from the banks of the river
and now the Principal Secretary, Urban Development and Housing, has
taken a somersault and has filed an affidavit before the NGT stating
that for the purpose of determining 33 meters, the respondents
authorities are taking distance on the basis of revenue record and if any
encroachment or illegal construction is found within the said distance
which is to be maintained as open land and green belt, then the same
shall be demolished and removed in accordance with law.
4. Heard learned counsel for the parties.
5. The petitioner has filed a copy of the order dated 19.07.2021 passed by
the NGT in the case Dr. Subhash Chandra Pandey Vs. Chief
Secretary, State of M.P. reported in 2021 SCC Online NGT 2037.
Para 16 to 21 of the said order reads as under:
“16. We would find from the above that the State has
accepted the fact that the 33 mtrs. area from the flood plain
of the river has to be a No Construction Zone and developed
as a green belt area. The State has committed itself that the
same shall be implemented immediately and any
construction in the same would be stopped.
17. We have also noted from the above that the State has
categorically taken a stand that a joint inspection was
carried out from 16th July, 2014 at the instance of various
officials including those of the Town & Country Planning
Department, the Municipal Council, Kolar and the Revenue
officials to verify "the actual ground position pertaining to
the violation of the development permission and
construction activities". After carrying out the aforesaid
inspection the persons who prima facie admitted to be in
violation of the above norms were issued notices copies of
which have been filed before us by way of Annexure-RR/2
as a specimen. We have noted the fact that the period given
in the notice has elapsed and we would, therefore, now
expect from the Respondent/State and the authorities who
have issued notices, to complete the task of considering the
replies, if any, and hearing the parties concerned and pass
necessary orders in accordance with law within four weeks
from today. For the aforesaid purposes if necessary the dates
of hearing may be preponed by issuing fresh notices to the
concerned parties so as to complete this task within a period
of four weeks. Wherever the 33 Mtrs. No Construction Zone
has been found to have been violated steps for removing
such constructions shall be ordered to be taken by the party
violating the norms which shall also ensure removal of all
debris and also in case the said party fails to take these
aforesaid steps, the State shall be at liberty to remove such
constructions and recover costs from the violators.
18. It is further directed that apart from the removal of such
constructions raised within the 33 Mtrs. No Construction
Area as has been indicated in the superimposed satellite
images which have been filed at Annexure RR-3 along with
the said M.A. No. 347/2014 wherein by blue line indicates
the course of river and green line along with the same to be
within the 33 mtrs. limit for developing green belt. As prima
facie found by the State officials the said 33 mtrs. area shall
be developed by carrying out extensive plantation work as a
green belt along with the course of the river Kaliasot. Apart
from this, the State shall put permanent boundary pillars for
indicating the 33 mtrs. zone to the extent they have given in
these satellite images which have been filed and further
along the course of the river beyond the point which has not
been included in the satellite images which have been filed
before us which shall be maintained as No Construction
Zone and developed as a green belt. We may clarify here
that the task of identifying the area and the No Construction
Zone will not be restricted only in the case of persons to
whom notices have been issued post the inspection carried
out by the Respondent agencies and departments or the ones
enumerated by the Applicant but shall be a continuous
process and shall be carried out throughout the course of the
river on both sides.
19. The aforesaid task shall be carried out independently
and shall be completed within a period of three months from
the date of this order by the Respondents. We may only add
that the State has submitted before us that in many cases
such permissions along the course of the river have been
granted by the Village Panchayats where the Bhopal
Development Plan framed by the Town & Country Planning
is not applicable.
20. Be that as it may. The State and more particularly the
Panchayati Raj Department shall through the Chief
Secretary/Respondent No. 1 issue necessary orders to the
local authorities along such river bodies and river course to
ensure that at all times 33 Mtrs. area is maintained and the
green belts along the river course are raised by all the local
bodies including the Village Panchayats which shall ensure
planting, protection and survival of the trees and if
necessary assistance of the Forest Department, Govt. of
Madhya Pradesh shall be provided.
21. We may also note that the development of the green belt
along with river Kaliasot on both sides to the extent of 33
mtrs. area shall be carried out within this season of monsoon
2014 and shall be completed and report submitted before
this Tribunal within three months”.
6. From the aforesaid order, it is clear that the NGT had given a specific
direction that the authority shall ensure that all the times, 33 meters
area is maintained and the green belts are developed around the river
bodies and river course by planting, protection and survival of the trees
and, if necessary, assistance of the Forest Department, Govt. of M.P.
shall be provided.
It has also been directed that development of the
green belt along with river Kaliasote on both sides to the extent of 33
meters area shall be carried out within the season of monsoon, 2014
and shall be completed and report be submitted before the Tribunal
within 3 months. Thereafter, it appears that an execution application
was filed before the NGT which has been registered as Execution
Application No.1/2023 (CZ).
7. According to the petitioner, the grievance of the complainant is that in
spite of the order passed by the NGT in O.A.No.135/2014, the same is
not being executed. Thus, it is clear that the execution proceeding is
pending before the NGT with regard to 33 meters of area on both sides
of the river course of Kaliasote. As per order dated 11.8.2023 passed
by the NGT, it is clear that Principal Secretary, Urban Development
and Housing, has made a specific statement before the NGT that for
the purpose of determining 33 meters, respondent authorities are taking
distance on the basis of revenue record and if any encroachment or
illegal construction is found within the said distance, which is to be
maintained as open land and green belt, the same shall be demolished
and removed in accordance with law.
8. Whether a Principal Secretary has taken a somersault or not; whether
the method of determining area of 33 meters of both sides of river
course of river Kaliasote on the basis of revenue record is correct or
not; and, whether construction raised by the petitioner is situated
within the area of 33 meters or not; are the questions which can be
decided by the NGT only.
9. The petitioner can always file his objection to the execution
proceedings pointing out that his construction does not fall within the
area of 33 meters. It is for the NGT to decide as to whether area of 33
meters is to be measured from the natural course of river Kaliasote or
is to be determined on the basis of revenue records.
10. The matter is primarily related to the environment. Section 14 of
National Green Tribunal Act gives jurisdiction over all civil cases to
the Tribunal where a substantial question relating to environment
(including enforcement of any legal right relating to environment), is
involved and such question arises out of the implementation of the
enactments specified in schedule I and it is for the Tribunal to hear the
disputes arising from the questions referred to in sub section (1) of
section 14 and it is for the Tribunal to settle such disputes and pass
order thereon. The appeal against the order passed by the Tribunal lies
to the Supreme Court. Section 29 of the N.G.T. Act 2010 provides that
from the date of establishment of the Tribunal, no civil court shall have
jurisdiction to entertain any appeal in respect of any matter, which the
Tribunal is empowered to determine under its appellate jurisdiction.
11. Thus, this Court is of the considered opinion that the question raised by
the petitioner in the present petition lies within the exclusive
jurisdiction of the NGT and the High Court does not have any
jurisdiction to decide the objections raised by the petitioner.
12. It was submitted by counsel for the petitioner that the present petition
has been filed against the order passed by the Assistant Engineer,
Municipal Corporation, Bhopal, therefore, this Court has jurisdiction to
entertain this writ petition.
13. Considered the submissions made by counsel for the petitioner.
14. The State has to act through its multiple functionaries. The name of
the authority who has issued the impugned order is not material to
adjudicate as to whether this Court has jurisdiction to entertain this
petition or not; but, the material aspect is as to whether the subject
matter and the dispute in question lies within the jurisdiction of this
Court or not ?
15. As already pointed out, the impugned order has been issued in the light
of pendency of execution proceedings before the NGT who had
already directed the authorities to develop a green belt on an area of 33
meters on both sides of the course of river of Kaliasote and if any
encroachment is found then it has to be removed in the light of order
dated 11.8.2023 passed in execution application No.1/23(CZ).
Accordingly, this Court is of the considered opinion that this petition is
not maintainable as this Court has no jurisdiction to entertain the
dispute involved in the present case.
16. It is accordingly dismissed.
However, liberty is granted to the
petitioner that if so advised, then he can approach the National Green
Tribunal for redressal of his grievance.
(G.S. AHLUWALIA)
JUDGE
HEMANT SARAF
2024.01.12 18:56:04
+05'30'
HS
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review