Judgments
LegalFirms.in Judgments · legalfirms.in/judgments/manoharlal-vs-the-state-of-madhya-pradesh-20240123/ · Printed 19 Nov 2026
Constitutional

Manoharlal vs The State of Madhya Pradesh

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Madhya Pradesh High Court
Date
23 January 2024
Case No.
WP 28930/2021
Result
Disposed
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

16. In view of the above, the Writ Petition allowed the impugned order dated 17.12.2021 passed by respondent No.4 & 5 is quashed. The petitioners shall be at liberty to claim compensation from the State for illegal demolition in the civil suit. But at this stage, the cost of Rs. 25,000.00 is liable to be paid to the petitioners by the State. The Collector-Dhar shall be at liberty to recover this cost from Shri Bonder Singh Kalesh the Sub Divisional Officer (Revenue) Sardarpur DistrictDhar who passed the order dated 17.12.2021 after conducting an enquiry as directed above.

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

-1- IN THE HIGH COURT OF MADHYA PRADESH AT I N D O R E BEFORE HON'BLE SHRI JUSTICE VIVEK RUSIA ON THE 23rd OF JANUARY, 2024 WRIT PETITION No. 28930 of 2021 BETWEEN:MANOHAR LAL S/O VENI RAM JAIN, AGED ABOUT 87 YEARS, 1. OCCUPATION: BUSINESS, R/O 47 TILAK MARG WARD NO. 10 TEH. SARDARPUR (MADHYA PRADESH) MANOJ KUMAR S/O MANOHARLAL JAIN, AGED ABOUT 60 YEARS, 2. OCCUPATION: BUSINESS 47 TILAK MARG WARD NO. 10, RAJGARH (MADHYA PRADESH) .....PETITIONERS (BY SHRI ROHIT KUMAR MANGAL, ADVOCATE.) AND THE STATE OF MADHYA PRADESH THROUGH PRINCIPAL 1. SECRETARY, REVENUE DEPARTMENT, MANTRALAYA, VALLABH BHAWAN, BHOPAL (MADHYA PRADESH) 2. COMMISSIONER (REVENUE) INDORE DIVISION, MOTI BUNGALOW, M.G. ROAD, INDORE (MADHYA PRADESH) 3. COLLECTOR DHAR, DISTRICT DHAR (MADHYA PRADESH) 4. SUB DIVISIONAL OFFICER (REVENUE) SARDARPUR, DISTRICT DHAR (MADHYA PRADESH) 5. BONDERSINGH KALESH OCCUPATION: SUB DIVISIONAL OFFICER (REVENUE) SARDARPUR, DISTRICT DHAR (MADHYA PRADESH) 6. MUNICIPAL COUNCIL RAJGARH, TEHSIL SARDARPUR, DISTRICT DHAR (MADHYA PRADESH) .....RESPONDENTS (BY SHRI RAJWARDHAN GAWDE, GOVERNMENT ADVOCATE FOR THE STATE. SHRI KOUSTUBH PATHAK, ADVOCATE FOR THE RESPONDENT NO.1. BY SHRI DURGESH SHARMA, ADVOCATE FOR THE RESPONDENT NO.6.) -------------------------------------------------------------------------------------------------------- This petition coming on for orders this day, the court passed the following: Signed by: DIVYANSH SHUKLA Signing time: 25-01-2024 17:13:01 -2- ORDER 01. The petitioners have filed the present petition challenging the order dated 18.12.2021 passed by respondent No.4&5 under section 248 of M.P. Land Revenue Code, 1959 (hereinafter referred to as the “Code”). According to the petitioners, they owned an ancestral house No.47, Tilak Marg, Ward No.10, Municipal Council, Rajgarh, Tehsil Sardarpur, District Dhar. It was 100 years old and a dilapidated condition, therefore, a notice was issued by the Municipal Council for demolition of the old construction. 02. The petitioners applied for the construction of shops and residences and that was granted on 04.01.2021 by Council. Thereafter they started the construction of a building strictly in accordance with the sanction map and completed it in the month of November 2021. 03. respondent No.4&5 issued a notice to petitioners on 29.11.2021 alleging that the construction is made on a Government land bearing survey No.574 which is recorded as the road in the revenue record, therefore, such illegal construction is liable to be removed. The petitioners submitted an explanation that the entire construction was raised as per the building permission granted by the Municipal Council and there is no encroachment on any side of the road. According to the petitioner, the copies of R.I. report were not supplied to them, and the final order was passed on 18.12.2021 and communicated on 20.12.2021 for demolishing the building. The petitioners approach this court to protect the building from demolition by respondent No.4&5 is petition before this Court. 04. Before filing this petition, the petitioner has already approached the civil Court seeking a decree of declaration of title and permanent injunction. According to the petitioner, the learned civil Court granted the order of status quo dated 20.12.2021 and despite that Signed by: DIVYANSH SHUKLA Signing time: 25-01-2024 17:13:01 -3- the respondents have dismantled some portion of the building. Now, the petitioner is challenging the final order passed in pursuant to the showcause notice which is the subject matter of civil Court. The petitioner is challenging the order passed by respondent No.4&5 under Section 248 of the Code on the ground that the Sub-Divisional Officer is not a competent authority to pass an order under Section 248 of the Code. according to the petitioners proper demarcation was not carried out before passing the impugned order and no proper opportunity of a hearing was given to the petitioner in a hasty manner without there being any urgency in the matter, hence, the entire action is bad in law. 05. After notice, the respondents No. 1 to 4 have filed the reply by submitting that the land bearing survey No.572 area of 1.986 hectares and survey No.574.387 is recorded in the name of the Government. Survey No.572 is Aabadi land on which plot No.47 is situated and survey No.574.387 is a Government road adjacent to the plot No.47. The petitioner while raising the construction encroached on some part of the survey No.574, therefore, the SDO has rightly initiated action being a Nazul Officer. The Writ Petition is not maintainable as the petitioner has already filed a civil suit before the Civil Judge, Senior Division, Sardapur which is pending as RCSA-112/2021. 06. Along with the reply, the respondents have filed a copy of the order dated 17.12.2021 passed under Section 248 of MPLRC whereas the petitioners have filed the same order but dated 18.12.2021. According to the petitioners, this order has been filed by the Municipal Council in a civil suit and they obtained the certified copy of the same, therefore, the respondents have prepared the forged order dated 17.12.2021 to justify their illegal action. 07. Vide order dated 09.01.2024, this Court has directed the respondents 1 to 4 to produce the original record of Case No.01/A- Signed by: DIVYANSH SHUKLA Signing time: 25-01-2024 17:13:01 -4- 68/2021-22. Today, the record is produced in which the original copy of the order dated 17.12.2021 is available on record which is filed as Annexure R/2 in this petition apart from that there are order sheets also which reveal that the final was passed on 17.12.2021 section 248 of the Code. 08. On 18.12.2021, a copy of the order dated 17.12.2021 was forwarded to the Tehsildar, Executive Magistrate, CMO, Nagar Parishad, Rajgah, etc. Since the copy of the order dated 18.12.2021 as claimed by the petitioner is filed in civil Court, therefore, the civil Court shall examine this issue whether the order dated 18.12.2021 is a manipulated or forged order or the order dated 17.12.2021 is an original order which available in the original file. 09. In the civil Court this issue can be decided that the petitioners have raised the construction strictly on the permission granted by the Council on plot No.47, the issue of encroachment is also a disputed question of fact which is liable to be decided by way of evidence. This Court cannot record the finding that the petitioner has not encroached on the Government land, therefore, the civil Court is a competent Court to decide this controversy between the parties. In case of illegal demolition also, the petitioner is liable to quantify the loss and can claim before the civil Court. 10. But this court can certainly examine the conduct and manner in which respondent No.4&5 proceeded in this matter. The order sheet reveals that the respondent No.4&5 registered a case on 27.11.2021, issued notice to the petitioners for appearance on 30.11.2021 and thereafter, proceeded ex-parte on 08.12.2021. So far the service of notice to petitioner No.2 is concerned, the report was submitted that he has refused to take the notice and the Sub Divisional Officer has proceeded ex-parte but there is no report in respect of service of notice Signed by: DIVYANSH SHUKLA Signing time: 25-01-2024 17:13:01 -5- to petitioner No.1 who is a joint owner of this property. 11. On the basis of the report submitted by respondent No.4&5 order of demolition was passed on 17.12.2021 and the next day copy of the order was sent to the Tehsildar, Executive Magistrate, Police and CMO for demolition of the building constructed by the petitioners. Thereafter on 21.12.2021, a report has been submitted that a part of the building has been demolished. 12. In the matter of demolition, when there is no immediate threat to any life of any person from the building, the day to day proceeding ought not to be conducted. Sufficient opportunity should be given to the owner of the building to defend and if any adverse order is passed then avail the remedy of appeal available under the law. There was no hurry or urgency in this matter for the demolition of the building by conducting day-to-day proceedings. Within 10 days, the report was obtained, and the final order was passed and on the next day, the direction was issued to demolish. The malafide is apparent in the conduct of respondent No.4&5. 13. The petitioner was given the building permission by the Council and they started the construction which was completed at least a year during that period, no one raised any objection and when the building was completed, immediate proceedings were initiated without giving any proper opportunity of hearing to the owners and the demolition activities have been started. 14. In the original file there is a complaint submitted by one Ajay Vyas to respondent No.4 & 5 that Manohar Jain has illegally constructed a shopping complex. The said letter was entertained by respondent No.4&5 under Section 248 of the Code and within a month an order of demolition without recoding any evidence and proper opportunity of hearing and breathing time to the petitioner to contest this matter. Signed by: DIVYANSH SHUKLA Signing time: 25-01-2024 17:13:01 -6- Normally, these Revenue Authorities never proceed so quickly on an anonymous complaint, but in this case, it appears that due to some exterior considerations, such a quick action has been taken which is also liable to be enquired by the collector. 15. Admittedly Sub Divisional Officer is not the competent authority to exercise the power under section 248 of the Code as held by this court in the case of The State of M.P. Versus Uttam Chand reported in 2000(2) JLJ 143. The Tehsildar is competent to pass an order of eviction of the encroacher that too from the open agricultural land. 16. In view of the above, the Writ Petition allowed the impugned order dated 17.12.2021 passed by respondent No.4 & 5 is quashed. The petitioners shall be at liberty to claim compensation from the State for illegal demolition in the civil suit. But at this stage, the cost of Rs. 25,000.00 is liable to be paid to the petitioners by the State. The Collector-Dhar shall be at liberty to recover this cost from Shri Bonder Singh Kalesh the Sub Divisional Officer (Revenue) Sardarpur DistrictDhar who passed the order dated 17.12.2021 after conducting an enquiry as directed above. (VIVEK RUSIA) JUDGE Divyansh Signed by: DIVYANSH SHUKLA Signing time: 25-01-2024 17:13:01

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All MP HC judgments →
LegalFirms.in Directory
Find an advocate for this matter
Dealing with a similar case? Find an advocate who handles this kind of matter on LegalFirms.in.
Find an advocate →