IN
THE
HIGH COURT OF MADHYA PRADESH
AT JABALPUR
BEFORE
HON'BLE SHRI JUSTICE RAVI MALIMATH,
CHIEF JUSTICE
&
HON'BLE SHRI JUSTICE VISHAL MISHRA
ON THE 8th OF JANUARY, 2024
WRIT PETITION No. 2601 of 2023
BETWEEN:GANNON DUNKERLEY CO.LTD. THROUGH ITS AGM
LEGAL AND TAXATION OFFICER SHRI RAMESH
MISHRA S/O SHRI SURENDRA PRASAD MISHRA AGE
57YEARS R/O R81, JAISHRIDHAN COOPERATIVE
HOUSING SOCIETY, BANGUR NANAR, GOREGAON
WEST (MAHARASHTRA)
.....PETITIONER
(BY SHRI R.K. VERMA - SENIOR ADVOCATE WITH SHRI SAHIL
SONKUSALE - ADVOCATE)
AND
Signed by: LORETTA RAJ
Signing time: 1/12/2024
12:08:30 PM
1.
M.P. ROAD DEVELOPMENT CORPORATON LTD.,
THORUGH
ITS
CHAIRMAN/
MANAGING
DIRECTOR 45-A, ARERA HILLS, BHOPAL
(MADHYA PRADESH)
2.
CHIEF
ENGINEER
(ADB),
M.P.
ROAD
DEVELOPMENT
CORPORATION, 45-A ARERA
HILLS BHOPAL 462011 (MADHYA PRADESH)
3.
DIVISIONAL
MANAGER,
M.P.
ROAD
DEVELOPMENT
CORPORATION, CIVIL LINES,
JABALPUR (MADHYA PRADESH)
4.
MINISTRY OF ROAD TRANSPORT AND HIGHWAY
GOVT. OF INDIA, THROUGH ITS SECRETARY,
TR AN SPORT BHAWAN 1, PARLIAMENT, NEW
DELHI (DELHI)
5.
PUNJAB NATIONAL BANK, THROUGH ITS
M ANAGER LARGE CORPORATE BRANCH, 14TH
FLOOR, F-WING MAKER TOWER CUFFE PARADE
MUMBAI 400005 (MAHARASHTRA)
.....RESPONDENTS
(SHRI PRASHANT SINGH - ADVOCATE GENERAL WITH SHRI ANVESH
SHRIVASTAVA - ADVOCATE FOR RESPONDENTS NO.1 TO 3, SHRI
DEVASHISH SAKALKAR - ADVOCATE FOR INTERVENOR)
T h is petition coming on for orders this day, Hon'ble Shri Justice
Vishal Mishra passed the following:
ORDER
Heard on I.A. No. 13792 of 2023 : an application under Order 1 Rule 10
of the CPC seeking intervention in the writ petition on the ground that he is a
sub-contractor.
2.
There is no locus of the sub-contractor to intervene into the writ petition
on the ground that whatever dispute or claims he is raising is against the
petitioner and not the answering respondents. It is an interse settlement between
the petitioner and the intervenor. Therefore, the intervenor is having no locus to
intervene in this writ petition itself.
3.
Therefore I.A. No.13792 of 2023, being not maintainable as the intervenor
is having no locus to participate in the proceedings, is rejected.
4.
This petition has been filed seeking following reliefs "(i) Hon'ble Court may be pleased to quash and set aside the order of
recovery dated 24.01.2023 (Annexure P/1) passed by the respondent
No.2.
(ii) Hon'ble Court further be pleased to quash the recovery of sum of
Rs.85.42 crores imposed on the petitioner unilaterally and the
respondents be restrained from effecting any recoveries from the
petitioner through coercive means unless the dispute between the
parties is finally adjudicated by an independent authority/arbitrator.
(iii) Hon'ble Court be pleased to restrain the respondents from
effecting any recovery from the petitioner in pursuance to the
impugned order dated 24.01.2023 (Annexure P/1) from the bank
guarantee BG No.09020005619 dated 16.03.2019 for Rs.7,54,92,483/lying with the respondents or through any coercive means against the
petitioner unless the dispute between the parties is finally adjudicated
Signed by: LORETTA RAJ
Signing time: 1/12/2024
12:08:30 PM
by an independent authority/arbitrator.
(iv) Any other suitable relief deemed fit in the facts and circumstances
of the case may also kindly be granted together with the cost of this
petition. "
5.
It is the case of the petitioner that petitioner is a registered Public Ltd.
Company constituted under the Companies Act, 1956. The work of
rehabilitation and upgradation of Barela to Mandla Section of NH-12-A from the
existing kilometer 22/8 to 89/6 on Engineering, Procurement, Construct (EPC)
basis in accordance with the terms and conditions setforth in the contract NIT
was issued by respondent No.1 wherein the petitioner submitted the bid. The
petitioner's bid was accepted and a letter of acceptance dated 27.07.2015 was
issued. In terms of the LOA, a contract was also executed between the parties.
Cost of the work was Rs.251.64 crores and the time period for completion was
18 months. That vide letter dated 24.01.2023, it was informed that the petitioner
failed to perform contractual obligations despite sufficient opportunities being
granted and have committed material breach and default of the provisions of the
contract agreement and accordingly the contract agreement stood terminated
and a recovery is directed to be made from the petitioner. The same is put to
challenge by filing a writ petition on the ground that there is a procedure for in
house dispute resolution mechanism and the petitioner had invoked the same.
As the same is pending consideration without deciding the dispute raised by the
petitioner, no orders for recovery could have been passed. Placing reliance
upon the judgments passed by the Hon'ble Supreme Court in the case of Tulsi
Narayan Garg v. M.P. Road Development Authority : 2019 SCC Online SC
1158 the petitioner has filed the present petition.
6.
Initially, this court granted interim relief to the petitioner on 01.02.2023.
Thereafter, on an application I.A. No.2537 of 2023 seeking a direction to the
Signed by: LORETTA RAJ
Signing time: 1/12/2024
12:08:30 PM
respondents to remove the seal of the premises of the petitioner and to permit
the petitioner to remove the articles of his ownership as well as that of his subcontractors, an order dated 20.03.2023 was passed. The court has rejected the
application. But, on a concession given by the Advocate General that as there
are certain perishable items, the respondents may look into the same and may
release the same on terms and conditions. Another order dated 08.05.2023 was
passed considering various documents filed by the petitioner along with I.A.
No.6240 of 2023 and I.A. No.6289 of 2023 wherein it was observed that release
of the article will be done after calculating the market value as on the date of
possession and this exercise is to be completed after giving opportunity to the
petitioner to participate in the valuation process.
7.
Today, the matter has been listed for consideration on I.A. No.18709 of
2023, which is an application for seeking appropriate direction. The
respondents are seeking a direction that liberty be granted to remove/re-locate
the plant and machinery of the petitioner as the same has not been removed
despite directions given by this court as the petitioner has not deposited the
bank guarantee in terms of order dated 08.05.2023. The learned Advocate
General has pointed out that in house mechanism which was invoked by the
petitioner has been answered and an order has been passed by the authorities.
The learned Advocate General has also brought to the notice of this court a
letter dated 28.12.2023 which is a letter written by the petitioner-company to the
Divisional Manager, MPRDC Ltd. pointing out the fact that "we are not in a
financial position to furnish the bank guarantee". It is contended that the
petitioner himself has not complied with the directions issued in the court on
08.05.2023.
8.
Signed by: LORETTA RAJ
Signing time: 1/12/2024
12:08:30 PM
Now in terms of relevant clause in the agreement, the petitioner has to
invoke Clause 26.3 which deals with arbitration. Counsel appearing for the
petitioner could not dispute the fact that in the in house mechanism invoked by
the petitioner a final order has been passed. He fairly submits that he will be
invoking the Clause 26.3 which deals with arbitration. But as far as the order
dated 08.05.2023 is concerned the same stands not complied with by the
respondent/authorities as the petitioner has or not permitted to participate in the
valuation process.
9. The fact remains that these are contract matters. The scope of interference
in the contract matters is very limited. It is an admitted position that the contract
of the petitioner has been terminated. The recovery order was issued. The in
house mechanism invoked by the petitioner has been answered by the
authorities. Now the only remedy available to the petitioner is to invoke the
provisions of Clause 26.3 and to invoke the arbitration.
10.
The Hon'ble Supreme Court in the case of Tata Motors Limited v. Brihan
Mumbai Electric Supply & Transport Undertaking (BEST) and others : 2023
SCC OnLine SC 671has held as under :"48. This Court being the guardian of fundamental rights is dutybound to interfere when there is arbitrariness, irrationality, mala
fides and bias. However, this Court has cautioned time and again that
courts should exercise a lot of restraint while exercising their powers
of judicial review in contractual or commercial matters. This Court is
normally loathe to interfere in contractual matters unless a clear-cut
case of arbitrariness or mala fides or bias or irrationality is made out.
One must remember that today many public sector undertakings
compete with the private industry. The contracts entered into between
private parties are not subject to scrutiny under writ jurisdiction. No
doubt, the bodies which are State within the meaning of Article 12 of
the Constitution are bound to act fairly and are amenable to the writ
jurisdiction of superior courts but this discretionary power must be
exercised with a great deal of restraint and caution. The courts must
realise their limitations and the havoc which needless interference in
commercial matters can cause. In contracts involving technical issues
the courts should be even more reluctant because most of us in Judges'
Signed by: LORETTA RAJ
Signing time: 1/12/2024
12:08:30 PM
robes do not have the necessary expertise to adjudicate upon
technical issues beyond our domain. The courts should not use a
magnifying glass while scanning the tenders and make every small
mistake appear like a big blunder. In fact, the courts must give “fair
play in the joints” to the government and public sector undertakings
in matters of contract. Courts must also not interfere where such
interference will cause unnecessary loss to the public exchequer. (See:
Silppi Constructions Contractors v. Union of India, (2020) 16 SCC
489)."
11. Thus, considering the fact that this is a contract matter wherein the
contract agreement has been terminated and as provided in the agreement
Clause 26.3 deals with the dispute resolution mechanism, the petitioner may
invoke the same. In a petition under Article 226 of the Constitution of India
against the termination of contract and subsequent recovery, no relief can be
extended to the petitioner.
12. The petition sans merit and is accordingly dismissed. Petitioner is always
at liberty to invoke clause 26.3 of the agreement.
(RAVI MALIMATH)
CHIEF JUSTICE
LR
Signed by: LORETTA RAJ
Signing time: 1/12/2024
12:08:30 PM
(VISHAL MISHRA)
JUDGE
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review