Civil · Reportable judgment

Delhi Development Authority vs Tejpal & Ors.

Court
Supreme Court of India
Date
17 May 2024
Case No.
CIVIL APPEAL No. 6798/2024
Result
Disposed
Bench
Surya Kant, Dipankar Datta, Ujjal Bhuyan
Citation
[2024] 5 S.C.R. 1211 : 2024 INSC 456
Acts & Sections
Land Acquisition Act, 1894 Right to Fair Compensation and Transparency… Limitation Act, 1963 Constitution Supreme Court Rules, 2013
Supreme Court Reports [2024] 5 S.C.R. 1211 : 2024 INSC 456
Issue for consideration
Whether the appellants made out sufficient cause for condonation of delay on the grounds of subsequent change of law brought in by Indore Development Authority v. Shailendra [2018] 2 SCR 1 and Indore Development Authority v. Manoharlal [2020] 3 SCR 1, public interest and justice, COVID-19 pandemic, suppression of material facts by the landowners, leeway to be granted to government entities etc.
Headnote

Land Acquisition – Land Acquisition Act, 1894 – Right to Fair Compensation and Transparency in Land Acquisition Rehabilitation and Resettlement Act, 2013 – s.24(2) – Deemed lapse of land acquisition proceedings initiated under the 1894 Act, on non-payment of compensation or non-taking of possession – Interpretation – Change of law – Condonation of delay sought on the basis of such subsequent change of law – Limitation Act, 1963 – s.24(2) was interpreted in Pune Municipal Corporation v. Harak Chand Mistrimal Solanki [2014] 1 SCR 783 and Sree Balaji Nagar Residential Association v. State of Tamil Nadu [2014] 7 SCR 799 – Following Pune Municipal Corporation and Sree Balaji, the High Court allowed the landowners’ claim and declared the acquisition proceedings as lapsed on account of non-payment of compensation or non-taking of possession – However, eventually five-judge bench in Indore Development Authority v. Manoharlal [2020] 3 SCR 1 overruled Pune Municipal Corporation and Sree Balaji and Indore Development Authority v. Shailendra [2018] 2 SCR 1 – Present cases filed by the appellants before and after the decision in Shailendra as well as after the decision in Manoharlal in view of re-interpretation of s.24(2) of the 2013 Act therein, against various orders of the High Court whereby acquisition proceedings were declared to have lapsed in terms of s.24(2) – Delay in filing – Condonation of delay sought on the basis of subsequent change of law in view of the decisions in Shailendra and Manoharlal – Impermissibility: Held: In most of the present cases, the prescribed period of limitation had already expired long before the judgments in Shailendra and Manoharlal were delivered – Appellants let the limitation period lapse because they saw no case on merits for appeal – However, when the law was subsequently re-interpreted in Shailendra and Manoharlal, they approached this Court with the present matters – Instead of showing a sufficient cause arising within the period of limitation, the appellants are using an event after the expiry of such period to justify the delay – A party cannot be allowed to take advantage of its deliberate inaction during the limitation period – If subsequent change of law is allowed as a valid ground for condonation of delay, it would open a Pandora’s Box where all the cases that were subsequently overruled, or the cases that had relied on such cases, would approach this Court and would seek a relief based on the new interpretation of law – When a case is overruled, it is only its binding nature as a precedent that is taken away and the lis between the parties is still deemed to have been settled by the overruled case – When Manoharlal overruled Pune Municipal Corporation and Sree Balaji and other cases relying on them, it only overruled their precedential value, and did not reopen the lis between the parties – Therefore, the mere fact that the impugned orders in the present case were overruled by Manoharlal would not be a sufficient ground to argue that the cases should be reopened – Delay cannot be condoned based on subsequent change of law brought in by Shailendra and Manoharlal. [Paras 22, 25-27, 29]

Read the full headnote (7 more paragraphs)

Land Acquisition – Public interest – Right to Fair Compensation and Transparency in Land Acquisition Rehabilitation and Resettlement Act, 2013 – s.24(2) – Condonation of delay in filing appeals sought by the appellants-government entities on grounds of public interest – Public infrastructure projects such as hospitals, schools, expansion of metro, etc. built on a large number of acquired lands – Elements of public interest: Held: While balancing the interest of the public exchequer against that of individuals, there are many other interests at stake, and it might not be possible to undo the acquisitions without causing significant cascading harms and losses to public infrastructure – Effect of non-condonation of delay would go beyond mere financial loss to the exchequer, and instead extend to the public at large – There would be unscrambling the egg if compensation paid would have to be clawed back or possession taken would have to be reversed – In many cases, development projects might also have to be undone – Rights have been vested to the public at large, given the public infrastructure that has come up on a large number of these acquired lands especially, in cases where the possession was taken – When balancing public with private interest, the quantum and adequacy of compensation do not compel much – Hence, the comparative impact on the respondent-landowners would be minimal – Multiplicity of contradictory judicial opinions on s.24(2) of the 2013 Act made the present set of circumstances sui generis – The constant flux in the legal position of law created significant challenges for the appellants while approaching this Court – Impact of not condoning the delay, discussed – Larger interest of justice mandates condonation of the delay. [Paras 50-56] Land Acquisition – Land Acquisition Act, 1894 – Right to Fair Compensation and Transparency in Land Acquisition Rehabilitation and Resettlement Act, 2013 – Limitation Act, 1963 – s.17 – Condonation of delay sought on allegations of concealment by respondents-landowners – High Court allowing the landowners’ claim declared the acquisition proceedings as lapsed – Condonation of delay in filing present appeals sought by the appellants-authorities inter alia on ground of suppression of material facts by the landowners before High Court in certain cases as regards previous unsuccessful litigations, acquisitions being already complete, landowners being only subsequent purchasers who acquired the lands after they were notified for the acquisition – Scope of inquiry: Held: Neither the landowners were called upon to refute or admit the allegations of concealment of facts attributed to some of them nor, the appellants were asked to produce original records and documents to substantiate their allegation of concealment and suppression of material facts – Entering into an arena of factual controversy at such an advanced stage of litigation, and that too without giving adequate opportunities to the parties can be a potential threat to the cause of justice – No definitive opinion expressed on allegations of concealment – However, appellants have discharged prima facie burden for the limited purpose of making out a case for condonation of delay in the cases concerned – A detailed fact-finding inquiry is necessary to ascertain the rightful title-holder and the claimant of receiving the compensation – Hence, there exist sufficient grounds for the condonation of delay – Orders of the High Court set aside in such cases – Relevant writ petitions stand restored on the file of the High Court – Directions issued. [Paras 20, 21, 70] Limitation Act, 1963 – Objective – s.5 – “sufficient cause”; “within such period” – Law as regards condonation of delay – Discussed.

Limitation Act, 1963 – “sufficient cause” – Condonation of delay – Subsequent overruling of a judgement cannot be a sufficient cause for condonation of delay – Exception: Held: Cases pending before this Court will be an exception – If the lis is still pending and has not reached finality, those cases would be decided on the basis of five-judge bench decision in Indore Development Authority v. Manoharlal [2020] 3 SCR 1 as a decision on the interpretation of law is applied retrospectively unless the court specifically rules as to its prospective applicability. [Paras 29, 30]

Judgments/Orders – Judgments interpreting law – Applicability: Held: Judgment interpreting law is applied retrospectively unless specifically made prospective. [Para 30]

Land Acquisition – Limitation – Delay on part of government entities – Condonation of – Government entities, if to be allowed leeway for:

Held: The delay cannot be condoned mechanically only because the appellant is a government entity – Government entities must show bona fide and demonstrate diligence in pursuing the matter – The proposition that government entities ought to be afforded greater latitude on issues of delay on account of administrative exigencies, is no longer a precedent to be followed routinely – If delay were to be condoned merely on the basis of a broad general assertion of bureaucratic indifference, without requiring demonstration of bona fide or an act of mala fide on the part of specific individuals, it would create an artificial distinction between the private parties and the government entities vis-à-vis the law of limitation which would not be in conformity with the spirit of equality before law as guaranteed under the Constitution – Allowing such latitude would further distort incentives for the government and encourage more laxity by the bureaucracy in its general functioning, thereby undermining quality governance. [Paras 35, 39] Land Acquisition – Limitation – COVID-19 pandemic – Cases filed after the expiration of the period of limitation – Appellants sought condonation of delay inter alia on account of COVID-19 pandemic – Order dtd.23.03.2020 passed in In Re: Cognizance for Extension of Limitation whereby period of limitation was extended for proceedings before all courts/tribunals in the country from 15.03.2020 till further orders, and various orders passed by this Court from time to time – Benefit thereof, if can be availed by appellants:

Held: No – Orders passed In Re: Cognizance for Extension of Limitation were intended to benefit vigilant litigants who were prevented due to the pandemic and the lockdown, from initiating proceedings within the period of limitation prescribed by general or special law – Appellants can avail the benefit of the aforesaid order only in a case where the period of limitation expired between 15.03.2020 and 28.02.2022 – Thus, if the delay occurred on account of the COVID-19 pandemic as laid down in In Re: Cognizance for Extension of Limitation, such delay can be condoned. [Paras 45, 64] Constitution of India – Article 142 – Exercise of powers under – Land Acquisition – Cases where appellants did not take possession of the acquired land and also did not pay compensation and thus, cannot seek protection under Indore Development Authority v. Manoharlal [2020] 3 SCR 1 – Nonconclusion of acquisition proceedings – Exercise of powers u/Article 142:

Held: Substantial harm would ensue towards the public at large if the acquisition proceedings are not concluded promptly – To prevent such an outcome and after considering the unique facts and circumstances of such batch of cases, powers exercised u/Article 142 in the interests of doing complete justice – Directions issued. [Para 72, 73]

Keywords: Land acquisition · Subsequent change of law · Contradictory judicial opinions · Law re-interpreted · Re-interpretation of law · Subsequent overruling of a judgement · Limitation · Condonation of delay · Sufficient cause for condonation of delay · Compensation deposited in the treasury · Possession not taken · Compensation not paid · Nonpayment of compensation · Non-taking of possession · Acquisition proceedings declared to have lapsed · Period of limitation already expired · Delay not justified

As published in the Supreme Court Reports, Supreme Court of India. Headnotes prepared by: Divya Pandey. Text from the Indian Supreme Court Judgments open data set (Dattam Labs), CC BY 4.0.

Full Judgment Text

Judgment Surya Kant, J. Table of contents* A. Facts C. Law on Condonation of Delay B. Contentions of parties D. Whether delay should be condoned in the present cases? D.1. Suppression of facts by the landowners D.2. Change of law D.3. Leeway to be granted to government entities D.4. COVID-19 Pandemic D.5. Supreme Court frowning upon the filing of fresh SLPs D.6. Public interest and justice D.7. Delay already condoned in some cases E. Conclusion and Directions Appendix List A: Suppression of facts List B: Notice neither on delay nor on merits List D: Leave granted in previous SLP
Full text available to subscribers
Subscribe to access complete judgment text, daily digests, and AI-powered legal research tools. For informational and research purposes only.
View Subscription Plans →
Annual plans from ₹1,599 + GST.

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

All SC judgments →