Civil · Reportable judgment

Bhimashankar Sahakari Sakkare Karkhane Niyamita vs Walchandnagar Industries Ltd. (Wil)

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Supreme Court of India
Date
10 April 2023
Case No.
Civil Appeal No. 6810 of 2022
Result
Dismissed
Bench
M.R. Shah, Krishna Murari
Citation
[2023] 4 S.C.R. 361 : 2023 INSC 335
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.
Supreme Court Reports [2023] 4 S.C.R. 361 : 2023 INSC 335
Headnote

Arbitration and Conciliation Act, 1996 – s.34(3) – Limitation Act, 1963 – s.2(j) r/w s.4 – “period of limitation” – General Clauses Act, 1897 – s.10 – Application u/s.34(3) – Filing of, after the expiry of 120 days but filed on the first day of reopening after the winter/Christmas vacation – Last day of the condonable period of 30 days u/s.34(3) had fallen during the said vacation – Benefit of s.4, Limitation Act, if available – Held: No – Issue is not res integra – In Assam Urban Water Supply and Sewerage Board vs. Subash Projects and Marketing Limited reported as [2012] 1 SCR 403 it has been held that the benefit of exclusion of period during which Court is closed is available only when the application for setting aside the award is filed within ‘prescribed period of limitation’ and it is not available in respect of period extendable by the Court in exercise of its discretion – Further, the contention of the appellant on the applicability of s.10 of the General Clauses Act is also untenable in the light of proviso to s.10 of the General Clauses Act – No error committed by the High Court and Trial court in refusing to condone the delay caused in preferring application u/s.34 which was beyond the period prescribed u/s.34(3).

Arbitration and Conciliation Act, 1996 – s.43(1) – Plea of the appellant that Limitation Act shall not be applicable to the proceedings under the Arbitration Act – Held: Has no substance – s.43(1) specifically provides that Limitation Act, 1963 shall apply to arbitrations as it applies to proceeding in Court – Limitation Act, 1963.

Dismissing the appeal, the Court

Read the full headnote (6 more paragraphs)

HELD: 1.1 Section 34(3) of the Arbitration Act and Sections 2(j) and 4 of the Limitation Act, 1963 fell for consideration before this Court in the case of Assam Urban. Even the very issue raised in the present appeal fell for consideration before this Court in the case of Assam Urban. In the aforesaid decision, this Court interpreted the aforesaid provisions and has specifically observed and held that the benefit of exclusion of period during which Court is closed is available only when application for setting aside the award is filed within ‘prescribed period of limitation’ and it is not available in respect of period extendable by the Court in exercise of its discretion. Therefore, as such the question involved in the present appeal is squarely answered against the appellant and the said issue is as such not res integra. [Para 7.1][377-B-D; 380-A]

Assam Urban Water Supply and Sewerage Board v. Subash Projects and Marketing Limited (2012) 2 SCC

624 : [2012] 1 SCR 403 – relied on.

1.2 Now, so far as the submission on behalf of the appellant that the Limitation Act shall not be applicable to the proceedings under the Arbitration Act is concerned, the aforesaid has no substance. Section 43(1) of the Arbitration Act specifically provides that Limitation Act, 1963 shall apply to arbitrations as it applies to proceeding in Court. However, as observed and held by this Court in the case of Assam Urban, Limitation Act, 1963 shall be applicable to the matters of arbitration covered by 1996 Act save and except to the extent its applicability has been excluded by virtue of express provision contained in Section 34(3) of the Arbitration Act. [Para 8][380-D-E]

1.3 Now, so far as reliance placed upon Section 10 of the General Clauses Act, 1897 on behalf of the appellant is concerned, at the outset it is required to be noted that such a contention is untenable in light of the proviso to Section 10 of the General Clauses Act, 1897, which specifically excludes the application of Section 10 of the General Clauses Act, 1897 to any act or proceeding to which the Indian Limitation Act, 1877 applies. Reference to 1877 Act will now have to be read as reference to Limitation Act, 1963 in view of Section 8 of the General Clauses Act, 1897. Therefore, in light of the application of Limitation Act, 1963 to the proceedings under the Arbitration Act and when Section 10 of the General Clauses Act, 1897 specifically excludes the applicability of Section 10 to any act or proceeding to which Indian Limitation Act, 1963 applies and in light of the definition of “period of limitation” as defined under Section 2(j) read with Section 4 of the Limitation Act and as observed and held by this Court in the case of Assam Urban, benefit of exclusion of period during which the Court is closed shall be available when the application for setting aside award is filed within “prescribed period of limitation” and shall not be available in respect of period extendable by Court in exercise of its discretion. [Para 9][380G-H; 381-A-C]

HUDA & Anr. v. Dr. Babeswar Kanhar & Anr. (2005) 1 SCC 191 : [2004] 6 Suppl. SCR 282; Manohar Joshi v. Nitin Bhaurao Patil and Ors. (1996) 1 SCC 169 : [1995] 6 Suppl. SCR 421; Sagufa Ahmed & Ors. v. Upper Assam Polywood Products Private Limited and Others (2021) 2 SCC 317; Union of India v. Popular Construction Co. (2001) 8 SCC 470 : [2001] 3 Suppl. SCR 619; State of Maharashtra v. Borse Brothers Engineers and Contractors Pvt. Ltd. (2021) 6 SCC 460; Consolidated Engineering Enterprises v. Principal Secretary, Irrigation Department and Ors. (2008) 7 SCC 169 : [2008] 5 SCR 1108; State of Maharashtra v. Hindustan Construction Co. Ltd. (2010) 4 SCC 518 : [2010] 4 SCR 46; Sridevi Datla v. Union of India (2021) 5 SCC 321 – referred to.

Read this judgment in
हिन्दी Hindi PDF ਪੰਜਾਬੀ Punjabi PDF

Translations made available by the Supreme Court of India in its e-SCR, opened as PDF files from the Indian Supreme Court Judgments data set. A translation is for understanding the judgment; the English judgment is the authentic text for all official purposes.

As published in the Supreme Court Reports, Supreme Court of India. Text from the Indian Supreme Court Judgments open data set (Dattam Labs), CC BY 4.0.

Ask LexAI about this judgment What was decided, on what reasoning, and which later cases follow it. Answers name the judgments they rely on. Ask

Filed under

Arbitration and Conciliation Act, 1996 Limitation Act, 1963 Section 34, Arbitration and Conciliation Act, 1996 Section 4, Limitation Act, 1963 Section 2, Limitation Act, 1963 Arbitration and Conciliation Act Condonation of delay

Work out the figure: Limitation calculator

Guides on this topic, in plain language:

The law this judgment cites

Opens the section on Law Maker (lawmaker.in), our sister site for law students.

Cases cited

As listed in the Supreme Court Reports. Linked where the judgment is on LegalFirms.in.

  • [2012] 1 SCR 403 relied on
  • [2004] 6 Suppl. SCR 282 referred to
  • [1995] 6 Suppl. SCR 421 referred to
  • [2001] 3 Suppl. SCR 619 referred to
  • [2008] 5 SCR 1108 referred to
  • [2010] 4 SCR 46 referred to

Cited in 3 later judgments on LegalFirms.in

From the case lists those reports print.

Full Judgment Text

The Judgment of the Court was delivered by M. R. SHAH, J. 1. Feeling aggrieved and dissatisfied with the impugned judgment and order dated 23.02.2022 passed by the High Court of Karnataka, at Kalaburagi in Misc. First Appeal No.201018/2018 by which the High Court has dismissed the said appeal and has confirmed the order dated 02.04.2018 passed by the learned III Additional District & Sessions Judge, Vijayapur (hereinafter referred to as “trial Court”) in rejecting the application for condonation of delay caused in preferring the application under Section 34 of the Arbitration and Conciliatio
Full text available to subscribers
Subscribe to access complete judgment text, daily digests, and AI-powered legal research tools. For informational and research purposes only.
View plans →
Annual plans from ₹799 + GST.

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All SC judgments →

Arbitration & Mediation advocates near the Supreme Court of India

Dealing with a similar matter? Send a free enquiry to advocates who handle it. Fees are agreed with the advocate directly.

All Arbitration & Mediation advocates in India