Assistant Engineer (D1), Ajmer Vidyut Vitran Nigam Limited & Anr. vs Rahamatullah Khan alias Rahamjulla
SC · 18 February 2020
[2020] 2 S.C.R. 929 : 2020 INSC 205
Electricity Act, 2003: s. 56(2) – Disconnection of supply in default of payment – Term ‘first due’ in s.56(2) – Meaning of – Commencement limitation period of two years, when – Held: Electricity charges would become “fir…
Hindustan Zinc Limited (H.Z.L.) vs Ajmer Vidyut Vitran Nigam Limited
SC · 4 December 2019
[2019] 15 S.C.R. 113 : 2019 INSC 1319
Electricity Act, 2003 – ss.86(1)(f) and ss.37, 42, 158 – Appellant has four high tension electricity connections for its units at Chanderiya, Debari, Aghucha and Dariba, for which four contracts with the respondent were…
Directorate of Enforcement (PMLA) vs Eastern Institute for Integrated Learning in Management University and Ors
Sikkim HC · 14 September 2019
From the judgment…Act, 2013, the National Green Tribunal Act, 2010, the Income Tax Act, 1961, the Central Excise Tax Act, 1944, and the Electricity Act, 2003 have similar provisions wherein, being Special Acts, certain period of limitations with the clear words 'Not Exceeding' or 'But not thereafter' have been provi
M/s Adani Power (Mundra) Ltd. vs Gujarat Electricity Regulatory Commission and Ors.
SC · 2 July 2019
[2019] 8 S.C.R. 1017 : 2019 INSC 711
Electricity Act, 2003 – ss. 86 (1) (F), 95 – Respondent No. 2-Procurer initiated the process of bidding for supply of power on long term basis, by issuing Request for Qualification – Three separate bids were invited – Ap…
Maharashtra State Electricity Distribution Co. Ltd. vs The Appellate Authority & Anr.
SC · 15 February 2018
[2018] 2 S.C.R. 537 : 2018 INSC 144
Electricity Act, 2003 – ss. 126, 127 – Respondent No.2 are consumers of electricity, which is supplied to them by the State Electricity Board – The sleuths of the Board visited the respondent no.2’s factory and replaced…