The State of Tripura vs MS. N.G. Bhattacharjee Const. Co.

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Tripura High Court
Date
25 January 2021
Case No.
Arb.A. 1/2017
Result
Dismissed
Bench
S.g. Chattopadhyay, Akil Kureshi
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

19. 12.2008 aforesaid, for which the contractor claimed damages for breach of contract. [28] From the discussions made above, it stands established that the appellant has failed to discharge his obligation created under the contract. Unilateral rescission of the contract by the employer on invalid ground was clearly unjustified for which the contractor is entitled to compensation for loss in terms of Section 73 of the Indian Contract Act. The damages estimated and claimed by the contractor have been tailored by the arbitrator after scrutiny. His award dated 24.09.2014 has been approved by the learned District Judge vide the impugned judgment dated 19.09.2016. As stated above, the Apex Court in M/S A.T.Brij Paul Singh(supra) has held that in such situation it would be unnecessary to go into the minute details of the work executed in relation to the value of the works contract and a broad evaluation would be sufficient. In the given case we find no illegality in the Arbitrator’s evaluation of loss which has been approved by the learned District Judge. The interest on the award for loss of profit and the award with regard to the cost of the arbitral proceedings is also found justified. [29] Similarly, in the case of Dwaraka Das (supra) the Apex Court has succinctly held that for breach by improperly rescinding the contract, the contractor is entitled to claim damages for loss of profi…

10. Although various theories have been propounded by the Judges and jurists in England regarding the juridical basis of the doctrine of frustration, yet the essential idea upon which the doctrine is based is that of impossibility of performance of the contract, in fact impossibility and frustration are often used as interchangeable expressions. The changed circumstances, it is said, make the performance of the contract impossible and the parties are absolved from the further performance of it as they did not promise to perform an impossibility.” [37] Relying on the decision in Satyabrata Ghose (supra), the Apex Court reiterated the same principle in Sushila Devi vs. Hari Singh (supra) and held as follows: “11. In our opinion on this point the conclusion of the appellate court is not sustainable. But in fact, as found by the trial court as well as by the appellate court, it was impossible for the plaintiffs to even get into Pakistan. Both the trial court as well as the appellate court have found that because of the prevailing circumstances, it was impossible for the plaintiffs to either to take possession of the properties intended to be leased or even to collect rent [1968] 3 S. C. R. 339. from the cultivators. For that situation the plaintiffs were not responsible in any manner. As observed by this Court in Satyabrata Ghose v. Mugneeram Bangur and Co.1954 SCR 310 = (AIR 1954 SC 4…

Filed under

Arbitration and Conciliation Act, 1996 Indian Contract Act, 1872 Section 34, Arbitration and Conciliation Act, 1996 Section 73, Indian Contract Act, 1872 Section 56, Indian Contract Act, 1872 Arbitration and Conciliation Act

Guides on this topic, in plain language:

The law this judgment cites

Opens the section on Law Maker (lawmaker.in), our sister site for law students.

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

HIGH COURT OF TRIPURA AGARTALA Arb. Appeal No. 01 of 2017 BEFORE HON’BLE THE CHIEF JUSTICE MR.AKIL KURESHI HON’BLE MR. JUSTICE S.G.CHATTOPADHYAY …………..Appellant(s). The State of Tripura Versus M/S N.G.Bhattacharjee Construction Company Office Lane: Agartala West Tripura For the Appellant(s) For the Respondent(s) Date of hearing Date of delivery of Judgment and Order Whether fit for reporting ... ..….Respondent(s). : : : Mr. Nepal Majumder, Adv. Mr. Suman Bhattacharjee, Adv. 01.12.2020 : 25.01.2021 Yes No  JUDGMENT [S.G.Chattopadhyay, J] This Appeal under Section of The Arbitration and Conciliation Act, 1996(“the 1996 Act” hereinafter) has been preferred by the State of Tripura (‘the employer’ hereunder) against judgment dated 19.09.2016 delivered by the District Judge, West Tripura in case No. Misc.(ARB)34 of 2015 whereby the application filed by the employer under Section 34 of the 1996 Act Arb. A 1/2017 for setting aside the arbitral award dated 24.09.2014 had been dismissed. [2] The basic facts and the controversy brought before this court are as follows: The employer floated Notice Inviting Tender (NIT hereinafter) for execution of the work namely “Diversion Scheme at Andhicherra, Lalsingmura under Bishalgarh block / Head works and distribution system”. Stipulated time for completion of the work was 02(two) years. The respondent (‘the contractor’ hereunder) submitted his tender for the work in terms of the NIT on 05.10.2005 and acceptance of the tender was communicated to the contractor by the employer vide letter No. F. TS - 428 / WRD - II / W / 6943 - 54 dated 16.02.2006. By the said letter of acceptance, the contractor was asked to complete formal agreement with the employer within 7 days and he was also directed to start the work at once and complete the work within 02(two) years reckoning from the 15th day after the said date of acceptance of tender. Pursuant to the said work order dated 16.02.2006, the contractor and the employer executed formal Arb. A 1/2017 agreement on 08.03.2006. Despite awarding the work, the employer did not hand over the site to enable the contractor to commence the work. The contractor, therefore, wrote several letters to the employer for handing over the site to him to avoid loss of time. Vide his letter dated 17.03.2006, he pointed out to the employer that it would be difficult to carry out the work if monsoon starts and he urged the employer to hand over the site with plan and design immediately. Vide subsequent letters dated 13.09.2006, 12.10.2006, 10.11.2006 & 03.12.2006, he informed the employer that he kept manpower and machinery ready at the site since issuance of the work order and he suffered huge financial loss as a result of the delay in handing over the site. Finally, vide letter dated 05.12.2006, he again requested the employer for handing over the site. [3] On the other hand, the employer, vide letter No.TS-428/EE / WRD-II / W / Shadow / 23338-344 dated 19.12.2008 informed the contractor that “due to poor bearing capacity of the proposed site” the work was closed and the work order issued vide No.F.TS-428/WRDII/W/6943-54 dated 16.02.2006 stood cancelled. The Arb. A 1/2017 contractor was asked to contact the employer for refund of the earnest money deposited by him. [4] Thereafter, the contractor vide letter dated 07.01.2009, informed the employer about his inability to accept the unilateral cancellation of the work order and proposed to the employer to strengthen the bearing capacity of the site by doing necessary civil engineering works, else to provide an alternative site for execution of the work as per terms of the tender. He conveyed to the employer, his willingness and readiness to perform the contract at the agreed rate with allowance of price escalation as per clause 10CC of the agreement. [5] In response, the employer vide letter No.TS- 428/EE/WRD-II/W/Shadow/74-178 dated 13.01.2009 turned down the said proposal of the contractor and further asked him to take back the earnest money deposited by him. [6] Then the contractor, vide letter dated 11.02.2009 submitted the following claim for breach of contract: “Schedule of claim Arb. A 1/2017 (i) Damages for loss on account of loss of profit @10% on contract amount …..Rs.14,06,286/- of Rs.1,40,62,000/- (ii)Damages on account of anfractuous expenses on over heads being the salary paid to the site staff comprising of representative and graduate engineer. a)Representative for 34 months @Rs.5000/- per month ….Rs.1,70,000/- b) Site engineer for 29 months @Rs.8000/- per month ….Rs.2,32,000/- Total [7] Rs.18,08,286/-“ The contractor demanded payment of such damages within 28.02.2009 failing which he claimed 12% annual interest on the amount from 01.03.2009. Vide application dated 13.04.2009, the contractor proposed to the employer for appointment of an arbitrator in terms of clause 25 of the agreement for resolving the disputes between them. [8] Ultimately, vide letter dated 25.04.2009, the employer appointed the arbitrator and the matter was referred to the sole arbitrator, so appointed, for adjudication of the disputes between the parties and make award on the claims / counter claims referred by the parties subject to their admissibility in terms of clause 25 of the agreement. The sole arbitrator conducted the arbitral proceedings and decided the matter vide order dated 24.09.2014 in favour of the contractor. The relevant extract of the Award is as under: Arb. A 1/2017 “FINDINGS AND AWARD “........................................................................................................ In view of my above findings, the award on the claims of the claimant contractor is summarized below: AWARD ON THE CLAIMS OF THE CLAIMANT The Arbitrator is to decide Award 1. Whether the claimant is entitled to get damages being the loss of profit @10% on the contract amount of Rs.1,40,62,858/only due to breach of contract committed by the Respondent. Whether the claimant is entitled to get damages on account of anfractuous expenses on overheads being the salary paid to the staff comprising of representative and graduate engineer. a) Representative for 34 months @Rs.5000/- per month. b) Site engineer for 29 months @8000/- per month. Whether the claimant is entitled to get interest @12% p.a. on Rs.18,08,286/- from the date of cause of action / dispute i.e.24.02.2009 till realization. Whether the claimant is entitled to get Rs.25,000/- cost of arbitration proceedings. THIS CLAIM HAS BEEN PARTIALLY ESTABLISHED PARTLY. HENCE I AWARD RS.8,43,771/-(RUPEES EIGHT LAKHS FORTY-THREE THOUSAND SEVEN HUNDRED SEVENTY-ONE ONLY UNDER THIS ISSUE) THIS CLAIM HAS NOT BEEN ESTABLISHED. HENCE, I AWARD NOTHING UNDER THIS ISSUE. THE CLAIM HAS BEEN ESTABLISHED. I AWARD SIMPLE INTEREST @8% (EIGHT PERCENT) P.A. ON THE AWARDED SUM OF RS.8,43,771/(RUPEES EIGHT LAKHS FORTY-THREE THOUSAND SEVEN HUNDRED SEVENTY-ONE)ONLY w.e.f. 24/02/2009 UP TO THE DATE OF AWARD. THE AWARD SHALL CARRY FURTHER INTEREST @ 9.50%(NINE POINT FIVE ZERO PERCENT)P.A FROM THE DATE OF PUBLISHING THE AWARD TILL THE DATE OF ACTUAL PAYMENT IF THE AWARDED SUM WITH INTEREST AND COST IS NOT PAID WITHIN 3 (THREE)MONTHS. THIS CLAIM HAS BEEN ESTABLISHED. HENCE I AWARD RS.5,000/-(RUPEES FIVE THOUSAND)ONLY UNDER THIS ISSUE. The stamp duty charges of Rs.75/-(Rupees seventyfive) only have been borne by the claimant contractor.” [9] The arbitrator has thus tailored the claim of the contractor. He claimed 10% loss of profit on the contract value. The arbitrator has given him less. His Arb. A 1/2017 claim for damages for loss towards payment of salary to his representative, site engineer and labourers has also been rejected by the arbitrator. He claimed Rs.25,000/as the cost of arbitral proceedings which has been reduced to Rs.5,000/- by the arbitrator. But the contractor did not dispute the arbitral award. [10] The employer, being aggrieved with the said arbitral award, filed an application under Section 34 of the 1996 Act in the court of the District Judge, West Tripura at Agartala. The District Judge vide the impugned judgment dated 19.09.2016, dismissed the application and approved the arbitral award. [11] Aggrieved with the said judgment of the District Judge, the employer has challenged the arbitral award by means of filing this appeal under Section 37 of the 1996 Act. [12] Mr. Nepal Majumder, learned counsel appearing for the employer, has argued that there is no merit in the claim of the contractor. Mr. Majumder, learned counsel has submitted written arguments in the case contending, inter alia, as follows: Arb. A 1/2017 (i)The Arbitrator as well as the learned District Judge failed to appreciate the fact that the employer had to terminate the works contract in view of the soil testing report confirming poor subsoil condition at the site and in view of Section 56 of the Contract Act, failure of the employer in performing the contract in such situation cannot be termed as breach of contract entitling the contractor to damages for loss. (ii)The contractor was not entitled to the damages claimed by him because he could not establish by evidence that he actually invested any capital for execution of work and as a result of delay in handing over the site, his capital was blocked which he could have invested elsewhere and earned profit. (iii) The learned District Judge failed to appreciate the fact that the contractor could not prove any financial loss as a result of cancellation of the works contract. Counsel for the employer has relied on few decisions which shall be discussed at a later stage. Arb. A 1/2017 [13] Conversely, Mr. Suman Bhattacharjee, learned counsel representing the contractor submits that the learned District Judge upheld the arbitral award after proper appreciation of evidence and facts and circumstances of the case and as such the findings of the learned District Judge do not call for any interference in appeal. [14] Further submission on behalf of the contractor is that termination of the contract on the ground of poor load bearing capacity of soil is beyond the terms of the said contract between the parties. Moreover, in the recommendation part of the Geotechnical Investigation Report, various measures were suggested for improvement of the load bearing capacity of the soil. Without exploring the feasibility of those suggestions, the employer arbitrarily cancelled the works order and that too unilaterally without giving stipulated notice to the contractor. Such unilateral cancellation of the works contract by the employer is a clear breach of contract for which the contractor is entitled to the damages claimed by him. Arb. A 1/2017 [15] Mr. Bhattacharjee, learned counsel of the contractor has further argued that it is manifest on the face of the record that the contractor was always willing and ready to perform the contract. The employer on the other hand was reluctant to perform the contract for which right from the beginning, the employer delayed in handing over of the site to the contractor and ultimately cancelled the works contract unilaterally to the disadvantage of the contractor causing huge financial loss to him. [16] According to Mr. Bhattacharjee, learned counsel, the contractor proved that he invested money for engagement of manpower and installation of machinery at the site for execution of the work and thereby suffered huge financial loss for cancellation of the contract. According counsel, the to arbitrator Mr. rightly Bhattacharjee, made the learned award to compensate his loss which was also approved by the learned District Judge. Learned counsel, therefore, urges this court for dismissing the appeal. [17] As noted by us, the employer vide letter No.F.TS-428/WRD-II/W/6943-54 dated 16.02.2006 issued Arb. A 1/2017 the work order to the contractor and asked him to complete the work within a period of 02(two) years in terms of the agreement and it was stipulated that the period of 02 years would be reckoned from the 15 th day from the date of issuance of the said work order i.e. from 16.02.2006. Despite awarding the work contract, the employer did not hand over the site to the contractor to commence the work. In order to demonstrate his readiness and willingness to perform the contract, the contractor vide his letter dated 10.11.2006 informed the employer that he had already set up a camp shed and constructed approach road to the site to start the work and again urged the employer to hand over the site. He wrote several other letters, as quoted above, to the employer for handing over the site to him. Finally, vide letter dated 03.12.2007, the contractor wrote to the employer that unless the site was handed over to him immediately, he would raise his demand for damages for loss of profit and for loss owing to his investment in manpower and machinery. The employer, thereafter, vide letter dated 19.12.2008, cancelled the contract and asked the contractor to take back the earnest money deposited by him. In this factual back ground, the contractor Arb. A 1/2017 claimed before the Arbitral Tribunal that unilateral cancellation of the works contract on the ground of poor load bearing capacity of the soil at the site without serving notice on him amounted to breach of contract for which he was entitled to damages for loss of profit and other investments. [18] In the counter statement, the employer stated that though they were interested for execution of the work, the soil condition did not permit the execution. According to the employer, Geo-technical investigation of the site was conducted twice. Once in January, 2008 and then in July, 2008 which revealed that the soil foundation at the site was very poor and not suitable for execution of such work. Alternative proposals were also explored, but it did not work. According to the employer, the works contract had to be cancelled for unforeseen reason and the contractor was not entitled to damages because he did not make any investment for execution of the work. [19] In his rejoinder, the contractor stated that work order was issued to him on 16.02.2006 with a direction to commence the work at once and complete the work within the stipulated period of two years which Arb. A 1/2017 would be complete on 02.03.2008, whereas, soil test was conducted by the employer in January, 2008 i.e. almost at the end of the contract period and again in July, 2008 and such act of the employer demonstrated the unwillingness of the employer to perform the contract. Further contention of the contractor in his rejoinder was that the Safe Bearing Capacity (SBC) of the soil at the site could have been easily improved by the employer by taking the measures suggested by the experts in the recommendation part of their Geotechnical Investigation Report. Therefore, the plea of the employer that the termination of the contract by reason of supervening impossibility was saved under Section 56 of the Indian Contract Act, 1872 was not acceptable. The findings of the arbitrator, on the said issues, were as under: “I have carefully gone through the contract document at page 83 i.e. the design data which provides for procedure to be adopted in case of bearing capacity of the soil in case the same is found below 10T/sqm. I have also carefully considered the pleadings and arguments advanced on the side of the parties including documents filed with the claim statement and defence statement. From Annexure R/3 i.e. soil testing report of July, 2008, I find that SBC was found as 9 T/sqm, which is seen at page 12 of the said Geotechnical Investigation Report for the proposed diversion scheme of Arb. A 1/2017 Andhicherra as done by the expert EMC construction, Agartala for raft foundation at 4.5 m from existing ground level with suggestion given at Sl.No(iii) by the said expert at page 12 of Annexure R/3. Had the respondent any interest in getting the work executed by the claimant, it ought to have followed the provision of agreement at page 83 (Design Data) in case of bearing capacity found below 10 T/sqm including the suggestion given the EMC Construction. I have also examined the letter of the claimant dated 17/01/2009(Exhibit C/15) particularly the contraction made by it in para 11(i),(ii) and (iii) and the proposal as was submitted appears to me a reasonable one being within the parameters of the contract agreement vide page 83 but the respondent refused to accept any of the said proposal. During hearing proceedings, the respondent agreed to provide alternate side for executing the same type of job and the claimant acceded to such proposal however with a condition of allowing rate enhancement of additional 70% over the original agreement rate of 49.90% above i.e. rate enhancement of 10% each year for seven years, which is as per Government Order as reflected in Tripura Gazette Extraordinary Issue, June 7 2007 A.D. A copy of which has been submitted as Annexure 2 with the written counter argument filed on 01/08/2013. Such proposal from the side of the claimant appears to me to be quite reasonable and in the interest of public work. From the activities of the claimant contract, I find that he was all through ready and willing to execute the work but it is the respondent who has failed to discharge its obligations under the contract. The respondent backed out from its own commitment of providing alternate site though on such commitment, the arbitration proceeding was kept in abeyance for a considerable period of time for amicable settlement by providing alternate side, which the respondent has failed as intimated during the hearing held on 27/03/2014. The respondent’s contention that for impossibility and frustration of the contract as per Section 56 of the Indian Contract Act, is held to be unsustainable in law as the contract has itself taken care of for improving the bearing capacity of soil at page 83, which the respondent that it had power to close the agreement under Clause 13 of the agreement is also held to be unsustainable and hence fails as the letter of the respondent dated 19/12/2008(Exhibit C/14) does not indicate Arb. A 1/2017 exercise of power under Clause 13 of the agreement for and on behalf of the Governor of Tripura.” [20] Finally, vide award dated 24.09.2014, the arbitrator partially accepted the claim of the contractor and made the award as quoted above. [21] The learned District Judge found no reason to interfere with the award made by the arbitrator and accordingly turned down the application filed by the employer under Section 34 of the 1996 Act. Relevant paragraphs of the judgment containing the findings of the learned District Judge are as under: “10. Under the scheme of Section 34 of the Arbitration and Conciliation Act, judicial review is restrained to the extent if the Arbitrator acts beyond the scope of reference and if the award of the Arbitrator is in conflict with public policy of India. Explanation to Section 34(1)(b)(ii) of the Act makes it clear that if the making of the award was induced or affected by fraud or corruption or was in violation of Section 75 and Section 81 of the Arbitration and Conciliation Act, 1996, it shall be deemed to be against the public policy of India. 11. In the case at hand there is no indication that the sole Arbitrator or the parties did not keep anything confidential relating to the arbitration and there is no allegation of violation of the Provision of Section 81 of the Arbitration and Conciliation Act, 1996. 12. The argument of learned counsel Mr. Sengupta that Clause 13 of the agreement empowers to the department to cancel the work order at any time is also not acceptable. Clause 13 of the agreement deals with a situation where after commencement of the work the Governor decides that any part of the work is not required to be executed, the Engineer-in-charge shall give notice in writing of the fact to the contractor who shall have no claim to any payment whatsoever on Arb. A 1/2017 account of any profit which he might have derived from the execution of the work in full. 13. In the case at hand the work was not commenced at all. Rather it was unilaterally cancelled after more than two years. Work order was issued on 16-02-2006, to be commenced from 03-03-2006 and to be completed within 02-03-2008. The department petitioner conducted geo technical investigation in the months of January and July, 2008 which is even after the stipulated period of completion of the work. Ultimately, the work order was unilaterally cancelled on 19-12-2008. 14. What necessarily follows is that the opposite party-contractor being a professional organization could not do any work for more than two years and could not utilize its capital for that period. 15. The doctrine of frustration stipulated under Section 56 of the Indian Contract Act is not applicable at all. Rather under Section 56 of the Act the petitioner department being promissor failed to keep its promise for the fact that the work site was not proper for undertaking the diversion scheme. If the petitioner department conducted geo technical investigation before issuing the work order, this situation could be avoided. Meaning thereby the petitioner department did not exercise reasonable diligence and if such reasonable diligence was exercised by the petitioner department, it might have come to the knowledge of the petitioner department that the soil of the work site was not fit for undertaking the diversion scheme and in turn no loss would have occurred to the opposite partycontractor. Therefore, under Section 56 read with Section 73 of the Indian Contract Act, the petitioner department is liable to compensate for loss caused to the opposite party-contractor by breach of contract. Therefore, I do not find any misconduct or any arbitrary finding on the part of the sole Arbitrator. The sole Arbitrator allowed 6% as loss of profit on the contract value against the claim of 10% by the opposite party-contractor.” [22] In the present case, manifestly there is a breach of contract. Learned District Judge has rightly held that the employer should have conducted the Geotechnical Investigation of soil at the site before they issued the work order and in that event they could have Arb. A 1/2017 avoided the situation. Findings of the learned District Judge that contract the employer unilaterally improperly without issuing rescinded the notice the to contractor as contemplated under clause 13 of the agreement is not also incorrect. It would be apposite at this stage to reproduce clause 13 of the agreement which is as under: “Clause 13: If at any time after the commencement of the work the Governor of Tripura shall for any reason whatsoever not require the whole thereof as specified in the tender to be carried out the Engineer-in-Charge shall give notice in writing of the fact to the contractor who shall have no claim to any payment of compensation whatsoever on account of any profit or advantage which he might have derived from the execution of the work in full, but which he did not derive in consequence of the full amount of the work not having been carried out, neither shall he have any claim for compensation by reason of any alterations having been made in the original specifications, drawings, designs and instructions which shall involve any curtailment of the work as originally contemplated. Provided that the contractor shall be paid the charges on the cartage only of materials actually and bonafide brought to the site of the work by the contractor and rendered surplus as result of the abandonment or curtailment of the work or any portion thereof and then taken back by the contractor provided Engineer-in-Charge shall have in all such cases the option of taking over all or any such materials at their purchase price or at local current rate whichever may be less. “In the case of such stores having been issued from Government stores and returned by the contractor to Government stores, credit shall be given to him by the Engineer-in-Charge at rates not exceeding those at which they were originally issued to him, after taken into consideration and education for claims on account of any deterioration or damage while in the custody of the contractor and in this respect the decision of the Engineer-in-Charge shall be final” Arb. A 1/2017 [23] Obviously, the employer never issued such notice to the contractor and most arbitrarily terminated the contract. Evidently, the recommendations of the experts projected in the Geotechnical Investigation Report for improvement of soil condition at the site were totally ignored. Contractor’s proposal for alternative site was not at all considered. Behaviour of the employer right from the beginning manifested their unwillingness in performing the contract. In these circumstances, the finding of the learned District Judge with regard to breach of contract on the part of the employer is well founded. The award of damages for loss of profit, is therefore, absolutely justified. The Apex Court in M/S A.T.Brij Paul Singh and Ors. vs. State of Gujrat reported in (1984) 4 SCC 59 has succinctly held that when a work is entrusted to a contractor, he is always in a reasonable expectation of profit and therefore, he will be entitled to damages for loss of profit, if the other party commits breach of the contract. The observation of the Apex Court is as under: “10….. ordinarily a contractor while submitting his tender in response to an invitation to tender for a works contract reasonably expects to make profits. What would be the measure of profit would depend upon Arb. A 1/2017 facts and circumstances of each case. But that there shall be a reasonable expectation of profit is implicit in a works contract and its loss has to be compensated by way of damages if the other party to the contract is guilty of breach of contract cannot be gainsaid.” [24] in In Dwaraka Das vs. State of M.P. and Anr. reported (1999) 3 SCC 500, the Apex Court having relied on A.T.Brij Paul Singh and Ors (supra), allowed the claim of the contractor for damages @ 10% on the contract value and held that where there is a breach of contract committed by the government by improperly rescinding the contract, the court should make a broad evaluation of damages without going into the minute details. Observation of the Apex Court in paragraph 9 of the judgment in this regard is as follows: “9. The claim of the petitioner for payment of Rs. 20,000 as damages on account of breach of contract committed by the respondent- State was disallowed by the High Court as the appellant was found to have not placed the material on record to show that he had actually suffered any loss on account of the breach of contract. In this regard, the appellate court observed: Arb. A 1/2017 "It is not his case that for due compliance of the contract he had advanced money to the labourers or that he had purchased materials or that he had incurred any obligations and on account of breach of contract by the defendants he had to suffer loss on the above and other heads. Even in regard to the percentage of profit he did not place any material on record but relied upon assessment of the profits by the Income Tax Officer while assessing the income of the contractors from building contracts." Such a finding of the appellate court appears to be based on wrong assumptions. The appellant had never claimed Rs. 20,000 on account of alleged actual loss suffered by him. He had preferred his claim on the ground that had he carried out the contract, he would have earned profit of 10% on Rs. 2 lacs which was the value of the contract. This Court in A.T. Brij Paul Singh v. State or Gujarat, [1984] 4 SCC 59 while interpreting the provisions of Section 73 of the Contract Act,1872 has held that damages can be claimed by a contractor where the government is proved to have committed breach by improperly rescinding the contract and for estimating the amount of damages, court should make a broad evaluation instead of going into minute details. It was specifically held that where in the works contract, the party entrusting the work committed breach of contract, the contractor is entitled to claim the damages for loss of profit which he expected to earn by undertaking the works contract. Claim of expected profits is legally admissible on proof of the breach of contract by the erring party. It was observed:(SCC pp.64-65, paras 10-11) "What would be the measure of profit would depend upon facts and circumstances of each case. But that there shall be a reasonable expectation of profit is implicit in a works contract and its loss has to be compensated by way of damages if the other party to the contract is guilty of breach of contract cannot be gainsaid. In this case we have the additional reason for rejecting the contention that for the same type of work, the work site being in the vicinity of each other and for identical type of work between the same parties, a Division Bench of the same High Court has accepted 15 per cent of the value of the balance of the works contract would not be an unreasonable measure of damages for loss of profit. Now if it is well-established that the respondent was guilty of breach of contract inasmuch as the rescission of contract by the respondent is held to be unjustified, and the plaintiff-contractor had executed a part of the works contract, the contractor would be entitled to damages by way of loss of profit. Adopting the measure accepted by the High Court in the facts and circumstances of the case between the same parties and for the same type of work at 15 per cent of the value of the remaining parts of the works contract, the damages for loss of profit can be measured." Arb. A 1/2017 To the same effect is the judgment in Mohd. Salamatullah v. Government of Andhra Pradesh,(1977)3 SCC 590 : AIR (1977) SC 1481. After approving the grant of damages in case of breach of contract, the court further held that the appellate court was not justified in interfering with finding of fact given by the trial court regarding quantification of the damages even if it was based upon guess work. In both the cases referred to hereinabove, 15% of the contract price was granted as damages to the contractor. In the instant case however, the trial court had granted only 10% of the contract price which we feel was reasonable and permissible, particularly when the High Court had concurred with the finding of the trial court regarding breach of contract by specifically holding that "we, therefore, see no reason to interfere with the finding recorded by the trial court that the defendants by rescinding the agreement committed breach of contract." It follows therefore, as and when the breach of contract is held to have been proved being contrary to law and terms of the agreement, the erring party is legally bound to compensate the other party to the agreement. The appellate court was, therefore, not justified in disallowing the claim of the appellant for Rs. 20,000 on account of damages as expected profit out of the contract which was found to have been illegally rescinded.” [25] Similarly, relying on the principle laid down in the case of M/S A.T.Brij Paul Singh and Ors (supra), the Bombay High Court in Union of India Vs. Vaman Prestressing Co.Ltd. reported in 2019 SCC On Line Bom 192 declined to interfere with the Arbitrator’s assessment awarding 10% damages to the contractor towards loss of profit for breach of contract by the other side and held as under: 7. In A.T. Brij Paul Singh vs. State of Gujarat AIR 1984 SC 1703, the Supreme Court considered the question of damages payable to a contractor of a works contract upon the employer committing a breach by improper rescission of the contract. The court held that ordinarily, when the contractor submits his tender in response to an invitation to Arb. A 1/2017 tender for a works contract, a reasonable expectation of profits is implicit in it and its loss has to be compensated by way of damages if the other party to the contract is guilty of breach of contract. The court held that though what would be the measure of profit would always depend upon facts and circumstances of each case, whilst estimating such loss of profit, it would not be necessary to go into minute details; what would be sufficient and expected of the court would be a broad evaluation of the matter. In other words, not only is a claim of loss of profits admissible, but the measure of damages in that case has to be worked out by taking a broad view of the matter. In A.T. Brij Paul Singh's case, the Supreme Court considered adoption of a measure of damages by the High Court in the facts and circumstances of the case between the same parties and for the same type of work at 15% of the value of the remaining work as an acceptable measure even for another contract for assessing damages towards loss of profit. 8. This law was followed by a Division Bench of our court in Mahanagar Gas Ltd. vs. Babulal Uttamchand & Co.2013 (5) Bom.C.R. 756 . Our court held as follows: “16. Thus, it is clear from the dicta of the Apex Court reproduced above that the claim for damages by a party is admissible once it demonstrates that the other party has committed breach of the fundamental terms of the contract. In the Government contracts which are undertaken by the contractor for earning profits, it is implicit that once there is breach, the object of earning profit is nullified. Once such fundamental breach occurs, the party is presumed to have suffered loss of profit. In the case of MSK Project India (supra) the Apex Court has categorically laid down that the claim by contractor for damages as expected profit out of contract, cannot be disallowed on the ground that there was no proof that he has suffered actual loss. The Apex Court in the case of A.T. Brij Paul Singh V/s. State of Gujrat, held that in case of Government contract where the Government commits breach by improperly rescinding the contract the Court should carry out a broad evaluation regarding the damages instead of going into minute details. In the present case the Respondent had made a claim for loss of profit. The Arbitrator was not expected to go through Arb. A 1/2017 the minute details to ascertain the exact figure of damages. The Arbitrator applied rough and ready formula to arrive at the damages payable. Once the Arbitrator arrives at a figure, even by guesswork, the Court may not interfere with it, if it is not unreasonable. 17. The Apex Court in the case of (Mohd. Salamatullah Vs. Government of AP) 11 (1977) 3 SCC 590, while dealing with the grant of damages in the case of breach of contract, held that the appellate Court was not justified in interfering with the quantification of damages, even if they were based on guesswork. In the present case the Arbitrator has granted 10% damages towards the loss of profit. We do not intend to interfere with the award of grant of damages. Not only it appears reasonable to us in facts of the present case, we must also bear in mind the scope of appeal under Section 37 of the Arbitration Act.” [26] With regard to the contention of the employer that the theory of frustration as contemplated under Section 56 of the Indian Contract Act, applies to this case by reason of the supervening impossibility in discharging the contract due to poor soil condition at the site, the learned District Judge has rightly held that the employer should have conducted such soil test before entrusting the work to the contractor and in that event the loss of the contractor for breach of the contract could have been avoided. The learned District Judge has also correctly held that the doctrine of frustration is not applicable in this case because the situation which allegedly prevented the employer from discharging the contract was not Arb. A 1/2017 unexpected and such situation arose due to lack of diligence on the part of the employer. [27] It has surfaced from record that the employer abruptly terminated the contract without issuing notice to the contractor in terms of Clause 13 of the agreement and without exploring the possibilities of improvement of the site by recommendation taking part measures of suggested Geotechnical in the Investigation Report. Even, the proposal of the contractor for providing an alternative site was not also taken care of. Under the agreement between the parties, the employer was under an obligation to hand over the site in a proper state along with the plan and design so as to enable the contractor to execute the work within time. Apparently, the contractor issued several letters to the employer followed by reminders to hand over the site to him along with the plan and design. But, the work site was never handed over to the contractor and the employer unilaterally and arbitrarily cancelled the works contract vide letter dated 19.12.2008 aforesaid, for which the contractor claimed damages for breach of contract. Arb. A 1/2017 [28] From the discussions made above, it stands established that the appellant has failed to discharge his obligation created under the contract. Unilateral rescission of the contract by the employer on invalid ground was clearly unjustified for which the contractor is entitled to compensation for loss in terms of Section 73 of the Indian Contract Act. The damages estimated and claimed by the contractor have been tailored by the arbitrator after scrutiny. His award dated 24.09.2014 has been approved by the learned District Judge vide the impugned judgment dated 19.09.2016. As stated above, the Apex Court in M/S A.T.Brij Paul Singh(supra) has held that in such situation it would be unnecessary to go into the minute details of the work executed in relation to the value of the works contract and a broad evaluation would be sufficient. In the given case we find no illegality in the Arbitrator’s evaluation of loss which has been approved by the learned District Judge. The interest on the award for loss of profit and the award with regard to the cost of the arbitral proceedings is also found justified. [29] Similarly, in the case of Dwaraka Das (supra) the Apex Court has succinctly held that for breach by Arb. A 1/2017 improperly rescinding the contract, the contractor is entitled to claim damages for loss of profit which he expected to earn by undertaking the works contract and the court should make a broad evaluation of such loss instead of going into the minute details. [30] Counsel for the employer relied on the following decisions: (i) (ii) (iii) (iv) (v) (vi) (vi) A.T. Brij Paul Singh vs. State of Gujarat reported in (1984) 4 SCC 59 Dwaraka Das vs. State of M.P reported in AIR 1999 SC 1031 Bharat Cooking Coal Ltd. Vs. L.K.Ahuja, (2004) 5 SCC 109 Sunley(B) and Co. Ltd vs. Cunward White Star, reported in (1940) 1KB 740 The State of Rajasthan vs. Ferro Concrete Construction reported in (2009) 12 SCC 1 Sushila Devi vs. Hari Singh reported in AIR 1971 SC 1756 Satyabrata Ghosh vs. Mugne Ram Bangur & Co. reported in AIR 1954 SC 44. [31] As it has been discussed above, in the case of A.T. Brij Paul Singh (supra), it has been held by the Apex Court that claim of the contractor for recovery of expected profit out of contract for unjustified rescission of contract cannot be disallowed even without proof of actual loss. The appellant, therefore, cannot derive any benefit from the decision. Arb. A 1/2017 [32] (supra) Decision of the Apex Court in A.T. Brij Paul Singh was followed in the case of Dwaraka Das. Therefore, the appellant cannot also derive any benefit from Dwaraka Das which has been relied upon by him. [33] in In Bharat Cooking Coal Ltd. Vs. L.K.Ahuja, reported (2004) 5 SCC 109 the Apex Court in a completely different factual context held that claim for loss of profit cannot be granted unless it is established that had the contractor received the amount due under contract, he would have utilized the same for some other business in which he could have earned profit. The principle having been made in a completely different factual back ground clearly distinguishable from the given case, the decision cannot help the appellant. [34] In the decision aforesaid in Bharat Cooking Coal Ltd., the Apex Court also referred to (B) Sunley and Co. Ltd vs. Cunard White Star Ltd, reported in (1940) 1KB 740. The facts of Sunley and Co. Ltd., (supra), are also clearly distinguishable from the facts of the instant case and therefore, the decision is of no relevance to the case in hand. Arb. A 1/2017 [35] In the case of The State of Rajasthan & Anr., (supra), the contractor started the work entrusted to him. But he could not complete the work on account of delay and breaches. After he stopped the work, the employer issued notice to the contractor asking him to resume the work failing which the work would be got executed through another agency by treating the existing contract as having been abandoned. The contractor started insisting for a fresh agreement on various grounds. Ultimately, when the employer started taking steps to get the work executed through a different agency, the contractor sued the employer. In this factual context the Apex Court held that award of the Arbitrator based on delay was not proper and it was held that the Arbitrator in the case committed legal misconduct. Thus, the appellant of the present case cannot derive any benefit from the said decision which was given in a different factual context. [36] Co. & In Satyabrata Ghose appellant vs. Mugneeran Bangur and Anr. respondents, (supra), the Apex Court while discussing the scope and ambit of Section 56 of the Arb. A 1/2017 Indian Contract Act vide paragraphs 9 & 10 of the judgment has held as under: “9. The first paragraph of the section lays down the law in the same way as in England. It speaks of something which is impossible inherently or by its very nature, and no one can obviously be directed to perform such an act. The second paragraph enunciates the law relating to discharge of contract by reason of supervening impossibility or illegality of the act agreed to be done. The wording of this paragraph is quite general, and though the illustrations attached to it are not at all happy, they cannot derogate from the general words used in the enactment. This much is clear that the word "impossible" has not been used here in the sense of physical or literal impossibility. The performance of an act may not be literally impossible but it may be impracticable and useless from the point of view of the object and purpose which the parties had in view; and if an untoward event or change of circumstances totally upsets the very foundation upon which the parties rested their bargain, it can very well be said that the promisor finds it impossible to do the act which he promised to do. 10. Although various theories have been propounded by the Judges and jurists in England regarding the juridical basis of the doctrine of frustration, yet the essential idea upon which the doctrine is based is that of impossibility of performance of the contract, in fact impossibility and frustration are often used as interchangeable expressions. The changed circumstances, it is said, make the performance of the contract impossible and the parties are absolved from the further performance of it as they did not promise to perform an impossibility.” [37] Relying on the decision in Satyabrata Ghose (supra), the Apex Court reiterated the same principle in Sushila Devi vs. Hari Singh (supra) and held as follows: “11. In our opinion on this point the conclusion of Arb. A 1/2017 the appellate court is not sustainable. But in fact, as found by the trial court as well as by the appellate court, it was impossible for the plaintiffs to even get into Pakistan. Both the trial court as well as the appellate court have found that because of the prevailing circumstances, it was impossible for the plaintiffs to either to take possession of the properties intended to be leased or even to collect rent [1968] 3 S. C. R. 339. from the cultivators. For that situation the plaintiffs were not responsible in any manner. As observed by this Court in Satyabrata Ghose v. Mugneeram Bangur and Co.1954 SCR 310 = (AIR 1954 SC 44), the doctrine of frustration is really an aspect or part of the law of discharge of contract by reason of supervening unpossibility or illegality of the act agreed to be done and hence comes within the purview of Section 56 of the Indian Contract Act. The view that Section 56 applies only to cases of physical impossibility and that where this section is not applicable recourse can be had to the principles of English law on the subject of frustration is not correct. Section 56 of the Indian Contract Act lays down a rule of positive law and does not leave the matter to be determined according to the intention of the parties. The impossibility contemplated by Section 56 of the Contract Act is not confined to something which is not humanly possible. If the performance of a contract becomes impracticable or useless having regard to the object and purpose the parties had in view then it must be held that the performance of the contract has become impossible. But the supervening events should take &way the basis of the contract and it should be of such a character that it strikes at the root of the contract.” [38] Having considered the case in the light of the legal principles laid down by the Apex Court in the cases referred to supra, we are of the view that the view adopted by the arbitrator is a plausible view which cannot be disturbed in exercise of limited jurisdiction and scope of this appeal which is filed for challenging the arbitral award which was also confirmed by the District Court. Arb. A 1/2017 [39] In view of the aforesaid discussions, we do not perceive any substance in the appeal and accordingly, the same stands dismissed. Send back the LCR. (S.G.CHATTOPADHYAY),J (AKIL KURESHI),CJ Saikat Sarma, P.A Arb. A 1/2017

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All Tripura HC judgments →

Arbitration & Mediation advocates near the Tripura High Court

Dealing with a similar matter? Send a free enquiry to advocates who handle it. Fees are agreed with the advocate directly.

All Arbitration & Mediation advocates in India