HIGH COURT OF TRIPURA
AGARTALA
Arb. Appeal No. 01 of 2017
BEFORE
HON’BLE THE CHIEF JUSTICE MR.AKIL KURESHI
HON’BLE MR. JUSTICE S.G.CHATTOPADHYAY
…………..Appellant(s).
The State of Tripura
Versus
M/S N.G.Bhattacharjee
Construction Company
Office Lane: Agartala
West Tripura
For the Appellant(s)
For the Respondent(s)
Date of hearing
Date of delivery of
Judgment and Order
Whether fit for reporting
... ..….Respondent(s).
:
:
:
Mr. Nepal Majumder, Adv.
Mr. Suman Bhattacharjee, Adv.
01.12.2020
:
25.01.2021
Yes No
JUDGMENT
[S.G.Chattopadhyay, J]
This
Appeal
under
Section
of
The
Arbitration and Conciliation Act, 1996(“the 1996 Act”
hereinafter) has been preferred by the State of Tripura
(‘the
employer’
hereunder)
against
judgment
dated
19.09.2016 delivered by the District Judge, West Tripura
in case No. Misc.(ARB)34 of 2015 whereby the application
filed by the employer under Section 34 of the 1996 Act
Arb. A 1/2017
for setting aside the arbitral award dated 24.09.2014 had
been dismissed.
[2]
The basic facts and the controversy brought
before this court are as follows:
The employer floated Notice Inviting Tender
(NIT hereinafter) for execution of the work namely
“Diversion Scheme at Andhicherra, Lalsingmura under
Bishalgarh block / Head works and distribution system”.
Stipulated time for completion of the work was 02(two)
years.
The
respondent
(‘the
contractor’
hereunder)
submitted his tender for the work in terms of the NIT on
05.10.2005
and
acceptance
of
the
tender
was
communicated to the contractor by the employer vide
letter No. F. TS - 428 / WRD - II / W / 6943 - 54 dated
16.02.2006.
By
the
said
letter
of
acceptance,
the
contractor was asked to complete formal agreement with
the employer within 7 days and he was also directed to
start the work at once and complete the work within
02(two) years reckoning from the 15th day after the said
date of acceptance of tender. Pursuant to the said work
order dated 16.02.2006, the contractor and the employer
executed formal
Arb. A 1/2017
agreement on
08.03.2006. Despite
awarding the work, the employer did not hand over the
site to enable the contractor to commence the work. The
contractor,
therefore,
wrote
several
letters
to
the
employer for handing over the site to him to avoid loss of
time. Vide his letter dated 17.03.2006, he pointed out to
the employer that it would be difficult to carry out the
work if monsoon starts and he urged the employer to
hand over the site with plan and design immediately.
Vide subsequent letters dated 13.09.2006, 12.10.2006,
10.11.2006 & 03.12.2006,
he informed the employer
that he kept manpower and machinery ready at the site
since issuance of the work order and he suffered huge
financial loss as a result of the delay in handing over the
site. Finally, vide letter dated 05.12.2006, he again
requested the employer for handing over the site.
[3]
On the other hand, the employer, vide letter
No.TS-428/EE / WRD-II / W / Shadow / 23338-344 dated
19.12.2008 informed the contractor that “due to poor
bearing capacity of the proposed site” the work was
closed and the work order issued vide No.F.TS-428/WRDII/W/6943-54 dated 16.02.2006 stood cancelled. The
Arb. A 1/2017
contractor was asked to contact the employer for refund
of the earnest money deposited by him.
[4]
Thereafter, the contractor vide letter dated
07.01.2009, informed the employer about his inability to
accept the unilateral cancellation of the work order and
proposed to the employer to strengthen the bearing
capacity of the site by doing necessary civil engineering
works, else to provide an alternative site for execution of
the work as per terms of the tender. He conveyed to the
employer, his willingness and readiness to perform the
contract at the agreed rate with allowance of price
escalation as per clause 10CC of the agreement.
[5]
In response, the employer vide letter No.TS-
428/EE/WRD-II/W/Shadow/74-178
dated
13.01.2009
turned down the said proposal of the contractor and
further asked him to take back the earnest money
deposited by him.
[6]
Then
the
contractor,
vide
letter
dated
11.02.2009 submitted the following claim for breach of
contract:
“Schedule of claim
Arb. A 1/2017
(i) Damages for loss on account of loss of profit @10% on contract amount
…..Rs.14,06,286/-
of Rs.1,40,62,000/-
(ii)Damages on account of anfractuous expenses on over heads being the
salary paid to the site staff comprising of representative and graduate
engineer.
a)Representative for 34 months @Rs.5000/- per month
….Rs.1,70,000/-
b) Site engineer for 29 months @Rs.8000/- per month
….Rs.2,32,000/-
Total
[7]
Rs.18,08,286/-“
The contractor demanded payment of such
damages within 28.02.2009 failing which he claimed 12%
annual interest on the amount from 01.03.2009. Vide
application dated 13.04.2009, the contractor proposed to
the employer for appointment of an arbitrator in terms of
clause 25 of the agreement for resolving the disputes
between them.
[8]
Ultimately, vide letter dated 25.04.2009, the
employer appointed the arbitrator and the matter was
referred
to
the
sole
arbitrator,
so
appointed,
for
adjudication of the disputes between the parties and
make award on the claims / counter claims referred by
the parties subject to their admissibility in terms of clause
25 of the agreement. The sole arbitrator conducted the
arbitral proceedings and decided the matter vide order
dated 24.09.2014 in favour of the contractor. The
relevant extract of the Award is as under:
Arb. A 1/2017
“FINDINGS AND AWARD
“........................................................................................................
In view of my above findings, the award on the claims of the
claimant contractor is summarized below:
AWARD ON THE CLAIMS OF THE CLAIMANT
The Arbitrator is to decide
Award
1. Whether the claimant is entitled to
get damages being the loss of profit
@10% on the contract amount of
Rs.1,40,62,858/only
due
to
breach of contract committed by
the Respondent.
Whether the claimant is entitled to
get
damages
on account
of
anfractuous expenses on overheads
being the salary paid to the staff
comprising of representative and
graduate engineer.
a) Representative for 34 months
@Rs.5000/- per month.
b) Site engineer for 29 months
@8000/- per month.
Whether the claimant is entitled to
get
interest
@12%
p.a.
on
Rs.18,08,286/- from the date of
cause
of
action
/
dispute
i.e.24.02.2009 till realization.
Whether the claimant is entitled
to get Rs.25,000/- cost of
arbitration proceedings.
THIS
CLAIM
HAS
BEEN
PARTIALLY
ESTABLISHED
PARTLY.
HENCE
I
AWARD
RS.8,43,771/-(RUPEES
EIGHT
LAKHS FORTY-THREE THOUSAND
SEVEN HUNDRED SEVENTY-ONE
ONLY UNDER THIS ISSUE)
THIS CLAIM HAS NOT BEEN
ESTABLISHED. HENCE, I AWARD
NOTHING UNDER THIS ISSUE.
THE CLAIM HAS BEEN ESTABLISHED.
I AWARD SIMPLE INTEREST @8%
(EIGHT PERCENT) P.A. ON THE
AWARDED SUM OF RS.8,43,771/(RUPEES EIGHT LAKHS FORTY-THREE
THOUSAND
SEVEN
HUNDRED
SEVENTY-ONE)ONLY
w.e.f.
24/02/2009 UP TO THE DATE OF
AWARD. THE AWARD SHALL CARRY
FURTHER INTEREST @ 9.50%(NINE
POINT FIVE ZERO PERCENT)P.A
FROM THE DATE OF PUBLISHING THE
AWARD TILL THE DATE OF ACTUAL
PAYMENT IF THE AWARDED SUM
WITH INTEREST AND COST IS NOT
PAID WITHIN 3 (THREE)MONTHS.
THIS
CLAIM
HAS
BEEN
ESTABLISHED. HENCE I AWARD
RS.5,000/-(RUPEES
FIVE
THOUSAND)ONLY
UNDER
THIS
ISSUE.
The stamp duty charges of Rs.75/-(Rupees seventyfive) only have been borne by the claimant contractor.”
[9]
The arbitrator has thus tailored the claim of
the contractor. He claimed 10% loss of profit on the
contract value. The arbitrator has given him less. His
Arb. A 1/2017
claim for damages for loss towards payment of salary to
his representative, site engineer and labourers has also
been rejected by the arbitrator. He claimed Rs.25,000/as the cost of arbitral proceedings which has been
reduced
to
Rs.5,000/-
by
the
arbitrator.
But
the
contractor did not dispute the arbitral award.
[10]
The employer, being aggrieved with the said
arbitral award, filed an application under Section 34 of
the 1996 Act in the court of the District Judge, West
Tripura at Agartala. The District Judge vide the impugned
judgment dated 19.09.2016, dismissed the application
and approved the arbitral award.
[11]
Aggrieved with the said judgment of the
District Judge, the employer has challenged the arbitral
award by means of filing this appeal under Section 37 of
the 1996 Act.
[12]
Mr.
Nepal
Majumder,
learned
counsel
appearing for the employer, has argued that there is no
merit in the claim of the contractor. Mr. Majumder,
learned counsel has submitted written arguments in the
case contending, inter alia, as follows:
Arb. A 1/2017
(i)The Arbitrator as well as the learned District
Judge failed to appreciate the fact that the
employer had to terminate the works contract
in view of the soil testing report confirming
poor subsoil condition at the site and in view of
Section 56 of the Contract Act, failure of the
employer in performing the contract in such
situation cannot be termed as breach of
contract entitling the contractor to damages
for loss.
(ii)The contractor was not entitled to the
damages claimed by him because he could not
establish by evidence that he actually invested
any capital for execution of work and as a
result of delay in handing over the site, his
capital was blocked which he could have
invested elsewhere and earned profit.
(iii)
The
learned
District
Judge
failed
to
appreciate the fact that the contractor could
not prove any financial loss as a result of
cancellation of the works contract.
Counsel for the employer has relied on few
decisions which shall be discussed at a later stage.
Arb. A 1/2017
[13]
Conversely, Mr. Suman Bhattacharjee, learned
counsel representing the contractor submits that the
learned District Judge upheld the arbitral award after
proper
appreciation
of
evidence
and
facts
and
circumstances of the case and as such the findings of the
learned District Judge do not call for any interference in
appeal.
[14]
Further submission on behalf of the contractor
is that termination of the contract on the ground of poor
load bearing capacity of soil is beyond the terms of the
said contract between the parties. Moreover, in the
recommendation part of the Geotechnical Investigation
Report,
various
measures
were
suggested
for
improvement of the load bearing capacity of the soil.
Without exploring the feasibility of those suggestions, the
employer arbitrarily cancelled the works order and that
too unilaterally without giving stipulated notice to the
contractor. Such unilateral cancellation of the works
contract by the employer is a clear breach of contract for
which the contractor is entitled to the damages claimed
by him.
Arb. A 1/2017
[15]
Mr. Bhattacharjee, learned counsel of the
contractor has further argued that it is manifest on the
face of the record that the contractor was always willing
and ready to perform the contract. The employer on the
other hand was reluctant to perform the contract for
which right from the beginning, the employer delayed in
handing over of the site to the contractor and ultimately
cancelled
the
works
contract
unilaterally
to
the
disadvantage of the contractor causing huge financial loss
to him.
[16]
According
to
Mr.
Bhattacharjee,
learned
counsel, the contractor proved that he invested money
for
engagement
of
manpower
and
installation
of
machinery at the site for execution of the work and
thereby suffered huge financial loss for cancellation of the
contract.
According
counsel,
the
to
arbitrator
Mr.
rightly
Bhattacharjee,
made
the
learned
award
to
compensate his loss which was also approved by the
learned District Judge. Learned counsel, therefore, urges
this court for dismissing the appeal.
[17]
As noted by us, the employer vide letter
No.F.TS-428/WRD-II/W/6943-54 dated 16.02.2006 issued
Arb. A 1/2017
the work order to the contractor and asked him to
complete the work within a period of 02(two) years in
terms of the agreement and it was stipulated that the
period of 02 years would be reckoned from the 15 th day
from the date of issuance of the said work order i.e. from
16.02.2006. Despite awarding the work contract, the
employer did not hand over the site to the contractor to
commence the
work. In order
to
demonstrate
his
readiness and willingness to perform the contract, the
contractor vide his letter dated 10.11.2006 informed the
employer that he had already set up a camp shed and
constructed approach road to the site to start the work
and again urged the employer to hand over the site. He
wrote several other letters, as quoted above, to the
employer for handing over the site to him. Finally, vide
letter dated 03.12.2007, the contractor wrote to the
employer that unless the site was handed over to him
immediately, he would raise his demand for damages for
loss of profit and for loss owing to his investment in
manpower and machinery. The employer, thereafter, vide
letter dated 19.12.2008, cancelled the contract and asked
the contractor to take back the earnest money deposited
by him. In this factual back ground, the contractor
Arb. A 1/2017
claimed
before
the
Arbitral
Tribunal
that
unilateral
cancellation of the works contract on the ground of poor
load bearing capacity of the soil at the site without
serving notice on him amounted to breach of contract for
which he was entitled to damages for loss of profit and
other investments.
[18]
In
the
counter
statement,
the
employer
stated that though they were interested for execution of
the work, the soil condition did not permit the execution.
According to the employer, Geo-technical investigation of
the site was conducted twice. Once in January, 2008 and
then in July, 2008 which revealed that the soil foundation
at the site was very poor and not suitable for execution of
such work. Alternative proposals were also explored, but
it did not work. According to the employer, the works
contract had to be cancelled for unforeseen reason and
the contractor was not entitled to damages because he
did not make any investment for execution of the work.
[19]
In his rejoinder, the contractor stated that
work order was issued to him on 16.02.2006 with a
direction to commence the work at once and complete
the work within the stipulated period of two years which
Arb. A 1/2017
would be complete on 02.03.2008, whereas, soil test was
conducted by the employer in January, 2008 i.e. almost
at the end of the contract period and again in July, 2008
and
such
act
of
the
employer
demonstrated
the
unwillingness of the employer to perform the contract.
Further contention of the contractor in his rejoinder was
that the Safe Bearing Capacity (SBC) of the soil at the
site could have been easily improved by the employer by
taking the measures suggested by the experts in the
recommendation part of their Geotechnical Investigation
Report. Therefore, the plea of the employer that the
termination of the contract by reason of supervening
impossibility was saved under Section 56 of the Indian
Contract Act, 1872 was not acceptable.
The findings of the arbitrator, on the said
issues, were as under:
“I have carefully gone through
the contract document at page 83 i.e. the
design data which provides for procedure to
be adopted in case of bearing capacity of the
soil in case the same is found below
10T/sqm.
I have also carefully considered
the pleadings and arguments advanced on
the side of the parties including documents
filed with the claim statement and defence
statement. From Annexure R/3 i.e. soil
testing report of July, 2008, I find that SBC
was found as 9 T/sqm, which is seen at page
12 of the said Geotechnical Investigation
Report for the proposed diversion scheme of
Arb. A 1/2017
Andhicherra as done by the expert EMC
construction, Agartala for raft foundation at
4.5 m from existing ground level with
suggestion given at Sl.No(iii) by the said
expert at page 12 of Annexure R/3. Had the
respondent any interest in getting the work
executed by the claimant, it ought to have
followed the provision of agreement at page
83 (Design Data) in case of bearing capacity
found below 10 T/sqm including the
suggestion given the EMC Construction.
I have also examined the letter
of the claimant dated 17/01/2009(Exhibit
C/15) particularly the contraction made by it
in para 11(i),(ii) and (iii) and the proposal as
was submitted appears to me a reasonable
one being within the parameters of the
contract agreement vide page 83 but the
respondent refused to accept any of the said
proposal.
During hearing proceedings, the
respondent agreed to provide alternate side
for executing the same type of job and the
claimant acceded to such proposal however
with
a
condition
of
allowing
rate
enhancement of additional 70% over the
original agreement rate of 49.90% above i.e.
rate enhancement of 10% each year for
seven years, which is as per Government
Order as reflected in Tripura Gazette
Extraordinary Issue, June 7 2007 A.D. A copy
of which has been submitted as Annexure 2
with the written counter argument filed on
01/08/2013. Such proposal from the side of
the claimant appears to me to be quite
reasonable and in the interest of public work.
From the activities of the claimant contract, I
find that he was all through ready and willing
to execute the work but it is the respondent
who has failed to discharge its obligations
under the contract. The respondent backed
out from its own commitment of providing
alternate site though on such commitment,
the arbitration proceeding was kept in
abeyance for a considerable period of time
for
amicable
settlement
by
providing
alternate side, which the respondent has
failed as intimated during the hearing held on
27/03/2014.
The
respondent’s contention
that for impossibility and frustration of the
contract as per Section 56 of the Indian
Contract
Act,
is
held
to
be
unsustainable in law as the contract has itself
taken care of for improving the bearing
capacity of soil at page 83, which the
respondent that it had power to close the
agreement under Clause 13 of the agreement
is also held to be unsustainable and hence
fails as the letter of the respondent dated
19/12/2008(Exhibit C/14) does not indicate
Arb. A 1/2017
exercise of power under Clause 13 of the
agreement for and on behalf of the Governor
of Tripura.”
[20]
Finally, vide award dated 24.09.2014, the
arbitrator partially accepted the claim of the contractor
and made the award as quoted above.
[21]
The learned District Judge found no reason to
interfere with the award made by the arbitrator and
accordingly turned down the application filed by the
employer under Section 34 of the 1996 Act. Relevant
paragraphs of the judgment containing the findings of the
learned District Judge are as under:
“10.
Under the scheme of Section 34 of the
Arbitration and Conciliation Act, judicial review is
restrained to the extent if the Arbitrator acts beyond
the scope of reference and if the award of the
Arbitrator is in conflict with public policy of India.
Explanation to Section 34(1)(b)(ii) of the Act makes it
clear that if the making of the award was induced or
affected by fraud or corruption or was in violation of
Section 75 and Section 81 of the Arbitration and
Conciliation Act, 1996, it shall be deemed to be against
the public policy of India.
11.
In the case at hand there is no indication that
the sole Arbitrator or the parties did not keep anything
confidential relating to the arbitration and there is no
allegation of violation of the Provision of Section 81 of
the Arbitration and Conciliation Act, 1996.
12.
The argument of learned counsel Mr. Sengupta
that Clause 13 of the agreement empowers to the
department to cancel the work order at any time is also
not acceptable. Clause 13 of the agreement deals with
a situation where after commencement of the work the
Governor decides that any part of the work is not
required to be executed, the Engineer-in-charge shall
give notice in writing of the fact to the contractor who
shall have no claim to any payment whatsoever on
Arb. A 1/2017
account of any profit which he might have derived from
the execution of the work in full.
13.
In the case at hand the work was not
commenced at all. Rather it was unilaterally cancelled
after more than two years. Work order was issued on
16-02-2006, to be commenced from 03-03-2006 and to
be completed within 02-03-2008. The department
petitioner conducted geo technical investigation in the
months of January and July, 2008 which is even after
the stipulated period of completion of the work.
Ultimately, the work order was unilaterally cancelled
on 19-12-2008.
14.
What necessarily follows is that the opposite
party-contractor being a professional organization
could not do any work for more than two years and
could not utilize its capital for that period.
15.
The doctrine of frustration stipulated under
Section 56 of the Indian Contract Act is not applicable
at all. Rather under Section 56 of the Act the petitioner
department being promissor failed to keep its promise
for the fact that the work site was not proper for
undertaking the diversion scheme. If the petitioner
department conducted geo technical investigation
before issuing the work order, this situation could be
avoided. Meaning thereby the petitioner department
did not exercise reasonable diligence and if such
reasonable diligence was exercised by the petitioner
department, it might have come to the knowledge of
the petitioner department that the soil of the work site
was not fit for undertaking the diversion scheme and in
turn no loss would have occurred to the opposite partycontractor. Therefore, under Section 56 read with
Section 73 of the Indian Contract Act, the petitioner
department is liable to compensate for loss caused to
the opposite party-contractor by breach of contract.
Therefore, I do not find any misconduct or any
arbitrary finding on the part of the sole Arbitrator. The
sole Arbitrator allowed 6% as loss of profit on the
contract value against the claim of 10% by the
opposite party-contractor.”
[22]
In the present case, manifestly there is a
breach of contract. Learned District Judge has rightly held
that
the
employer
should
have
conducted
the
Geotechnical Investigation of soil at the site before they
issued the work order and in that event they could have
Arb. A 1/2017
avoided the situation. Findings of the learned District
Judge
that
contract
the
employer
unilaterally
improperly
without
issuing
rescinded
the
notice
the
to
contractor as contemplated under clause 13 of the
agreement is not also incorrect. It would be apposite at
this stage to reproduce clause 13 of the agreement which
is as under:
“Clause 13: If at any time after the
commencement of the work the Governor of Tripura
shall for any reason whatsoever not require the
whole thereof as specified in the tender to be
carried out the Engineer-in-Charge shall give notice
in writing of the fact to the contractor who shall
have no claim to any payment of compensation
whatsoever on account of any profit or advantage
which he might have derived from the execution of
the work in full, but which he did not derive in
consequence of the full amount of the work not
having been carried out, neither shall he have any
claim for compensation by reason of any alterations
having been made in the original specifications,
drawings, designs and instructions which shall
involve any curtailment of the work as originally
contemplated.
Provided that the contractor shall be
paid the charges on the cartage only of materials
actually and bonafide brought to the site of the work
by the contractor and rendered surplus as result of
the abandonment or curtailment of the work or any
portion thereof and then taken back by the
contractor provided Engineer-in-Charge shall have
in all such cases the option of taking over all or any
such materials at their purchase price or at local
current rate whichever may be less. “In the case of
such stores having been issued from Government
stores
and
returned
by
the
contractor
to
Government stores, credit shall be given to him by
the Engineer-in-Charge at rates not exceeding those
at which they were originally issued to him, after
taken into consideration and education for claims on
account of any deterioration or damage while in the
custody of the contractor and in this respect the
decision of the Engineer-in-Charge shall be final”
Arb. A 1/2017
[23]
Obviously, the employer never issued such
notice to the contractor and most arbitrarily terminated
the contract. Evidently, the recommendations of the
experts
projected
in
the
Geotechnical
Investigation
Report for improvement of soil condition at the site were
totally ignored. Contractor’s proposal for alternative site
was not at all considered. Behaviour of the employer right
from the beginning manifested their unwillingness in
performing the contract. In these circumstances, the
finding of the learned District Judge with regard to breach
of contract on the part of the employer is well founded.
The award of damages for loss of profit, is therefore,
absolutely justified. The Apex Court in M/S A.T.Brij Paul
Singh and Ors. vs. State of Gujrat reported in (1984) 4 SCC
59 has succinctly held that when a work is entrusted to a
contractor, he is always in a reasonable expectation of
profit and therefore, he will be entitled to damages for
loss of profit, if the other party commits breach of the
contract. The observation of the Apex Court is as under:
“10….. ordinarily a contractor while
submitting his tender in response to an
invitation to tender for a works contract
reasonably expects to make profits. What would
be the measure of profit would depend upon
Arb. A 1/2017
facts and circumstances of each case. But that
there shall be a reasonable expectation of profit
is implicit in a works contract and its loss has to
be compensated by way of damages if the other
party to the contract is guilty of breach of
contract cannot be gainsaid.”
[24]
in
In Dwaraka Das vs. State of M.P. and Anr. reported
(1999) 3 SCC 500,
the Apex Court having relied on
A.T.Brij Paul Singh and Ors (supra), allowed the claim of
the contractor for damages @ 10% on the contract value
and held that where there is a breach of contract
committed by the government by improperly rescinding
the contract, the court should make a broad evaluation of
damages
without
going
into
the
minute
details.
Observation of the Apex Court in paragraph 9 of the
judgment in this regard is as follows:
“9. The claim of the petitioner for payment of Rs.
20,000 as damages on account of breach of
contract committed by the respondent- State was
disallowed by the High Court as the appellant was
found to have not placed the material on record to
show that he had actually suffered any loss on
account of the breach of contract. In this regard,
the appellate court observed:
Arb. A 1/2017
"It is not his case that for due
compliance of the contract he had
advanced money to the labourers or
that he had purchased materials or that
he had incurred any obligations and on
account of breach of contract by the
defendants he had to suffer loss on the
above and other heads. Even in regard
to the percentage of profit he did not
place any material on record but relied
upon assessment of the profits by the
Income Tax Officer while assessing the
income of the contractors from building
contracts."
Such a finding of the appellate court appears
to be based on wrong assumptions. The appellant
had never claimed Rs. 20,000 on account of
alleged actual loss suffered by him. He had
preferred his claim on the ground that had he
carried out the contract, he would have earned
profit of 10% on Rs. 2 lacs which was the value of
the contract. This Court in A.T. Brij Paul Singh v.
State or Gujarat, [1984] 4 SCC 59 while
interpreting the provisions of Section 73 of the
Contract Act,1872 has held that damages can be
claimed by a contractor where the government is
proved to have committed breach by improperly
rescinding the contract and for estimating the
amount of damages, court should make a broad
evaluation instead of going into minute details. It
was specifically held that where in the works
contract, the party entrusting the work committed
breach of contract, the contractor is entitled to
claim the damages for loss of profit which he
expected to earn by undertaking the works
contract. Claim of expected profits is legally
admissible on proof of the breach of contract by
the erring party. It was observed:(SCC pp.64-65,
paras 10-11)
"What would be the measure of profit
would
depend
upon
facts
and
circumstances of each case. But that
there shall be a reasonable expectation
of profit is implicit in a works contract
and its loss has to be compensated by
way of damages if the other party to
the contract is guilty of breach of
contract cannot be gainsaid. In this
case we have the additional reason for
rejecting the contention that for the
same type of work, the work site being
in the vicinity of each other and for
identical type of work between the
same parties, a Division Bench of the
same High Court has accepted 15 per
cent of the value of the balance of the
works contract would not be an
unreasonable measure of damages for
loss of profit.
Now if it is well-established that the
respondent was guilty of breach of
contract inasmuch as the rescission of
contract by the respondent is held to be
unjustified, and the plaintiff-contractor
had executed a part of the works
contract, the contractor would be
entitled to damages by way of loss of
profit. Adopting the measure accepted
by the High Court in the facts and
circumstances of the case between the
same parties and for the same type of
work at 15 per cent of the value of the
remaining parts of the works contract,
the damages for loss of profit can be
measured."
Arb. A 1/2017
To the same effect is the judgment in Mohd.
Salamatullah
v.
Government
of
Andhra
Pradesh,(1977)3 SCC 590 : AIR (1977) SC 1481.
After approving the grant of damages in case of
breach of contract, the court further held that the
appellate court was not justified in interfering with
finding of fact given by the trial court regarding
quantification of the damages even if it was based
upon guess work. In both the cases referred to
hereinabove, 15% of the contract price was
granted as damages to the contractor. In the
instant case however, the trial court had granted
only 10% of the contract price which we feel was
reasonable and permissible, particularly when the
High Court had concurred with the finding of the
trial court regarding breach of contract by
specifically holding that "we, therefore, see no
reason to interfere with the finding recorded by
the trial court that the defendants by rescinding
the agreement committed breach of contract." It
follows therefore, as and when the breach of
contract is held to have been proved being
contrary to law and terms of the agreement, the
erring party is legally bound to compensate the
other party to the agreement. The appellate court
was, therefore, not justified in disallowing the
claim of the appellant for Rs. 20,000 on account of
damages as expected profit out of the contract
which was found to have been illegally rescinded.”
[25]
Similarly, relying on the principle laid down in
the case of M/S A.T.Brij Paul Singh and Ors (supra), the
Bombay
High
Court
in
Union
of
India
Vs.
Vaman
Prestressing Co.Ltd. reported in 2019 SCC On Line Bom 192
declined to interfere with the Arbitrator’s assessment
awarding 10% damages to the contractor towards loss of
profit for breach of contract by the other side and held as
under:
7. In A.T. Brij Paul Singh vs. State of Gujarat AIR
1984 SC 1703, the Supreme Court considered the
question of damages payable to a contractor of a
works contract upon the employer committing a
breach by improper rescission of the contract. The
court held that ordinarily, when the contractor
submits his tender in response to an invitation to
Arb. A 1/2017
tender for a works contract, a reasonable
expectation of profits is implicit in it and its loss
has to be compensated by way of damages if the
other party to the contract is guilty of breach of
contract. The court held that though what would
be the measure of profit would always depend
upon facts and circumstances of each case, whilst
estimating such loss of profit, it would not be
necessary to go into minute details; what would be
sufficient and expected of the court would be a
broad evaluation of the matter. In other words, not
only is a claim of loss of profits admissible, but the
measure of damages in that case has to be worked
out by taking a broad view of the matter. In A.T.
Brij Paul Singh's case, the Supreme Court
considered adoption of a measure of damages by
the High Court in the facts and circumstances of
the case between the same parties and for the
same type of work at 15% of the value of the
remaining work as an acceptable measure even for
another contract for assessing damages towards
loss of profit.
8. This law was followed by a Division Bench of our
court in Mahanagar Gas Ltd. vs. Babulal
Uttamchand & Co.2013 (5) Bom.C.R. 756 . Our
court held as follows:
“16. Thus, it is clear from the dicta of the
Apex Court reproduced above that the claim
for damages by a party is admissible once it
demonstrates that the other party has
committed breach of the fundamental terms
of the contract. In the Government
contracts which are undertaken by the
contractor for earning profits, it is implicit
that once there is breach, the object of
earning profit is nullified. Once such
fundamental breach occurs, the party is
presumed to have suffered loss of profit. In
the case of MSK Project India (supra) the
Apex Court has categorically laid down that
the claim by contractor for damages as
expected profit out of contract, cannot be
disallowed on the ground that there was no
proof that he has suffered actual loss. The
Apex Court in the case of A.T. Brij Paul
Singh V/s. State of Gujrat, held that in case
of
Government
contract
where
the
Government commits breach by improperly
rescinding the contract the Court should
carry out a broad evaluation regarding the
damages instead of going into minute
details. In the present case the Respondent
had made a claim for loss of profit. The
Arbitrator was not expected to go through
Arb. A 1/2017
the minute details to ascertain the exact
figure of damages. The Arbitrator applied
rough and ready formula to arrive at the
damages payable. Once the Arbitrator
arrives at a figure, even by guesswork, the
Court may not interfere with it, if it is not
unreasonable.
17. The Apex Court in the case of (Mohd.
Salamatullah Vs. Government of AP) 11
(1977) 3 SCC 590, while dealing with the
grant of damages in the case of breach of
contract, held that the appellate Court was
not justified in interfering with the
quantification of damages, even if they
were based on guesswork. In the present
case the Arbitrator has granted 10%
damages towards the loss of profit. We do
not intend to interfere with the award of
grant of damages. Not only it appears
reasonable to us in facts of the present
case, we must also bear in mind the scope
of appeal under Section 37 of the
Arbitration Act.”
[26]
With regard to the contention of the employer
that the theory of frustration as contemplated under
Section 56 of the Indian Contract Act, applies to this case
by reason of the supervening impossibility in discharging
the contract due to poor soil condition at the site, the
learned District Judge has rightly held that the employer
should have conducted such soil test before entrusting
the work to the contractor and in that event the loss of
the contractor for breach of the contract could have been
avoided. The learned District Judge has also correctly
held that the doctrine of frustration is not applicable in
this case because the situation which allegedly prevented
the employer from discharging the contract was not
Arb. A 1/2017
unexpected and such situation arose due to lack of
diligence on the part of the employer.
[27]
It has surfaced from record that the employer
abruptly terminated the contract without issuing notice to
the contractor in terms of Clause 13 of the agreement
and without exploring the possibilities of improvement of
the
site
by
recommendation
taking
part
measures
of
suggested
Geotechnical
in
the
Investigation
Report. Even, the proposal of the contractor for providing
an alternative site was not also taken care of. Under the
agreement between the parties, the employer was under
an obligation to hand over the site in a proper state along
with the plan and design so as to enable the contractor to
execute the work within time. Apparently, the contractor
issued several letters to the employer followed by
reminders to hand over the site to him along with the
plan and design. But, the work site was never handed
over to the contractor and the employer unilaterally and
arbitrarily cancelled the works contract vide letter dated
19.12.2008 aforesaid, for which the contractor claimed
damages for breach of contract.
Arb. A 1/2017
[28]
From the discussions made above, it stands
established that the appellant has failed to discharge his
obligation
created
under
the
contract.
Unilateral
rescission of the contract by the employer on invalid
ground was clearly unjustified for which the contractor is
entitled to compensation for loss in terms of Section 73 of
the Indian Contract Act. The damages estimated and
claimed by the contractor have been tailored by the
arbitrator after scrutiny. His award dated 24.09.2014 has
been approved by the learned District Judge vide the
impugned judgment dated 19.09.2016. As stated above,
the Apex Court in M/S A.T.Brij Paul Singh(supra) has held
that in such situation it would be unnecessary to go into
the minute details of the work executed in relation to the
value of the works contract and a broad evaluation would
be sufficient. In the given case we find no illegality in the
Arbitrator’s evaluation of loss which has been approved
by the learned District Judge. The interest on the award
for loss of profit and the award with regard to the cost of
the arbitral proceedings is also found justified.
[29]
Similarly, in the case of Dwaraka Das (supra) the
Apex Court has succinctly held that for breach by
Arb. A 1/2017
improperly rescinding the contract, the contractor is
entitled to claim damages for loss of profit which he
expected to earn by undertaking the works contract and
the court should make a broad evaluation of such loss
instead of going into the minute details.
[30]
Counsel
for
the
employer
relied
on
the
following decisions:
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vi)
A.T. Brij Paul Singh vs. State of Gujarat reported
in (1984) 4 SCC 59
Dwaraka Das vs. State of M.P reported in AIR
1999 SC 1031
Bharat Cooking Coal Ltd. Vs. L.K.Ahuja, (2004) 5
SCC 109
Sunley(B) and Co. Ltd vs. Cunward White Star,
reported in (1940) 1KB 740
The State of Rajasthan vs. Ferro Concrete
Construction reported in (2009) 12 SCC 1
Sushila Devi vs. Hari Singh reported in AIR 1971
SC 1756
Satyabrata Ghosh vs. Mugne Ram Bangur & Co.
reported in AIR 1954 SC 44.
[31]
As it has been discussed above, in the case of
A.T. Brij Paul Singh (supra), it has been held by the Apex
Court that claim of the contractor for recovery of
expected profit out of contract for unjustified rescission of
contract cannot be disallowed even without proof of
actual loss. The appellant, therefore, cannot derive any
benefit from the decision.
Arb. A 1/2017
[32]
(supra)
Decision of the Apex Court in A.T. Brij Paul Singh
was
followed
in
the
case
of
Dwaraka
Das.
Therefore, the appellant cannot also derive any benefit
from Dwaraka Das which has been relied upon by him.
[33]
in
In Bharat Cooking Coal Ltd. Vs. L.K.Ahuja, reported
(2004) 5 SCC 109
the Apex Court in a completely
different factual context held that claim for loss of profit
cannot be granted unless it is established that had the
contractor received the amount due under contract, he
would have utilized the same for some other business in
which he could have earned profit. The principle having
been made in a completely different factual back ground
clearly distinguishable from the given case, the decision
cannot help the appellant.
[34]
In the decision aforesaid in Bharat Cooking Coal
Ltd., the Apex Court also referred to (B) Sunley and Co. Ltd
vs. Cunard White Star Ltd,
reported in (1940) 1KB 740. The
facts of Sunley and Co. Ltd., (supra), are also clearly
distinguishable from the facts of the instant case and
therefore, the decision is of no relevance to the case in
hand.
Arb. A 1/2017
[35]
In the case of
The State of Rajasthan & Anr.,
(supra), the contractor started the work entrusted to him.
But he could not complete the work on account of delay
and breaches. After he stopped the work, the employer
issued notice to the contractor asking him to resume the
work failing which the work would be got executed
through another agency by treating the existing contract
as having
been
abandoned. The contractor started
insisting for a fresh agreement on various grounds.
Ultimately, when the employer started taking steps to get
the work executed through a different agency, the
contractor sued the employer. In this factual context the
Apex Court held that award of the Arbitrator based on
delay was not proper and it was held that the Arbitrator
in the case committed legal misconduct. Thus, the
appellant of the present case cannot derive any benefit
from the said decision which was given in a different
factual context.
[36]
Co.
&
In Satyabrata Ghose appellant vs. Mugneeran Bangur and
Anr.
respondents,
(supra), the Apex Court while
discussing the scope and ambit of Section 56 of the
Arb. A 1/2017
Indian Contract Act vide paragraphs 9 & 10 of the
judgment has held as under:
“9. The first paragraph of the section lays down
the law in the same way as in England. It
speaks of something which is impossible
inherently or by its very nature, and no one can
obviously be directed to perform such an act.
The second paragraph enunciates the law
relating to discharge of contract by reason of
supervening impossibility or illegality of the act
agreed to be done. The wording of this
paragraph is quite general, and though the
illustrations attached to it are not at all happy,
they cannot derogate from the general words
used in the enactment. This much is clear that
the word "impossible" has not been used here
in the sense of physical or literal impossibility.
The performance of an act may not be literally
impossible but it may be impracticable and
useless from the point of view of the object and
purpose which the parties had in view; and if an
untoward event or change of circumstances
totally upsets the very foundation upon which
the parties rested their bargain, it can very well
be said that the promisor finds it impossible to
do the act which he promised to do.
10. Although various theories have been
propounded by the Judges and jurists in
England regarding the juridical basis of the
doctrine of frustration, yet the essential idea
upon which the doctrine is based is that of
impossibility of performance of the contract, in
fact impossibility and frustration are often used
as interchangeable expressions. The changed
circumstances, it is said, make the performance
of the contract impossible and the parties are
absolved from the further performance of it as
they
did
not
promise
to
perform
an
impossibility.”
[37]
Relying on the decision in
Satyabrata Ghose
(supra), the Apex Court reiterated the same principle in
Sushila Devi vs. Hari Singh (supra) and held as follows:
“11. In our opinion on this point the conclusion of
Arb. A 1/2017
the appellate court is not sustainable. But in fact,
as found by the trial court as well as by the
appellate court, it was impossible for the plaintiffs
to even get into Pakistan. Both the trial court as
well as the appellate court have found that
because of the prevailing circumstances, it was
impossible for the plaintiffs to either to take
possession of the properties intended to be leased
or even to collect rent [1968] 3 S. C. R. 339. from
the cultivators. For that situation the plaintiffs
were not responsible in any manner. As observed
by this Court in Satyabrata Ghose v. Mugneeram
Bangur and Co.1954 SCR 310 = (AIR 1954 SC 44),
the doctrine of frustration is really an aspect or
part of the law of discharge of contract by reason
of supervening unpossibility or illegality of the act
agreed to be done and hence comes within the
purview of Section 56 of the Indian Contract Act.
The view that Section 56 applies only to cases of
physical impossibility and that where this section
is not applicable recourse can be had to the
principles of English law on the subject of
frustration is not correct. Section 56 of the Indian
Contract Act lays down a rule of positive law and
does not leave the matter to be determined
according to the intention of the parties. The
impossibility contemplated by Section 56 of the
Contract Act is not confined to something which is
not humanly possible. If the performance of a
contract becomes impracticable or useless having
regard to the object and purpose the parties had in
view then it must be held that the performance of
the contract has become impossible. But the
supervening events should take &way the basis of
the contract and it should be of such a character
that it strikes at the root of the contract.”
[38]
Having considered the case in the light of the
legal principles laid down by the Apex Court in the cases
referred to supra, we are of the view that the view
adopted by the arbitrator is a plausible view which cannot
be disturbed in exercise of limited jurisdiction and scope
of this appeal which is filed for challenging the arbitral
award which was also confirmed by the District Court.
Arb. A 1/2017
[39]
In view of the aforesaid discussions, we do not
perceive any substance in the appeal and accordingly, the
same stands dismissed.
Send back the LCR.
(S.G.CHATTOPADHYAY),J
(AKIL KURESHI),CJ
Saikat Sarma, P.A
Arb. A 1/2017
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review