HIGH COURT OF TRIPURA
AGARTALA
RFA 15 of 2015
1. The State of Tripura,
represented by the Secretary-cum-Commissioner,
Public Works Department(WR), Civil Secretariat,
New Capital Complex, P.O. Kunjaban, Agartala,
West Tripura
2. The Chief Engineer,
Public Works Department(Water Resources),
Government of Tripura, Kunjaban, P.O. Agartala,
District : West Tripura
3. The Superintending Engineer,
Water Resource Circle No.II,
Government of Tripura, P.O. Kumarghat,
District : North Tripura
4. The Executive Engineer,
Water Resources Division No.VII,
Government of Tripura, P.O. Pecharthal,
District : North Tripura
5. The Executive Engineer,
I & FM Division No.VI,
now Water Resources Division No.VI,
Government of Tripura, P.O. Kailashahar,
District : North Tripura
6. The Assistant Engineer,
Water Resources Sub-Division,
Government of Tripura,
P.O. Dharmanagar, District : North Tripura
----Appellant(s)
Versus
Sri Kajal Datta,
son of late Harendra Kumar Datta,
Government Contractor, D.N.V. Road,
P.O. & P.S. Dharmanagar, District : North Tripura
---- Respondent(s)
For Appellant(s)
:
Mr. M. Debbarma, Addl. G.A.
For Respondent(s)
:
Mr. A Dasgupta, Adv.
Date of delivery of
Judgment & Order
:
11.12.2019
Whether fit for
reporting
:
YES
BEFORE
HON‟BLE MR. JUSTICE S. TALAPATRA
HON‟BLE MR. JUSTICE ARINDAM LODH
Judgment & Order(Oral)
Heard Mr. M. Debbarma, learned Addl. G.A. appearing for
the appellants. None appears for the respondent today, even though,
on previous occasion Mr. A. Dasgupta, learned counsel who has
entered in appearance for the respondent had submitted the written
synopsis of his submissions, which this court would take into
consideration for adjudication of the lis.
2.
This is an appeal under Section 96 of the CPC which
arises from the judgment dated 26.11.2014, pursuant to which, the
decree dated 29.11.2014 was drawn up by the Civil Judge, Senior
Division, North Tripura, Dharmanagar in Title Suit No.37 of 2010. The
respondent is a reputed contractor and he had entered in a contract
under No.CE/EE/I and FMD-VI/KLS/Agree/54 of 2004-05 for the work
titled “High Capacity L.I. Scheme at Narendranagar under Damcherra
Block/Job No.TR/MI/04/AIBP/2003-04/Gr-I/SH: Construction of Pump
House, Intake Well, Protection of River Bank and Distribution System”
with the Executive Engineer, IMFM Division No.VI Kailashahar now
Water Resource Division No.VI,Kailashahar.
3.
There is no dispute that the work order was issued on
22.11.2004 by the defendant No.2 i.e. the said Executive Engineer for
the estimated value of Rs.1,40,99,355/- prescribing two years as the
time for completion of the work. The plaintiff, the respondent herein,
mobilized his resources to complete the said work within the stipulated
time and to avert the escalation of material prices. But for the delay
on the part of the defendants No.1 and 2, the site of intake well was
handed over to the plaintiff on 20.12.2004 and that too without
supplying the lay out and detailed drawings, which were given to the
plaintiff on 20.12.2005 on repeated persuasions. Even the soil testing
report was given belatedly. The plaintiffs in the meanwhile wrote
several letters on 15.12.2004, 07.01.2005, 13.04.2005, 09.12.2005
etc. for early handing over the site for execution of the work but the
defendant No.2, in particular, failed to hand over the site on the
ground that the land was not available from the L.A. Collector. By the
letter
under
No.F.4-4,
F.7-4/EE/INFMD/KLS/88/35-37
dated
10.02.2005 the Executive Engineer informed the plaintiff that the
other site cannot be handed over unless and until the intake well is
completed till a certain stage. But the plaintiff pleaded in the plaint
there was no such condition in the contract. Thus, the plaintiff was
restrained from executing the work for a long period. When the
plaintiff was proceeding with the work of intake well, in the month of
July, 2006, the defendant No.2 stopped the said work as they had
proposed to change the number of entry ports/pockets from 8 to 4,
and the final decision was given on 16.11.2006 after a long gap about
four months. For such undesirable action on behalf of the defendant
No.2,
the
plaintiff
suffered
huge
pecuniary
loss.
In
such
circumstances, the plaintiff had a detailed discussion with the
defendant No.2 on 29.08.2006. On that discussion the defendant No.2
agreed to hand over the sites of the remaining sub-head works, layout etc. and DI Pipes to the plaintiff within two months but ultimately
the defendants failed to their commitment.
4.
On 06.11.2006 the plaintiff had requested the defendant
No.2 for handing over the remaining sites and other necessary inputs
with facilities for performance of the balance contractual works. On
16.11.2006, the defendant No.2 by his letter informed the plaintiff
that for the remaining works, site would be handed over to the
plaintiff as soon as the land was available from the L.A. Collector and
the stipulated materials would be issued as soon as those were
available in the government store. Without notice to the plaintiff, all
related papers relating to the said contract were transferred to the
jurisdiction of the defendant No.1 [the Water Resource Division
No.VII, Pecharthal]. The defendant No.1 had served a notice under
Clause-3 of
the
agreement
for
determination/rescission
of
the
contract.
5.
By the reply dated 01.02.2008, the petitioner disputed
the allegation and per contra he had placed his case of negligence and
failure on the part of the defendants [the appellants] in affording the
work site and the resources were agreed to be supplied by them, after
repeated persuasions made by the plaintiff. He has given details of his
actions. Be that as it may, by the memorandum No.F.10(14)/EE/WRDVIII/PTL/5053-60 dated 25.02.2009, the said contract was rescinded.
The defendant No.3, the Assistant Engineer Water Resource Division,
Dharmanagar was asked to measure the work done by the plaintiff
and process the final bill. For such rescission the petitioner suffered
further pecuniary loss on account of the resources he had mobilized.
6.
The plaintiff served a demand notice under Section 80(1)
of the CPC claiming compensation to the extent of Rs.33,18,618/-.
When the demand was not met, the plaintiff instituted the suit being
T.S.37 of 2010 for declaration of his entitlement to the damage and
recovery of such damages as would be ascertained by the court
against the claim of the plaintiff i.e. Rs.33,18,618/-.
7.
The respondents denied their negligence and contended
that the entire claim of the plaintiff is frivolous, baseless and as such,
the plaintiff is not entitled to such damage. That apart, the defendants
have stated that the letter dated 10.02.2005 was rightly issued as the
intake well is the core structural construction of the contract. But the
plaintiff was not at all inclined to complete the job of intake well and
abruptly stopped the work of intake well on a lame excuse and
demanded handing over other sites which were peripheral. All the
averments are generally denied and seriously disputed by the
defendants. However, it has been admitted that the plaintiff was ready
and willing to complete the balance work, but the defendant No.1 did
not agree to such proposal considering his past conduct. They have
further denied that they had any intention to deliberately cause any
loss to the plaintiff. They have categorically denied that the plaintiff
had submitted his bills on 31.07.2009 on price escalation.
The said
claim was denied and disputed. The defendants have categorically
stated that the claim of the plaintiff is grossly unreasonable,
unsubstantiated, unfounded and unsustainable. In para-5 of the
written statement, the defendants had asserted as follows :
“That, this court has got no jurisdiction to entertain
the suit become of clear stipulation of Arbitration
clause in the Contract Agreement entered upon
between the Executive Engineer of the Department
and the plaintiff stating that in that event of any
disputes arising out of the agreement and during the
course of its performance the disputes would be
referred to the arbitrator who would be appointed as
per the terms of the agreement. On this ground along
a preliminary issue should be framed to decide as to
whether the instant suit can be proceeded without
exhausting the procedure under the Contract
Agreement.”
It is to be noted that the defendants No.1 to 4 and the
defendants No.5 to 6 had filed separate written statements, but there
was hardly any distinction. The defendants No.5 and 6 took the same
defence like the other defendants.
8.
On appreciation of the pleadings the following issues
were framed :
ISSUES
(I) Whether the Distribution System and River
Protection Works could be done simultaneously with
Intake Well.
(II) Whether defendants committed breach of
contract by failing to first perform their obligation to
hand over site-land for distribution system and River
Protection Works and prevented plaintiff to complete
the Works & otherwise.
(III) Whether plaintiff is entitled to compensation
for “loss of profit” and other compensatory reliefs as
claimed.
(IV) Whether plaintiff is entitled to receive his dues
on price escalation and final bill of work.
(V) Whether plaintiff is entitled to refund of the
security deposit lying with defendants.
(VI) Whether plaintiff is entitled to costs, interest
and any other relief.”
9.
It is apparent that no issue was framed on maintainability
of the suit, even though the dispute arises from the execution of the
contract, in which according to the defendants, there exists a clause
for resolution of disputes by arbitration. That apart, the original
contract was not submitted with the written statement but that
[Exbt.A/16, the original agreement] was produced later on in the court
at the insistence of the plaintiff. The plaintiff adduced two witnesses
including him and the defendant adduced one witness. The plaintiff
introduced as many as eighteen documentary evidence [Exbt.A/1 to
Exbt.A/18].
10.
While determining the issue No.1 it has been observed by
the trial judge that the plaintiff did not invoke the arbitration clause.
Despite non-framing of the issue of maintainability, the trial judge
while determining the issue No.1 has observed that the plaintiff and
the defendants admitted the fact that there was an arbitration clause
in the agreement/contract [Exbt.A/16] and the plaintiff did not invoke
that clause to resolve the dispute between the parties. The defendants
having received the demand notice [Exbt.1/15] did not give any reply
nor did they refer the matter to the arbitration. On institution of the
suit, the defendant proceeded to contest the suit by filing the written
statement and thus, they waived their right to insist this court to refer
the matter to the arbitration in terms of Section 8 of the Arbitration
and Conciliation Act, 1996. Further, the trial court while deciding the
issue No.1, has quite categorically observed that there was no express
provision in the agreement whether the works were to be done
simultaneously or phase by phase. DW-1, Dilip Kumar Acharjee,
Executive Engineer, DWS Department has admitted that to complete
the work within time, it was required that the contractual work would
be started simultaneously.
11.
There is no dispute that by the work order dated
22.11.2004 the time as prescribed for completion of the work was two
years. But it is partly admitted and partly established by the plaintiff
that the defendants did not hand over work sites to the plaintiff at a
time
in
spite
of
several
reminders
and
persuasions.
Despite
assurances made by the defendant No.2, no action was taken to
remove the difficulty of the plaintiff. That apart, from the notice as
issued under Clause-3 of the agreement/contract, it would be
apparent that the work was stopped by the defendants, not by the
plaintiff. So far the delay is concerned, the various correspondences as
made by the plaintiff would demonstrate that the delay is solely
attributable to the defendants. Thus, the issue No.1 and 2 was
decided in the affirmative and in favour of the plaintiff.
12.
Having appreciated the issues No.3, 4 and 5, the trial
court had observed that it was not possible to ascertain on the part of
the court whether the plaintiff had purchased huge quantity of
materials for completion of the contractual works or the actual
expenditure the plaintiff had incurred towards payment of wages, hire
charge of the machineries which were kept idle etc. The plaintiff had
incurred a huge loss having been obstructed by the defendants. That
apart, it has not been denied by the defendants that the plaintiff had
deposited a sum of Rs.1,89,230/- as security to the defendants
against the contractual work. It has been further observed by the trial
court that the plaintiff is also entitled to get a sum of Rs.1,00,000/from the defendants against the final bill. Thereafter, the trial court
has observed that for sudden cancellation of agreement without any
reasonable grounds, the plaintiff is entitled to get Rs.15,13,897/- from
the defendants for loss of expected profit. Thereafter, the trial court
has observed as under :
Section 73 of the contract Act deals with the
compensation of loss or damage caused by breach of
contract which provides that „When a contract has
been broken, the party who suffers by such breach is
entitled to receive, from the party who has broken
the contract, compensation for any loss or damage
caused to him thereby, which naturally arose in the
usual course of things from such breach, or which
the parties knew, when they made the contract, to be
likely to result from the breach of it. Such
compensation is not to be given for any remote and
indirect loss or damage sustained by reason of the
breach.‟
In the case of M/S A.T. Briz Paul Singh & brothers Vs
State of Gujarat reported in AIR 1984 SC 1703 the
Hon‟ble Supreme Court of India held that “in case of
Breach of Contract in respect of works contract for
construction of a portion of the road by the State, the
contractor is entitled to claim damages on the basis
of expected profit on balance of works contract.
However measure of damages would depend on facts
of each case”.
In the case of State of Kerala vs K Bhaskaran
reported in AIR 1985 Kerala 49 it was held by the
High Court of Kerala that in the case of breach of
contract by the Govt. where the entire work
indicating Government‟s obligation to supply cement
to the contractor and refusal by the Govt. to do so
without proper reasons and ultimately cancellation of
contract by the Govt. on the ground of non
commencement of work by the contractor is a kind of
breach of contract wherein the Government is solely
responsible for such breach on contract as per
provision of Section 73 of the Indian Contract Act.
So, in view of the aforesaid findings of the Hon‟ble
Apex Court and the Hon‟ble High Court of Kerala and
considering the facts and circumstances of the
present suit I find sufficient reasonable grounds to
decide the aforesaid issues in favour of the plaintiff
and, accordingly, those are decided in favour of the
plaintiff.”
[Emphasis added]
13.
Since all the issues were decided in favour of the plaintiff,
the trial court has returned the finding that the plaintiff is entitled to
get 9% interest p.a. on the amount of money he is entitled to realize
from the defendants. Thereafter, a sum of Rs.15,13,837/- has been
awarded for loss of the expected profit from the contractual work,
Rs.1,00,000/- towards the final bill on the basis of the works done by
the plaintiff and further, the plaintiff has been declared to be entitled
to Rs.1,89,230/- as refund of the security deposit. The total amount,
thus, has been ascertained as Rs.18,03,067/-(Eighteen lakhs three
thousand sixty seven) with interest at the rate of 9% p.a. from the
date of institution of the suit i.e. 14.12.2010 till the date of
realization.
14.
Mr. M. Debbarma, learned Addl. G.A. appearing for the
appellants has submitted that the court has no jurisdiction to try the
suit as the dispute arose from the said contract where there is a
specific arbitration clause in the agreement/contract. The duty of the
court was to discard the suit from its jurisdiction by referring the same
to arbitration. Mr. Debbarma, learned Addl. G.A. has further submitted
that the trial judge has not appreciated the documents or has given
any reason how he has determined Rs.15,13,837/- as the loss of
expected profit from the contractual work. It would be apparent that
the estimated cost of the work was Rs.1,18,59,160/-.The plaintiff had
only completed a small part of the intake well. There was no hindrance
whatsoever to complete the said part of the work, but he despite
specific
instructions
raised
untenable
pleas.
Hence,
the
said
assessment of loss of expected profit cannot be affirmed in the appeal.
That apart, the bill dated 16.11.2009 as raised by the plaintiff
[Exbt.A/12] was completely ignored while assessing damage. The
plaintiffs claimed therein as under :
Sl.No.
1.
2.
3.
4.
Details of Claim
For blockage of cash capital in cost of materials
Rs.18,93,100/- as per Annexure-I for 3 years 9
months from December, 2004 to August, 2008 @
Rs.12% p.a.
For daily wages paid to three chowkidars @ Rs.65/each daily for 3 years 9 months from December,
2004 to August, 2008.
For wharfage and storage @3% on cost of materials.
For loss of spillage and damages by weathering and
moss deposit during the period of storage @10% on
cost of materials.
Amount Claimed
Rs.8,51,895.00
Rs.2,63,250.00
Rs.56,793.00
Rs.1,89,310.00
Rs.13,51,248.00
Total
15.
Mr. Debbarma, learned Addl. G.A. has further contended
that there is no tenable foundation for assessing the damage and as
such, such damage cannot be maintainable being in contrast to the
provisions of Section 73 of Indian Contract Act.
16.
Mr. Dasgupta, learned counsel in his written brief has
contended that if Section 5 of the Arbitration and Conciliation Act,
1996 is read with Section 8 of the said Act, it would be apparent that
there is no absolute bar but the right of the defendants have taken
good care of, under sub-Section (1) of Section 8 of the said Act, which
provides that the defendant may apply to the court, not later than
when submitting his first statement on the substance of the dispute to
refer to arbitration. But sub-Section (2) of the Section 8 of the said
Act mandates that such application shall not be entertained unless it is
accompanied by the original copy of the agreement or a duly certified
copy thereof. The defendants have admittedly not followed that
process. He has submitted that the several letters of the plaintiffs as
brought on record would show that despite repeated insistence, the
defendants failed to discharge their obligation by handing over the
lay-out and detailed design and the sites of the work for a long time.
Even on asking of the plaintiff, they did not hand over the other sites
to complete the work within the stipulated time. Even the materials
which were supposed to be supplied by the defendants were not
supplied. In the letter dated 16.11.2006 [Exbt.A/5] the respondent
No.2 has stated that the work site would be handed over the plaintiff
as soon as the lands were made available to the department from the
L.A. Collector. Even the appellants had failed to hand over the work
site to the plaintiff till August, 2008. Therefore, the plaintiff could not
be blamed for the delay or the non-completion of the work within
time. DW-1 has admitted the said fact during his cross-examination.
Mr. Dasgupta, learned counsel has defended the assessment as that
has been done on the cost of the work including the rate above
18.89%.
17.
Having appreciated the submissions for the counsel and
the grounds of the appeal, this court is of the view the following
questions are material for determining the appeal :
“1) Whether the suit is barred for existence of
arbitration clause in the contract ?
2) Whether there is any breach of contract in
question by the defendant?
3)Whether the plaintiff suffered loss or damage for
such breach?
4) What would be the compensation for the loss or
damage caused to him in the event of the breach of
contract?
5) Whether the trial court has enquired into the
relevant factors while determining the loss or
damage?”
18.
It is apparent that the defendants failed to hand over the
requisite lay-out and design within a reasonable time, when in the
work order it has been categorically stated that the plaintiff has to
start the work within fifteen days positively from the date of issue of
the work order and he had to complete the work within two years. It
appears that in the agreement there is no mention of completing the
work in a phase manner. Thus, it was the option left to the contractor
(the plaintiff) to decide how to execute the work under instruction of
the defendant No.2. It has been admitted by DW-1 that till August,
2008, the required sites except for the intake well, were not handed
over to the respondent [the plaintiff]. So far the construction of the
intake well is concerned, its construction was delayed by belated
handing over of the lay-out and detailed design. Therefore, there
cannot be any amount of doubt regarding the breach of contract. But
the conduct of the plaintiff in construction of the intake well has to be
verified in the light of the time taken by him and leaving the work
incomplete for rescission of the said contract by the defendant No.1.
Can failure to complete the work within the time of two years adding
the period that was taken by the defendant No.2 in supplying the layout and the detailed design be considered composite in breach?
Accordingly, the liability has to be adjusted. The defendants are liable
to pay the loss in the circumstances, in terms of Section 73 of the
Indian Contract Act but to what extent?
19.
While making reference to the submission, the factual
aspects have been restated at the cost of repetition. Mr. M.
Debbarma, learned Addl. G.A., appearing for the appellants has
contended that [1] It is for the obstinacy of the plaintiffs in the suit
that the intake well and pump house could not be completed within
the prescribed time, [2] the plaintiff-respondent has claimed that he
has suffered Rs.15,13,897/- for the non-cooperation and delay in
supplying site and drawing up the intake well and pump house. Thus,
it has been pleaded that the plaintiff-respondent is entitled to
Rs.15,13,897/- from the defendant-appellants. But there is no
analysis how such loss had been suffered by the plaintiff-respondent,
[3] there is no evidence regarding escalation of price of the materials
and labour, which thus can be realized under Clause 10 CC of the
contract.
20.
Mr. Debbarma, learned Addl. G.A. has further submitted
that the determination of the damage in the form of expected profit is
without any
foundation
of
evidence.
That
apart, the
plaintiff-
respondent without understanding the value of instruction given to
him for completing the intake well including the pump house first had
beendemanding for giving the design for the other part of the work in
the periphery. Mr. Debbarma, learned Addl. G.A. has submitted that
intake well is the main structure of the whole contract work. Only after
completion of intake well and pump house, the plaintiff was required
to undertake the distribution system and finally, the work for
protection of the river bank. But the plaintiff was not at all inclined to
complete the intake well and abruptly stopped the work of intake well
voluntarily and requested for other sites which was not at all required
at that time. The defendants have claimed that by the letters dated
15.12.2004, 07.01.2005, 07.02.2005, 13.04.2005 and 09.12.2005,
handing over the sites of other subhead works namely distribution
system, protection of river bank etc. were pressed, so that the plaintiff
could proceed with the execution of the said work simultaneously, for
gainful
utilization
of
his
procured
materials,
labour
force
and
establishment for completing the work within the prescribed period.
But the defendant No.2 had failed to hand over the sites inasmuch as
the land acquisition collector could not give possession of the land
required
for
completing
the
contractual
work.
The
defendant-
appellants even though denied such allegation, but from the latter
part of their reply, it appears that the same was the plaintiff‟s
approach. Finally, when the plaintiff-respondent stopped the work
voluntarily and he showed gross disinclination to continue with the
work, the work had been rescinded after giving the due notice by
invoking the Clause-3 of the contract. Despite the frivolous allegations
raised, the defendant-appellants tried to persuade the plaintiffrespondent to complete the work, but he did not show any progress.
21.
Mr. Debbarma, learned Addl. G.A. has finally stated that
the plaintiff-respondents‟ claim of loss for non-performance of the
balanced part of the contract is unfounded. Denying such claim, but
assuming that for non-performance, the profit has been lost. The
profit cannot be disproportionate. The bill that was submitted for
escalation of price on 31.07.2009 was not supported by any
document. Even the claim for refund of the security deposit is subject
to determination of the contract as the contract has been rescinded for
non-completion of the work. The defendant-appellants may raise their
liability for rescission. Mr. Debbarma, learned Addl. G.A. has referred
to the following passage of the written statement :
“Defdts. Humbly state that plaintiff in his letter dated
1`7.11.2009 has demanded Rs.1,16,6,548/- for the
work which he even did not undertake and as such
he is not entitled to any amount as claimed by him.
Further under the agreement the D.I. pipe would be
supplied by the department and as no work was
executed and there was no requirement of supplying
the said D.I. pipe due to non performance of the
contract by the plaintiff, the department did not
supply the same and hence it is not understood how
he claimed the cost of Rs.91,7,786/- against the high
capacity L.I. scheme at Narendranagar. Further the
plaintiff has not complete the intake well and
stopped the work abruptly without completing the
same. So, unless and until the work of intake well
was is not completed the protection of the river bank
and construction of the pump house did/does not
arise and payment against those works cannot be
considered.”
[Emphasis added]
Mr. Debbarma, learned Addl. G.A. has thus submitted
that the suit was liable to be dismissed.
22.
Mr. A. Dasgupta, learned counsel has filed the written
submission against the grounds raised in this appeal. So far the
jurisprudential objection as to the maintainability of the suit is
concerned it has been stated that Section 5 of the Arbitration and
Conciliation Act, 1996 has to be read with Section 8, which Section
provides an exemption. A joint reading shows that there is no absolute
bar in filing a suit. Even if, there is an arbitration clause in the
agreement, sub-section (1) of Section 8 provides that in such case the
defendant may apply to the court within the stipulated time, not later
than the day of submitting his first statement on the substance of the
dispute, to refer the case to the arbitrator. Sub-section (2) provides
that such application shall not be entertained unless it is accompanied
by the original copy of the arbitration agreement or a duly certified
copy thereof, else the Civil Judge before whose court the suit is
pending, may continue the process of adjudication. The defendant-
appellants did never submit such application as contemplated under
Section 8 of the Arbitration and Conciliation Act, 1996.
23.
Mr. Dasgupta, learned counsel has further submitted that
the appellants have taken an unsustainable plea to escape from their
failure to act in terms of the agreement. Even though they were not in
a position to hand over the site as the acquisition was still incomplete,
they had arrogantly contended in the written statement that the
distribution system and protection of river bank works could not be
done simultaneously. In fact, the intake well was located on the bank
of the river and the pump house was to be constructed over it. The
distribution system [70% of the total contract work] was spread over
1300 mtrs. long pipe line to be used for irrigation of the paddy field
and the protective construction for the river bank which was spread
over 2,800 sq. mtrs. of the river apron and slope. Thus, the
construction works were not inextricably related to the intake well and
to be precise, independent of the construction of intake well, and it
was technically feasible to carry out the works simultaneously. It has
been succinctly stated that in the terms of the contract it had nowhere
been provided that works to be done one after another, because of
any technical reason. Moreover, there hanged a possibility of erosion
of the work if the river banks were not protected. On 16.11.2006, the
defendant No.2 had written a letter [Exbt.A/6] to the plaintiffrespondents by stating as follows:
“…the work site will be handed over to you as soon
as the lands are made available to the department
from the L.A. Collector.”
There is no controversy that the appellants failed to give
the work site even after that letter till August, 2008 and took a
pretentious plea that the pipe-lines and protection work could not be
done simultaneously, along with the Intake Well and thus, work sites
for the same, would be given one by one after completion of Intake
Well. The appellants took this „unreasonable plea‟ to cover their lapses
and failure to hand the work sites. Thus was contended by the
plaintiff.
24.
Mr. Dasgupta, learned counsel has further stated that the
defendant-appellants were obliged to hand over the work sites to the
plaintiff-respondent
to
commence
work
simultaneously.
He
has
referred to the testimony of DW in his cross-examination and Exbt.A/5
to contend that the defendant-appellants failed to perform their
obligation under the contract and such brazen breach of contract
prevented the plaintiff-respondent from completing the work. But the
plaintiff-respondent has admitted that D.I. and C.I.
pipes were
supposed to be supplied by the defendant-appellants against payment
of cost. While the rate was floated by the plaintiff-respondent it was
analyzed on the prevailing rate. But that did not stay in that level.
25.
According to Mr. Dasgupta, learned counsel, the trial
Judge has rightly ascertained loss of profit on the total cost of works
at 18.89% against the works which was allotted to the plaintiffrespondent,
but
the
plaintiff-respondent
was
prevented
from
executing the contract by various illegal means. Hence, the plaintiffrespondent is entitled to get the compensation to be assessed in
terms of Section 73 of the Contract Act. It has been further asserted
that D.I. and C.I. pipes were to be supplied by the defendantappellants on payment by the plaintiff-respondent [the Contractor].
For no reason, the plaintiff-respondent can be made liable for failure
of executing the work of the distribution system and protection of river
bank. According to the plaintiff, that forms 78% of the total contract
works to be completed within two years. When the time was initially
stipulated for two years but, thereafter for failure of the defendantappellants, the time was extended for further one and half year. In
such circumstances, when there was escalation in the cost of materials
and labour, and it occurred during the period of contract, as such, the
plaintiff- respondent is entitled to price escalation under clause 10 CC
of the said contract.
26.
At this juncture, let this court examine how the plaintiff
has justified the claim of damage to the extent of Rs.15,13,897/- as
loss of profit, Rs.13,51,248/- for the loss occasioned to the plaintiff for
materials remaining unutilized and blocking of capital, Rs.52,000/- for
higher charge for the machineries, Rs.01,12,243/- for price escalation
Rs.1,00,000/- against the pending final bill and Rs.01,89,230/- as
refund of the security deposit. In paragraphs 13 to 18 of the plaint,
the plaintiff has given the reasons and in the schedule the plaintiff has
given the details of the damage or claim.
27.
It has been stated by the plaintiff in para-13 of the plaint
that as the defendant No.1 failed to give the sites and other inputs
after waiting for a period of “two months”, the plaintiff abandoned the
site at the risk and responsibility of the defendants by communicating
the same by the letter dated 27.08.2008. In para-14, the plaintiff has
stated that the rescission was wholly unwarranted. However, by the
communication dated 25.02.2009, the defendant No.3 was directed to
process the final bill after taking the measurement. The plaintiff has
succinctly stated that the defendants failed to provide the work sites
and other sub-head works viz. distribution system, protection of river
banks etc. and non-performance to that effect prevented the plaintiff
from execution of the said works. Therefore, the defendant No.1 could
not have called for completion of the performance. The plaintiff has
stated that according to the usage of trade and standard practice, the
contract consisted of 15% as the contractor‟s profit for the purpose of
execution. On the basis of the standard practice over the estimated
account, the plaintiff claimed Rs.15,13,897/- on account of loss of
profit. The plaintiff detailed his claim in the schedule-A, which is
reproduced hereinafter. The plaintiff has however admitted that the
balance of work except the intake well and the pump house was never
handed over to him. Thus, the plaintiff raised the bill of loss on
17.11.2009.
SCHEDULE-A
Cost of the following items of the „Schedule of work‟ under the contract
afreement could not be executed by the plaintiff for respondent‟s failure to
provide the work-sites.
High capacity L.I. Scheme at
Narendranagar under Damcherra Block/
Distribution system-Item No.1 to 16=
Protection of river bank-Item No.1 to 3=
Construction of pump house-Item No.1 to 18=
Add.@18.89% above
As per the agreement (+)
Rs.91,07,786.00
Rs.2,08,263,00
Rs.4,46,377.00
Rs.97,62,426.00
Rs.18,44,548.00
Total:
Rs.116,05,548.00
Rates of above contract work items whether of T.S.R. or A.R. include 15%
(fifteen) as contractor‟s profit for the purpose of execution.
Therefore, the loss of profit sustained by the plaintiff being prevented to
execute the above item of works.
Rs.1,16,06,548 x 15
Amount claimed
=
Rs.15,13,897/-
=
Rs.15,13,897/-
(Rupees Fifteen lakhs thirteen thousand Eight hundred ninety seven) only.
28.
According to the plaintiff [para-16 of the plaint], after
receipt of the work order, he made the assessment and procured
materials [main items] for the whole work to ensure steady progress
of the work and also to get advantage by procurement in bulk and to
immune him from the price hike but for non-availability of the balance
work from the defendants, the materials so procured for the work
remained unutilized causing huge loss to the plaintiff. In Schedule-B,
as reproduced below, the petitioner has made an attempt to show the
materials remained unutilized from December-2004 to August-2008
waiting for the balanced work. When he raised the bill for this
unutilized, the defendants denied to pay him.
Schedule-B
Sub-Schedule-B(I)
Statements of material purchased but remained unutilized from December2004 to August-2008 waiting for the balance work-sited from the
respondents;
1. 1st Class Bricks-2,58,000 Nos.
@ Rs.4000/- per 1000 Nos.
Rs.10,32,000/-
2. Brick-bats(Jhama)-450 cum.
@ Rs.900/- per cum.
Rs.4,05,000/-
3. Stone chips-40 cum.
@ Rs.1600/- per cum.
Rs.64,000/-
4. Sand-642 cum.
@ Rs.300/- per cum.
Rs.1,92,600/-
5. Steel (assorted) for reinforcement
6650 Kg. @ Rs.30/- per Kg.
Rs.1,99,500/-
Total =
Rs.18,93,100/-
Sub-Schedule-B-(II)
Details of claim :
1. For blockage of cash capital in cost of
materials Rs.18,93,100/- as per Sub-Schedule-I
for 3 years 9 months, from December-2004 to
August-2008 @ 12% p.a.
Rs.8,51,895/-
2. For daily wages paid to three chowkidars @
Rs.65/- each for the above period
Rs.2,63,250/-
3. For wharfage and storage @ 3%
on cost of materials
Rs.56,793/-
4. For loss by spillage and damage by weathering
and moss deposit during the above period @ 10%
on cost of materials
Rs.1,89,310/-
Total=
Rs.13,51,248/-
(Rupees thirteen lakhs fifty one thousand two hundred forty eight) only.
29.
The plaintiff has claimed to get Rs.52,000/- as loss
occasioned by the hire-charge for construction machineries. But the
bill the plaintiff raised for the said hire-charge on 24.11.2009 was also
not honoured. He has shown in Schedule-C the details, and hence the
said Schedule-C is reproduced below :
SCHEDULE-C
1. Hire charge of 1 No. concrete mixer (7 to 10 cft.)idling
from December-2004 to December-2005 waiting for lay-out
plain and sites for other works
@ Rs.3000/- per month
1x 13x/.3000/=
Rs.39,000/2. Hire charge of 1 No. concrete vibrator idling for
above period and reason @ Rs.1000/- per month
1 x 13 x Rs.1000/=
Rs.13,000/-
Total =
Rs.52,000/(Rupees fifty two thousand) only.
Even, the plaintiff has raised the bill for escalation of
price on 21.07.2009 to the extent of Rs.1,12,243/-. Further, the
plaintiff
has
asked
for
recovery
of
a
sum
to
the
extent
of
Rs.1,00,000/- [as the final bill]. The plaintiff has also asked for refund
of the security deposit amounting to Rs.1,89,230/-.
30.
The defendants, however, have categorically stated in
para-17 of their written statement that after completing 7 to 8 mtrs.
of the intake well, abruptly the plaintiff had stopped the work and
withdrew all his labours from the work site and denied to continue the
construction work. The defendants have denied that the plaintiff was
compelled to abandon the site as he was made to wait „for two
months‟. The defendants have asserted that the matter or earning
profit depends on the due performance on the contract works, which
the plaintiff has miserably failed and on the contrary, caused loss to
the
defendants.
The
defendants
are
entitled
to
invoke
the
compensatory clause of the agreement. All other allegations have
been denied. But they have stated that by the letter dated
17.11.2009, the plaintiff had demanded Rs.1,16,6,548/- for the works
which he did not even undertake. There is no grounds, tenable or
otherwise how the plaintiff has assessed cost of Rs.91,07,786/against the high capacity L.I. Scheme at Narendranagar.
31.
It would be apparent from the records that the plaintiff
had adduced three witnesses including himself, in support of his claim.
The plaintiff has stated as PW-1 the plaint-story and introduced
eighteen documents but from the list of those documents it is
apparent that he has not adduced any purchase vouchers or credit
note to show that he has really purchased the materials against which
he claimed the escalation etc.
32.
PW-2, Gautam Pal, the Manager of the plaintiff has stated
that in the agreement there were four schedules viz.(1) Distribution
System [76% of the contract value] (2) Construction of Pump House
[4% of the contract value] (3) Protection of River Bank [2% of the
contract value] (4) Construction of Intake Well [78% of the contract
value]. According to him, the site for the distribution system and
protection of the river bank could not be handed over by the
defendants. He has stated that for non-handing over the site, the
workers remained idle and waited for a period of two months. The
plaintiff was in the emerged circumstances compelled to abandon the
site at the risk of the defendants. Thereafter, the defendants did not
ask for the performance. Even this witness did not state anything
about the purchase of the materials for the entire project and did not
give the corroborative statement in respect of the unutilized materials.
33.
PW-3, Md. Abdul Chupan was a construction worker who
was engaged by the plaintiff for the said work at Narendrapur,
Damcherra. According to him, when the site for the intake well was
handed over, the plaintiff immediately started the work by soil testing
etc., but the design lay-out was given after one year and the work of
the intake well was stopped by the defendants in July, 2006, which
statement is contrary to the statement of PWs-1 and 2. Thus, it has
created the question about the integrity of the plaintiff‟s story.
34.
For the defendant, one Dilip Kumar Poddar, Executive
Engineer [DW-1] has stated that unless the construction of intake well
and pump house were completed, the design for the distribution
system could not have been finalized but the plaintiff did not complete
the work of the intake well. He has denied that the defendant had
stopped the work of the intake well. But he has admitted that the
defendant No.2 by his letter dated 16.11.2006 had informed that the
remaining work site would be handed over to the plaintiff as soon as
the land would be available to the department by the L.A. Collector
and the stipulated materials would be issued as soon as those were
made available to the departmental store. DW-1 has categorically
stated that no materials were found in the work site. Thus, the claim
of the plaintiff is frivolous, baseless and therefore, unsustainable. DW1 has stated that the suit is virtually a gamble in litigation. That is the
reason why the plaintiff could claim Rs.91,07,786/- against the high
capacity L.I. Scheme at Narendranagar not doing admittedly any
work. He did not deviate from his statement made in the examinationin-chief. The Civil Judge, Senior Division after appreciating the
evidence
has
Schedule-B-(I),
decreed
the
compensation
Schedule-B(II)
and
against
Schedule-C.
Schedule-A,
Thus
the
total
compensation as decreed is [Rs.15,13,833/- as loss of expected profit
+ Rs.1,00,000/- on account of final bill + Rs.01,89,230 as refund of
security deposit] =Rs.18,03,067/- with 9% interest from the date of
institution of the suit i.e. 14.12.2010 till realization.
35.
In
this
appeal
the
said
determination
has
been
challenged.
36.
For deciding the relevant questions as are noted already,
let us decide the question relating to the breach of contract first. It
appears from the agreement that the work involved high skill and
efficiency and at the same time the period for completion was very
short as intake well were to be erected below river bed. During the
rainy season such type of work cannot be executed. The works were
construction of intake well, construction of pump house and laying of
1,370 mtr. D.I. pipe line. It has been categorically stated that the
agency had to arrange all materials, machinery except D.I. pipes at
his own cost. D.I. Pipes will be supplied by the department from
Agartala at specified issue-rate. This court has noticed that the site for
laying down of distribution system was not even in the control of the
defendants. Without getting the possession of the land under their
control, they had settled the contract and issued the work order with
such a strict time-frame for completing the work. Even in the contract,
there was no provision that only after construction of intake well and
pump house, the lay-out and the materials for the distribution system
along with design would be handed over to the plaintiff. Even,
according to the plaintiff, the work order was issued on 22.11.2004
but the site was not handed over before 20.12.2005. during this
period, the plaintiff addressed several letters dated 25.12.2004,
07.01.2005, 07.02.2005, 13.04.2005, 09.12.2005 asking for early
handing over of the site for the entire work. But the site was not in
their control. Even the design of the intake well was changed from
eight entry ports to four entry ports and the final decision was given
on 16.11.2006. For this period, according to the plaintiff the work got
stalled. The plaintiff has admitted that on 29.08.2006 he had a
detailed discussion with the defendant No.2 at Kailashahar and it was
decided that the entire sight of design will be handed over to the
plaintiff within two months but that was not given. On 26.11.2006, the
defendant No.2 by his letter No.F.EE/WR/6/6 informed the plaintiff
that the remaining work sites would be handed over as soon as the
land was available to the department.
But suddenly, by invoking
clause–3 of the contract/agreement the work was proposed to be
rescinded and for that purpose, a show cause was issued asking why
the delay had taken place in completing the work. The plaintiff had
given the reasons for such delay which was wholly attributable to the
defendants inasmuch as till 07.06.2008, for want of the handing over
of site, the remaining works could not be started. Thus, it appears
that the defendants failed to comply with the provisions of the
agreement and when they entered into the agreement they did not
have control over the site for the distribution system. Even in the
contract, there had been no stipulation that the work had to be
executed stage by stage. As such, the defendants had committed
breach of contract by failing to discharge reciprocal obligation.
37.
Now
let
us
take
the
question
relating
to
the
maintainability of the suit in view of Section 5 of the Arbitration and
Conciliation Act, 1996. Section 5 of the Arbitration and Conciliation Act
provides that notwithstanding anything contained in any other law for
the time being in force in matters governed by Chapter-I, no judicial
authority shall intervene except where so provided in that chapter [the
part].
38.
There is no dispute between the parties that in the
agreement there exist an arbitration clause but the plaintiff did not
take recourse to the said clause. But equally it is true that the
defendant did not follow the procedure of Section 8 of the Arbitration
and Conciliation Act which provides that a judicial authority before
which an action is brought in a matter which is the subject matter of
the arbitration agreement shall, if a party to the arbitration agreement
or any person claiming through or under him, so applies not later than
the date of submitting the first statement on the substance of the
dispute, then notwithstanding any judgment, decree or order of the
Supreme Court or any Court, refer the parties to arbitration unless it
finds that prima facie no valid arbitration agreement exists.
39.
Sub-section (2) of Section 8 categorically provides that
the application referred to in Sub-Section (1) shall not be entertained,
unless, it is accompanied by the original arbitration agreement or a
duly certified copy thereof. In this case, admittedly, the defendant did
not file such application with the arbitration agreement asking the trial
Judge to send the dispute to arbitration. Therefore, the defendants
cannot project the question of maintainability of the suit qua Section 5
of the Arbitration and Conciliation Act.
40.
The another question which this court has framed for
decision as regards the substance of the dispute is that whether under
the agreement/contract, the plaintiff was supposed to get the entire
site with design simultaneously for commencing the work. It has been
noticed by this court that it was under the discretion of the authority
how to provide the site or design. This court is of the view that such
right has not been reserved in the contract. Having read the entire
contract agreement it appears that the work was time bound and as
such, it was only expected that the entire work site with material
design would be handed over to the plaintiff [the contractor] but by
not doing so serious impediment had been caused in execution of the
work. Thus, the allegation of non-performance and consequential
rescission cannot stand the scrutiny of law. The said act is failure of
discharging the obligation in the realm of the contract by the
defendants. Therefore, the rescission in the considered view of this
court is not only unreasonable but also oppressive in nature. Hence,
on the basis of such rescission, the plaintiff cannot be held responsible
for any loss if at all caused to the plaintiff.
41.
Whether the determination of the expected loss
to the
extent of Rs.15,13,897/- is sustainable? Since there is no provision for
liquidated damage, Section 73 of the Indian Contract Act would be
applicable for determining the damage, if any. Under section 73 of
Indian Contract Act there can be three kinds of damages recoverable
from the defendants and those are (1) nominal damages, (2) general
damages and (3) special damages. Nominal damages are those which
occur in cases where, for instance the sellers bring an action for nonacceptance of the goods, price of which has arisen since the contract
was made. In such cases, no pecuniary loss has been sustained for a
breach of contract, only nominal damages are the appropriate
remedy. General damages are those which are awarded when the
judge cannot point out any measure by which they are to be assessed
except by the opinion and the judgment of a reasonable man. But the
special damages are those which are given in respect of any
consequences reasonably or probably arising from the breach of the
contract complained of. As a general rule, the amount of damages
recoverable is governed by the extent of the actual damages
ascertained in consequence of the defendant‟s act.
42.
In Victoria Laundry (Windsor) Ltd. v. Newman
Industries Ltd., reported in (1949) 2 KB 528 the principles have
been summarized in respect of test of remoteness of liability: (a) In
cases of a breach of contract the aggrieved party is only entitled to
recover such part of the loss as was at the time of the contract
reasonably foreseeable as liable to result from the breach; (b) what
was at the time reasonably so foreseeable depends upon the
knowledge then possessed by the parties or at all events by the party
who later commits the breach and (c) for this purpose knowledge
„possessed‟ is of two kinds viz. imputed and actual.
43.
It is the admitted position that no work did commence for
distribution system and protection of river bank, meaning 78% of the
total work as the land could not be provided by the defendants. Out of
the total work, [18% + 4%] 22 % works were taken up by the
plaintiff and finally left incomplete which resulted in the rescission of
the contract. It is to be mentioned that within two months of handing
over the site for that 22% work, the plaintiff abandoned the work and
thereafter he raised the claim for expected loss, loss for unutilized
materials, loss for hire-charge of the machineries, loss for retaining
the labourers, loss for price escalation etc. True, it is that the
defendants did not hand over the entire site but the defendants had
only handed over the site for 22% of the work. Thus, where the work
did not commence and when there is no materials to show in respect
of the purchase of the materials for the entire project together,
mobilization of the labour for the entire work as we have not come
across any payment register or any purchase voucher for which the
plaintiff had to pay the higher price for the delay for purchasing the
materials when in the market the price escalated. No voucher of
payment for hiring machineries is in the record. Thus, it is very
difficult to account for the expected loss. However, so far as 22% of
the work is concerned the plaintiff would be entitled to 15% loss for
the said work for 22%. PW-2 has on the basis of the contract vouched
in the trial that from Schedule-A this court can gather the value of the
intake well and pump house. The estimated cost is shown at
Rs.4,46,377/-. With that amount 18.89% would be added. Thus the
total value of that work would come Rs.5,30,697.61. As per the rate
schedule, the contractor profit would be 15% of the said amount i.e.
Rs.79,604/-. But for wasting two months by the petitioner another
sum of Rs.1,50,000/- is awarded on general damages. Thus, the total
loss would come to Rs.2,29,604/- .
44.
Whether the plaintiff can get any extra amount for the
price escalation under Clause-10CC of the agreement? There is no
evidence of price escalation or purchase of the materials used for the
work after such escalation and as such, the plaintiff is not entitled to
get any amount under Clause-10CC of the agreement.
45.
The last and final question is whether the determination
in respect of other component is maintainable. The trial Judge has
declared that the plaintiff is entitled to realize Rs.1,00,000/- as the
pending final bill. The trial Judge has further declared that the plaintiff
is entitled to Rs.1,89,230/- as refund of the security deposit. Since
this court has observed that the breach has been committed by the
defendants, the defendants cannot withhold any amount of the final
bill or cannot forfeit the security deposit and as such there is no
infirmity in the said determination by the trial Judge. Hence, those are
affirmed.
Thus,
the
plaintiff
is
entitled
to
recover
a
sum
of
Rs.5,18,834/- (Five lakhs eighteen thousand eight hundred thirty four)
without any adjustment in the final bill, from the defendants. The said
amount shall carry interest @ 6% p.a. from 14.12.2010 [the date of
institution of the suit] till the date of realization.
46.
Having
observed
thus,
the
judgment
dated
26.11.2014 stands partly interfered with.
In the result, the appeal stands partly allowed. Draw
the
decree accordingly.
Send down the LCRs thereafter.
JUDGE
Sabysachi B
JUDGE
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review