Sri. Smarjit Das vs The State of Tripura and 4 Others

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Tripura High Court
Date
4 February 2021
Case No.
WP(C) 912/2018
Result
Dismissed
Bench
Akil Kureshi
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

5. Similar issues had come up before the learned Single Judge of this Court who had refused to direct the corporation to reframe the pension scheme upon which the aggrieved retired employees had filed Writ Appeal No.67 of 2020 and connected appeals which were dismissed by a Division Bench on 17.11.2020. In the said decision Division Bench after referring to the factual aspects noted above, had made following observations: “It can thus be seen that the Corporation though envisaged a new pension scheme for its employees and also took the certain concrete steps in furtherance of this proposal, the pension scheme could not be formalized for want of Government sanction. More importantly, the Corporation needed financial assistance from the Government to sustain any such scheme for payment of pension, which the Government flatly refused. As noted, the decision that the government conveyed to the Corporation was that it is not obligatory for the State Government to continue to fund to the Corporation and the Corporation has to decide how to manage its finances. It was made clear that the Finance Department shall not provide any financial assistance to Corporation for implementation of any such scheme. It was, therefore, left to the Corporation to decide whether to continue the scheme or to wind it up. If under such circumstances, it was not possible for the Corporation to proceed further…

6. In the result, these petitions are dismissed. Pending application(s), if any, also stands disposed of. (AKIL KURESHI), CJ Pulak

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

HIGH COURT OF TRIPURA AGARTALA 1. WP(C) No.834/2018 Sri Santosh Chandra Chaudhuri ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) Connected with 2. WP(C) No.836/2018 Sri Chandra Sekhar Kar ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 3. WP(C) No.837/2018 Sri Goutam Majumder ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 4. WP(C) No.838/2018 Sri Tapan Kumar Debnath ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 5. WP(C) No.839/2018 Sri Tapan Majumder ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 6. WP(C) No.840/2018 Sri Rakesh Sinha ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 7. WP(C) No.841/2018 Sri Chandan Kumar Bhowmik ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 8. WP(C) No.842/2018 Sri Ratan Debbarma ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 9. WP(C) No.848/2018 Sri Bisheswar Debnath ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 10. WP(C) No.849/2018 Sri Kishore Debbarma ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 11. WP(C) No.850/2018 Sri Sanjoy Das ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 12. WP(C) No.851/2018 Sri Bachu Mia ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 13. WP(C) No.852/2018 Sri Bishwajit Dey ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 14. WP(C) No.853/2018 Smt. Dipali Das ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 15. WP(C) No.854/2018 Sri Kirit Kishore Rupini ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 16. WP(C) No.855/2018 Sri Parimal Datta ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 17. WP(C) No.856/2018 Sri Haripada Debnath ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 18. WP(C) No.857/2018 Sri Buddha Debbarma ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 19. WP(C) No.858/2018 Sri Bibhas Saha ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 20. WP(C) No.859/2018 Smt. Madhuri Reang ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 21. WP(C) No.908/2018 Sri Sushanta Debnath ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 22. WP(C) No.909/2018 Sri Suchit Roy ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 23. WP(C) No.910/2018 Sri Chandan Ghatak ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 24. WP(C) No.911/2018 Sri Rajib Nandi ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 25. WP(C) No.912/2018 Sri Smarajit Das ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 26. WP(C) No.913/2018 Maman Hossain ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 27. WP(C) No.914/2018 Sri Partha Kumar Deb ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 28. WP(C) No.915/2018 Sri Krishnabashi Debbarma ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 29. WP(C) No.916/2018 Sri Debasish Reang ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 30. WP(C) No.917/2018 Sri Rakesh Sharma ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 31. WP(C) No.918/2018 Sri Sanjib Paul ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 32. WP(C) No.919/2018 Sri Keshab Das ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) 33. WP(C) No.920/2018 Sri Binay Bhusan Bhowmik ----Petitioner(s) Versus The State of Tripura & others -----Respondent(s) For Petitioner(s) : Mr. Arijit Bhowmik, Advocate. For Respondent(s) : Mr. D. Sarkar, Advocate, Mr. P.K. Ghosh, Advocate. HON’BLE THE CHIEF JUSTICE MR. AKIL KURESHI Date of hearing and judgment : 4th February, 2021. Whether fit for reporting : NO. JUDGMENT & ORDER (ORAL) All these petitioners are existing employees of Tripura Rehabilitation Plantation Corporation Limited (hereinafter to be referred to as TRPC Ltd.). Their grievance is that the employer at one stage framed a pension scheme for all existing employees but subsequently withdrew the same and in the meantime, a handful of employees who had retired in the interregnum, got the benefit of the pension scheme. 2. The facts on record would suggest that a Board of Directors of the Corporation had in its 117th meeting which was held on 15.09.2015 considered agenda item No.5 pertaining to approval for introduction of a Group Pension Scheme under Life Insurance Corporation of India Limited for the retirement benefits of the regular employees of TRPC Ltd. The agenda and the subsequent resolution would show that a scheme was framed by the corporation for which funds would be parked by the corporation with the LIC and from such funds the LIC would pay pension to a retiring employee @ 50% of the last basic drawn. In fact, the corporation also entered into an agreement with LIC for creation of such a pension scheme. Perusal of this agreement would show that entire contribution towards the pension to be paid to the retiring employees would come from the coffers of TRPC Ltd. Consequently, a notification dated 19.09.2015 was issued which envisaged payment of pension to a retired employee at prescribed rates. The corporation had deposited a sum of Rs.5,00,00,000/- as a initial sum to operationalize the scheme. 3. All these steps were taken by the corporation without the approval of the Government. The corporation, therefore, approached the State Government for ex post facto clearance to the said pension scheme in which it was pointed out that the Board in its meeting dated 15.09.2015 had decided to frame a pension scheme. This would raise a requirement of Rs.16.36 crores for covering existing 170 employees of the corporation out of which Rs.11.17 crores was already deposited by the corporation with the LIC from its own resources. The corporation would need further funds from the Government for the said purpose. The Government conveyed to the corporation in no uncertain terms in a communication dated 26.09.2018 that the proposal of the corporation cannot be accepted. The Government would not fund the pension scheme of the corporation. The corporation has to take its own decision how to manage its finances looking into the workforce, profitability etc. It was reiterated that the Finance Department shall not provide any financial assistance to the TRPC Ltd. for implementation of the said pension scheme particularly if it is in violation of the rules of financial discipline. The Government thereupon left the corporation to decide the future course of action. The corporation thereupon resolved to discontinue the scheme and revert back to the original regime of gratuity and contributory provident fund scheme. It has also come on record that subsequently the Government allowed the TRPC Ltd. to implement the revised pay structure of its employees on the condition that the corporation enforces austerity measures and the funds parked with the LIC in various schemes is brought back to the corporation. Consequently, the corporation while implementing the revision in pay structure for its employees, also discontinued the pension scheme permanently and reclaimed the remaining funds from the LIC. Learned counsel for the corporation clarified that during the time when these issues were going on, 7 employees had retired from the corporation and who had for some time also received pensionary benefits as per the scheme of the corporation, however, upon discontinuation of the said scheme and withdrawal of the funds of the corporation from the LIC even these employees no longer received pension. 4. I do not find that the petitioners had made out any case for issuance of directions for reintroduction of the pension scheme nor any case of mala fide discrimination has been made out in favour of few chosen employees. As noted, the corporation had rather hastily framed a scheme and implemented it also without the approval of the Government which would be absolutely essential if the corporation relied on Government funding the scheme. The Government clarified that it would not in any manner subsidize such a pension scheme of the corporation and it would be for the corporation either to raise necessary resources for sustaining such scheme or decide its alternative future course of action. 5. Similar issues had come up before the learned Single Judge of this Court who had refused to direct the corporation to reframe the pension scheme upon which the aggrieved retired employees had filed Writ Appeal No.67 of 2020 and connected appeals which were dismissed by a Division Bench on 17.11.2020. In the said decision Division Bench after referring to the factual aspects noted above, had made following observations: “It can thus be seen that the Corporation though envisaged a new pension scheme for its employees and also took the certain concrete steps in furtherance of this proposal, the pension scheme could not be formalized for want of Government sanction. More importantly, the Corporation needed financial assistance from the Government to sustain any such scheme for payment of pension, which the Government flatly refused. As noted, the decision that the government conveyed to the Corporation was that it is not obligatory for the State Government to continue to fund to the Corporation and the Corporation has to decide how to manage its finances. It was made clear that the Finance Department shall not provide any financial assistance to Corporation for implementation of any such scheme. It was, therefore, left to the Corporation to decide whether to continue the scheme or to wind it up. If under such circumstances, it was not possible for the Corporation to proceed further with the implementation of the new pension scheme, no directions can be issued from the Court to the contrary. It is not as if a Corporation was winding up an existing long standing pension scheme to the detriment of its existing employees. Here is the case where out of benevolence the Corporation thought of framing a new pension scheme but which required Government sanction and financial assistance. The Government made it clear that it is under no mood to fund any such pension scheme. It was for the Corporation either to raise funds from its own resources to sustain in the scheme or to wind up the same. Under such circumstances, the petitioners cannot insist that the pension must be paid to them even though the scheme may not be functional. Merely because the Corporation has not yet taken a final decision how to rationalize these conflicting interests, would not mean the petitioners in the interim period should be paid pension. It is in this context that the learned Single Judge provided that if in future such pension scheme is implemented the petitioners would receive benefit on the same. Contrary to what was argued before us by the counsel for the petitioners, we do not see this as a case where an existing pension scheme is being bound up. Instead this is a case where an attempt on part of the Corporation to frame a new pension scheme failed on account of the Government assistance. Only question remains of interest on delayed payment of leave encashment. There has been considerable delay in payment of leave encashment though the Corporation had no ground to resist the payment. Learned counsel for the Corporation, however, submitted that since the present litigation was pending, the Corporation had stayed its hands off. Pendency of the petition by a litigant to claim a benefit which is not released by the employer can hardly be a ground to justify non-payment and to avoid the liability to pay interest on the delayed payment. Under the circumstances, these appeals are allowed only to the limited extent of directing the Corporation to pay simple interest @ 7% per annum on the amount of leave encashment payable to each petitioner for the period between 3 (three) months after retirement till actual payment. All appeals disposed of accordingly. application(s) if any, also stands disposed of.” Pending 6. In the result, these petitions are dismissed. Pending application(s), if any, also stands disposed of. (AKIL KURESHI), CJ Pulak

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All Tripura HC judgments →