Civil · Reportable judgment

Puri Constructions Pvt. Ltd. vs State of Madhya Pradesh & Ors.

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Supreme Court of India
Date
18 April 2018
Case No.
Civil Appeal No. 4261 of 2018
Bench
Adarsh Kumar Goel, R.F. Nariman
Citation
[2018] 4 S.C.R. 257 : 2018 INSC 360
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.
Supreme Court Reports [2018] 4 S.C.R. 257 : 2018 INSC 360
Headnote

Madhya Pradesh Madhyastham Adhikaran Adhiniyam, 1983: Jurisdiction of Arbitration Tribunal – Award passed by Arbitrator appointed by Delhi High Court – Execution of award allowed – Appeal against the execution order pending before Delhi High Court as the same had been deferred by High Court pending decision of Supreme Court by Larger Bench in *L.G. Chaudhary case – Held: In terms of decision by Larger Bench of Supreme Court, the decision of the dispute between the parties has to be settled in accordance with the 1983 Act – In view of the fact that award was passed long back and matter is pending for execution, it is directed that award would be treated to have been passed under 1983 Act – The pending proceedings before Delhi High Court transferred to Madhya Pradesh High Court to be treated as Revision Petition under 1983 Act – The other pending proceedings shall be transferred to Arbitration tribunal constituted under 1983 Act – Appeals disposed of.

Madhya Pradesh Rural Road Development Authority and Anr. v. L.G. Chaudhary Engineers and Contractors (2012) 2 SCC 495 : [2012] 2 SCR 162 – referred to.

Read this judgment in
हिन्दी Hindi PDF ਪੰਜਾਬੀ Punjabi PDF

Translations made available by the Supreme Court of India in its e-SCR, opened as PDF files from the Indian Supreme Court Judgments data set. A translation is for understanding the judgment; the English judgment is the authentic text for all official purposes.

As published in the Supreme Court Reports, Supreme Court of India. Text from the Indian Supreme Court Judgments open data set (Dattam Labs), CC BY 4.0.

Ask LexAI about this judgment What was decided, on what reasoning, and which later cases follow it. Answers name the judgments they rely on. Ask

Cases cited

As listed in the Supreme Court Reports. Linked where the judgment is on LegalFirms.in.

  • [2012] 2 SCR 162 referred to

Full Judgment Text

The following Order of the Court was passed: ORDER 1. Delay condoned. Leave granted. 2. We have heard learned counsel for the parties and perused the record. 3. An agreement was executed between the parties on 11th May, 1984 for construction of Assembly building in the State of Madhya Pradesh. Dispute arose from the agreement. The High Court of Delhi appointed an arbitrator vide order dated 13th December, 1988. The Arbitrator gave the award on 21st June, 1989 which was made Rule of the Court by Delhi High Court on 28th September, 1989. Execution proceedings were taken by the appellant. Lea
Full text available to subscribers
Subscribe to access complete judgment text, daily digests, and AI-powered legal research tools. For informational and research purposes only.
View plans →
Annual plans from ₹799 + GST.

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All SC judgments →

Corporate & Commercial advocates near the Supreme Court of India

Dealing with a similar matter? Send a free enquiry to advocates who handle it. Fees are agreed with the advocate directly.

All Corporate & Commercial advocates in India