Civil · Reportable judgment

Mr. Anand Rao Korada Resolution Professional vs M/s. Varsha Fabrics (P) Ltd. & Ors.

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Supreme Court of India
Date
18 November 2019
Case No.
Civil Appeal Nos. 8800-8801 of 2019
Result
Allowed
Bench
Indu Malhotra, R. Subhash Reddy
Citation
[2019] 14 S.C.R. 695 : 2019 INSC 1259
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.
Supreme Court Reports [2019] 14 S.C.R. 695 : 2019 INSC 1259
Headnote

Insolvency and Bankruptcy Code, 2016 – ss.7, 13, 14, 231 and 238 – Respondent No.5 divested its 100% shareholding in respondent No.4 in favour of respondent Nos.1 to 3 – Respondent No.4 shut down its factory – Respondent No.13-Workers’ Union filed writ petition and sought payment of arrears and current salaries of the workmen – High Court directed Labour court to quantify the amount payable to workmen – During the pendency of the writ petition, a financial creditor filed petition u/s 7 of the IBC, 2016 before NCLT for initiation of the Corporate Insolvency Resolution Process (CRPF) against respondent No.4 – NCLT declared moratorium u/s.14 of the IBC – During the pendency of moratorium, in the pending writ petition High Court directed valuation of a land owned by respondent No.4 and passed the orders for carrying out auction of the assets of the respondent No.4 – Propriety of – Held: Not proper – In view of the provisions of the IBC, the High Court was not justified in passing the orders for carrying out auction of the assets of the respondent No.4, once the proceedings under the IBC had commenced and an order declaring moratorium was passed by the NCLT – Alienation of the assets of the respondent No.4 during the pendency of the proceedings under the IBC would jeopardise the interest of all the stakeholders – However, it is open for the respondent No.13 to file an application u/regulation 9 of the IBC for payment of arrears, salaries before the competent authority – Therefore, orders passed by the High Court set aside.

Allowing the appeals, the Court

HELD: 1. The Insolvency and Bankruptcy Code, 2016 was published in the Gazette of India on 28.05.2016. It was framed as a complete code to consolidate and amend the laws relating to insolvency resolution of corporate entities, partnership firms, and individuals in a time-bound manner, for maximisation of the value of the assets of such persons, and balance the interest of all the stakeholders. The Corporate Insolvency Resolution Process (“CIRP”) could be initiated when a corporate debtor commits a default, either by a financial creditor, or an operational creditor, or the corporate debtor itself. Section 12 of the IBC provides a time-frame to complete the CIRP. As per Section

Read the full headnote (2 more paragraphs)

13 of the IBC, the Adjudicating Authority i.e. the National Company Law Tribunal (“NCLT”) shall declare a moratorium for the purposes referred to in Section 14 of the IBC. [Para 6] [699G-H; 700-A-B]

2. In view of the provisions ss.14, 231 and 238 of the IBC, the High Court ought not to have proceeded with the auction of the property of the Corporate Debtor – Respondent No. 4 herein, once the proceedings under the IBC had commenced, and an Order declaring moratorium was passed by the NCLT. The High Court passed the impugned Interim Orders dated 14.08.2019 and 05.09.2019 after the CIRP had commenced in this case. The moratorium having been declared by the NCLT on 04.06.2019, the High Court was not justified in passing the Orders dated 14.08.2019 and 05.09.2019 for carrying out auction of the assets of the Respondent No. 4 – Company i.e. the Corporate Debtor before the NCLT. The subject matter of the auction proceedings before the High Court is a vast chunk of land admeasuring about 330 acres, including Railway lines and buildings. If the assets of the Respondent No. 4 – Company are alienated during the pendency of the proceedings under the IBC, it will seriously jeopardise the interest of all the stakeholders. As a consequence, this Court set aside the impugned Interim Orders dated 14.08.2019 and 05.09.2019 passed by the High Court, as parallel proceedings with respect to the main issue cannot take place in the High Court. The sale or liquidation of the assets of Respondent No. 4 will now be governed by the provisions of the IBC. [Para 9] [702-B-F]

Read this judgment in
हिन्दी Hindi PDF ਪੰਜਾਬੀ Punjabi PDF

Translations made available by the Supreme Court of India in its e-SCR, opened as PDF files from the Indian Supreme Court Judgments data set. A translation is for understanding the judgment; the English judgment is the authentic text for all official purposes.

As published in the Supreme Court Reports, Supreme Court of India. Text from the Indian Supreme Court Judgments open data set (Dattam Labs), CC BY 4.0.

Ask LexAI about this judgment What was decided, on what reasoning, and which later cases follow it. Answers name the judgments they rely on. Ask

Filed under

Insolvency and Bankruptcy Code, 2016 Section 7, Insolvency and Bankruptcy Code, 2016 Section 14, Insolvency and Bankruptcy Code, 2016 Section 238, Insolvency and Bankruptcy Code, 2016

The law this judgment cites

Opens the section on Law Maker (lawmaker.in), our sister site for law students.

Cited in 1 later judgment on LegalFirms.in

From the case lists those reports print.

Full Judgment Text

The Judgment of the Court was delivered by INDU MALHOTRA, J. Leave granted. 1. The present Civil Appeals have been filed by the Appellant – Resolution Professional appointed by the National Company Law Tribunal for the Corporate Debtor – M/s Hirakud Industrial Works Ltd., to challenge the interim Orders dated 14.08.2019 and 05.09.2019 passed by the Odisha High Court in W.P. (Civil) No. 7939/2011. 2. This Court vide Order dated 23.09.2019 issued Notice to all the parties, including the Writ Petitioners i.e. the Hirakud Workers’ Union – Respondent No. 13 herein. The Appellant was directed to
Full text available to subscribers
Subscribe to access complete judgment text, daily digests, and AI-powered legal research tools. For informational and research purposes only.
View plans →
Annual plans from ₹799 + GST.

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All SC judgments →

Employment & Labour advocates near the Supreme Court of India

Dealing with a similar matter? Send a free enquiry to advocates who handle it. Fees are agreed with the advocate directly.

All Employment & Labour advocates in India