IN THE HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
Case No: Arb P. No. 90/2025.
Uploaded on:19.05.2026
M/s Sharat Puri Contractor,
Govt. Contractors and Builders, 227,
Sector No.1, Trikmuta Nagar, Jammu
through its Partner Shri karan Puri,
aged 32 years, S/O Shri Sharat Puri
R/O 227, Sector No.1, Trikuta nagar,
Jammu.
…Petitioner(s)/Appellant(s)
Through: Mr. R.K.Gupta, Sr. Advocate with
Mr. Udhay Bhaskar, Advocate.
Vs.
1. Union Territory of Jammu and
Kashmir through its Commissioner
Secretary, PWD (R&B), Civil
Secretariat, Jammu.
2. Chief Engineer, PWD (R&B) Peer
Panjal, Rajouri.
3. Executive Engineer, PWD (R&B),
Division, Rajouri.
Through:
…. Respondent(s)
Ms. Monika Kohli, Sr. AAG with
Ms. Sagira Jaffar, Advocate.
CORAM: HON’BLE MR. JUSTICE SANJAY DHAR, JUDGE
ORDER
15.05.2026
1. Through the medium of present petition, the petitioner has invoked
the jurisdiction of this Court under Section 11(6) of the Arbitration
and Conciliation Act, 1996 seeking appointment of an independent
Arbitrator.
Arb.P No.90/2025
2. As per the case of the petitioner, it is a partnership firm duly
registered with the Registrar of Firms, and Shri Sharat Puri is one of
its partners and is, thus, competent to file the present petition and
pursue the case.
3. Pursuant to e-NIT No. 20 of 2014-15 dated 27.08.2014, a contract for
the construction of District Office Complex G+2 (three-storeyed) at
Rajouri was allotted to the petitioner firm vide communication No.
CEJ/G/11097-11098 dated 18.10.2014, for a contract value of Rs.
7,20,68,937/-. Pursuant to allotment of the contract, Agreement No.
05/OW-A of 2014-15 dated 26.12.2014 came to be executed between
the petitioner firm and respondent No. 3. The date of commencement
of the work was fixed as 25.10.2014, and the date of completion was
fixed as 25.04.2016.
4. According to the petitioner, after deploying men and machinery at the
site, the construction work was commenced. However, respondent
No. 3, under the instructions of the District Development
Commissioner, Rajouri, directed the petitioner to suspend the work till
23.12.2014. Thereafter, on 25.12.2014, the District Development
Commissioner, Rajouri verbally instructed the petitioner firm to
resume the work. Again, vide communication dated 24.04.2015,
respondent No. 3 directed the petitioner to stop further execution of
the work.
5. It is further submitted that vide communication dated 11.05.2015, the
petitioner requested respondent No. 3 to settle an amount of Rs. 40.61
lakhs towards the expenditure incurred on mobilization advance. It
has also been submitted that respondent No. 3, vide communication
Arb.P No.90/2025
dated 15.05.2015, requested the Superintending Engineer, PWD
(R&B) Circle, Rajouri, to authorize completion of one block of the
building up to the functional level. In the said communication, it was
also intimated that the petitioner had submitted a bill amounting to
Rs. 40.61 lakhs on account of advance payments made to the suppliers
towards mobilization advance and allied expenses.
6. According to the petitioner, repeated representations were made to the
respondents seeking resumption of the contract work; however, no
decision was taken by the respondents. It is stated that vide
communication dated 05.04.2019, the petitioner requested respondent
No. 2 to take a decision regarding resumption of the work, which
request was reiterated vide communication dated 28.08.2019.
However, no response was received from the respondents. Thereafter,
vide communication dated 07.02.2020, the petitioner is stated to have
once again highlighted the issue concerning the losses suffered by it
on account of the prolonged pendency of the decision regarding either
resumption of the contract work or termination of the contract.
7. It has further been submitted that the respondents issued fresh e-NIT
No. 8 of 2024-25 dated 27.05.2024, inviting expression of interest for
the very same work which had earlier been allotted to the petitioner,
though at a different location. Upon acquiring knowledge of the same,
the petitioner addressed a detailed communication dated 01.07.2024 to
respondent No. 2. Simultaneously, the petitioner invoked Clause 24.1
of the SBD/General Conditions of Contract and requested the Chief
Engineer for resolution of the pending disputes. However, no response
was received from the respondents, from which it can reasonably be
Arb.P No.90/2025
inferred that the competent authority has failed to take any decision
within 45 days from the date of receipt of the request for resolution of
disputes.
8. It has further been submitted that, vide email dated 12.12.2024, the
petitioner invoked Clause 25(1) of the SBD/General Conditions of
Contract and requested that the disputes/claims of the petitioner firm
be referred to the Arbitral Tribunal. However, despite the aforesaid
email dated 12.12.2024, the disputes have not been referred to the
Arbitral Tribunal by the respondents. Hence, the present petition.
9. The respondents have filed objections to the petition, wherein it has
been submitted that the disputes raised by the petitioner are premature
and are not arbitrable at this stage, as the matter involves
administrative decisions and issues relating to execution of
government work, which require examination at the departmental
level. It has further been submitted that the pre-conditions for
invocation of the arbitration agreement have not been fulfilled by the
petitioner.
10.On merits, it has been submitted that during the execution of the work,
certain administrative issues arose with regard to the project site, as
the land in question was under consideration by the Government for
transfer and approval by the competent authorities. In view of these
developments, the higher authorities issued directions advising that
the construction work should not proceed until a final decision
regarding the land was taken. It has further been submitted that the
Divisional
Commissioner,
Jammu
vide communication
dated
25.03.2025, advised that it would not be appropriate to proceed with
Arb.P No.90/2025
the construction work at the site till a final decision regarding transfer
of the land was taken by the Government. Thus, the execution of the
work was affected due to the reasons beyond the control of the
respondents.
11.Heard and considered.
12.So far as the existence of the arbitration agreement contained in
Clause 25 of the General Conditions of Contract is concerned, the
same is not in dispute. As per the said clause, either party has the
option to refer the decision of the competent authority to arbitration
within twenty-eight days from the date of the competent authority’s
written decision. The clause further provides that in cases where the
initial contract price, as mentioned in the letter of acceptance, is Rs. 5
crores or below, the dispute or difference in respect whereof the
competent authority has rendered a decision shall be referred to a sole
arbitrator. However, where the initial contract price exceeds Rs. 5
crores, the dispute is required to be referred to an Arbitral Tribunal
comprising three arbitrators, one each to be appointed by the
Employer and the contractor, and the third to be chosen by the two
arbitrators so appointed, who shall act as the Presiding Arbitrator.
13.It has been pleaded by the petitioner that when the respondents issued
fresh e-NIT No. 8 of 2024-25 dated 27.05.2024 inviting expression of
interest, the petitioner addressed a detailed communication dated
01.07.2024, inter alia, invoking Clause 24.1 of the SBD/General
Conditions of Contract and made a request to the competent authority,
i.e., the Chief Engineer, for resolution of the pending disputes.
However, no decision was taken by the competent authority, which
Arb.P No.90/2025
compelled the petitioner to invoke the arbitration clause contained in
Clause 25(1) of the SBD/General Conditions of Contract by making a
request for reference of the disputes/claims to the Arbitral Tribunal.
This aspect of the matter has not been disputed by the respondents.
The pleadings of the parties clearly disclose that disputes have arisen
between them relating to the contract executed between the parties.
Therefore, in order to determine the said disputes, an Arbitrator is
required to be appointed, particularly when the appointing authority
has failed to appoint the arbitrator in terms of the covenants of the
arbitration clause.
14.In view of the above, the petition is allowed and, with the consent of
the learned counsel for the parties, Shri Varinder Singh Bhau, Former
District Judge, J&K Higher Judicial Service appointed as the Sole
Arbitrator to adjudicate upon the disputes and differences between the
parties arising out of and in connection with the agreement referred to
above.
15.A copy of this order shall be communicated to the learned Sole
Arbitrator by the Registry of this Court within a period of fifteen (15)
days from today, and the learned Arbitrator is requested to forward the
“Statutory Statement of Disclosures” under Section 11(8) read with
Section 12(1) of the Arbitration and Conciliation Act, 1996, to the
parties within a period of two weeks from the date of receipt of this
order.
16.The parties shall appear before the learned Sole Arbitrator on the date
and at the place to be fixed by him. It is further directed that all
arbitration costs and the fees of the Arbitral Tribunal shall be borne
Arb.P No.90/2025
equally by the parties and shall remain subject to the final award that
may be passed by the learned Arbitrator in relation to the costs.
17.Disposed of.
(Sanjay Dhar)
Judge
Jammu
15.05.2026
Madan Verma-Secy
Whether order is speaking?
Whether order is reportable?
MADAN LAL VERMA
2026.05.19 18:45
I attest to the accuracy and
integrity of this document
Arb.P No.90/2025
Yes
No
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.