The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
12. That with respect to paragraph no.14, it is stated that the total cost of the work order issued by the NHM, Tripura, this year for installing Medical Gas Pipeline System in 8(eight) hospitals of the State was Rs.6,31,59,224, which works out to an average price of Rs.78,94,903 per turnkey job of installing Medical Gas Pipeline System; whereas the petitioner himself has shown in the tabular statement of the para that for the NIT called by the Director of Health Services for installing similar systems in 10(ten) hospitals of the State, he had quoted an average price of Rs.92,03,349, which is 16.57% higher than the average installation price finalized through the NHM tender. Thus, the complaint received through the email dated 25-082021 about the petitioner’s rates being exceptionally high was found to be authentic; and in the interest of the State, the Govt. of Tripura was compelled to cancel the work order dated 20-08-2021.” Page - 7 of 14 In paragraph 11 of the affidavit, according to the State Government thus, the rates quoted by the petitioner were exceptionally high. However, in the paragraph 12, it is stated that in comparison to other turnkey projects implemented by the petitioner in the present case the rate quoted was 16.57% higher. In this affidavit, the Government has also referred to a term of the contract which would enable the Government to cancel the contract at any…
3. That, in pursuant to the direction of this Hon’ble High Court under the queries No.2 “What was the basis for the Government to raise the estimated cost of the project from Rs.3 crores to Rs.9 crores?” I say that the estimated cost of the project was raised because the estimate cost of the tender of NHM was specified of Rs.3,00,00,000/- for 2(two) district & 1(one) Sub-Divisional Hospital. Accordingly the Director of Health Services floated the e-tender with the same estimate cost Rs.3,00,00,000/- and it was found out that the average cost estimate of each hospital is Rs.1,00,00,000/-. So, it is found out that the total cost estimate of 10(ten) nos. different SubDivisional Hospital was supposed to be Rs.10,00,00,000/- initially. But as there was no option to edit the tender value in the e-tender portal and also there was an urgency to combat COVID-19 situation and a letter was also received from the Ministry of Health & Family Department where it is mentioned that it was decided to commission 1,222 PSA Oxygen Plants sanctioned under PM CARES across all the States/UTs covering all 736 districts of the country by 15th August, 2021 and instructed to put in all the resources to complete the commissioning of PSA Plant sanctioned under PM CARES for State/UT in time of top priority basis by completing augmentation of MGPS work along with DG set availability by 10th August 2021. So, r…
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
Page - 1 of 14
HIGH COURT OF TRIPURA
AGARTALA
WP(C) No.637 of 2021
M/s Premier Cryogenics Limited.
………… Petitioner(s).
- Vs. The State of Tripura and Ors.
………… Respondent(s).
For Petitioner(s)
: Mr. S Chakraborty, Advocate,
Mr. I Choudhury, Advocate.
For Respondent(s) : Mr. Debalaya Bhattachariya, Govt. Advocate,
Mr. S Saha, Advocate.
HON’BLE THE CHIEF JUSTICE MR. AKIL KURESHI
HON’BLE JUSTICE MR. S G CHATTOPADHYAY
_O_R_D_E_ R_
23/9/2021
(Akil Kureshi, CJ).
This petition is filed by one M/s Premier Cryogenics Limited, a
company registered under Companies Act, 1956 to challenge an order,
dated 7th September 2021, by which the Government of Tripura was
pleased to cancel a work order issued to the petitioner company, on 28th
August 2021, for supply and commissioning of Medical O2 Gas pipe line
systems for PAC Oxygen Plant for ten hospitals in the State.
[2]
Brief facts are as under :
Page - 2 of 14
The Government of Tripura required reliable source of continuous
supply of oxygen in its hospitals to meet with the Corona challenges. The
Government of Tripura, therefore, decided to install ten such plants in
different hospitals in the State and for which purpose invited public tenders
from illegible interested parties. A public notice was issued for such
purpose, on 16th July 2021. Estimated cost was indicated at Rs.3 crores.
The petitioner was interested in undertaking the works and, therefore, made
its bid. The petitioner was found technically qualified and its offer of
installation of all such plants at a total cost of Rs.9.29 crores (rounded off)
was accepted. A work order was also issued in favour of the petitioner on
20th August 2021 by the Government. The work had to be completed within
fifteen days.
[3]
The case of the petitioner is that since the entire project had to be
completed within a very short time, soon upon receipt of the work order the
petitioner started acquiring the necessary equipments and machinery for
installation. However, on 25th August 2021, the respondent No.3 i.e. the
Joint Secretary and Director of Health Services, Government of Tripura,
issued a show cause notice to the petitioner calling upon the petitioner why
the work order should not be cancelled. Forty-eight hours were granted for
such purpose. This show cause notice was based on an averment that the
petitioner had quoted higher rates in the tender of supplying and
Page - 3 of 14
commission of the plants in comparison to the rates quoted by National
Health Mission(NHM), Tripura. The petitioner was also instructed to stop
all commissioning works.
[4]
The petitioner replied to the show cause notice under
communication, dated 27th August 2021 and pointed out that it had not
quoted any higher rates than those offered to NHM. The petitioner pointed
out that the rates quoted in the present case as compared to those the
petitioner had quoted to NHM were more than comparable. The petitioner
highlighted this aspect in the reply in following manner :
“We provide below the rates at which similar works have been
allotted to us by NHM and DHS :
1. NHM
a. Dhalai - Rs.94,57,119.00
b. Gomti- Rs.90,80,560.00
Average - Rs.92,68,839.00
2.
DHS
a. Teliamura - Rs. 93,14,828.00
b. RGM - Rs.93,81,607.00
c. Chailengta - Rs.90,06,727.00
d. Tripura Sundari - Rs.88,48,058.00
e. Kanchanpur - Rs.93,69,409.00
f. Kherengbar - Rs.88,28,000.00
g. Amarpur - Rs.92,45,819.00
h. Bimal Sinha - Rs.94,31,412.00
i. Sabroom - Rs.1,01,65,945.00
j. Bishalgarh - Rs.94,04,283.00
Page - 4 of 14
Average - Rs.92,99,608.00
Average (excluding Sabroom) Rs.92,03,349.00
The rates quoted by us for the 2 hospitals awarded to us by NHM
Tripura are Rs.94.57 lakh and Rs.90.80 lakh, average of the 2 being
Rs.92.68 lakh. Whereas, the rates quoted to DHS varied from
Rs.88.28 lakh to Rs.101.65 lakh, average being Rs.92.99 lakh. The
increase is only Rs.0.31 lakh or mere 0.3%. Thus, it is not a fact that
we have quoted high at DHS.
In fact, there is only one hospital (Sabroom DHS) where the rate is
higher than NHM hospitals. That is because of long pipe network
required in that hospital. All other 9 DHS hospital rates are lower than
NHM hospital at Dhalai. If we exclude that hospital, the average of
DHS hospital is Rs.0.65 lakh lower.
It is our assessment that the cost structure of the hospitals allotted to
us under DHS and NHM does not vary much. Which is why our
quoted rate or all hospitals are within a band of Rs.88.28 lakh to
Rs.101.65 lakh, i.e. within a small range of Rs.6.70 lakh from the
average price.
Further, please consider the fact that this tender is for turnkey
construction and operation & maintenance and bidders quote separate
rate for each hospital, depending on own assessment of quantity of
materials required, installation cost, O & M cost, distance from major
town, etc. We quoted a different rate for each hospital - whether NHM
or DHS based on our own assessment of cost of execution at each
hospital. The price of one hospital cannot be compared to another
hospital, as each hospital has unique layout and circumstances.
An analysis of the various cost items shows that in DHS hospitals
number of Outlet and Flowmeter is less, leading to a cost reduction of
about Rs.24,34,600. This is offset by increase in pipe length and pipe
fittings, of additional cost about Rs.17.50 lakh. Most importantly, in
several DHS hospitals there are road crossings and requirement of
Page - 5 of 14
constructing overhead mechanical bridges for the pipeline, which is
not there in NHM hospitals. Extra expenditure on this account is about
Rs.10.50 lakh. Other cost components like Manifold, installation
expenses, supervision expenses, manpower for O & M remain the
same for all the hospitals. Details given below :
Item
Copper pipe
DHS
Hospitals
as Price
implication
compared to NHM for 10 DHS hospital
hospitals
in comparison to
NHM hospitals
About 250 metre More
(+) 14,00,000
Pipe fittings
About 10% more
(+) 3,50,000
Manifold
Same
-
Outlet
About 100 less
(-) 14,50,400
Flowmeter
About 100 less
(-) 9,84,200
Installation
Same
-
Supervision
Same
-
Manpower for 5
years
Overhead
Pipeline
Structure Support
10 Metre Wide Road
Crossing
Total implication
Same
-
expense
(+) 5,50,000
(+) 6,00,000
(+) 4,65,800
Thus, there is slightly higher cost in DHS hospitals and accordingly,
we have quoted a mere 0.3% higher. There is some variation in
individual hospital based on our estimate of pipe length, Outlets and
Mechanical Structure requirement, though not more than a few
percentages points.
In view of the above, we request you to please drop the SCN at the
earliest.”
Page - 6 of 14
Unimpressed by the petitioner’s representation, the Joint
Secretary passed the impugned order cancelling the work order upon which
this petition has been filed.
[5]
In response to notice issued, the respondents have appeared and
filed their reply. In the reply, dated 18th September 2021, in order to
support the impugned order it is primarily stated as under :
“11. That, with respect to paragraph no.13, it is vehemently denied
that there was any extraneous consideration other than taking an
abundant precaution against proceeding further with execution of the
work order at the allegedly exceptional high rates pending the
verification of the aforesaid email complaint.
12.
That with respect to paragraph no.14, it is stated that the total
cost of the work order issued by the NHM, Tripura, this year for
installing Medical Gas Pipeline System in 8(eight) hospitals of the
State was Rs.6,31,59,224, which works out to an average price of
Rs.78,94,903 per turnkey job of installing Medical Gas Pipeline
System; whereas the petitioner himself has shown in the tabular
statement of the para that for the NIT called by the Director of Health
Services for installing similar systems in 10(ten) hospitals of the State,
he had quoted an average price of Rs.92,03,349, which is 16.57%
higher than the average installation price finalized through the NHM
tender. Thus, the complaint received through the email dated 25-082021 about the petitioner’s rates being exceptionally high was found
to be authentic; and in the interest of the State, the Govt. of Tripura
was compelled to cancel the work order dated 20-08-2021.”
Page - 7 of 14
In paragraph 11 of the affidavit, according to the State
Government thus, the rates quoted by the petitioner were exceptionally
high. However, in the paragraph 12, it is stated that in comparison to other
turnkey projects implemented by the petitioner in the present case the rate
quoted was 16.57% higher. In this affidavit, the Government has also
referred to a term of the contract which would enable the Government to
cancel the contract at any stage.
[6]
We have heard learned counsel for the parties for final disposal of
the petition. This petition was heard from time to time and we had
requested the Government to produce the original file concerning the
tender and its cancellation. We had also required the Government to file an
additional affidavit on certain specific questions. We would refer to these
factual aspects a while later. For the time being we may recall, in the
present case, after accepting the tender of the petitioner the Government
cancelled the same on the ground that the rate quoted was high. It may be
that in contractual relations, the State Government has considerable
leverage. It is possible to the Government to argue that termination of
contract can give rise to a civil dispute for which the petitioner must be
relegated to civil remedies. However, any such view would ignore the
primary requirement of every State action must confirm to equality and
Page - 8 of 14
reasonableness flowing from Article 14 of the Constitution. If the decision
of the State Government to cancel the contract once awarded is found to be
wholly arbitrary, the same must be quashed. Once the State Government
had invited tender and accepted the rates quoted by the successful bidder,
unless some special grounds are shown, even a State agency cannot be
allowed to walk out of its commitments on the ground that on a subsequent
thinking the rates were found to be higher. Of course, there would be an
exception to this general proposition namely, if there is any fraud or mala
fides pointed out, the Court may grant greater leverage to the Government
and insist that the aggrieved person may approach the Civil Court where all
issues of facts can as well be examined.
[7]
With this angle in mind, we had requested the learned
Government Advocate to produce the original files before us. Before we
refer to the documents contained in the file, we may refer to one more
relevant development. After cancelling the work order of the petitioner, the
Government had quoted fresh tender for the same purpose. This time
around, the Government had declared the estimated cost at Rs.9 crores. The
questions therefore which arose were, was there any major difference in the
technical specifications and capacity requirements between the two tenders
namely, (i) during which the petitioner was awarded with the contract and
Page - 9 of 14
(ii) which the Government wanted to award afresh after cancelling the
petitioner’s tender and if there was no change, what was the reason for
revising the estimated cost from Rs.3 crores indicated in the previous
tender to Rs.9 crores in the subsequent tender. In our order, dated 21st
September 2021, we had raised these queries for the Government to clarify
on affidavit.
“Before we take a final view, let the respondents clarify these
aspects of the matter namely :
(i)
Whether the technical specification of the project in
both the tenders was same or different in terms of production capacity
as well as other technical requirements; and
(ii) What was the basis for the Government to revise the
estimated cost of the project from Rs.3 crores to Rs.9 crores.”
[8]
In response to the said order, the Government has filed an
affidavit today in which it is stated as under :
“2. That, in pursuant to the direction of this Hon’ble High Court
under the queries No.1.
“Whether the technical specification of the project in both the
tenders was same or different in terms of production capacity
as well as other technical requirements?”
I Say that the technical specification of the project in both the
tenders was same. The evaluation committee was examined the draft
DNIT format of National Health Mission (NHM) with corrigendum
and then they are views that the draft e-tender format of NHM with
Corrigendum-1 are found appropriate to float as e-tender. Only one
Page - 10 of 14
item was added as “Emergency Manifold” Size 1 × 2 with 1 × 14.
Regulator for smooth supply of Oxygen from cylinder when PSA
Oxygen plant fails. But the items capacities of the technical
requirements are different.
AND
3.
That, in pursuant to the direction of this Hon’ble High Court
under the queries No.2
“What was the basis for the Government to raise the
estimated cost of the project from Rs.3 crores to Rs.9
crores?”
I say that the estimated cost of the project was raised because
the estimate cost of the tender of NHM was specified of
Rs.3,00,00,000/- for 2(two) district & 1(one) Sub-Divisional Hospital.
Accordingly the Director of Health Services floated the e-tender with
the same estimate cost Rs.3,00,00,000/- and it was found out that the
average cost estimate of each hospital is Rs.1,00,00,000/-. So, it is
found out that the total cost estimate of 10(ten) nos. different SubDivisional Hospital was supposed to be Rs.10,00,00,000/- initially.
But as there was no option to edit the tender value in the e-tender
portal and also there was an urgency to combat COVID-19 situation
and a letter was also received from the Ministry of Health & Family
Department where it is mentioned that it was decided to commission
1,222 PSA Oxygen Plants sanctioned under PM CARES across all the
States/UTs covering all 736 districts of the country by 15th August,
2021 and instructed to put in all the resources to complete the
commissioning of PSA Plant sanctioned under PM CARES for
State/UT in time of top priority basis by completing augmentation of
MGPS work along with DG set availability by 10th August 2021. So,
rather than cancelling the tender, administrative approval was received
from the Government for the excess amount.
Page - 11 of 14
A copy of the letter from the Ministry of Health & Family
Department is annexed hereto and marked as Annexure - R/3.”
[9]
Two things initially become clear from this Government
affidavit. Firstly, there is virtually no difference in the technical
specifications and capacity requirement of oxygen production plants in the
two tender processes. The Government has candidly stated that only change
is an additional item which does not appear to be of any significant
difference on interim cost. In that view of the matter, the Government owed
a duty to explain how and why the original estimated cost of Rs.3 crores
had now been revised to Rs.9 crores in the fresh tenders. Here the
explanation emerging from paragraph three of the said affidavit is that the
earlier estimation was incorrect and due to shortage of time, proper care
could not be taken. In other words, the Government admits that publishing
estimated cost of Rs.3 crores in the first tender, was incorrect and the
correct estimate would be Rs.9 crores as has been done in the subsequent
tender notice.
[10]
Going by this forthright declaration of the Government, the very
foundation for cancelling the work order of the petitioner disappears. We
may recall, the show-cause notice required the petitioner to explain why the
petitioner had offered higher rates as compared to the rates offered to
Page - 12 of 14
NHM. This show cause notice was issued because one private person had
made a complaint to the Government that the contractor was awarded at an
extremely high rate. We have perused this complaint in which the basis
taken by the complainant was that the cost estimated by the Government
was Rs.3 crores for their project. As against this, the petitioner’s offer at
Rs.9.29 crores was accepted which is exorbitant. If the Government now
admits that the cost estimation of Rs.3 crores in the previous tender was an
error and the correct estimate of Rs.9 crores indicated in the second tender
is accurate, the very plank on which the Government’s show-cause notice
and its final decision rested disappear.
[11]
In order to take extra precautions, we had also perused the
Government files which would reveal that initially, the committees
appointed for looking into the complaint of the private complainant advised
not to cancel the contract citing proper reasons. Subsequently, however at
the higher level, a decision seemed to have been taken to cancel the
contract and to invite fresh tenders. It is not necessary to refer to detailed
notes presenting one viewpoint or the other. All this pales into
insignificance once we take into account two important factors noted above
namely, the work to be executed in both the tenders advertised by the
Government is the same and the cost estimation of Rs.3 crores declared
Page - 13 of 14
previously was wrong and one which was subsequently revised to Rs.9
crores was correct. The offer of the petitioner at Rs.9.29 crores for
undertaking the work therefore, even going by the Government disclosures,
was not high.
[12]
In conclusion, we find that the Government had accepted the offer
of the petitioner after due consideration. The contract awarded was
cancelled primarily on a private complaint which rested only on one factor
namely, that the offer of the petitioner which was accepted at Rs.9.29
crores was excessively high compared to the estimated cost of Rs.3 crores.
The Government in the fresh tenders for execution of the same work has
revised its cost estimation to Rs.9 crores and also justified this on affidavit
before us disclosing that the previous estimation was wrong. The very basis
for cancellation of the contract, therefore, disappears. Allowing the
Government to cancel the contract under such circumstances, merely
because it is a matter pertained to contractual relationship between the two
parties, would be upholding a wholly arbitrary decision.
[13]
Under the circumstances, impugned order dated 7th September
2021 is set aside. Considering the urgent requirements, the petitioner was
given fifteen days to complete the work. The petitioner must do so within
further 14(fourteen) days that we grant it. However, starting point of these
Page - 14 of 14
14(fourteen) days requires some adjustment. If the Government wishes to
challenge this order, it would be open for the Government to indicate such
decision to the petitioner within 10(ten) days from today. If no indication is
given, it would be open for the petitioner to start the work on 4 th October
2021 and complete the same latest by 18 th October 2021. It is further
provided that even if the Government decides to challenge this judgment, it
must act within reasonable time. In other words, in absence of approach to
the Supreme Court by the State Government, the petitioner would start the
work on 8th November 2021 and complete it by 22nd November, 2021.
[14]
The petition is disposed of with these observations and
directions. Pending application(s), if any also stands disposed of.
( S G CHATTOPADHYAY, J )
Sukhendu
( AKIL KURESHI, CJ )
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review