HIGH COURT OF TRIPURA
AGARTALA
WP(C) No.537 of 2024
M/s M.P. Khaitan, a Partnership Firm, Represented by its Partners,
i. Shri Sanjay Khaitan,
ii. Shri Govind Khaitan,
iii. Shri Virendra Khaitan,
All of them are sons of late Mahabir Prasad Khaitan, permanent residents of
97SD, Block-E, 3rd Floor, New Alipore, Kolkata, PIN-700053, presently
residing at Kunjaban Colony, Abhoynagar near Tripura Small Industries Office,
P.O. Abhoynagar, P.S. New Capital Complex, Sub-Division- Agartala, District
West Tripura, PIN-799005.
.........Petitioner(s)
Versus
1. The Tripura University, represented by its Vice Chancellor, having his office
at Suryamaninagar, Agartala, Tripura, PIN-799130.
2. The Registrar, Tripura University, having his office at Suryamaninagar,
Agartala, Tripura, PIN-799130.
3. M/s Engineering Projects (India) Limited, represented by its Executive
Director, having his office at Block-A, Hindustan Tower, 4th Floor, Hindustan
Tower, Jawahar Nagar, National Highway 37, Beltola, Guwahati, PIN-781022,
having its local office at 21 Krishnanagar Road, Bijoy Kumar Chowmuhani,
Agartala-799001 represented by its Deputy General Manager.
4. The Deputy General Manager, M/s Engineering Projects (India) Limited,
having his office at 21 Krishnanagar, Bijoy Kumar Chowmuhani, Agartala799001.
………Respondent(s).
For Petitioner(s)
: Mr. Somik Deb, Sr. Advocate,
Mr. Pranabindu Chakraborty, Advocate.
For Respondent(s)
: Mr. Debalay Bhattacharya, Sr. Advocate,
Mr. S. Saha, Advocate.
HON’BLE THE CHIEF JUSTICE MR. APARESH KUMAR SINGH
HON’BLE MR. JUSTICE ARINDAM LODH
Order
14/08/2024
Heard Mr. Somik Deb, learned senior counsel for the petitioner
and Mr. Debalay Bhattacharya, learned senior counsel for the respondentsTripura University.
2.
Facts as pleaded by the writ petitioner are briefly stated as under:
Tripura University [TU, for short] issued an NIT for execution of
work titled as “Construction of Phase II Project Works (Part I) of the Tripura
University at Suryamaninagar, Agartala, Tripura (West)” with an estimated
period of completion as 30 months from the date of issue of the work order.
Respondent No.3- M/s Engineering Projects (India) Limited [EPIL, for short]
turned out to be the successful tenderer with whom agreement was entered by
TU. For execution of the labour component of the said work, EPIL further
issued NIT reference No.DLI/CON/713/414 titled as “Construction of various
buildings and allied development works at Tripura University campus,
Suryamaninagar, Tripura (West)” on a turnkey basis with an estimated
completion period of 24 months. Petitioner, being the successful tenderer, got
Letter of Intent on 03.05.2014 and entered into a contract with EPIL on
19.05.2014. The stipulated date for completion of the work was 18.05.2016.
Suitable extensions were granted due to project delays which the petitioner
attributes to EPIL and TU. Petitioner claims to have successfully completed the
work and handed over the project to EPIL on 28.12.2018 in respect of which an
intimation letter of completion was also issued by EPIL. He submitted his final
bill on 20.12.2021 incorporating claims for enhanced rates due to price increase
for the delay. Petitioner has referred to the report of a Sub-Committee
constituted by TU which, according to him, accepted the legitimacy of his
claims, acknowledging the delays from 12.12.2016 to 31.12.2018. Petitioner
has approached this Court as despite completion of work, EPIL has not released
the security deposit of Rs.1,65,82,247/-, his outstanding dues of Rs.31,23,309/and the amount claimed for price variation of Rs.1,88,98,395.13. Despite
request made, EPIL has not responded. Petitioner also apprehends that due to
the delay following the expiry of defect liability period of one year from the
date of completion of the work on 28.12.2018, the rate of GST on works
contract enhanced to 18% would be now levied upon the petitioner, though at
the time of execution of the work, it was 12% only. Therefore, petitioner has
approached this Court in writ jurisdiction with the following prayers:
“i) Issue Rule, calling upon the respondents and each one of them, to show cause
as to why a Writ of Certiorari and/or in the nature thereof, shall not be issued, for
directing them, to transmit the records, appertaining to this writ petition, lying
with them, for rendering substantive and conscionable justice to the petitioner;
ii) Issue Rule, calling upon the respondents and each one of them to show cause
as to why a Writ of Mandamus and/or in the nature thereof, shall not be issued,
for mandating/directing them, to forthwith release the admitted dues, due and
payable to the petitioner, under the heads of Security Deposit, amounting to
Rs.1,65,82,247/-, outstanding dues, amounting to Rs.31,23,309/-, & Price
Variation, amounting to Rs.1,88,98,395.13/-, in favour of the petitioner, despite
successful execution of the work on 24.12.2019, alongwith Interest @15% from
the respective dates the amounts fell due, till the date of actual payment;
iii) Issue Rule, calling upon the respondents and each one of them to show cause
as to why a Writ of Mandamus and/or in the nature thereof, shall not be issued,
for mandating/directing them, to abstain from levying GST at the rate of 18%
(instead of 12%), while releasing the admitted dues, due and payable to the
petitioner;
iv) Issue Rule, calling upon the respondents and each one of them to show cause
as to why a Writ of Prohibition and/or in the nature thereof, shall not be issued,
for restraining/prohibiting them, from levying GST at the rate of 18% (instead of
12%), while releasing the admitted dues, due and payable to the petitioner;
v) Call for the records appertaining to this writ petition;
vi) After hearing the parties, be pleased to make the Rule Absolute in terms of i.
& ii. above;
vii) Costs of and incidental to this writ proceeding;
viii) Any other Relief(s) as to the Hon'ble High Court may deem fit and proper”
3.
Learned senior counsel for the petitioner has referred to Clause 5
of the General Conditions of Contract entered into between TU and EPIL
which provides for the stipulated completion period of 30 months from the 15 th
day after the letter of award or from the date of site hand over which was
extendable under Clause 5A. He further submits that time was extended on
multiple times by the TU in favour of EPIL as would be evident from
Annexure-4. Since extensions were granted without penalties of liquidated
damages, time does not appear to be the essence of the contract. Reference is
made to Clause 8 which provides for procedure for issuance of completion
certificate once the contractor has fulfilled his obligations. The completion
letter was issued on 28.12.2018 from EPIL indicating the fault on petitioner’s
part. He has also referred to Clause 10 of the contract which stipulates that no
price variation will be allowed within the initial 30 months completion period,
but it would be applicable for the extended period, the computation of which is
governed by Clause 10.2.
4.
Learned senior counsel for the petitioner has also referred to
Clause 25 which provides for arbitration for settling any dispute, differences or
questions arising from the contract. The arbitration process is governed by the
Arbitration and Conciliation Act, 1996 or any statutory modification thereof.
The jurisdiction of the dispute resolution would be within Agartala. He has
referred to Clause 35 which relates to release of security deposit after expiry of
12 months defect liability period following the handing over of the project. It is
submitted that since completion letter was issued on 28.12.2018, there is no
reason why the security deposit and other outstanding dues be not released in
his favour. He has also referred to Clause 76 which provides for in-house
remedies and then reference to arbitration by the CMD of EPIL, if necessary.
Learned senior counsel for the petitioner submits that Clause 76 is not
invocable as there is no dispute or difference between the petitioner and the
EPIL. The grievance of the petitioner is regarding non-payment of admitted
dues which the TU has to release in favour of EPIL in turn to be paid to the
petitioner. Petitioner has invested considerable amounts in execution of the
work, but despite completion of work and satisfactory completion certificate
issued in his favour, the dues have not been paid. Therefore, he has been
compelled to approach this Court for relief.
5.
Mr. Debalay Bhattacharya, learned senior counsel for the
respondents-Tripura University, submits that the dispute essentially relates
between the petitioner and the EPIL. The respondents-Tripura Univeristy is no
way privy to the contract between these two parties. The writ petition is,
therefore, not maintainable for seeking a relief against TU in the circumstances
that there is no subsisting agreement between TU and the petitioner. Petitioner,
being a sub-contractor of the EPIL if at all, is guided by the terms and
conditions of the contract entered between them which provides forum for
adjudication of disputes and differences. Since there is no direct nexus of the
petitioner with the respondent No.1-Tripura University, it has unnecessarily
been impleaded as a party herein. Therefore, this Court may refuse to entertain
the writ petition as many questions of fact and construction of terms and
conditions inter-parties are involved. The appropriate remedy would be in
arbitration proceedings or the competent Civil Court.
6.
We have considered the submission of learned senior counsel for
the petitioner and the respondents-Tripura University and taken note of the
relevant bare facts placed from the records.
Having regard to the nature of the dispute raised by the petitioner
arising out of execution of works under a contract and that too between the
petitioner and respondent No.3-EPIL in which the Tripura University is
nowhere privy, we are of the considered opinion that the writ jurisdiction is not
the right remedy for seeking relief. The dispute between the petitioner and
EPIL, if any, and that if related to TU could only be agitated in an appropriate
forum agreed between the parties or before the competent Civil Court where
issues of fact and construction of terms and conditions inter-parties between the
petitioner and EPIL and between TU and EPIL could be gone into. As such, we
are not inclined to entertain in the writ petition. It is accordingly dismissed.
Petitioner may have liberty to approach the appropriate forum for relief.
7.
Pending application(s), if any, shall stand disposed of.
(ARINDAM LODH), J
Pijush/
signed by MUNNA SAHA
MUNNA SAHA Digitally
Date: 2024.08.16 14:50:02 +05'30'
(APARESH KUMAR SINGH), CJ
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review