M/s Jaypee Projects Limited vs The State of Tripura and 4 others

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Tripura High Court
Date
16 August 2023
Case No.
WP(C) 405/2022
Result
Disposed
Bench
Justice
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

3. 9 of the writ petition. Petitioner's revised claim has not been finally consideredand disposed of as yet. I7] Respondents No.1 to 5 have filed a counter affidavit which in substance refers to Clause 25 of the contract containing the mechanism for settlementof disputes. Learned AdvocateGeneral submits that the claim being raised by the petitioneris amenable to the mechanism provided for settlement of disputes under Clause 25 which the petitioner should have invoked. The quantum of the claim raised by the petitioner has never been admitted. Therefore,the writ petitionis not maintainableon the basis of disputed facts. [8] Rival submissionshave been made on the question of arbitrability of the claim raised by the petitioner. On the one hand, learned senior counsel for the petitioner has taken objection to the stand of the respondents for reference of the dispute for arbitration on the ground that if part of the claim such as at item (ii) and (iii) relatingto escalationbills cannot be bifurcatedfrom the whole claim the matter could not be referred for arbitration in terms of Section 8 of the Arbitration and Conciliation Act, 1996 as amended. It is also submitted that the respondents have all along engaged in correspondenceand discussion on the question of escalationbills raised by the petitionerat item (ii) and (iii) in particular. The claim does not stand denied by the competent au…

28. 02.2022 (Annexure-24 to the writ petition). Learned counsel for petitioner and learned Advocate General both have agreed to confine the claims as are borne out from the letter dated 28.02.2022 submitted by the petitioner in response to the request of respondentNo.S vide letter dated 11.02.2022 which has been extracted hereinabove. Such exercise would necessarily require scrutiny of the records relating to execution of the work by the petitioner and also the terms and conditions of the agreement entered into between the parties. The exercise may entail considerable time. Therefore, this Court without expressing anything on the merits of the claim of the petitioner is inclined to dispose of the writ petition with a direction to the competentauthority under the respondentsto take a decision on the claim of the petitioneras are contained in Annexure-24 dated 28.02.2022 to the writ petition within a reasonable time preferablywithin a period of 12(twelve)weeks from the date of receiptof copy of this order. Needless to say, the competent authority would take a decision and pass areasonedorder on the claim of the petitioner within the aforesaid time.In case, theclaim of the petitioneror part of it is found to be admissible, the respondent authoritieswould ensure that the admissibledues are released in favour of the petitioner within a reasonable period preferably within 8(eight) weeks …

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

Page 1 of10 HIGH COURT OF TRIPURA AGARTALA WP(C) No.405 of 2022 M/sJaypee Projects Limited, a Company, incorporated under the Companies Act, 1956, having its registered office at Trinity 5G, 226/1, A.J.C Bose Road, Kolkata-700020,Representedby its Director, Sri Dilip Kumar Ghorai, son of Late Gobinda Prasad Ghorai, having his office at Trinity 5G, 226/1, A.J.C Bose Road,Kolkata-700020. Petitioner(s) VERSUS 1. The State of Tripura, represented by the Commissioner& Secretary, Public Works Department(Roads &Buildings),Governmentof Tripura, having his office at New Secretariat Complex, Gorkhabasti,Agartala, PO- Kunjaban. 2. PS-New Capital Complex, Sub-Division-Agartala,District-WestTripura. The Commissioner & Secretary, Public Works Department (Roads & Buildings), Govemment of Tripura, having his office at New Secretariat Complex, Gorkhabasti,Agartala, PO- Kunjaban, PS-New Capital Complex. Sub-Division-Agartala, District-WestTripura. 3. The Chief Engineer, Public Works Department (Roads & Buildings), Government of Tripura, having his office at New Secretariat Complex, Gorkhabasti, Agartala, PO- Kunjaban, PS-New Capital Complex, Sub Division-Agartala,District-WestTripura. The Superintending Engineer, Public Works Department (Roads & Buildings), Government of Tripura, having his office at New Secretariat Complex, Gorkhabasti,Agartala, PO- Kunjaban, PS-New Capital Complex, Sub-Division-Agartala,District-WestTripura. The Executive Engineer, Public Works Department (Roads & Buildings), Government of Tripura, having his office at Capital Complex Division, Kunjaban,Agartala,PO- Kunjaban,PS-New Capital Complex, Sub-Division Agartala, District-WestTripura Respondent(s) For Petitioner(s) Mr. Somik Deb, Senior Advocate. Mr. Pranabindu Chakraborty,Advocate. For Respondent(s) Mr. S.S. Dey, Advocate General. Ms. Ayantika Chakraborty,Advocate. 16th August, 2023. Date of hearing & Judgment Whether fit for reporting YES HON'BLE THE CHIEF JUSTICE MR. APARESHKUMAR SINGH JUDGMENT & ORDER (ORAL) Heard Mr. Somik Deb, learned senior counsel appearing for the petitioner. Also heard Mr. S.S. Dey, learned Advocate General appearing for the State respondents. |2] The instant writ petition is primarily for payment of contractualdues totaling Rs.5,02,92,681.10/-along with interest @ 18% from the date it fell due i.e. 31.07.2012. Though the petitioner had prayed for quashing of a letter dated 28.07.2021 (Annexure-9) but it appears that it does not correspond to the pleading of the writ petition and in fact, there is no such letter. Therefore, learned senior counsel for the petitionerdoes not press that prayer. [3] Brief facts, as are necessary for consideration of the issue at hand are that the petitioner was awarded the work under the Agreement No. T/01/CE/EE(CCD)y2007-08 for an amount of Rs.15,16,76,040.00/-, The stipulated date of completion was January, 2009. The said nature of work is reproduced hereunder: "Construction of New capital Complex, Agartala (Project cost Rs. 177.00 crores)/Composite Tripura Legislative Assembly Building and the New Secretariat of New Capital Complex, Agartala/Construction of Tripura Legislative Assembly Building/BalanceWork." The original work was completed on 19.11.2011and the additional work was also completed by 18.04.2015.The Executive Engineer, Public Works Department (Roads & Buildings), Government of Tripura, Capital Complex Division, respondent No.5 issued completion certificates dated 19.11.2011 and 18.04.2015 (Annexure-2) for original work and additional work respectively in favour of the petitioner.Petitionerraised 14(fourteen) numbers of escalation bill on 19.05.2018.The respondent No.5 vide letter dated 07.09.2018 directed the AssistantEngineerto take on record summary of the billappended with the letter for an amount of Rs. 1,85,80,985.52/-as Annexure-A with the observation that the escalation bill has been prepared as per provision of the agreement under Clause-10 up to 19th running account bill. Thereafter, an exchange of correspondencestarted between the petitioner and respondent No.5 and also the petitioner and respondent No. 4, the Superintending Engineer, Public Works Department (Roads & Buildings), Government of Tripura on the subject of revision of the escalation billsubmitted by the petitioner. Annexure- 12 dated 22.03.2021l was issued by respondent No.5 upon petitioner asking him to withdraw his request for arbitrationmade through letter dated 15.02.2021 so that the matter can be placed before the Chief Engineer, PWD(Buildings). It also made an observation that the payment for the final escalation bill will be made to the petitioneron receipt of the approval of the competent authority. The security deposit as claimed by him willalso be paid in due course. Petitionerreplied vide Annexure-13 dated 06.04.2021 that he cannot seek to withdraw his letter dated 15.02.2021since his claims are yet to be settled/finalized.He was again asked by respondent No.5 vide letter dated 18.l10.2021 (Annexure-1S)to re-submit his bills dated 10.03.202 I indicating that the escalation bils were to be processed to respondent No,3 for according approval. As desired by respondent No.3, petitioner was requested to re-submit the quarter wise escalation bill for the total period considering the first quarter from April, 2007 to June, 2007 in place of July, 2007 to September,2007. Petitionerwas served with a reminderletter dated 20.11.2021(Annexure-16) by respondent No.5. Thereafter, vide letter dated 24.11.2021 (Annexure-17),the respondent No.4 also directed the petitioner to attend discussion on letter of the petitioner dated 08.09.2021 on 30.11.2021. Respondent No.4 again asked the petitioner vide letter dated 27.01.2022 (Annexure-22)to attend the meeting and discuss the issue relating to the letters dated 22.12.2021 and 22.01.2022 on the claim for outstandingdues. The matter remained unresolved. Finally,by Annexure-23 dated 11.02.2022,the petitioner was informed by respondentNo.5 in the followingmanner: "To The Director, JAYPEE PROJECTS LTD 11, Clive Row (Dr. Rajendra Prasad Sarani) Kolkata-700001 Mob-6290749647 Email:info@jaypee.co.in Subject: "Construction of New Capital Complex at Agartala composite Tripura LegislativeAssembly Buildingsand the New Secretariatof Capital Complex, Agartala/Construction of Tripura Legislative Assembly Buildings/BalanceWork"-regarding. Agreement No. T/01/CE/EE/CCD/07-08 Date of completion:-21/07/2012 Project Cost: Rs.177.00 Crore Ref:- Your letter (i)No.F.C-024/DKG/061/21-22dated 22-12-2021 (ii) No.F.C-024/DKG/21-22/057dated 08.09.2021 Sir, Please refer to your letter No. referred under SI. No.(ii) wherein you have requested this office to resolve your "revised schedule of claims/disputes"under the above agreement within 15(fifteen) days and stated that if no positive action was taken from this end within the given time, you would have no other option but to take legal action as per law. In this connection, a meeting was held in the office of the SuperintendingEngineer, Project Unit, PWD(Buildings)when the issue of your schedule of claims was discussed in detail in presence of your representativeSmt. SomdattaDas. In this regard, it is to inform you that the revised schedule of claims/disputesas raised by you in your above letter is not correct as up-to date payment already made against your final bill in March 2021 and provisionalpayment of Rs.l.89 crore made as per your bills received till March, 202 1. Final Escalationbill as submitted by you is not based on scope & provision of the Agreement clause, hence could not be processed to Authority for approval. Escalationbills so far submitted in differenttimes were not based on provisionsof scope of Agreement clause though out of total final projected Escalation bill submitted by you of Rs.2.46 crore, an amount of Rs.1.89 crore already paid to you provisionally,which is above 77% of total bill. Your Final Escalation bills submitted under reference under Sl. No.1 is found not prepared in accordance with the escalation clause of the agreement and it is to be re-submitted fresh for taking further course of action from this end. From the above break-up of payment made, it is concluded that you have no outstanding dues to claim to us. However, you are requested to please submit the Final Escalation bills in correct shape this office for obtainingapproval of the same from the competentauthorityat an early. After getting approval of Escalation bill, your all outstanding payment will be made on availabilityof fund as soon as possible. Hence your request to consider the appointmentof arbitratoras per provision of clause 25 of the agreement for settlement of disputes/claims and taking legal action against the department as per law is not at all justifiedand acceded to. Yours faithfully Sd/ (Er. Manik Debnath) Executive Engineer, Capital Complex Division, PWD (R&B) Kunjaban Extension,Agartala. Copy to: 1) The Chief Engineer, PWD(Buildings) New Secretariat Complex, Agartala for kind informationplease. 2) The Superintending Engineer, Project unit PWD(Buildings) New SecretariatComplex, Agartala for kind informationplease. Executive Engineer Capital Complex Division, PWD(R&B) Kunjaban Extension, Agartala." Petitioner has thereafter submitted his reply which is dated 28.02.2022(Annexure-24)addressedto the respondentNo.5. |6] Learned senior counsel for the petitioner submits that the outstandingclaim of the petitioner is contained in a tabular chart at Annexure 24 and it also corresponds to the request made by the petitioner at paragraph 3.9 of the writ petition. Petitioner's revised claim has not been finally consideredand disposed of as yet. I7] Respondents No.1 to 5 have filed a counter affidavit which in substance refers to Clause 25 of the contract containing the mechanism for settlementof disputes. Learned AdvocateGeneral submits that the claim being raised by the petitioneris amenable to the mechanism provided for settlement of disputes under Clause 25 which the petitioner should have invoked. The quantum of the claim raised by the petitioner has never been admitted. Therefore,the writ petitionis not maintainableon the basis of disputed facts. [8] Rival submissionshave been made on the question of arbitrability of the claim raised by the petitioner. On the one hand, learned senior counsel for the petitioner has taken objection to the stand of the respondents for reference of the dispute for arbitration on the ground that if part of the claim such as at item (ii) and (iii) relatingto escalationbills cannot be bifurcatedfrom the whole claim the matter could not be referred for arbitration in terms of Section 8 of the Arbitration and Conciliation Act, 1996 as amended. It is also submitted that the respondents have all along engaged in correspondenceand discussion on the question of escalationbills raised by the petitionerat item (ii) and (iii) in particular. The claim does not stand denied by the competent authority even till date. As such, petitioner has rightfully invoked the writ jurisdiction for appropriate directions/mandamus upon the respondents to considerand decide the claim of the petitionerin accordancewith law. It is also submitted that the issuance of completioncertificateboth for original work and additional work is in itself a proof of due execution of the work by the petitioner.Whether the outstandingclaims relating to escalation bills as per the terms and conditions of the agreement are admissible or not and whether the remaining claims relating to return of security deposit and interest are admissible or not has to be decided by the competent authority of the Department.In case, the part of the claim or whole of it is allowed or some part of it is disputed then only the question of invoking an alternative dispute resolution mechanism or the forum of the competent Civil Court for adjudicationon the disputed amount can be raised. [91 Therefore,a suitable directionmay be passed upon the respondent authorities to consider and take a decision on the claim of the petitioner in accordancewith law within a stipulatedtime period as the petitionercontinues to suffer on account of non-paymentof the outstandingdues being a running business concern. |10] Learned Advocate General has at the outset taken objection to the maintainability of the writ petition in view of the availability of adispute redressal mechanism under Clause 25 of the agreement. He also submits that none of the dues are admitted by the respondents. Noneof the correspondences placed on record do show a final admission of the claim of the petitionerby the competentauthority. If the claims are not finally resolved, no writ of mandamus or appropriatedirection can be issued for pavment thereof as the petitioner has prayed for in the writ petition. |11] However, learned Advocate General does not dispute that after the series of correspondencesbetween the petitionerand the respondent authorities and the discussionmade on the claims raised by the petitioner,no final decision has been taken by the competent authority either rejecting the claim or admitting part or whole of it. Learned Advocate General is, therefore, not averse to the propositionthat the competent authority can be directed to take a decision on the outstandingclaim of the petitioneras at Annexure-24. |12] I have considered the submissions of learned counsel for the parties and taken note of the relevant pleadings and also the documents placed from the record referred to hereinabove. The chronology of dates and correspondencesreferred to in the narrative hereinabovecreates the impression that tilldate no decision on the claim of the petitioner has been taken by the competent authority under the respondents. It is also evident that his claims have not been outrightly rejected. The series of correspondences up to Annexure-23 dated 11.02.2022 indicates that the respondents have once again requested the petitionerto submit the final escalation bill in correct shape for obtaining approvalfrom the competent authority at an early date. It also indicates that after getting approval of the escalation bill, his outstanding payment will be made on availabilityof fund as soon as possible. In fact, the letter dated 11.02.2022 also indicates that the request for arbitration under Clause 25 of the agreement for settlement of disputes/claimsand taking legal action against the department is not at all justified and acceded. In such circumstances, the obvious inference is that the decisions on the outstanding claims of the petitioner are yet to be taken. Whether the dues are admissible or not cannot be determined in the present writ petition since they relate to admissibility of the claims as per the terms and conditions agreed between the parties as per the measurements and the records relating to the execution of the work maintained by the respondent authorities. |13] Court is of the In the aforesaid circumstances, therefore, this considered opinion that the competent authority under the respondents take a decision on the claims of the petitioner, as referable in should letter dated the 28.02.2022 (Annexure-24 to the writ petition). Learned counsel for petitioner and learned Advocate General both have agreed to confine the claims as are borne out from the letter dated 28.02.2022 submitted by the petitioner in response to the request of respondentNo.S vide letter dated 11.02.2022 which has been extracted hereinabove. Such exercise would necessarily require scrutiny of the records relating to execution of the work by the petitioner and also the terms and conditions of the agreement entered into between the parties. The exercise may entail considerable time. Therefore, this Court without expressing anything on the merits of the claim of the petitioner is inclined to dispose of the writ petition with a direction to the competentauthority under the respondentsto take a decision on the claim of the petitioneras are contained in Annexure-24 dated 28.02.2022 to the writ petition within a reasonable time preferablywithin a period of 12(twelve)weeks from the date of receiptof copy of this order. Needless to say, the competent authority would take a decision and pass areasonedorder on the claim of the petitioner within the aforesaid time.In case, theclaim of the petitioneror part of it is found to be admissible, the respondent authoritieswould ensure that the admissibledues are released in favour of the petitioner within a reasonable period preferably within 8(eight) weeks thereafter.In case the petitioneris aggrievedby the decision taken by the respondent authorities,he may have hisremedy in an appropriate proceeding before the appropriate forum in accordance with law. The writ petition stands disposed of in the aforesaidmanner. Pending application(s),if any, also stands disposed of. Apanesh eumae Sigh (APARESHKUMAR SINGH), CJ Rudradeep RUDRADEEP BANERJEE BANERJEE Date: 2023.08.21 16:27:08 +05'30'

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All Tripura HC judgments →