M/s Jaypee Projects Limited vs The State of Tripura and 4 Ors.

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Tripura High Court
Date
21 December 2022
Case No.
WP(C) 872/2022
Result
Dismissed
Bench
T. Amarnath Goud
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

36. 3. Third, Section 34(3) reflects the principle of unbreakability. Dr Peter Binder in International Commercial Arbitration and Conciliation in UNCITRAL Model Law Jurisdictions, 2nd Edn., observed: “An application for setting aside an award can only be made during the three months following the date on which the party making the application has received the award. Only if a party has made a request for correction or interpretation of the award under Article 33 does the time-limit of three months begin after the tribunal has disposed of the request. This exception from the three-month time-limit was subject to criticism in the working group due to fears that it could be used as a delaying tactics. However, although “an unbreakable time-limit for applications for setting aside” was sought as being desirable for the sake of “certainty and expediency” the prevailing view was that the words ought to be retained “since they presented the reasonable consequence of Article 33”. [21] In view of above observation and on the observation made by the Apex Court, this Court is of the view that the writ petitioner at one point of time claimed for Rs.27,46,96,122.55/- and further in the additional affidavit he has claimed for Rs.16,87,99,319.20/-. When the learned senior counsel is making his submission and different demand at different point of time, it is not for this Court to decide these dis…

Filed under

Constitution of India Article 226, Constitution of India

The sections, explained

The law this judgment cites

Opens the section on Law Maker (lawmaker.in), our sister site for law students.

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

HIGH COURT OF TRIPURA A_G_A_R_T_A_L_A WP(C) No. 872 of 2022 1. M/s Jaypee Projects Limited, a Company, incorporated under the Companies Act, 1956, having its registered office at Trinity 5G, 226/1, A.J.C. Bose Road, Kolkata-700020, represented by its Director, Sri Dilip Kumar Ghorai, son of late Gobinda Prasad Ghorai, having his office at Trinity 5G, 226/1, A. J. C. Bose Road, Kolkata-700020. …..Petitioner -V E R S U S- 1. The State of Tripura, represented by the Commissioner & Secretary, Public Works Department (Roads & Buildings), Government of Tripura, having his office at New Secretariat Complex, Gorkhabasti, Agartala, P.O. Kunjaban, P.S. New Capital Complex, Sub-DivisionAgartala, District: West Tripura. 2. The Commissioner & Secretary, Public Works Department (Roads & Buildings), Government of Tripura, having his office at New Secretariat Complex, Gorkhabasti, Agartala, P.O. Kunjaban, P.S. New Capital Complex, Sub-Division-Agartala, District: West Tripura. 3. The Chief Engineer, Public Works Department (Roads & Buildings), Government of Tripura, having his office at New Secretariat Complex, Gorkhabasti, Agartala, P.O. Kunjaban, P.S. New Capital Complex, Sub-Division-Agartala, District: West Tripura. 4. The Superintending Engineer, Public Works Department (Roads & Buildings), Government of Tripura, having his office at New Secretariat Complex, Gorkhabasti, Agartala, P.O. Kunjaban, P.S. New Capital Complex, Sub-Division-Agartala, District: West Tripura. 5. The Executive Engineer, Public Works Department (Roads & Buildings), Government of Tripura, having his office at Agartala, Division No. III, P.O. Kunjaban, P.S. New Capital Complex, SubDivision: Agartala, District: West Tripura. ….. Respondents. B_E_F_O_R_E HON’BLE THE CHIEF JUSTICE (ACTING) For Petitioner(s) : For Respondent(s) : Date of hearing Date of delivery of judgment and order Whether fit for reporting : Mr. Somik Deb, Sr. Advocate. Mr. Abir Baran, Advocate. Mr. S. S. Dey, Advocate General. Ms. A. Chakraborty, Advocate. 16.12.2022. : : 21.12.2022 NO JUDGMENT & ORDER Heard Mr. Somik Deb, learned senior counsel assisted by Mr. Abir Baran, learned counsel appearing for the petitioner. Also heard Mr. S. S. Dey, learned Advocate General assisted by Ms. A. Chakraborty, learned counsel appearing for the respondents. [2] This present petition has been filed under Article-226 of the Constitution of India for enforcement of the Constitutional rights of the petitioner granted under Articles-14, 19, 21 and 300A of the Constitution of India also for transmitting the records, relevant to the subject matter of this writ petition for rendering substantive and conscionable justice to the petitioner. Further, to direct the respondents to forthwith pay off the outstanding dues to the petitioner, amounting to Rs.27,46,96,122.55/- along with interest @18% from the date it fell due. [3] The brief fact which falls for considering in this writ petition is that for execution of the civil work, namely “Construction of the Composite Tripura Legislative Assembly Building and the new Secretariat of New Capital Complex, Agartala, Tripura” the Executive Engineer, Capital Complex Division PWD (R&B) issued a tender notice, pursuant whereto, the petitioner was selected for execution of the said work and accordingly, the work order was issued in favour of the petitioner. [4] After the successful completion of the work, the project was duly handed over to the respondents and accordingly, by letters, the Executive Engineer, Capital Complex Division, PWD (R&B) issued completion certificates for original work and extra work respectively, in favour of the petitioner and no dispute arose as to the said work, either during or after execution of the same. Thereafter, the Executive Engineer, Capital Complex Division PWD (R&B) issued a letter to the Assistant Engineer, Capital Complex Sub-Division-I PWD (R&B) as well forwarding a copy of the petitioner, thereby stating that the petitioner claimed an Escalation Bill, under up to 19th RA Bill, the amount of Escalation Bill has been scrutinized/modified by the respondents to Rs.1,85,80,985.52/-. [5] Thereafter, the Director of the issued a letter to the Executive Engineer, PWD (R&B), Government of Tripura, thereby requesting to release the balance Final Bill, including the Escalation Bill, amounting to Rs.1,76,40,892.1/-, within a period of one month, to avoid the 18% interest, to be counted with effect from 31.07.2012. Thereafter, the Director of the petitioner issue a reminder letter, to the Executive Engineer, PWD (R&B), Government of Tripura, thereby requesting to release the balance final bill, including the escalation bill, amounting to Rs.1,76,40,892.1/- along with 18% interest claimed on to the above amount. [6] Thereafter, the Director of the petitioner further issued another reminder letter to the Executive Engineer, Capital Complex Division, PWD (R&B) Government of Tripura, thereby requesting to release the balance final bill, including the escalation bill, amounting to Rs.1,76,40,892.1/- along with 18% interest claimed on to the above amount. Furthermore, the Director of the petitioner issued another reminder letter to the Executive Engineer, Capital Complex Division, PWD (R&B), Government of Tripura, thereby requesting to release the balance final bill, including the escalation bill, amounting to Rs.1,76,40,892.1/- along with 18% interest claimed on to the above amount. [7] Mr. Somik Deb, learned senior counsel assisted by Mr. Abir Baran, learned counsel appearing for the petitioner has submitted that Clause31.1 of the agreement inter alia provided for the final completion certificate which provided that on successful completion of the entire works covered by the contractor to the full satisfaction of the engineer, the contractor shall ensure that the works have been completed to the satisfaction of the engineer. Thereafter, upon the satisfactory fulfillment of the works by the contractor as stated above, the contractor would be entitled to apply to the engineer for a final completion certificate in respect of the entire work. [8] He has submitted that Clause-34 of the Agreement inter alia provided for the defect liability period or period of maintenance which provided that the contractor should maintain the whole of permanent works in a thoroughly sound, substantial, efficient and perfect condition during the defects liability period of 365 days after the virtual date of completion of the whole of the works as was certified by the engineer, which should be remedied at his own cost and that also to the satisfaction of the engineer which might have become apparent, prior to or during the maintenance or defect liability period, which raised out of the materials or workmanship or default of the contractor. [9] He has stressed upon Clause-47 of the Agreement inter alia provided that if the prices of material or wages of labour required for the execution of the work increase, the contractor shall be compensated for such increase and as per the provisions, the amount of the contract shall accordingly be varied, subject to the condition that such compensation for escalation in prices shall be available only for the work done during the stipulated period of the contract including such period, for which the contract is validated, which was extended under the provisions of Clause-28 of the contract without any action under Clause-49. [11] According to Clause-37.2 of the Agreement all the tendered rates shall be inclusive of all taxes and levies, payable under respective statutes. It was further noted that pursuant to the constitution (46th Amendment) Act, 1982 if any further tax of levy was imposed by any statute, the last stipulated date for receipt of the tender including extensions, if any, and that the contractor thereupon necessarily and properly pays such taxes, the contractor would be reimbursed or deducted from the amount so paid and further provided that such payments, if any, was not in the opinion of the engineer attributable to delay in execution of the work within the control of the contractor. [12] It would evidently be cleared that the petitioner was diligent in executing the work and that the petitioner was successful in completing the work in due time. The respondents have admitted that the petitioner has executed the work to the fullest satisfaction to the said respondent-authority and hence, the deferment of payment, solely founded on non-grant of fund by the respondents. It is an established principle in contractual parlance that the employer owes the responsibility to pay off the amounts, due and payable to the contractor, within a reasonable time and prolonged non-payment is unsustainable. [13] He has further submitted that the respondents have not disputed the claim of the petitioner, urging for payment of the outstanding dues. On the other hand, the respondents have sought to contend that eh payment f the outstanding dues, to the petitioner would be made, as and when the fund therefore is sanctioned and paid by the respondent-State. He has further contended that even though the agreement in question provides for resolution of any dispute, by way of arbitration, but since, the respondents themselves have admitted their liability, on to the request of the petitioner for the appointment of arbitrator, it remains beyond the cavil of any dispute that the remedy that is available to the petitioner, is either way of institution of a money suit, or by way of presentation of a writ petition, under Article-226 of the Constitution of India. [14] It is an established principle in commercial transaction, that prompt payment is the rule, and indefinite non-payment is wholly misplaced. In view of the above, it is apparently very clear that by not making payment to the petitioner for such prolonged time, the respondents have invaded the rights of the petitioner, guaranteed under Article-14, 19 (1) (g), 21 and 300A of the Constitution of India and the said violates the rights of the petitioner, merit to be immediately remedied, by directing the respondents to pay off the outstanding of Rs.27,46,96,122.55/- along with @18% from the date it fell due. [15] Per contra, Mr. S. S. Dey, learned Advocate General assisted by Ms. A. Chakraborty, learned counsel appearing for the respondents has submitted on the very point of maintainability of the writ petition. He has submitted that the present petition is full of pleadings raising disputed question of facts concerning espoused civil rights of the petitioner, none of which have admitted by the respondents. The petitioners had executed some civil works and is claiming release of balance payment, the quantum of which, as claimed by the petitioner has never been admitted and hence, the espoused right of the petitioner, if any, is under rebuttal. Hence, no writ petition is maintainable to ascertain the civil rights and liabilities of parties that too on the basis of disputed facts. [16] He has further averred that the petitioner had submitted bill on 26.04.2022 claiming payment at escalated rates. The claim of the petitioner has since been answered vide letter No.F.25(250)/EE-III/PWD(R&B)/4633-36 dated 18.10.2022 inter alia informing the petitioner that the said price escalation bill is not maintainable in view of Cluse-47 of the contract between the parties, thus, the petitioner was requested to resubmit a fresh bill as per Clause-47 of the Contract. For the purpose of reference, the relevant portion may be reproduced herein below: “Not applicable for works for which estimated cost put to tender is less than Rs.1.00 crore stipulated time form completion is less than or equal to twenty four months.”The stipulated time for completion of the work in question being twenty four months, the aforesaid bar applies.” [17] The contract between the parties provides for alternative dispute redressal mechanism in Clause-24, 25 and 26 which the petitioner is free to exhaust. Although the writ petitioner vide his letter with reference No.C34/NSRCC/JPL/DKG/2021-22/049 dated 27.07.2021 has sought for settlement of dispute through alternative dispute redressal mechanism and accordingly the said prayer for appointment of an arbitrator was under consideration, meanwhile the contractor, the writ petitioner had again filed an escalation bill which in violation of Clause-47 of the agreement. Hence, in the factum of existence of the aforesaid alternative dispute redressal mechanism in the contract itself, the present writ petition with disputed question of facts is not maintainable in the eye of law. [18] Mr. Dey, learned G.A. in regard to the payment to the petitioner has drawn attention of this Court to Annexure-8. For the purpose of reference, the letter No. F.25-250/EE-III/12,674-78 may be reproduced herein below: “To, The Jypee Projects Limited, 11 Civil Row[Dr.Rajendra Prasad Sarani] Kolkata-700001 Sub: Request for making different payments. Reference:- Your letter dated -09January, 2019 8th January, 2019 earlier different reference in this regard. Sir, With reference to subject cited above, I am to state that this office has examined your request for payment of Rs.1,21,63,33/- outstanding against GST as claimed by you. In this regard, I am to state that as per clause no.37.2 of the agreement which clarifies conditions for reimbursement/rebate of levy/taxes if levied after the receipt of tenders which inter alia says that such taxes/levies that contractor shall be reimbursed/deducted that amount so paid, provided such payment, if any, is not, in the option of the engineer (whose decision shall be final and binding on the contractor) attributable to the delay in execution of work within the control of the contractor. As GST came into force w.e.f. 01/07/2017 after the stipulated date of completion of said agreement which is 10.01.2013 and time extension related to the said work is processed by this office to the competent authority and final decision is yet to be communicated from their end, that will clearly determine how much proportionate delay of execution of the said work attributable to Agency and how much to the department. As this decision is yet to be taken by competent authority and without this, this office is not in position to ascertain your above said claim for payment of Rs.1,21,63,338/- reimbursement against GST. It is further stated that after the finalization of time extension by competent authority, the detailed matter will be processed to the higher authority for decision/orders and appropriate action will be taken by this office accordingly, including your demand for reimbursement of VAT (Tripura WCT) as per clause No.37.2 of the agreement. In response to your request for release of amount of Rs.20,00,000/- kept in held on account of interest of mobilization advance has already been refunded to you and in addition to this, we have also released amount of Rs.22,83,477/-/ kept in held on account of VAT deduction in the regime of GST due to non availability of specific instructions in this regard. Now you liable to pay applicable GST from end for the payments your have received during the period of 01.07.2017 to 30.09.2018 (in regime of GST when no deduction of VAT is applicable and no deduction of GST at source was notified.) In response to your request for payment of balance amount towards the final bill of Rs.284.82 lakhs, I am to state that against the bill value of Rs4288.24 lakhs (up to 24th RA), we have already paid an amount of Rs.4245.20 lakhs ( as on 28.02.2019) and final bill is yet to received from respective sub division. The remaining amount will be paid subject to availability of funds and finalization of time extension/final deviation and your demand for 18% simple interest on pending bill amount is fully unwarranted because no such clause exists in the agreement of the said work. Yours faithfully, (Er. Priyabrata Paul) Executive Engineer, Agartala Division No.III PWD (R&B)” [19] Mr. Dey, learned A.G. in support of his case has placed his reliance upon a decision of the Hon‟ble Apex Court in Bhaven Construction v. Esecutive Engineer, Sardar Sarovar Narmada Nigam Limited and Another, reported in (2022) 1 SCC 75, wherein, the Court held thus: “18. In any case, the hierarchy in our legal framework mandates that a legislative enactment cannot curtail a Constitutional right. In Nivedita Sharma v. Cellular Operators Association of India, (2011) 14 SCC 337, this Court referred to several judgments and held: “11. We have considered the respective arguments/submissions. There cannot be any dispute that the power of the High Courts to issue directions, orders or writs including writs in the nature of habeas corpus, certiorari, mandamus, quo warranto and prohibition under Article 226 of the Constitution is a basic feature of the Constitution and cannot be curtailed by parliamentary legislation - L. Chandra Kumar v. Union of India, (1997) 3 SCC 261. However, it is one thing to say that in exercise of the power vested in it under Article 226 of the Constitution, the High Court can entertain a writ petition against any order passed by or action taken by the State and/or its agency/ instrumentality or any public authority or order passed by a quasi- judicial body/authority, and it is an altogether different thing to say that each and every petition filed under Article 226 of the Constitution must be entertained by the High Court as a matter of course ignoring the fact that the aggrieved person has an effective alternative remedy. Rather, it is settled law that when a statutory forum is created by law for redressal of grievances, a writ petition should not be entertained ignoring the statutory dispensation. [Emphasis supplied] It is therefore, prudent for a Judge to not exercise discretion to allow judicial interference beyond the procedure established under the enactment. This power needs to be exercised in exceptional rarity, wherein one party is left remediless under the statute or a clear „bad faith‟ shown by one of the parties. This high standard set by this Court is in terms of the legislative intention to make the arbitration fair and efficient.” [20] Viewed from a different perspective, the arbitral process is strictly conditioned upon time limitation and modeled on the „principle of unbreakability‟. This Court in P. Radha Bai v. P. Ashok Kumar, (2019) 13 SCC 445, observed: 36.3. Third, Section 34(3) reflects the principle of unbreakability. Dr Peter Binder in International Commercial Arbitration and Conciliation in UNCITRAL Model Law Jurisdictions, 2nd Edn., observed: “An application for setting aside an award can only be made during the three months following the date on which the party making the application has received the award. Only if a party has made a request for correction or interpretation of the award under Article 33 does the time-limit of three months begin after the tribunal has disposed of the request. This exception from the three-month time-limit was subject to criticism in the working group due to fears that it could be used as a delaying tactics. However, although “an unbreakable time-limit for applications for setting aside” was sought as being desirable for the sake of “certainty and expediency” the prevailing view was that the words ought to be retained “since they presented the reasonable consequence of Article 33”. [21] In view of above observation and on the observation made by the Apex Court, this Court is of the view that the writ petitioner at one point of time claimed for Rs.27,46,96,122.55/- and further in the additional affidavit he has claimed for Rs.16,87,99,319.20/-. When the learned senior counsel is making his submission and different demand at different point of time, it is not for this Court to decide these disputed claims. [22] It is also seen from Annexure-8 that the respondents have paid certain amounts and the remaining amount will be paid subject to availability of funds and finalization of time extensions/final deviation. Learned senior counsel appearing for the petitioner has submitted that no amount have been paid and with regard to the other claims in respect to the percentage i.e. material component as 70% and labour component as 30% and it has been decided that material component would be 75% and the labour component would be 25%. All these disputed questions of fact are involved in this writ petition concerning espoused civil rights of the petitioner, none of which are admitted by the respondents. [23] In any case, the hierarchy in our legal framework mandates that a legislative enactment cannot curtail a Constitutional right. There cannot be any dispute that the power of the High Courts to issue directions, orders or writs including writs in the nature of habeas corpus, certiorari, mandamus, quo warranto and prohibition under Article-226 of the Constitution of India is a basic feature of the Constitution and cannot be curtailed by parliamentary legislation. It is settled law that when a statutory forum is created by law for redressal of grievances, a writ petition should not be entertained ignoring the statutory dispensation. Although, the petitioner vide his letter dated 27.07.2021 has sought for settlement of the dispute through alternative dispute redressal mechanism and the said prayer is under consideration. [24] In view of above analysis, this Court is of the considered opinion that no writ petition is maintainable to ascertain the civil rights and liabilities of parties that too on the basis of disputed facts. Thus, it is not for this Court to decide the matter when alternative mechanism are available to the petitioner and in the factum of existence of the aforesaid alternative dispute redressal mechanism in the contract itself, the present writ petition with disputed question of facts, is not maintainable. Accordingly, the same stands dismissed. As a sequel, miscellaneous applications pending, if any, shall stand closed. CHIEF JUSTICE (ACTING) A.Ghosh

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All Tripura HC judgments →