M/s C & C Constructions Ltd. vs IRCON International Ltd.

Court
Supreme Court of India
Date
31 January 2025
Case No.
Civil Appeal No. 6657 of 2023
Result
Dismissed
Bench
Abhay S. Oka, Ujjal Bhuyan
Citation
[2025] 1 S.C.R. 1413 : 2025 INSC 138
Acts & Sections
Arbitration and Conciliation Act, 1996
Supreme Court Reports [2025] 1 S.C.R. 1413 : 2025 INSC 138
Issue for consideration
Matter pertains to the order passed by the Division Bench of the High Court, dismissing an appeal u/s.37 of the Arbitration and Conciliation Act, 1996, holding that the requirement of clause 49.5 was never waived by the respondent, that clause 49.5 was a valid clause, upheld the arbitral award.
Headnote

Arbitration and Conciliation Act, 1996 – s.37 – Arbitration award – Scope of interference in an appeal u/s.37 – Dispute between the appellant and the respondent over construction of Road Over Bridges – Case of the appellant that delay in construction work for the reasons attributable to the respondent, resulted in additional financial burdens – Appellant sought extension of time, and the same was extended by the respondent – Appellant then sought damages on account of delay on part of the respondent, however, the claims rejected – Thereafter, undertakings by the appellant that it would not claim anything extra other than escalation for the work executed – Two years later, the appellant invoked arbitration clause on basis of the claims raised – Arbitral tribunal rejected the claims based on clause 49.5 of GCC which disentitles the appellant from raising any claim for damages or compensation for failure or delay caused by the respondent in fulfilling its obligations under the contract – Petition u/s.34 by the appellant – Dismissed by the Single Judge of the High Court holding that the clause 49.5 would bar the appellant’s claim – Appeal before the Division Bench u/s.37 also dismissed – Correctness:

Held: Scope of interference in an appeal u/s.37, in examining an order, setting aside or refusing to set aside an award, is limited and restricted – On facts, the appellant acted upon clause 49.5 and sought an extension of time on three occasions – Solemn undertaking by the appellant not to make any claim other than escalation in respect of delays in the completion of work, however, claim made contrary to the undertakings – By the undertakings, the appellant agreed not to make a claim contrary to what is provided in clause 49.5, thus, by conduct, the appellant was estopped from challenging the validity of clause 49.5 – Furthermore, Clause 49.4 would apply when the delay is not due to the respondent – In the said matter, the delay was on the part of the respondent, hence, clause

Read the full headnote (1 more paragraph)

49.5 would apply and not clause 49.4 – Also it cannot be inferred that clause 49.5 was waived by the respondent – Respondent stated that the claim for financial burden would have to be dealt with together with the proposal for an extension of time, and the said claim cannot be processed separately – Thus, on two occasions, on specific requests made by the appellant under clause 49 of the GCC, the extension of time was granted by the respondent – Except sub-clause 5 of clause 49, no other sub-clause which provides for grant of extension when the delay was attributable to the respondent – Thus, the order passed by the Division Bench upheld – General Conditions of Contract – Clause 49.5. [Paras 19, 23, 26-29]

Keywords: Arbitration award · Arbitral award · Arbitration clause · Scope of interference in appeal u/s.37 · Construction of Road Over Bridges · Delay in construction work · Additional financial burdens · Extension of time · Damages · Escalation for the work executed · Claim for damages or compensation · Solemn undertaking · Estopped from challenging validity of clause 49.5 · Delay · Financial burden · General Conditions of Contract Clause 49.5

As published in the Supreme Court Reports, Supreme Court of India. Headnotes prepared by: Nidhi Jain (2023) 9 SCC 85. Text from the Indian Supreme Court Judgments open data set (Dattam Labs), CC BY 4.0.

Full Judgment Text

Judgment Abhay S. Oka, J. FACTUAL ASPECTS 1. This appeal arises out of the impugned judgment and order of the Division Bench of the High Court of Delhi dated 1st March, 2021, which is passed in an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (for short, ‘the Arbitration Act’). 2. We refer to a few factual aspects of the case. An agreement dated 28th June, 2012 was entered into between the appellant and the respondent for constructing five Road Over Bridges (for short, ‘ROBs’) and their approaches at different locations in the State of Rajasthan. The schedule of com
Full text available to subscribers
Subscribe to access complete judgment text, daily digests, and AI-powered legal research tools. For informational and research purposes only.
View Subscription Plans →
Annual plans from ₹1,599 + GST.

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

All SC judgments →