Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

12. In view of the discussions made hereinabove, the order dated 10.11.2014 issued by the appellate authority is hereby set aside and the matter is remitted to the appellate authority to arrive at a fresh decision and to pass a reasoned order after considering all the facts and circumstances arising out of the execution of the works as narrated above.

13. With the aforesaid observation and direction, the instant writ petition stands disposed of. (ARINDAM LODH, J) (SANJAY KAROL, CJ)

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

HIGH COURT OF TRIPURA AGARTALA WP(C) NO.518 OF 2014 Sri Kalyan Debnath, S/O Late Upendra Chandra Debnath, Resident of Kamalpur, P.S. Kamalpur, District-Dhalai, Tripura. ----Petitioner(s) Versus 1. The State of Tripura, represented by the Secretary to the Government of Tripura, Public Works Department, Civil Secretariat, New Capital Complex, P.O. Kunjaban, Agartala, West Tripura. 2. The Commissioner & Secretary to the Government of Tripura, Public Works Department, P.O. Kunjaban, Agartala, West Tripura. 3. The Chief Engineer, Public Works Department, Civil Secretariat, New Capital Complex, P.O. Kunjaban, Agartala, West Tripura. 4. The Engineer-in-Chief, Public Works Department(R&B), Civil Secretariat, New Capital Complex, P.O. Kunjaban, Agartala, West Tripura. ----Respondent(s) For Petitioner(s) : Mr. A. Gan Chowdhury, Advocate For Respondent(s) : Mr. D. Sarma, Addl. G.A. Date of hearing & delivery of Judgment & Order : 09.01.2019 Whether fit for reporting No : HON’BLE THE CHIEF JUSTICE MR. SANJAY KAROL HON’BLE MR. JUSTICE ARINDAM LODH J U D G M E N T & O R D E R (O R A L) (Lodh, J) Heard Mr. A. Gan Chowdhury, learned counsel appearing for the petitioner as well as Mr. D. Sarma, learned Addl. G.A. appearing for the respondents. 2. The facts in the writ petition, in a nutshell, are that while the petitioner was serving as Junior Engineer under the respondents he was charged under Rule 14 of the CCS(CC&A) Rules, 1965 vide Memo.No.F.6(58)-PWD(E)/70(III)-(S-II) dated 22.09.1994 and the charges are as under: “ARTICLE NO.-I That the said Sri Kalyan Debnath while functioning as Junior Engineer during the period 21.10.93 to 8.12.93 was entrusted to look after the routine nature of works of SDO(PWD), Kamalpur Sub-Division during the absence of Sri Animesh Das, S.D.O.(PWD) Kamalpur during puja holidays from 22.10.93 to 29.10.93 disobeyed the instruction of higher officials, thus liable for action under C.C.S.(C.C.A) Rules. ARTICLE NO.-II That during the aforesaid period and while functioning in the aforesaid office, Sri Kalyan Debnath awarded 4(four) nos. of works to different contractor without having any verbal or written concurrence from his higher authorities. For such act the Department is to be discharged the liabilities to the tune of Rs.1,91,800/-(Rupees one lac ninety-one thousand) only. Awarding of works without observing codal formalities is beyond the competency of the Junior Engineer Sri Kalyan Debnath. Thus Sri Debnath is liable to be charged under C.C.S.(C.C.A) Rules.” 3. Mr. Gan Chowdhury, learned counsel for the petitioner submits that on the eve of Durgapuja while all the higher officials and engineers went on leave, the petitioner was entrusted with the duties to carry out all the routine nature of works. Prior to six months of Durgapuja(1993), the department had prepared estimates for repairing 8(eight) numbers of dilapidated wooden bridges of the Sub-Division and those were required for urgent repairing for public use, standing over various cannels and rivers connecting the roads. The Superintending Engineer, 1 st Circle, Kumarghat assured the local bodies that the Department would keep the semi permanent timber bridges during Durgapuja holidays to avoid any kind of accident and such instruction was given to the office but the department could not repair the same. 4. It has been further submitted that the petitioner was given the charge of SDO routine duty during Puja holidays(1993) and due to absence of the higher officials of the department, the petitioner was instructed by a radio message by the Executive Engineer, PWD, Ambassa Division to perform the repair works of the SPT bridges by engaging departmental workers(carpenters and helpers) & materials as the localities and autonomous bodies put severe pressure on the department to repair the bridges on emergent basis to facilitate the public to use the same which were essential road connectivity for public convenience and to protect the people from any accident to enjoy the largest festival of the State. To comply with the order, the petitioner faced difficulties as no departmental carpenter was on duty and no dismantled timbers/materials were lying with the store and no timber was endorsed. The petitioner sent a crash message on 21.10.1993 to the Executive Engineer, Ambassa Division with a copy to the Superintending Engineer, 1st Circle, Kumarghat and the Chief Engineer for further instruction as the local bodies and public put severe pressure on the petitioner to repair minimum four numbers of timber bridges which were connecting the main roads and lying in such a condition that any moment accident could be happened. More so, the then Hon’ble Speaker of the Tripura Legislative Assembly called the petitioner in his residence and asked him to do the repair works immediately. But, he received no further instruction from the Executive Engineer, PWD. Accordingly, considering the urgency, he took up the repairing work of those timber bridges. 5. After taking over the charge by the SDO, the petitioner made aware of all the said works and the SDO, PWD inspected the spots along with the Executive Engineer and being satisfied they issued formal work orders to the carpenters engaged for execution of the repairing works and took the measurement of the said repair works and found the work as up to the mark and having been satisfied with the works, passed all the bills accordingly. To an utter surprise, the petitioner had received a Memo. dated 22.09.1994 by which he was charged with article of charges as aforstated. 6. Thereafter, a departmental proceeding was initiated against the petitioner and after completion of all the formalities he was found guilty by the inquiring authority and referred the matter to the disciplinary authority. The disciplinary authority after going through all the evidence on record vide order dated 25.09.2014 held the petitioner guilty and penalty was imposed upon the petitioner in the following terms: “The pay of Shri Kalyan Debnath, Ex. Jr. Engineer(now Asstt. Engineer) will be reduced by 3(three) increments in his existing scale of pay as Jr. Engineer and he will not earn any periodical increment for a period of 3(three) years w.e.from 25.01.2000. After expiry of the said period he will be allowed to get his normal increment in his scale of pay as Jr. Engineer from his reduced stage.” 7. Being aggrieved of that order dated 25.09.2014 passed by the disciplinary authority, the writ petitioner preferred a statutory appeal before the appellate authority. The appellate authority passed his order on 10.11.2014 whereby the order of penalty imposed by the disciplinary authority was affirmed and upheld in the following terms: “No.F.12(21)-PWD(E-II)/2000 GOVERNMENT OF TRIPURA PUBLIC WORKS DEPARTMENT Dated, Agartala, The 10/11/2014 ORDER WHEREAS a disciplinary proceeding was drawn up against Shri Kalyan Debnath, Jr. Engineer(now Assistant Engineer) posted in the office of the SDO(PWD), W.R. SubDivision, Kamalpur under the Executive Engineer, W.R. Division No.-V, Kamalpur, Dhalai, Tripura under Rule-14 of the CCS(CC&A) Rules, 1965 for his alleged misconduct vide this office Memorandum No.F.6(58)-PWD(E)/70(III)(S-2) dated 22.09.94. AND WHEREAS the above charged officer had submitted his written statement of defence denying the charges framed against him. AND WHEREAS Shri T. Bhattacharjee, TCS, GR-I, Addl. Commissioner of Departmental Inquiries, Govt. of Tripura, Agartala was appointed as Inquiry Officer and accordingly he delivered his findings on 26.11.99 vide Case No.F.417/INQ/95 sustaining the charges against the accused. AND WHEREAS the Disciplinary Authority accepted the findings of the Inquiring Authority. AND WHEREAS Shri Kalyan Debnath, Jr. Engineer(now Assistant Engineer) was given an opportunity with a copy of findings of the Inquiring Authority inviting his written representation, if any, on the findings of the Inquiring Authority vide this office Memo.No.F.12(21)-PWD(E-II)/2000 dated 18.07.2014 and accordingly Shri Debnath, Assistant Engineer submitted his written representation on 04.08.2014. AND WHEREAS the representation dated 04.08.2014 of Shri Kalyan Debnath, Junior Engineer(now Asstt. Engineer) has been carefully examined and duly considered with reference to the findings of the Inquiring Authority as well as documentary evidence on record but it is found that the representation does not contain any fresh materials and therefore, it was provisionally decided by the Disciplinary Authority that …. “The pay of Shri Kalyan Debnath, Ex. Jr. Engineer(now Asstt. Engineer) will be reduced by 3(three) increments in his existing scale of pay as Jr. Engineer and he will not earn any periodical increment for a period of 3(three) years w.e.from 25.01.2000. After expiry of the said period he will be allowed to get his normal increment in his scale of pay as Jr. Engineer from his reduced stage.” AND WHEREAS the above decision of the Disciplinary Authority was communicated to Shri Kalyan Debnath, Jr. Engineer(now Asstt. Engineer) vide this office Memo. of even No. dated 25.09.2014 and invited his representation, if any, on the proposed penalty and Shri Kalyan Debnath, Jr. Engineer(now Asstt. Engineer) submitted his representation on 22.10.2014. AND WHEREAS after due consideration of the representation dated 22.10.2014 of Shri Kalyan Debnath, Jr. Engineer(now Asstt. Engineer), it is found that the representation does not contain any fresh materials. NOW, THEREFORE, after careful consideration of all aspects in the matter, the Disciplinary Authority imposes the penalty as follows upon Shri Kalyan Debnath, Jr. Engineer(now Asstt. Engineer). “The pay of Shri Kalyan Debnath, Jr. Engineer(now Asstt. Engineer) will be reduced by three increments in his existing scale of pay and he will not earn any periodical increment for a period of three years w.e.from 25.01.2000. After expiry of the said period he will be allowed to get his normal increment in his scale of pay from his reduced stage.” 8. From a bare reading of the order of the appellate authority, it is clear that the appellate authority did not apply his mind in conformity with the law prescribed under CCS(CC&A) Rules, 1965. 9. Rule 11 of the CCS(CC&A) Rules mandates that even an order of penalty of withholding of increments of pay is issued that has to be grounded on good and sufficient reasons. 10. Rule 27(2)(b) of the Rules casts a statutory obligation upon the appellate authority to consider whether the findings of the disciplinary authority are warranted by the evidence on record. 11. Moreso, the principle of natural justice is to be followed in all executive actions. The order dated 10.11.2014 issued by the appellate authority, in our considered opinion, seems to be cryptic in nature and the appellate authority could not appreciate the pleas of the writ petitioner as well as did not discuss the evidence led in course of the proceedings. Moreover, we have noticed that the delinquent-petitioner was not afforded any opportunity of being heard personally, though, it is not mandatory, but principles of fair play and equitable justice want this. 12. In view of the discussions made hereinabove, the order dated 10.11.2014 issued by the appellate authority is hereby set aside and the matter is remitted to the appellate authority to arrive at a fresh decision and to pass a reasoned order after considering all the facts and circumstances arising out of the execution of the works as narrated above. 13. With the aforesaid observation and direction, the instant writ petition stands disposed of. (ARINDAM LODH, J) (SANJAY KAROL, CJ)

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All Tripura HC judgments →