HIGH COURT OF TRIPURA
AGARTALA
WP(C) NO.518 OF 2014
Sri Kalyan Debnath,
S/O Late Upendra Chandra Debnath,
Resident of Kamalpur, P.S. Kamalpur,
District-Dhalai, Tripura.
----Petitioner(s)
Versus
1. The State of Tripura, represented by the
Secretary to the Government of Tripura,
Public Works Department,
Civil Secretariat, New Capital Complex,
P.O. Kunjaban, Agartala, West Tripura.
2. The Commissioner & Secretary to the
Government of Tripura,
Public Works Department,
P.O. Kunjaban, Agartala, West Tripura.
3. The Chief Engineer,
Public Works Department,
Civil Secretariat, New Capital Complex,
P.O. Kunjaban, Agartala, West Tripura.
4. The Engineer-in-Chief,
Public Works Department(R&B),
Civil Secretariat, New Capital Complex,
P.O. Kunjaban, Agartala, West Tripura.
----Respondent(s)
For Petitioner(s)
:
Mr. A. Gan Chowdhury, Advocate
For Respondent(s)
:
Mr. D. Sarma, Addl. G.A.
Date of hearing & delivery
of Judgment & Order
:
09.01.2019
Whether fit for reporting
No
:
HON’BLE THE CHIEF JUSTICE MR. SANJAY KAROL
HON’BLE MR. JUSTICE ARINDAM LODH
J U D G M E N T & O R D E R (O R A L)
(Lodh, J)
Heard Mr. A. Gan Chowdhury, learned counsel appearing for
the petitioner as well as Mr. D. Sarma, learned Addl. G.A.
appearing for the respondents.
2.
The facts in the writ petition, in a nutshell, are that
while the petitioner was serving as Junior Engineer under the
respondents he was charged under Rule 14 of the CCS(CC&A)
Rules, 1965 vide Memo.No.F.6(58)-PWD(E)/70(III)-(S-II) dated
22.09.1994 and the charges are as under:
“ARTICLE NO.-I
That the said Sri Kalyan Debnath while functioning as
Junior Engineer during the period 21.10.93 to 8.12.93 was
entrusted to look after the routine nature of works of
SDO(PWD), Kamalpur Sub-Division during the absence of Sri
Animesh Das, S.D.O.(PWD) Kamalpur during puja holidays
from 22.10.93 to 29.10.93 disobeyed the instruction of higher
officials, thus liable for action under C.C.S.(C.C.A) Rules.
ARTICLE NO.-II
That during the aforesaid period and while functioning
in the aforesaid office, Sri Kalyan Debnath awarded 4(four)
nos. of works to different contractor without having any verbal
or written concurrence from his higher authorities. For such
act the Department is to be discharged the liabilities to the
tune of Rs.1,91,800/-(Rupees one lac ninety-one thousand)
only. Awarding of works without observing codal formalities is
beyond the competency of the Junior Engineer Sri Kalyan
Debnath. Thus Sri Debnath is liable to be charged under
C.C.S.(C.C.A) Rules.”
3.
Mr. Gan Chowdhury, learned counsel for the petitioner
submits that on the eve of Durgapuja while all the higher officials
and engineers went on leave, the petitioner was entrusted with
the duties to carry out all the routine nature of works. Prior to six
months
of
Durgapuja(1993),
the
department
had
prepared
estimates for repairing 8(eight) numbers of dilapidated wooden
bridges of the Sub-Division and those were required for urgent
repairing for public use, standing over various cannels and rivers
connecting the roads. The Superintending Engineer, 1 st Circle,
Kumarghat assured the local bodies that the Department would
keep the semi permanent timber bridges during Durgapuja
holidays to avoid any kind of accident and such instruction was
given to the office but the department could not repair the same.
4.
It has been further submitted that the petitioner was
given the charge of SDO routine duty during Puja holidays(1993)
and due to absence of the higher officials of the department, the
petitioner was instructed by a radio message by the Executive
Engineer, PWD, Ambassa Division to perform the repair works of
the SPT bridges by engaging departmental workers(carpenters
and helpers) & materials as the localities and autonomous bodies
put severe pressure on the department to repair the bridges on
emergent basis to facilitate the public to use the same which were
essential road connectivity for public convenience and to protect
the people from any accident to enjoy the largest festival of the
State. To comply with the order, the petitioner faced difficulties as
no departmental carpenter was on duty and no dismantled
timbers/materials were lying with the store and no timber was
endorsed. The petitioner sent a crash message on 21.10.1993 to
the Executive Engineer, Ambassa Division with a copy to the
Superintending Engineer, 1st Circle, Kumarghat and the Chief
Engineer for further instruction as the local bodies and public put
severe pressure on the petitioner to repair minimum four numbers
of timber bridges which were connecting the main roads and lying
in such a condition that any moment accident could be happened.
More so, the then Hon’ble Speaker of the Tripura Legislative
Assembly called the petitioner in his residence and asked him to
do the repair works immediately. But, he received no further
instruction
from
the
Executive
Engineer,
PWD.
Accordingly,
considering the urgency, he took up the repairing work of those
timber bridges.
5.
After taking over the charge by the SDO, the petitioner
made aware of all the said works and the SDO, PWD inspected the
spots along with the Executive Engineer and being satisfied they
issued formal work orders to the carpenters engaged for execution
of the repairing works and took the measurement of the said
repair works and found the work as up to the mark and having
been satisfied with the works, passed all the bills accordingly. To
an utter surprise, the petitioner had received a Memo. dated
22.09.1994 by which he was charged with article of charges as
aforstated.
6.
Thereafter, a departmental proceeding was initiated
against the petitioner and after completion of all the formalities he
was found guilty by the inquiring authority and referred the matter
to the disciplinary authority. The disciplinary authority after going
through all the evidence on record vide order dated 25.09.2014
held the petitioner guilty and penalty was imposed upon the
petitioner in the following terms:
“The pay of Shri Kalyan Debnath, Ex. Jr. Engineer(now
Asstt. Engineer) will be reduced by 3(three) increments in his
existing scale of pay as Jr. Engineer and he will not earn any
periodical increment for a period of 3(three) years w.e.from
25.01.2000. After expiry of the said period he will be allowed
to get his normal increment in his scale of pay as Jr. Engineer
from his reduced stage.”
7.
Being aggrieved of that order dated 25.09.2014 passed
by the disciplinary authority, the writ petitioner preferred a
statutory appeal before the appellate authority. The appellate
authority passed his order on 10.11.2014 whereby the order of
penalty imposed by the disciplinary authority was affirmed and
upheld in the following terms:
“No.F.12(21)-PWD(E-II)/2000
GOVERNMENT OF TRIPURA
PUBLIC WORKS DEPARTMENT
Dated, Agartala, The 10/11/2014
ORDER
WHEREAS a disciplinary proceeding was drawn up
against Shri Kalyan Debnath, Jr. Engineer(now Assistant
Engineer) posted in the office of the SDO(PWD), W.R. SubDivision,
Kamalpur
under
the
Executive
Engineer,
W.R.
Division No.-V, Kamalpur, Dhalai, Tripura under Rule-14 of the
CCS(CC&A) Rules, 1965 for his alleged misconduct vide this
office
Memorandum
No.F.6(58)-PWD(E)/70(III)(S-2)
dated
22.09.94.
AND
WHEREAS the above charged officer had submitted
his written statement of defence denying the charges framed
against him.
AND
WHEREAS Shri T. Bhattacharjee, TCS, GR-I, Addl.
Commissioner of Departmental Inquiries, Govt. of Tripura,
Agartala was appointed as Inquiry Officer and accordingly he
delivered his findings on 26.11.99 vide Case No.F.417/INQ/95
sustaining the charges against the accused.
AND
WHEREAS the Disciplinary Authority accepted the
findings of the Inquiring Authority.
AND
WHEREAS Shri Kalyan Debnath, Jr. Engineer(now
Assistant Engineer) was given an opportunity with a copy of
findings
of
the
Inquiring
Authority
inviting
his
written
representation, if any, on the findings of the Inquiring
Authority vide this office Memo.No.F.12(21)-PWD(E-II)/2000
dated 18.07.2014 and accordingly Shri Debnath, Assistant
Engineer submitted his written representation on 04.08.2014.
AND
WHEREAS the representation dated 04.08.2014 of
Shri Kalyan Debnath, Junior Engineer(now Asstt. Engineer)
has been carefully examined and
duly
considered with
reference to the findings of the Inquiring Authority as well as
documentary evidence on record but it is found that the
representation does not contain any fresh materials and
therefore, it was provisionally decided by the Disciplinary
Authority that ….
“The
pay
of
Shri
Kalyan
Debnath,
Ex.
Jr.
Engineer(now Asstt. Engineer) will be reduced by 3(three)
increments in his existing scale of pay as Jr. Engineer and
he will not earn any periodical increment for a period of
3(three) years w.e.from 25.01.2000. After expiry of the
said period he will be allowed to get his normal increment
in his scale of pay as Jr. Engineer from his reduced
stage.”
AND
WHEREAS the above decision of the Disciplinary
Authority was communicated to Shri Kalyan Debnath, Jr.
Engineer(now Asstt. Engineer) vide this office Memo. of even
No. dated 25.09.2014 and invited his representation, if any,
on the proposed penalty and Shri Kalyan Debnath, Jr.
Engineer(now Asstt. Engineer) submitted his representation on
22.10.2014.
AND
WHEREAS
after
due
consideration
of
the
representation dated 22.10.2014 of Shri Kalyan Debnath, Jr.
Engineer(now
Asstt.
Engineer),
it
is
found
that
the
representation does not contain any fresh materials.
NOW, THEREFORE, after careful consideration of all
aspects in the matter, the Disciplinary Authority imposes the
penalty as follows upon Shri Kalyan Debnath, Jr. Engineer(now
Asstt. Engineer).
“The pay of Shri Kalyan Debnath, Jr. Engineer(now
Asstt. Engineer) will be reduced by three increments
in his existing scale of pay and he will not earn any
periodical increment for a period of three years
w.e.from 25.01.2000. After expiry of the said period
he will be allowed to get his normal increment in his
scale of pay from his reduced stage.”
8.
From a bare reading of the order of the appellate
authority, it is clear that the appellate authority did not apply his
mind in conformity with the law prescribed under CCS(CC&A)
Rules, 1965.
9.
Rule 11 of the CCS(CC&A) Rules mandates that even
an order of penalty of withholding of increments of pay is issued
that has to be grounded on good and sufficient reasons.
10.
Rule 27(2)(b) of the Rules casts a statutory obligation
upon the appellate authority to consider whether the findings of
the disciplinary authority are warranted by the evidence on record.
11.
Moreso, the principle of natural justice is to be followed
in all executive actions. The order dated 10.11.2014 issued by the
appellate authority, in our considered opinion, seems to be cryptic
in nature and the appellate authority could not appreciate the
pleas of the writ petitioner as well as did not discuss the evidence
led in course of the proceedings. Moreover, we have noticed that
the delinquent-petitioner was not afforded any opportunity of
being heard personally, though, it is not mandatory, but principles
of fair play and equitable justice want this.
12.
In view of the discussions made hereinabove, the order
dated 10.11.2014 issued by the appellate authority is hereby set
aside and the matter is remitted to the appellate authority to
arrive at a fresh decision and to pass a reasoned order after
considering all the facts and circumstances arising out of the
execution of the works as narrated above.
13.
With the aforesaid observation and direction, the
instant writ petition stands disposed of.
(ARINDAM LODH, J)
(SANJAY KAROL, CJ)
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review