The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
13. Further, at Ex.P22, the Executive Engineer admits that there are some delays in finalization of the design of waste weir. Further, admitted that the schedule -9NC: 2026:KHC-D:784 RSA No. 1248 of 2006 HC-KAR rates of concerned area were increased by 15% in 1960-61. Therefore, the First Appellate Court allowed the claim of plaintiff and declared that he is entitled to 15% increase in the cost of labour and material for the period 31.12.1960 and 31.03.1963 over and above the agreed rate, which is found to be just and proper. Hence, the appeal is not found to be having involved substantial questions of law, so as to entertain the appeal. Therefore, the appeal is liable to be dismissed at admission stage itself.
14. Accordingly, the appeal is dismissed.
15. In view of disposal of the appeal, pending interlocutory applications, if any, stand disposed of as they do not survive for consideration.
16. No order as to cost. Sd/(HANCHATE SANJEEVKUMAR) MRK-para 1 to 10. PMP-para 11 to end. CT-AN List No.: 1 Sl No.: 21
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
-1NC: 2026:KHC-D:784
RSA No. 1248 of 2006
HC-KAR
IN THE HIGH COURT OF KARNATAKA, AT DHARWAD
DATED THIS THE 22ND DAY OF JANUARY, 2026
BEFORE
THE HON'BLE MR. JUSTICE HANCHATE SANJEEVKUMAR
REGULAR SECOND APPEAL NO. 1248 OF 2006
BETWEEN:
K. D. KAMAT AND COMPANY,
A FIRM OF ENGINEERS AND CONTRACTORS,
HAVING ITS HEAD OFFICE AT: HUBLI,
DIST. DHARWAD, BY ITS PROPRIETOR
SRI KRISHNARAO DADASAHEB KAMAT,
SINCE DECEASED BY HIS LR.
1.
SRI PRASAD S/O. KRISHNARAO KAMAT,
AGE: 46 YEARS, OCC: BUSINESS,
R/O. NO.282, NEW SHAHAPURI,
KOLHAPUR-416001 (MAHARASHTRA).
…APPELLANTS
(BY SRI V. NARAYANSWAMY, ADVOCATE)
MALLIKARJUN
RUDRAYYA
KALMATH
Location: High Court
of Karnataka,
Dharwad Bench
AND:
1.
THE STATE OF KARNATAKA,
BY ITS DEPUTY COMMISSIONER,
BELGAUM-590002.
2.
THE KARNATAKA URBAN WATER SUPPLY
AND DRAINAGE BOARD, BANGALORE,
BY ITS SECRETARY, BANGALORE-560001.
…RESPONDENTS
(BY SRI PRAVEENA Y. DEVAREDDIYAVARA, HCGP FOR R1;
M/S. KESVY & CO. ADVOCATES FOR R2.)
-2NC: 2026:KHC-D:784
RSA No. 1248 of 2006
HC-KAR
THIS REGULAR SECOND APPEAL IS FILED UNDER SECTION
100 OF THE CODE OF THE CIVIL PROCEDURE, 1908, PRAYING
TO MODIFY THE JUDGMENT AND DECREE DATED 02.01.2006
PASSED IN R.A.NO.124/1989, ON THE FILE OF THE
I ADDITIONAL DISTRICT JUDGE, BELAGAVI, IN SO FAR AS IT
HAS DISMISSED THE PLAINTIFF’S/APPELLANT’S CLAIM AND SET
ASIDE THE JUDGMENT AND DECREE DATED 07.12.1983 PASSED
IN O.S.NO.143/1974, ON THE FILE OF THE II ADDITIONAL CIVIL
JUDGE, BELAGAVI AND DECREE THE SUIT OF THE PLAINTIFF AS
PRAYED FOR AND ALLOW THE APPEAL WITH COSTS AND
INTEREST IN THE INTEREST OF JUSTICE AND EQUITY.
THIS APPEAL COMING ON FOR ADMISSION, THIS DAY
JUDGMENT WAS DELIVERED THEREIN AS UNDER:
ORAL JUDGMENT
(PER: THE HON'BLE MR. JUSTICE HANCHATE SANJEEVKUMAR)
Learned counsel Sri Sharad V. Magadum, has filed
memo for retirement from the case. Memo is accepted.
Learned counsel Sri Sharad V. Magadum is permitted to
retire from the case.
2.
The matter is not admitted and is still lying for
admission from the year 2006. Therefore, the appeal is
taken up to consider as to whether the appeal is having
merit involving substantial questions of law.
3.
The plaintiff has filed this Regular Second Appeal
challenging the judgment and decree dated 02.01.2006,
-3NC: 2026:KHC-D:784
RSA No. 1248 of 2006
HC-KAR
passed in R.A.No.124/1989, by the I Additional District
Judge, Belagavi (First Appellate Court), by which the appeal
is partly allowed, decreeing the suit in part. The First
Appellate Court has rejected the claim of plaintiff for oil and
fuel charges, for rebate in hire charges and assessment of
pitch work in cubic feet instead of square feet and further
declared that the plaintiff is entitled to 15% increase in the
cost of labour and material for the period from 31.12.1960
to 31.03.1963 over and above the agreed rate and directed
the defendant to prepare final bills accordingly.
4.
The suit filed by the plaintiff for finalizing the bills
and for payment of amount is dismissed in its entirety.
Being aggrieved by it, the plaintiff has preferred appeal and
the First Appellate Court has modified the judgment and
decree of the Trial Court and partly allowed the appeal as
discussed above.
-4NC: 2026:KHC-D:784
RSA No. 1248 of 2006
HC-KAR
5.
For
the
purpose
of
convenience
and
easy
reference, ranking of the parties is referred to as per their
status before the trial Court.
6.
It is the case of plaintiff as per the plaint
averments that the plaintiff is a contractor and engineer and
defendant Government has allotted to the plaintiff the work
of construction of earthen dam and allied work at Rakaskop
for Belagavi Water Supply Project. The plaintiff is a
successful bidder. It is the case of plaintiff that the plaintiff
is entitled for oil and fuel charges, for rebated hire charges
and assessment of pitch work in cubic feet instead of square
feet. Therefore, claimed that the defendant still owes
balance
of
Rs.50,000/-.
Therefore,
filed
a
suit
for
finalization of bill and recovery of amount.
7.
The Trial Court had dismissed the suit of plaintiff
assigning reasons that the plaintiff fails to prove that
plaintiff
is
entitled
for
rebate
in
hire
charges
and
assessment of pitch work in cubic feet instead of square
-5NC: 2026:KHC-D:784
RSA No. 1248 of 2006
HC-KAR
feet. Further assigned reasons that the claim of plaintiff is
barred by limitation. Accordingly dismissed the suit.
8.
Being aggrieved, the plaintiff has preferred the
Regular Appeal before the First Appellate Court. The First
Appellate Court has concurred with the finding of Trial Court
rejecting claim of plaintiff for rebate in hire charges of
machinery. Therefore, there is concurrent finding on this
fact. Upon considering the evidence on record on this point,
whether appreciation of evidence in this regard is correctly
made or not and pleadings of the plaintiff that the
Government has not supplied machineries which were
100% efficiency and therefore, expected work could not be
turned out from those machineries, therefore, the plaintiff
has
put
blame
on
the
Government
by
saying
the
Government has not supplied good conditioned machineries.
But contrary to this, the defendant submitted that the
machineries supplied to the plaintiff were in order and in
condition and both the trial Court and the First Appellate
Court upon appreciation of evidence on record held that
-6NC: 2026:KHC-D:784
RSA No. 1248 of 2006
HC-KAR
plaintiff has failed to prove that the machineries supplied
were not in good condition. Therefore, the claim of plaintiff
for rebated charges of machinery is rejected is found to be
just and proper as there was no perversity found in the
order.
9.
But so far as whether the plaintiff is entitled for
15% increase in the cost of labour and material for the
period of 31.12.1960 to 31.03.1963 over and above agreed
rate is entitled, the trial Court has rejected this claim. But
the First Appellate Court has allowed this claim of the
plaintiff. Therefore, there is a divergent finding in this
regard which is formulated as point No.3 by the First
Appellate Court.
10.
It is not in dispute that tender was called on
09.12.1957 and accepted on 12.09.1958 and the work
order was issued on 30.10.1958. The time fixed for
completion of work is 18 months from the date of work
order excluding the mansoon period commencing from
-7NC: 2026:KHC-D:784
RSA No. 1248 of 2006
HC-KAR
June 15 ending on 15th October of each year. Thus, the
period fixed for completion of work was 31.12.1960. But the
plaintiff has competed the work on 31.03.1963 and the
project was handed over to the Government on that day.
But it is the claim of plaintiff that on account of the delay
caused by the defendant Government in handing over the
site of project on account of due to delay in acquisition
proceedings, change in design of the project and some
works
and
inefficiency
in
the
machineries
of
the
Government, the plaintiff could not complete the work
before 31.12.1960. Therefore, the defendant contended
that the plaintiff is liable to make good the increase of
labour and material by 30% during the period from
31.12.1960 to 31.03.1963.
11.
PW.2
Upon considering the evidence in this regard of
and
Ex.P.23,
in
Ex.P23,
it
is
mentioned
that
possession of the land belonging to private persons was
taken over through private negotiations. PW.2, in the report
at Ex.P16, has explained the causes for the delay. Upon re-
-8NC: 2026:KHC-D:784
RSA No. 1248 of 2006
HC-KAR
appreciating of the evidence recorded by the First Appellate
Court and the documentary evidence at Ex.P16, Ex.P22 and
Ex.P23, it has been observed that the land had not been
acquired prior to the issuance of work order.
12.
In Ex.P22, the Executive Engineer has stated
that delay in execution of work was partly due to the
contractors, being instructed to excavate only a width of 50
feet for the approach and tail channel, as against the
approved full width of 150 feet, and also due to the fact
that the design of the waste weir had not been finalized.
Therefore, the words “delay due to slow progress by the
contractors themselves” are interpolated. The delay caused
was partly due to change in the width of excavation of the
approach and tail channel and non-finalization of the design
of waste weir.
13.
Further,
at
Ex.P22,
the
Executive
Engineer
admits that there are some delays in finalization of the
design of waste weir. Further, admitted that the schedule
-9NC: 2026:KHC-D:784
RSA No. 1248 of 2006
HC-KAR
rates of concerned area were increased by 15% in 1960-61.
Therefore, the First Appellate Court allowed the claim of
plaintiff and declared that he is entitled to 15% increase in
the cost of labour and material for the period 31.12.1960
and 31.03.1963 over and above the agreed rate, which is
found to be just and proper. Hence, the appeal is not found
to be having involved substantial questions of law, so as to
entertain the appeal. Therefore, the appeal is liable to be
dismissed at admission stage itself.
14.
Accordingly, the appeal is dismissed.
15.
In view of disposal of the appeal, pending
interlocutory applications, if any, stand disposed of as they
do not survive for consideration.
16.
No order as to cost.
Sd/(HANCHATE SANJEEVKUMAR)
JUDGE
MRK-para 1 to 10.
PMP-para 11 to end.
CT-AN
List No.: 1 Sl No.: 21
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review