Gujarat Urja Vikas Nigam Limited vs Green Infra Corporate Wind Private Limited and Others Etc.

Court
Supreme Court of India
Date
4 August 2025
Case No.
Civil Appeal No(s). 14098-14101 of 2015
Result
Dismissed
Bench
Sanjay Kumar, Satish Chandra Sharma
Citation
[2025] 8 S.C.R. 345 : 2025 INSC 922
Acts & Sections
Electricity Act, 2003 Income Tax Act, 1961 Income Tax Rules, 1962
Supreme Court Reports [2025] 8 S.C.R. 345 : 2025 INSC 922
Issue for consideration
Whether the four respondent companies were entitled to approach the Gujarat Electricity Regulatory Commission (GERC) for determination of the tariff for procurement of power by Appellant-GUVNL from their wind energy projects.
Headnote

Electricity Act, 2003 – ss.61, 62, 64, 86 – Income Tax Act, 1961 – s.32 – Power Purchase Agreements (PPAs) entered into between GUVNL and the respondent companies containing a clause w.r.t the tariff applicable for purchase of power from the respondent companies’ wind energy projects – Respondent companies approached the GERC seeking project-wise determination of tariff, claiming that they had not availed accelerated depreciation under the Income Tax Act, 1961 – Claim contested by GUVNL, arguing that they had willingly entered into PPAs and were bound to the tariff rate of ₹3.56 per kWh, and therefore, could not seek determination of tariff on a case-to-case basis – GERC decided the issue in favour of respondent companies – Order confirmed by the APTEL – Correctness:

Read the full headnote (1 more paragraph)

Held: GUVNL, an instrumentality of the State is bound to promote and give effect to the Government’s policy of encouraging generation of power from renewable energy sources – When the Government promulgated a policy in that regard, offering various incentives to wind energy projects, GUVNL cannot act contrary thereto by fixing a tariff for purchase of power from such wind energy projects contrary to the mandate of Order dated 30.01.2010 issued by GERC as per which the tariff of ₹3.56 per kWh was applicable only to those wind energy projects that availed the benefit of accelerated depreciation – It is not disputed that the four respondent companies did not avail such benefit – Thus, the question of applying to them the tariff that was only meant for wind energy projects that did avail accelerated depreciation would not arise – GUVNL cannot be guided only by its own commercial interests, like a private business entity and it’s conduct, as a State instrumentality, must be of the standard of a model citizen – It cannot contend that the respondent companies are estopped from seeking determination of tariff by the GERC as they had willingly signed PPAs with it at the tariff fixed for wind energy projects availing accelerated depreciation – As GUVNL failed to obtain commitments from the respondent companies that they would only avail accelerated depreciation at the time they had to choose that option, GUVNL has no indefeasible right to bind them to a tariff which was applicable only to such wind energy projects that availed accelerated depreciation – Orders passed by the GERC and the APTEL not interfered with – Income Tax Rules, 1962. [Paras 24, 25]

Keywords: Gujarat Electricity Regulatory Commission (GERC) · Determination of the tariff · Gujarat Urja Vikas Nigam Limited (GUVNL) · Procurement of power by GUVNL · Wind energy projects · Accelerated Depreciation · Procurement of power by distribution licensees · Project-wise determination of tariff · Determination of tariff on a case to case basis · Appellate Tribunal for Electricity (APTEL) · Instrumentality of the State · State instrumentality · Renewable energy sources

As published in the Supreme Court Reports, Supreme Court of India. Headnotes prepared by: Divya Pandey. Text from the Indian Supreme Court Judgments open data set (Dattam Labs), CC BY 4.0.

Full Judgment Text

Judgment Sanjay Kumar, J. 1. Gujarat Urja Vikas Nigam Limited (GUVNL), the appellant in these four appeals, assails the common judgment dated 28.09.2015 rendered by the Appellate Tribunal for Electricity (APTEL), New Delhi, in Appeal Nos. 198, 199, 200 and 291 of 2014. Thereby, the APTEL confirmed the orders dated 13.06.2014, 11.06.2014, 13.06.2014 and 20.09.2014 passed by the Gujarat Electricity Regulatory Commission (GERC), Gandhi Nagar, in Petition Nos. 1239 of 2012, 1221 of 2012, 1241 of 2012 and 1365 of 2013 filed by Green Infra Corporate Wind Private Limited, New Delhi; Vaayu (India) P
Full text available to subscribers
Subscribe to access complete judgment text, daily digests, and AI-powered legal research tools. For informational and research purposes only.
View Subscription Plans →
Annual plans from ₹1,599 + GST.

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

All SC judgments →