IN THE HIGH COURT OF MADHYA PRADESH
AT GWALIOR
BEFORE
HON'BLE SHRI JUSTICE MILIND RAMESH PHADKE
ON THE 31st OF MARCH 2023
ARBITRATION CASE No.70 of 2022
Between:ECOGREEN ENERGY GWALIOR PVT. LTD.
THROUGH ITS LEGAL EXECUTIVE
MR. KANISHK BEHAL, S/O MR.
PURUSHOTTAM BEHAL, OCCUPATION:
EMPLOYEE IN APPLICANT'S
COMPANY
HAVING REGISTERED OFFICE AT:
228-236, 2nd FLOOR, TOWR A,
SPAZE I-TECH PARK, SECTOR 49
SOHNA ROAD, GURUGRAM,
HARYANA -122018
ALSO AT:
PLOT NO.131, GROUND FLOOR,
SHARDA VIHAR, CITY CENTRE,
GWALIOR (M.P) 474001
…..PETITIONER
(BY MS. MEGHNA MITAL SANKHLA – ADVOCATE )
AND
1.
COMMISSIONER OF MUNICIPAL
CORPORATION GWALIOR
HAVING OFFICE AT:
MUNICIPAL CORPORATION
GWALIOR-474001, MADHYA
PRADESH
…..RESPONDENTS
(BY SHRI HARISH DIXIT – ADVOCATE )
-------------------------------------------------------------------------------This petition coming on for hearing this day, Hon'ble Shri
Justice Milind Ramesh Phadke passed the following:
ORDER
1.
An application on behalf of the applicant had come up
for hearing
under section 11(6)
of the Arbitration and
Conciliation Act, 1996 with a prayer for appointment of an
Arbitrator, in wake of Article 11 of the agreement which
provides for Dispute Resolution Mechanism specifically in
the light of Article 11.2 which provides for any dispute which
is not resolved amicably shall be finally settled by binding
arbitration under the Rules of Arbitration
of International
center for alternative dispute resolution, New Delhi.
2.
Before adverting to the merits of the case it is necessary
to quote the facts which has led to file the present application
before this Court.
Earlier a similar application was moved
seeking appointment of an Arbitrator before Delhi High Court
vide Arbitration Petition No.1120/2021. However, the same was
dismissed
on 16.3.2022 as it did not had the territorial
jurisdiction to entertain such petition, but with a liberty to file
the same before the Court of Competent Jurisdiction.
3.
The applicant is a company incorporated under the
Companies Act, 2013 having its registered office at 228-236,
2nd Floor, Tower A, Spaze I-Tech Park, Sector 49, Sohna Road,
Gurugram, Haryana -122018 and also at Plot No. 131, Ground
Floor, Sharda Vihar, City Centre, Gwalior. The Non-Applicant
is a State Instrumentality under Article 12 of the Constitution of
India. The Non-Applicant invited a tender from the public,
bearing No. UADD/25123, under the Public Private Partnership
("PPP") model for Implementation of Regional Integrated Solid
Waste Management (ISWM) project for 16 Urban Local Bodies
("ULBs") of the Gwalior Cluster (MP) ("the Project")
comprising of design, engineering, construction, financing,
procurement, operation & maintenance for door-to- door
transportation
and
secondary
collection,
transportation,
segregation, material recovery, treatment through waste to
energy processing facility and final disposal of the inerts in a
scientifically developed landfill and closure of old landfill
within the administrative limits of Municipal Corporation of
Gwalior and 15 other participating ULBS. The offer made by
the applicant
was accepted by the non-applicant and on
19.5.2017 a Concession Agreement was executed between
them. In terms of the Agreement executed the non-applicant
awarded the Applicant the abovementioned project.
4.
The said Project was to be implemented under a PPP
model as expressly mentioned under Clause (r) of Article 2.1 of
the Agreement and the Non-Applicant was equally obligated
under the Agreement as it was an equal partner to the Project.
The obligations included Non-Applicant's statutory duties to
ensure collection of waste as has been enshrined under the
Madhya Pradesh Municipal Corporation Act, 1956, Madhya
Pradesh Municipalities Act, 1961, Municipal Solid Waste
Management Rules, 2000 and the Solid Waste (Management
and Handling) Rules, 2016. In furtherance of its obligations
under the Concession Agreement, the Applicant has till date
invested an amount of Rs.1,08,79,00,000/- (Rupees One
Hundred Eight Crores Seventy Nine Lakhs Only) in the said
Project and till the dispute arose there were no disruption of
services in the collection and disposal of waste material in terms
of the said Agreement. From its very inception i.e. 2017 itself
on account of continuous breaches and failure to perform their
obligations under the Concession Agreement which resulted in
disruption of services and caused substantial losses to the
applicant.
5.
In terms of the Article 2.5 (II) (B) and Article 3 of the
Concession Agreement, it was the obligation of the NonApplicant to ensure that land free from encumbrances be
handed over to the Applicant for garbage landfill and
transportation station for collected garbage in order to have
smooth functioning of the whole Project. However even as late
as on 05.01.2021, i.e. after a lapse of three years, the NonApplicant was unable to handover all the required land in terms
of the Concession Agreement. The Non-Applicant as well as the
above- mentioned ULBS consistently failed to pay the monthly
Tipping Fees to the Applicant. Furthermore, wrongful
deductions were made and penalties were imposed on the
Applicant which led to the Project becoming financially
unviable and resultantly the Applicant was unable to pay its
workers causing disruptions in the Project. The Non-Applicant
further failed to fulfil one of its major obligations under Article
2.5 of the Concession Agreement, in terms of which the
Applicant was required to sign a Power Purchase Agreement
("PPA") within 180 days from the signing date of the
Concession Agreement
with the Madhya Pradesh Power
Management Company Limited ("MPPMCL") at an agreed
tariff rate of Rs. 6.39 per unit, as also recorded in Article 7.4 of
the Concession Agreement and the same was done only after a
delay of 2 years on 04.11.2019. Due to lack of support from the
Non-Applicant, the MPPMCL refused to execute the PPA with
the Applicant on the agreed tariff rate of Rs. 6.39 per unit,
despite the fact that the same was set out under the Concession
Agreement.
6.
Owing to continuous failure of the Non-Applicant to
perform their obligations under the Agreement, the Applicant
was constrained to issue Preliminary Termination Notice dated
05.10.2020 under Article 9.2(b) (ii) of the Concession
Agreement once again highlighting the defaults on the part of
the non-applicants for curing the said defaults. However, no
proposal was forwarded by the Non-Applicant
and in
retaliation the non-applicant also sent a Termination Notice
dated 10.11.2020 terminating the Concession Agreement on
account of "Concessionaire Event of Default" and invoked the
Bank
Guarantee
submitted
by
the
Applicant
worth
Rs.12,73,00,000/- without issuing any preliminary termination
notice as mandated under Article 9.2(a)(ii) of the Concession
Agreement.
7.
Constrained by the act of the non-Applicant as mentioned
earlier the applicant
had sent
a termination notice
dated
5.10.2020 under Article 9.2 (c) of the delayed amount being
due and payable by the non-applicant. Receiving no response
the applicant vide notice dated 3.8.2021 invoked Article 11.1
of the agreement seeking “Amicable Resolution”.
As
per
Article 11.1 of the Concession Agreement in case of any dispute
it was to be referred to Commissioner, Nagar Palika Nigam
Gwalior
and the Chief Executive Officer
for amicable
settlement and they were suggested to meet at the earliest
mutual convenience and in any event within 15 days of such
reference to discuss and make an attempt to amicably resolve
the dispute and in the evident the dispute is not amicably setled
within the aforesaid period either party may refer the Dispute
to Arbitration in accordance with the provisions of clause 11.2.
8.
Since there was no response, left with no other option
the applicant send a notice dated 13.9.2021
to the non-
applicant invoking Article 11.2 i.e. Arbitration Clause of the
agreement and proposed the name of Hon'ble Justice (Retd.)
Kurian Joseph and sought the non-applicant to nominate its
Arbitrator
within 30 days
from the receipt of the notice.
However, since no response was received from the nonapplicant, consequently applicant moved an application under
section 11 (6) of the Arbitration and Conciliation Act, 1996
before the Delhi High Court under Arbitration Case
No.1120/2021. However, the same was dismissed vide order
dated 16.3.2022 with a liberty to file the same before the Court
of competent jurisdiction. Thereafter the application was filed
before the Jabalpur Bench which was later-on withdrawn vide
order dated 3.9.2022 with liberty to approach this Court and
accordingly this application came to be filed.
9.
A reply has been filed on behalf of the non-applicant
inter-alia contending that the present application under section
11 (6) of the Arbitration and Conciliation Act 1996 is not
maintainable, as the dispute for resolving of which, applicant is
seeking appointment of arbitrator in the present petition is
governed by the Madhya Pradesh Madhyastham Adhikaran
Adhiniyam, 1983 and as such provisions of Act of 1996 are not
applicable in the present case.
In its reply it was further
contended that the MP Act of 1983 had received the assent of
the President on 17.10.1983 which was published in Madhya
Pradesh Gazette Extraordinary dated 12.10.1983. Section 7 of
the Act provides for Reference to Tribunal. Section 7 (1) lays
down that either party to a works contract shall irrespective of
the fact whether the agreement contains an arbitration clause or
not, refer in writing the dispute to the Tribunal and the words
'dispute', 'works contract' and 'Tribunal' are also defined under
Section 2 of the M.P. Act of 1983. As per section 2 (d):
"dispute" means claim of ascertained
money valued at Rupees 50,000 or more
relating to any difference arising out of
the execution or non-execution of a works
contract or part thereof.”
And as per section 2 (I) "works-contract" means:
“an agreement in writing for the execution
of any work relating to construction,
repair or maintenance of any building or
superstructure, dam, weir, canal, reservoir,
tank, lake, road, well, bridge, culvert,
factory,
work-shop,
powerhouse,
transformers or such other works of the
State Government or Public Undertaking
as the State Government may, by
notification, specify in this behalf at any
of its stages, entered into by the State
Government or by an official of the State
Government or Public Undertaking or its
official for and on behalf of such Public
Undertaking and includes an agreement
for the supply of goods or material and all
other matters relating to the execution of
any of the said works.”
As per section 2 (h) “Tribunal” means:
“An Arbitration Tribunal constituted
under Section 3 and includes a Bench
thereof constituted under Section 9.”
10.
It was further averred therein that the present contract in
question is a concession agreement executed between applicant
and non-applicant on 19.05.2017 for "Implementation of
Integrated Solid Waste Management Project". [ISWM].
According to the non-applicant it is a works contract which is
apparent from Clause 2.2 (a) and Clause 2.2(b) (i) by which
non-applicant had granted concession to the applicant to
construct operate and maintain the Project. Further the Scope of
Work prescribed in Clause 2.1 of the contract which includes
detailed designing and developing ISWM Facility including
systems for waste segregation, processing, and scientific
disposal, at Gwalior as per the MSW Rules 2000/2016 also
reveals that it includes the construction of the different
structures of the Project and as such it is a 'works contract'.
Similarly, clause 2.1 (j) (i) provides for design construction and
implementation of Waste to Energy Processing Facility [ power
plant] of installed capacity of minimum 10 MW for treatment
and processing of MSW of the Project Area. It is also more
clear
from the Schedule 2 of the Contract
which has
stipulation for construction requirements. It provides for
construction of following structures: Construction of Common
Infrastructure, Boundary Wall for the Facilities, Green Belts,
Access Roads and Internal Roads, Weigh Bridge Waiting Area,
Entrance and Security Cabin at ISWM Facility and Satellite
Facilities, Administration Building, Control Room, Laboratory,
Water Supply arrangements, Power Supply arrangements,
Lighting, Other Electrical Works,
System,
Storm Water Drainage
Leachate Management Facility, Fire and Safety
Equipment,
Waste Tipping and Segregation Area, Waste
Recovery and Segregation Facility, Digester, Signage.
11.
It was further averred in the reply that as per the
agreement the applicant was required to construct and establish
a Power Plant of 10 MW or more capacity to convert the solid
waste into electricity. Applicant was free to choose any
technology and operational methodology for management of
MSW for waste to energy technology subject to that the
technology should be proven and feasible for the waste of
project area. It provides that the petitioner/ concessionaire shall
also construct the Power Pooling Station so as to supply the
electricity generated by it to the State Transmission Grid. It was
also a condition of the contract that the construction of the
waste to energy plant and power pooling station shall conform
to the specifications issued by the GOI and Electricity
Company. Further the contract in Schedule 3 gives description
of maintenance works to be carried out by the applicant.
12.
Thus, from the face of the contract it was apparent that it
involves Construction, Operation and Maintenance of the Solid
Waste Management Project and
therefore it was a “Works
Contract”. It was further averred that the petitioner has raised
the dispute with regard to the non-applicant being unable to
hand over all the land free from encumbrances to the applicant
for construction of the facility, it had failed to pay the monthly
tipping fee and even had made wrongful deductions and
imposed penalties and had not signed the power purchase
agreement within the time prescribed for construction of Waste
to Energy facility and by way of said dispute the applicant has
claimed the termination payment of Rs.10355.67 lacs and an
amount of Rs.4524.95 lacs as damages and Rs.1273 lacs on
account of refund of performance guarantee and since these
claims are based on the breach/termination of contracts which is
a 'Work Contract' and such claims are quantified to an amount
more than Rs.50,000/- a dispute is required to be referred to
the Arbitration Tribunal as provided under the M.P. Act of 1983.
13.
A rejoinder has been filed in the matter on behalf of the
applicant and it is submitted that the parties to the concession
agreement have voluntarily and unequivocally chosen to refer
the disputes arising between the parties under the said
Agreement to arbitration which is to be conducted in
accordance with the Rules of International Centre for
Alternative Dispute Resolution, New Delhi (hereinafter,
"ICADR Rules") as it has been mentioned in Clause (a) of
Article 11.2 of the Agreement. It was further averred therein
that aforementioned clause explicitly provides for the Rules of
Arbitration of International Centre for Alternative Dispute
Resolution, New Delhi and the provisions of the Arbitration and
Conciliation Act, 1996 to be applicable to the dispute arising
between the parties. It was also averred that in addition to
Article 11.2(a), Clause (v) of Article 5 of Schedule 22 of the
Agreement also adopts the ICADR Rules as the sole governing
law for the arbitration proceedings and from the above
mentioned clauses of the Agreement, one can easily infer the
intention of the parties with respect to their choice of the
governing law, by consciously opting to make the Arbitration
and Conciliation Act, 1996 and the ICADR Rules applicable to
the dispute in question, according to which the parties have
voluntarily ousted the applicability of the Madhya Pradesh
Madhyastham Adhikaran Adhiniyam, 1983 and had there been
any intention to make the M.P. Act, 1983 applicable, the same
would have been explicitly mentioned in the Agreement to
express such intention.
14.
It is also averred therein that 'neutrality' is the essence of
any arbitration proceeding and more so when the State or a
State instrumentality is a party to the contract, keeping the
above essence in the fold of the Agreement, the parties
evidently chose a neutral forum, i.e. the ICADR to govern the
arbitration proceedings in the present matter and the purpose
behind this decision of the parties was to undoubtedly avoid any
undue influence of the 'State machineries' in the process of
arbitration. By way of rejoinder the applicant tried to canvass
that apart from the non-applicability of the Act of 1983 the
application of the Act of 1983 with its stringent Rules
is
contrary to the spirit of Arbitration and Conciliation Act, 1996
and also the law laid down by the Court. That part the applicant
had averred that the appointment of Arbitrator would be
governed by the terms of the agreement and once the parties
have agreed for a choice forum, the same cannot be departed
with.
15.
Arguments of the parties were based upon the similar
lines as their submissions made in the application and its reply.
16.
Learned counsel for the applicant submitted that
Arbitration is a creature of Contract and the parties are free to
choose the law governing the substance of dispute, the
procedure of arbitration, place and venue inter alia and
intention of the parties being paramount and they having
voluntarily and unequivocally chosen to refer the disputes
arising between them under the Agreement to arbitration to be
conducted in accordance with the Arbitration and Conciliation
Act, 1996 and the ICADR Rules, will definitely override the
nature of the contract and it will have bearing on the
applicability of the provisions of law which has been ousted. It
was further argued that the provisions of the Act of 1983 is in
the teeth of the law laid down by the Hon'ble Supreme Court
and is against the letter and spirit of the Arbitration and
Conciliation Act, 1996. To bolster his submission he placed
reliance in the matter of Bharat Aluminium Co. v Kaiser
Aluminium Technical Services Inc. (2016) 4 SCC 126, with
the contention that the terms of the contract will have to be
understood in the way the parties wanted and intended them
to be. In that context, particularly in agreements of arbitration,
where party autonomy is the ground norm, how the parties
worked out the agreement, is one of the indicators to decipher
the intention, apart from the plain or grammatical meaning of
the expressions and the use of the expressions at the proper
places in the agreement. She has further submitted that when
irrespective
of the nature of Agreement the parties after
expressly agreeing to the applicability of the ICADR Rules
now cannot resile from the same and in that context she
placed reliance in the matter
of M.P. Road Development
Corporation Vs. Ministry of Road, Transport and Highways
(MORT & H) & another, 2021 SCC OnLine MP 1599,
wherein the law regarding applicability of the governing Rules
agreed to by the parties was crystallized.
17.
It was further argued that the Act of 1983 is against the
spirit of Arbitration and Conciliation act and the law laid down
by the Hon'ble Supreme Court and for this contention she
placed reliance in the matter of TRF Ltd. Vs. Energo Projects
Ltd. (2017) 8 SCC 377 and Perkins Eastman Architects DPC
Vs. HSCC (India) Ltd. (2020) 20 SCC 760. With regard to
misuse of powers by the State Instrumentality to impose upon
the Applicant those terms and conditions which have not been
expressly mentioned in the Agreement and is equally bound to
uphold the terms of the agreement, reliance was placed in the
case of State of Madhya Pradesh Vs. M/s Sew Construction
Ltd. And others, 2022 SCC OnLine SC 1606. Thus on the
strength of the above arguments the counsel for the petitioner
prayed for appointment of Arbitrator as per the provisions of
Section 11 (6) while allowing the application as mentioned in
the Article 11.2 of the Arbitration and Conciliation Act.
18.
Per contra learned counsel for the non-applicant
submitted that the arguments as advanced by the counsel for the
applicant are misconceived and misdirected as the reliance
placed in the matter of M.P. Road Development Corporation
(supra) cannot be said to be applicable in the present context as
the same has been passed without referring and taken into
consideration the judgment of the Larger Bench of this Court
in the case of Viva Highways Ltd. Vs. Madhya Pradesh
Road Development Corporation Ltd., 2017 (2) M.P.L.J. 681
and
the Supreme Court in the matter of L.G. Chaudhary,
reported in 2012 (3) SCC 495. It was further submitted that the
Division Bench in the matter of M.P. Road
Development
Corporation (supra) was dealing with the issue of rejection of
an application under section 16 (2) of the Act of 1996, wherein
the objections raised with regard to the applicability of the Act
of 1983 to that of 1996 were rejected. The Division Bench
while deciding the said issue had just referred to the clauses of
the agreement, but had not gone into the issue as to whether
dispute under the Works Contract can referred to Arbitrator
under the Arbitration and Conciliation Act 1996 and had not
decided the said issue, therefore, it has no applicability. It has
further been argued that any judgment passed without
considering the earlier law though mentioned in the order and
the later decision is in conflict with earlier one, the earlier
Division Bench decision shall be followed, except when it is
explained by the later Division Bench, in the case the later
Division Bench shall be binding and also the decision of the
Larger Bench is binding on the similar Benches.
19.
With regard to the applicability of the Act of 1983 in the
cases where the contract is in nature of 'Works contract' in the
light of the decision of the Larger Bench of this Court in the
matter of Viva Highways (supra) and the Supreme Court in
the matter of L.G. Chaudharya (supra) the judgment passed in
M.P.
Road
Development
Corporation
(supra)
has
no
applicability.
20.
It has further been argued that the observation made in
the case of M.P. Road Development Corporation (supra) with
regard to non-applicability of the Act of 1983 are only passing
observations which are not based on sound reasoning and are
not made while proceeding to decide an issue, therefore, they
do not partake the nature
ratio decidendi of the judgment
and therefore, is not binding precedent. In that context reliance
was placed in the matter of decision in the matter of Central
Board of Dawoodi Bohara Community and another Vs.
State of Maharashtra and others, 2005 (2) SCC 673. For
similar preposition the counsel had placed reliance in the case
of Municipal Corporation of Delhi Vs. Gurnam Kaur
(1989) 1 SCC 101, Union of India and others Vs. Dhanwanti
Devi and others, 1996 (6) SCC 44
and
State of Uttar
Pradesh and another Vs. Synthetics and Chemicals Ltd. And
another, (1991) 4 SCC 139.
21.
With regard to the applicability of the Act of 1983 over
the present matter the counsel for the non-applicant submitted
that as per section 7 of the Act of 1983 either party to a 'Works
Contract' shall irrespective of the fact whether the agreement
contains an arbitration clause or not, refer
in writing
the
dispute to the Tribunal and since the present contract is a 'Works
Contract' as is apparent from clause 2.2 (a) and Clause 2.2 (b)
(i), Clause 2.1 clause (j) (i)
as it involves construction,
Operation and Maintenance of the Solid Waste Management
Project is defined under the Definition of Works Contract as
provided under section 2(i) of the M.P. Act and while placing
reliance in the matter of Viva Highways Limited (supra) the
order of Larger Bench of this Court which has laid down that
criteria deciding the 'Works Contract' and if it is a work
contract then the provisions of Act of 1983 would be applicable,
thus it was submitted by the counsel for the non-applicant that
the matter is required to be referred to the Arbitration Tribunal
as per the provisions of Act, 1983.
22.
It has also been argued by the counsel of the non-
applicant that the question of applicability of the Act of 1983
and non-applicability of provisions of Act of 1996 is no more
res integra.
Placing reliance in the matter of M.P. Rural
Road Development Authority Vs. L.G. Choudhary, (2012) 3
SCC 495 para 46 wherein it has been held that the M.P. Act
1983 assent of the President to the Act had been received on
17.10.1983
Gazette
which was published in the Madhya Pradesh
Extraordinary dated
12.10.1983
and
after the
requirement of Article 254 (2) of the Constitution was satisfied.
Thus, M.P. Act of 1983
prevails in the State of Madhya
Pradesh, thereafter Arbitration and Conciliation Act, 1996 was
enacted by Parliament repealing the earlier laws of Arbitration
of 1940 and also the Act of 1996 saves the provisions of M.P.
Act 1983 under sub-sections 2 (4) and 2(5) thereof, therefore,
there cannot be any repugnancy and the contention of the
applicant that the Act of 1983 is against the spirit of Arbitration
and Conciliation Act, 1996
and the law laid down by the
Hon'ble Supreme Court is misplaced and liable to be rejected.
23.
With regard to the applicability of the ICADR Rules
adopted in Clause 11.2 it was argued
that the institution
ICADR has been acquired by the New Delhi International
Arbitration Centre (NDIAC) with effect from 23.7.2019 vide
the New Delhi International Arbitration Centre Act, 2019 and
since as on the date of commencement of Arbitration
Proceedings in the present case that is vide alleged notice dated
13.9.2021 ICADR
had already been
existence, the Rules of ICADR
taken over and lost
cannot
be said to be in
existence and the parties have never chosen arbitration under
NDIAC nor the law binds them to have arbitration under
NDIAC on abolition of ICADR. On the strength of the above
arguments it was submitted that the present petition deserves to
be dismissed
and applicant is required
to be directed to
approach the Arbitration Tribunal under the Act of 1983.
24.
Heard the learned counsel for the parties and perused the
record.
DISCUSSION:
25.
It is first required to analyze clause 2.2 of the concession
agreement which is reproduced hereinbelow:
“2.2 Grant of Concession
(a) Subject to and in accordance with the terms
and conditions set out in this Agreement, the
Authority hereby irrevocably grants to
Concessionaire exclusive right, license and
authority, during the Concession Period i.e. 21
years from the appointed date to plan, construct,
operate and maintain the Project (the
"Concession") and the Concessionaire hereby
accepts the Concession and agrees to implement
the Project subject to and in accordance with the
terms and conditions set forth herein:
(b) Subject to and in accordance with the
provisions of this Agreement, the Concession
hereby granted shall oblige or entitle (as the
case may be) the Concessionaire i. To investigate, study, design, engineer,
procure, finance, construct, operate and
maintain the Project Facilities
ii. To exercise and/ or enjoy the rights, powers,
benefits,
privileges,
authorizations
and
entitlements granted under this Agreement
including undertaking of activities defined in
Scope of Work in Clause 2.1;
iii. Right of Way, access and license to the Site
for the purpose of and to the extent conferred by
the provisions of this Agreement;
iv. To receive and appropriate, funds for
Construction Works from the Authority as per
Schedule 16: Disbursement Schedule;
v. To receive and appropriate, Tipping Fee and
other considerations for implementation of the
Project in accordance with this Agreement;
vi. Commitment from M. P. Power Management
Company for purchase of electricity generated
from waste to energy plant at a levelized tariff
@ Rs. 6.39/Unit,
vii. To perform and fulfill all the obligations
under and in accordance with this Agreement;
viii. To bear and pay all costs, expenses and
charges in connection with or incidental to the
performance of the obligations of the
Concessionaire under this Agreement; and
ix. Neither assign, transfer or sublet or create
any lien or Encumbrance on this Agreement, or
the Concession hereby granted or on the whole
or any part of the Project Facility nor transfer,
lease or part possession thereof, save and except
as expressly permitted by this Agreement or the
Substitution Agreement.”
26.
It is also required to analyze
Article 11.2
of the
agreement executed between the parties which provides for
referring the matter to the Arbitrator in the case the dispute is
not resolved between the parties. Article 11.2 (a)
which
pertains to Arbitration is reproduced hereinbelow:
“11. Arbitration.
a. Procedure
Subject to the provisions of Clause 11.1,
any Dispute which is not resolved
amicably shall be finally settled by
binding arbitration under the "Rules of
Arbitration of International Centre for
Alternative Dispute Resolution, New
Delhi (The Rules)". The arbitration shall
be by a panel of three arbitrators, chaired
by commissioner, Urban Administration
and Development Madhya Pradesh, and
one to be appointed by each Party. The
Party requiring arbitration shall appoint an
arbitrator in writing, inform the other
Party about such appointment and call
upon the other party to appoint its
arbitrator. If within 30 days of receipt of
such intimation, the other Party fails to
appoint its arbitrator, the Party seeking
appointment of arbitrator may take further
steps in accordance with Arbitration Act."
27.
From bare reading of Article 2.2 it would be evident that
the said agreement pertains to grant of exclusive right, license
and authority to the Concessionarie during the concession
period from the date of appointment to plan, construct, operate
and maintain
the Project (the Concession)
and the
Concessionaire thereby accepted the Concession and agreed to
implement the Project subject to and in accordance with the
terms and conditions set forth therein and as per the definition
of section 2 (i) of M.P Madhyastham Adhikaran Adhiniyam,
1983 which defines 'Works Contract' which means:
“An agreement in writing for the
execution of any work
relating to
construction, repair or maintenance of any
building or superstructure, dam, weir,
canal, reservoir, tank, lake, road, well,
bridge, culvert, factory, work-shop,
powerhouse, transformers or such other
works of the State Government or Public
Undertaking as the State Government
may, by notification, specify in this behalf
at any of its stages, entered into by the
State Government or by an official of the
State Government or Public Undertaking
or its official for and on behalf of such
Public Undertaking and includes an
agreement for the supply of goods or
material and all other matters relating to
the execution of any of the said works”
and as the present concession agreement includes the
construction of different structure
maintenance, operation etc.
of the project there
it can be said
that the said
concession agreement comes under the purview of definition
of section 2(i) i.e. Work Contract of the Act of 1983.
28.
The Full
Bench of this Court in the case of Viva
Highways (supra) has summarized in conclusion as under:
“82. On the basis of foregoing analysis, we
may summarize our conclusions as under:
(i) If an agreement by whatever name called
falls within the definition of "works
contract" and difference between the parties
is covered in the definition of 'dispute' as
defined under the Adhiniyam of 1983, it has
to be referred for adjudication before the
Tribunal constituted under Section 3 of the
Adhiniyam of 1983.
(ii) In view of statutory provision
of Section 7 of the Adhiniyam of 1983,
even in cases where the parties have
incorporated a clause in such agreement
regarding resolution of dispute by some
other forum or under the Act of 1996, the
forum subject to (i) above, would be the
Tribunal under the Adhiniyam of 1983. This
conclusion, however, will presently not
include the cases of terminated contract,
which aspect is pending consideration
before a Larger Bench of the Supreme
Court. The decision of Larger Bench will
draw the curtains on this aspect.
(iii)
The
judgment
of
Jabalpur
Corridor(Supra) reported in 2014 (2) MPLJ
276 and Ashoka Infraways Ltd.(Supra)
reported in 2016 (2) MPLJ 685 are
overruled.
(iv) The substituted definition of "works
contract" is clarificatory in nature, hence it
will be retrospective in operation.
(v) The words "claim of ascertained money"
have a definite connotation and therefore
only such difference arising out of
execution or non-execution of a 'works
contract' which are related with claims of
above nature will be covered under Section
2(d) of the Adhiniyam of 1983.
29.
So far as repugnation between the Act of 1983 and Act of
1996 is concerned, it was considered by the Supreme Court in
the matter of L.G. Chaudhary (supra)
and later-on when
referred again and decided on 12.3.2018, whereby it was held
by the Hon'ble Supreme Court that in a case of 'Works Contract'
the dispute would be covered under the said Act
of 1983.
Thus, from the above it is clear that in cases where
the
agreement is in the nature of work contract and a dispute arise
out of the said contract the matter is to be referred to the
Arbitration Tribunal as per the provisions of Act of 1983.
30.
The next question which is posed as before this Court is
with regard to binding effect of conditions as contained in the
concession agreement with regard to the reference of the matter
to the authority mentioned therein to the exclusion of the legal
provisions by which the said agreement would be governed.
The applicant in this regard
placed reliance in the matter of
M.P. Road Development Corporation Vs. Ministry of Road,
Transport and Highways (MORT & H) and another, (supra)
wherein it has been held that if despite existence of the
Arbitration Tribunal under the Adhinyam of 1983, the parties
have agreed for arbitration under the aegis of ICADR in
accordance with the ICADR Rules and the Arbitration Act and
consciously did not mention about existence of the arbitration
tribunal established under the Adhiniyam of 1983, which then
was already in existence, the petitioner cannot be permitted now
to raise this plea, which is the ratio decidendi of the judgment,
as while making the said observations the earlier judgments of
the Larger Bench in Viva Highways
(supra)
and L.G.
Chaudhary (supra) were not discussed
nor the judgment
referred to the eventuality in the cases of Works Contract and
as has been held by the Supreme Court in the matter of Central
Board of Dawoodi Bohar Community and another Vs. State of
Maharashtra
and
others,
(supra)
that
a
mere
observation/passing reference, without reason by citing bare
provisions or judgments on the issue, will not be a binding
precedent.
31.
The other judgments cited by the counsel for the applicant
since do not pertains to the said preposition are not required to
be discussed. Hence, on the basis of the above discussion this
Court comes to a conclusion that the agreement in question is
a Works contract
as defined under section 2 (1) of the
Concession Agreement and therefore the matter is required to
be heard by the Arbitration Tribunal as constituted under the
Act of 1983, and therefore, the application under section 11(6)
of the Act is hereby rejected.
(Milind Ramesh Phadke)
Judge
Pawar/-
ASHISH
PAWAR
DN: c=IN, o=HIGH COURT OF MADHYA
PRADESH BENCH GWALIOR, ou=HIGH COURT
OF MADHYA PRADESH BENCH GWALIOR,
postalCode=474001, st=Madhya Pradesh,
2.5.4.20=022bf22fa73f89c6f6d933de1146a290a
49b3c94df18221974589b5a02e0fc6b,
pseudonym=FF3392C76BA2BA90DA179B68AB
DF35708A13E2D2,
serialNumber=45B88E29CF4FECAAA753C8CA8
740AD0DA9C3E498ADE24A066F820E24846008
AE, cn=ASHISH PAWAR
Date: 2023.05.19 12:27:18 +05'30'
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review