IN THE HIGH COURT OF MANIPUR
AT IMPHAL
WP(C) No. 481 of 2020
1. Yumnam Biramadhop Singh, aged about 72 years, S/o (L)
Y. Natum Singh, a resident of Keirak Leirak Achouba, P.O.
Kakching & P.S. Kakching, Kakching District, Manipur,
795103;
2. Thounajam Nongyai Meitei, aged about 60 years, S/o (L)
Th. Amuchou Singh, a resident of Keirak Leirak Achouba,
P.O. Kakching & P.S. Kakching, Kakching District, Manipur,
795103;
3. Elangbam Irobot Singh, aged about 62 years, S/o E. Tombi
Singh, a resident of Keirak Leirak Achouba, P.O. Kakching
& P.S. Kakching, Kakching District, Manipur, 795103.
… Petitioners
-Versus1. The Director General, National Rural Road Development
Agency (NRRDA), Ministry of Rural Development,
Government of India, 5 th Floor, NBCC Tower, Vikaji Cama
Place, New Delhi – 110066.
2. The State of Manipur represented by the Commissioner/
Principal Secretary/ Secretary/ Additional Chief
Secretary (RD & PR), Government of Manipur, Secretariat
Complex, Babupara, Imphal West District, Manipur –
795001;
3. The Chief Engineer, Rural Engineering Department
(RED)/Manipur State Rural Roads Development Agency
(MSRRDA), Government of Manipur, Smart Office
Complex, AT Line, North AOC Imphal, Manipur – 795005;
4. Executive Engineer, Rural Engineering Department
(RED)/Manipur State Rural Roads Development Agency
(MSRRDA), Government of Manipur, Smart Office
Complex, AT Line, North AOC Imphal, Manipur – 795005.
… Respondents
WP(C) No. 481 of 2020
Contd…/-
[2]
B E F O R E
HON’BLE MR. JUSTICE KH. NOBIN SINGH
ORDER
18-12-2020
[1]
Heard Shri B. Prem Sharma, learned Advocate appearing for
the petitioners; Shri Niranjan Sanasam, learned GA for the State
respondents and Shri S. Vijayanand Sharma, learned CGC for the Union
of India.
[2]
The validity and correctness of the order dated 18-07-2020
issued by the Chief Engineer, RED/ MSRRDA, Government of Manipur is
under challenge in this writ petition
[3.1]
According to the petitioners, they are the residents of Wabagai
Leirak Achouba, PO & PS Kakching, Manipur. The construction of a
bridge at Wabagai Leirak Achouba near the wooden bridge was proposed
by the former SE, Rural Engineering Department to be constructed under
PMGSY. After the said SE being promoted, new officials of the RED
suggested another location for construction of the said bridge at a place
between the Banyan trees and the Community Hall/ Mandap/ Club/
Electric Transformer. The grievance of the petitioners is that if the bridge
is constructed at the new location, it will affect the school playground,
where the children are playing, which is also being used as parking for
various ceremonies including marriage ceremonies. On top of that, it will
affect the homestead lands of some of the residents. In support of their
allegations, the petitioners have relied upon the photographs of the old
WP(C) No. 481 of 2020
Contd…/-
[3]
and new locations. In order to show the old proposed site and the new
proposed site, copies of the site plans have been filed as Annexure-A/6
and A/7 which are relied upon by them. Being aggrieved by the change of
location of the bridge, the petitioners submitted a representation dated
14-02-2020 to the Chief Engineer, RED, Government of Manipur who
failed to consider it. But in the month of June, 2020, the contractor started
bringing materials/ machines to constrict the bridge at the new proposed
site.
[3.2]
Being aggrieved by the inaction on the part of the Chief
Engineer, RED, the petitioners filed a writ petition being WP(C) No.289 of
2020 which was disposed of by this Court on 19-06-2020 directing that
the Chief Engineer, RED, Government of Manipur shall consider the
representation dated 14-02-2020 submitted by the petitioners as quickly
as possible within a period of two weeks therefrom.
[3.3]
In compliance with this Court’s order dated 19-06-2020, the
Chief Engineer, RED, Government of Manipur disposed of the said
representation vide its order dated 18-07-2020 which is impugned herein
by the petitioners on the inter-alia grounds that in a meeting held in the
month of September, 2020 at the Social Worker’s Club, the Executive
Engineer, RED who was present, stated that as per his knowledge from
the books, the best place would be the one which was initially proposed
by the State Government, the recording of which could be produced
before this Court; that the Executive Engineer and the Superintending
WP(C) No. 481 of 2020
Contd…/-
[4]
Engineer, RED decided to shift the construction of bridge at the new site
at the pressure of the local clubs; that the new site is not feasible for
construction of the bridge, as it will affect the residents of the area as
mentioned hereinabove and that the order dated 18-07-2020 was issued
by the Chief Engineer, RED without any application of mind misleading
the residents of the area including the petitioners.
[4]
In the affidavit filed by the Chief Engineer, RED, it has been
stated that before the expiry of two weeks granted by this Court for
disposal of the representation, the petitioners filed a writ petition being
WP(C) No.330 of 2020 and during its pendency, the representation was
disposed of. While disposing of the said writ petition, this Court vide its
order dated 21-08-2020 observed that the Court cannot dictate that the
bridge should be constructed in a particular location/ site and that the
same is a matter of experts. This fact has been deliberately concealed by
the petitioners in the present case and therefore, the instant petition
deserves dismissal as not maintainable. Relying upon the decisions
rendered by the Hon’ble Supreme Court in Anand Sharadchandra Oka
Vs. University of Mumbai, (2008) 5 SCC 217, Ayaaubkhan Noorkhan
Pathan Vs. State of Maharastra, (2013) 4 SCC 465, it has been stated
in the affidavit that the petitioners have no locus standi to challenge the
construction of the bridge as well as the impugned order. There is no
question of shifting the site of construction of the bridge and after the
proposal for the construction of the bridge being initiated sometime in the
year, 2015, the officials conducted survey and soil testing. The proposal
WP(C) No. 481 of 2020
Contd…/-
[5]
for the construction of the bridge was considered by the State Level
Committee in its meeting held on 08-12-2017 and its recommendation
was approved and sanction accorded by the Central Government vide its
letter dated 11-01-2018. Tender was floated vide NIT dated 27-10-2018
and the work order dated 26-07-2019 was issued to Shri L. Romesh
Singh for construction thereof.
[5]
On 09-09-2020 when the instant writ petition was listed for
consideration, this Court issued notice to the respondents and the Chief
Engineer, RED was directed to produce the relevant file for perusal by the
Court. On 14-10-2020 when the matter was listed, it was submitted by the
learned Government Advocate that the counter affidavit on behalf of the
respondent Nos.3 & 4 had been filed, although the same was not on
record. On 03-11-2020, the matter was heard and considered on the
issue relating to maintainability of the writ petition and the order thereof
was reserved by this Court.
[6]
At the outset, it is made clear that it is the State Government
or for that matter, the RED, Government of Manipur which has to decide
where the bridge will be constructed, under PMGSY, depending the
advice of the experts. In other words, it is the domain of the State
Government and the Court cannot interfere with it. Moreover, this Court is
not competent to examine the feasibility thereof. That is why this Court
while disposing of the writ petition being WP(C) No.330 of 2020, made its
observation in this regard. In the present case, this Court is concerned
WP(C) No. 481 of 2020
Contd…/-
[6]
only with the limited issue as to whether the RED, Government of
Manipur has shifted the site of the construction arbitrarily, without any
application of mind and without any formal decision being taken thereof,
which is likely to affect the interest of the residents including that of the
petitioners, the school playground etc. In other words, the issue is
whether the act of the RED, Government of Manipur is malafide and
unreasonable as contended by the petitioners.
[7]
Since the issue relating to the maintainability of the writ petition
was raised by the respondents, this Court considered it before going into
the merit of the case. After having heard the learned counsels appearing
for the parties, this Court vide its order dated 19.11.2020 held that the
instant writ petition could not be said to be not maintainable for the
reasons mentioned therein. The allegation of the petitioners was that the
proposed site had been shifted to a new site arbitrarily and without
application of mind which is likely to affect the interest of the residents, for
which they had relied upon the site plans filed herewith as Annexure-A/6
& A/7. In the counter affidavit filed by the Chief Engineer, RED, the
averments made in the petition about the said site plans were not denied.
Moreover, it is nowhere stated therein that the site plans might have been
manufactured by the petitioners to tarnish the image of the RED,
Government of Manipur with malafide intention and that they were not the
ones prepared by their engineers. It may be noted that if the averments
made in the writ petition are not specifically denied by the respondents,
there are decisions of the Hon’ble Supreme Court which have held that
WP(C) No. 481 of 2020
Contd…/-
[7]
the same shall be deemed to have been admitted by the m. In compliance
with this Court’s order dated 09-09-2020, some files were produced
before this Court by the State Government and on perusal thereof, it was
seen that there were no site plan at all. Assuming that the site plans
produced by the petitioners were not the ones prepared by the engineers
of the RED, Government of Manipur, there had to be a site plan which
would indicate the exact site where the bridge would be constructed by
the RED, Government of Manipur. Such a site plan indicating the exact
place of construction except mentioning it generally in the drawings as
Wabagai Leirak Achouba, was not there in the file and it was not clear as
to whether such a site plan was merely found missing from the file or it
had never been prepared by the engineers of the RED, Government of
Manipur. In any case, a site plan is said to be indispensable for the
construction of a bridge and therefore, it was the duty of the RED,
Government of Manipur to produce a copy of the site plan prepared by its
engineer, for perusal by this Court, so that the limited issue involved
herein could be decided at an early date.
[8]
On 03-12-2020, this Court directed the Chief Engineer, RED,
Government of Manipur to produce a copy of the site plan, prepared by
its engineers and matched with the drawings, for the construction of the
said bridge by the next date or alternatively, he might file an additional
affidavit by the next date as to the correctness or otherwise of the site
plans filed by the petitioners as Annexure-A/6 and A/7 in the writ petition
so that the petitioners could be asked to prove them. On 11-12-2020
WP(C) No. 481 of 2020
Contd…/-
[8]
when the matter came up for consideration, it was submitted by the
learned Government Advocate that the site plan had been filed on the
previous day but since the same was not on record, the matter was
adjourned to 18-12-2020 on which it was found that it was not a site plan
as such but a copy of the area shown in the google map.
[9]
The fact that no site plan could be filed by the respondent State
appears to have shown the fact that it was not there in the file which was
placed before this Court for perusal and returned to the Government
thereafter. This was the reason as to why this Court felt that the allegation
that the site of the construction of the bridge had been shifted, appears to
have some merit. A similar case came up before this Court two years ago
wherein a decision was taken by the State Government for construction
of a school probably under SSA at a particular place at Chairen and the
amount was received from the central Government but the school was
constructed at another place. This Court did not interfere with it, as the
construction of the school was already over by then. In the present case,
the construction of the bridge is not yet complete. In the absence of a site
plan and taking advantage of it, there is a probability that the site might
have been shifted. The change of site could not have been possible, if
there was a site plan for the reason that the drawings of the bridge might
have been prepared according to the area located at the site /spot. In any
case, this Court has expressed no opinion on the allegation of the
petitioners because the present case involves disputed question of facts.
WP(C) No. 481 of 2020
Contd…/-
[9]
[10]
When the matter is taken up for consideration, this Court has
expressed its difficulty to decide the issue involved herein in the absence
of the materials as regards the correct facts of the case. Accordingly, it
has been submitted by Shr B. Prem Sharma, learned Advocate appearing
for the petitioners that this petition can be disposed of by issuing an
innocuous order and therefore, the instant writ petition stands disposed of
with the
direction that the
petitioners shall submit
a
detailed
representation to the Chief Secretary, Manipur within a period of ten days
from the receipt of a copy of this order and in the event of such a
representation being received, the Chief Secretary, Manipur shall
consider it within a month from the date of receipt of the said
representation and dispose of the same by issuing a speaking order in
respect thereof.
Copies of this order shall be sent to the learned counsels
appearing for the parties and the Chief Secretary, Manipur through their
WhatsApp/e-mail.
JUDGE
FR / NFR
Victoria
WP(C) No. 481 of 2020
Contd…/-
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review