Vision Distribution Private Limited vs The State of Telangana

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Telangana High Court
Date
6 August 2026
Case No.
WA 794/2026
Result
Dismissed
Bench
Aparesh Kumar Singh, G.m. Mohiuddin
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

5. applicable at prevailing rate at the time of payments_ Payments to the bidder shall be made firough cheques/online.,, taxes A mere perusal of the payrnent schedule shows that the payment is in staggered manner, 90%o of the contract value is to be paid on delivery and successful installation of equipment at site and after verification of such ,l HCJ & G.II,II,') tt 1\,1..19J of2426 itetris h1 r'r1h()'i;re r1 llqcttcv School Education Department, Telangana, rcnrrining lit lu i: lo be paid altel submission of performance ceftificate issuecl b1 the dcparlment ' AT conclucted by TSTS. In case the site is not reac11. 759'n oF the contract value for the said site,'location is to be paid The pa)rnent autholit\ is under an obligation to verify the bidder's statement anci certit_r'rhe arllount to be paid to the bidder after certifying the softu'are ancl hardrr arc .qurplncnts The r.alue of r'' ork shall be decided by the clepartment. -fhc clepartrrent rnay erclude any item certified in a previous certillcate Or. ietluce the propofiion of any item previotLsly certified in any cefiificate in the lrght of the later intbrmation. Paunents shall be admissible after decluciirrg [hc flulher securiil. deposit. Tar Deduction at source. sales tax. 1'o)'alt) antl ,-rtlter tares applicable at the prer aiiing rates The aforesaid palrnent schetlule clearll shou's that the entire amount on successful in…

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

[ 3488 J IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD THURSDAY, THE SIXTH DAY OF AUGUST TWO THOUSAND AND TWENTY SIX PRESENT THE HONOURABLE THE CHIEF JUSTICE SRI APARESH KUMAR SINGH AND HONOURABLE SRI JUSTICE G.M. MOHIUDDIN THE WRIT APPEAL NO: 794 OF 2026 Writ Appeal under clause '15 of the Letters Patent preferred against the order dated 1211112025 in W.P.No.27469 of 2025 on the file of the High Court. Between: Vision Distribution Private Limited, Regd. Office at H-47, Bali Nagar, near Ramesh Nagar Metro Station, New Delhi 1100'15 Represented by its Authorised Representative, Mr Jasthi Sai Mohan Chowdhary ...APPELLANT / PETITIONER AND 1. The State of Telangana, Rep. by its Principal Secretary, School Education Department, Government of Telangana, Saifabad, Khairtabad, Hyderabad 500004 2. The Commissioner and State Project Director, School Education Department, Government of Telangana, B-block 2, Telephone Bhavan Road, Saifabad, Khairtabad, Hyderabad - 500004 3. The [Vlanaging Director, Telangana State Technology Services Ltd., HACA Bhavan, 2nd Floor, Opp. To Public Gardens, 5-10-103/40/206, Nampally, Hyderabad 500004 ...RESPONDENTS l.A. NO: 2OF 2026 Petition under Section 15'1 CPC praying that in the circumstances stated in the affidavit filed in support of the petition, the High Court may be pleased to release the due amount as admitted and recorded in the impugned Order dated 1211112025 passed by the learned single Judge in w.p No 27 469 of 2025 within a period of one week, pending disposai of the writ appeal. Counsel for the Appellant: SRt DAMA SESHADRT NAIDU, Sr. COUNSEL, REp. SRI D.SIVA SANKAR ACHARYA Counsel for the Respondent Nos.1 & 2: SRI T.VENKAT RAJU, GP FOR EDUCATION The Court delivered the following: JUDGMENT IN THE HIGH THE HON,BLE COURT FO] ^ r r rl#tdli." oF TELANGANA THE CHIEF JUS, rHE HoN,BLE sR, t^' APARESH K,MAR rJiT STICE C.M.MOHIUDDIN w RIT APPE AL No DA T ED :06 .0 Between Vision Distribution privare I'hc State ot. I [T,jr.,,,: .79 4o f2 026 8.2 026 Limited Appel lant ANI) elaneana principil srNc, S"c.era.1. ,iffi#:l, t:T;::t.,, JU DG M I]N T: I . . . Respondenb leard Mr. Darna representing Mr. D. Siva Sankar appellant/wri1 peritioner pieader 2. Scshaclri Naidu, fbr r duca,ion an(l ^.,r- r ,'. respondents , l #- a periocr ol.rive earned wri, c.un has : ;",. #; rr,rJ;'.ril:*;*:..,* ryoerabad' by to consider *" ."^,,^^."-^''. of the appellant pending pa-vrnenrs counsel for the Govem,,en, ::::::*^# "ff*_ :" _i fi D recror, Sarnagra senior counser a.tu.yu, r.,, "qrJd' tearned ;::;:,;:::: l/ide <trder under Iei directing the for release of rhe therein in accordance ", ,r,rl:jt:,'"st. with law. rnonths ,ru,r"tto the datc ol-recerpt ol.cop) o[.the within a order. The H(J3l;t'll'' _''J prcserrl appeal (@18')i, oithe ha' hectt prcttrred principal L'earned Se nior 3, thc bl bcing aggrievcd the due aurotint tiom Counsel tbr 29 08 101-l 'l Apex Cotrrt has approirched the direction oi tilc learncd to make the duc in the amottnt became dio n1t the furnished br concernod 'I :::" T".r,,- ,5: '- urit Court' the responclents -.'::::": are under obligatton pa) rne n1s '::::::...;, il:,.::t sttpt \\ithin thc time lbr the respondent scttletl u'ithin that WP No \\ aS l1e\ t]r a :: 27469 the *rittcn instructions behall lor the Stats on ot' interest but the claitn he rr riue tt illstILlcttolls State strbmits ol ol olr the bast s the learricti 'ounscl (io\ ernlllenl the rvhictr the lt is submitted prescnt appeal ttf course disposed be llaid arrd over Therefore' interest br r.108 2026 l.etrnled cotrnsel of l0l5 s'as of due tiom Rs l i 55'48'805/-' accrue up to Cortt t 4. the clairn ol Courts' and other l{igh this Courr in pa)rrents to make the realizrtion' thc melnorandum paragraph 8 oi .uu,r .,,on*usr: rearncd wrir dccisions of intetest the o[ 695 da1's 'a 189'o s'ould principal atnor'rnt non-grant of date till its to the appellant' hcrc is a dela--v ur://J/' that appellant submits clear\) indicated appellant uas According ',vrit appeal ll .t \,,. of thc Icspondent dm ined ' thc pending indicated that timetiatre a specilic l'o pa)'rnerlts could r \\ hich the State relcase the reqtrired budget has becn recl ucsted ro auontion trf lhis Court has beeu drarvn to 'lhe the tertrls anci conditiotls ol'the J HCJ & GMIVT,J tYA No.794 of2025 contract specifically the 'Pa).rnent Schedule' at clause 1l which reads as under "l l. PAYMENT SCHfDULE Pa),ments shall be made to the primary brdder if in case of consortium ot sole bidder as per the following schedule: Payment Schedule S.No Milestone D€scription On Delivery and successful installation of equipmenr at sire and % Pa),rn€nt 90% ofcontEct value after verification of such items by authorized agency,/School Education Tela On Acceptance Test Rernaining l0% of the will be paid afte. submission of performance certifi cate issued by the dept./AT conducted by TSTS. Two Sets of reports to be subrnfied. One set to Bitls division and one set to AT division Incase srte nor ready 75% of the Conrmct value lor that site/location Note: TSTS Shall Process the palment aganst the submission bills for minimum 100 schools. 11.1 Payment Authority The TSTS will make the paymenr as per payment terms and conditlons. l. 2. The Departmenr shall verif, the bidder,s statement and certify rhe amount to be paid to the bidder after certi! the software and hardware equipments. The Value o[work completed shall be decided by the Department. The Department may erclude cny item cinified ln a pre!,tous certificate or reduce the proportion of cny item preriously cenified in any certificate in the Iight of later informanon 3. The payments as admissible shall be made after deducting the tunher security deposit, tax deduction at source (TDS), sales tax, roya"lty and other 4. 5. applicable at prevailing rate at the time of payments_ Payments to the bidder shall be made firough cheques/online.,, taxes A mere perusal of the payrnent schedule shows that the payment is in staggered manner, 90%o of the contract value is to be paid on delivery and successful installation of equipment at site and after verification of such ,l HCJ & G.II,II,') tt 1\,1..19J of2426 itetris h1 r'r1h()'i;re r1 llqcttcv School Education Department, Telangana, rcnrrining lit lu i: lo be paid altel submission of performance ceftificate issuecl b1 the dcparlment ' AT conclucted by TSTS. In case the site is not reac11. 759'n oF the contract value for the said site,'location is to be paid The pa)rnent autholit\ is under an obligation to verify the bidder's statement anci certit_r'rhe arllount to be paid to the bidder after certifying the softu'are ancl hardrr arc .qurplncnts The r.alue of r'' ork shall be decided by the clepartment. -fhc clepartrrent rnay erclude any item certified in a previous certillcate Or. ietluce the propofiion of any item previotLsly certified in any cefiificate in the lrght of the later intbrmation. Paunents shall be admissible after decluciirrg [hc flulher securiil. deposit. Tar Deduction at source. sales tax. 1'o)'alt) antl ,-rtlter tares applicable at the prer aiiing rates The aforesaid palrnent schetlule clearll shou's that the entire amount on successful instaliation of the etluiprrent at site is not palable in one go' The pleadings on recorcl ilo not elarifl.on rh. part of the appellant th3 (lates oldelivery and successful instlllatiort ol the eqtripment at site and the claims made thereupon and also the specific period for r'r'hich the sum dtte remained unpaid. On th!' I)a( ol the responclents. the instructions only refer to the baiance clairu ,rl lls.i.1.71.12.807,- payable to the appellant. The claim of intcrest is 1i6t l'211'11 as per the contractual terms but the date on rvhich any sura becarre dLre and has not been paid in torms of the payment schedule arc quesrio..; or'1act i"hich cannot lre determinecr in writ lLrrisdiction ancr at ) HCI & GMII,J WA No.791of2026 this appellate stage. The claim of interest over the sums unpaid beyond the permissible date are issues which could be raised in a proceeding where questions of fact can be determined on the basis of pleadings and evidence adduced by the parties. The agreement provides for arbitration clause 5.15. Leamed counsel for the appellant has relied upon the decision of the Apex Court in the case of Surya Constructions v. State of Uttar Pradesh and othersr. The operative part of the same is extracted hereunder: "lt is clear, therefore, fiom the aforesaid order dated 22-03.2014 that there is no dispute as to the amount that has to be paid to the appellant. Despite this, when the appellant knocked at the doors of the High Court in a writ petition being writ Crvil No. 2521612014, the impugned judgrnent dated 02.05.2014 dismissed the \riit pehtion stating that disputed questions of fact arise and that the amount due arises out of a contmct. We are afraid the High Court was wholly incorect inasmuch as there was no disputed question of fact. On the contrary, the amount payable to the appellanr is wholly undisputed. Equally, it is well senled that where the State behaves arbitrarily, even in the realm ofcontract, the High Court could interfere under Article 226 of the Constitution oflndia IABL Intemational Ltd and Another v. Export Credit Guarantee Corporation oflndia Ltd. and Others ((2004) 3 SCC 553)1. This being the case and the work having been completed long back in 2009. we direct the Uttar Pradesh Jal Nigam to make the necessary payment within a period of fbur weeks fiom today- Given the long period of delay, inte.est at the rate of 6 per cent per annum may also be awarded." In the instant case, as observed hereinabove, there is no pleading or determination on facts as to the dates from which the sum became due and remain unpaid over which the claim of interest could be granted. As such, we are of the view that though the leamed writ Court has directed pa),rnent of amounts admitted as per the written instructions furnished by the Director of School Education & State Project Director, Samagra Shiksha, Telangana, Hyderabad, since there are no avennents or findings on the issue of interest accruable from the dates on which the sums due to the appellant ' lzorey ro scc ze+ HCJ & G.v;tt,J u:1 .\o.79t oJ2D6 becrrnre niiral:.ie . :i ,r i:,n[i fioI be proper lor this Court in erercise of appellatl.1:risrl,lior ,o rencler any iinding for.granting interest for. Horvever. it cloes not preclude the appellant from raising interest in an appropnate proceeding such as arbitration as prayed the claim of as per clause 5.15 of the agreement entered betrveen the parties. Theiefore. u.e do not find any reason to interfere in the order appeal. Accorcirngly. the instant writ Appeal is dismissed. un,ler There shall be no order as to costs Vliscellaneous applications. if any pencling. shall stand closed //TRUE COPY' SD/. N.SRIHARI DEPUTY RE GISTRAR SECTION OFFICER To, One CC to SRI D.SIVA SANKAR ACHARYA, Advocate [OPUC] Two ccs to GP FoR EDUCATTON, High court for the state of rerangana at Hyderabad [OUT] 3 Two CD Copies BSR TKS HIGH COURT DATED: 0610812026 JUDGMENT ,a' WA.No.794 ot 2026 .ri \, .r/ r'l l'\) 1 .J il,-' t-. t U l; 202 6 \. u,_ \\ DISMISSING THE WRIT APPEAL, WITHOUT COSTS b \ \ \9\ f. * (' I

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All Telangana HC judgments →
LegalFirms.in Directory
Find an advocate for this matter
Dealing with a similar case? Find an advocate who handles this kind of matter on LegalFirms.in.
Find an advocate →