The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
22. 4.2008 demanding among other to stop the construction activities of the Project until a holistic R&R policy of Manipur formulated through participatory process and acceptable to the people of Manipur is framed. However, the Chairman and other official members of the ERC opined that ERC has not been Page 4 entrusted with the task of framing such a policy applicable to the State of Manipur. The ERC has been constituted to review the RR Plan 1998 and recommend for implementation to the villages affected / to be affected due to the construction of Dam of Thoubal Multipurpose Project. viii) The State Government has revised and enhanced Rehabilitation & Resettlement Package for the affected families in respect of construction of residential buildings, dry low cost latrine, granary, rehabilitation grant and grant-in-aid for construction of churches. The revised Rehabilitation & Resettlement Programme has been implemented for Lamlai Khullen as Ramrei Phase-I (95 families) during the year 2008 and resettled at higher altitude within their village. ix) Rehabilitation & Resettlement Packages for Lamlai Mongbung (Kuki) Village (86 families) who left their village during the ethnic clash during 1993 have also been paid during the year 2009. But, the Rehabilitation & Resettlement Programme for the remaining 2 (two) villages namely (1) Chadong and (2) Lamlai Khunou were not implemented due to…
9. That, with reference to Paragraph No. 8 of the Writ Petition, the answering deponent denies the averments made therein, and the same is already explained in the foregoing Paragraph No. 3, 4, 5, 7 & 8 of my Affidavit-in-Opposition. After payment of R.R. Package and preparation of resettlement sites, the authority is duty bound to complete the construction of Thoubal Multipurpose Project within the time bound/stipulated period in the interest of public at large. [8] Therefore, there is substantial compliance of the Rehabilitation and Resettlement Plan, 1998 but Mr. M. Rakesh, learned counsel appearing for the petitioner pleads that Rehabilitation and Resettlement Plan package has not been fully implemented. This is fact in dispute. [9] The petitioner can point out any specific project or facility which has been omitted to be completed in the rehabilitation package to the respondent No. 1 and 3 who shall look into the grievance expressed and take Page 7 remedial measures in respect of the Rehabilitation and Resettlement Plan, 1998, if there is any shortfall in the same. [10] The petitioner is given liberty to highlight this issue by way of memorandum to respondent No. 1 & 3 within 4 (four) weeks from the date of receipt of a copy of this order and decision will be taken by the authority expeditiously. [11] Writ petition stands disposed of as above. Sandeep FR/NFR Page 8
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
Item No. 7
IN THE HIGH COURT OF MANIPUR
AT IMPHAL
W.P. (C) No. 593 of 2015
Mr. Vanreingam Kashung, aged about 36 years, S/O
lateThaoprang Kashung, a resident of Chadong Village,
P.O. & P.S. Litan, Ukhrul District, Manipur.
……. Petitioner
- Versus –
1. The State of Manipur through the Principal Secretary
(IFCD), Government of Manipur, Manipur Secretariat,
P.O. & P.S. Imphal, Imphal West District, Manipur.
2. The Chief Engineer, Irrigation and Flood Control
Department, Government of Manipur, P.O. & P.S.
Imphal, Imphal West District, Manipur.
3. The Deputy Commissioner, Ukhrul District, P.O. & P.S.
Ukhrul, Ukhrul District, Manipur.
…. Respondents
BEFORE
HON’BLE THE CHIEF JUSTICE MR. RAMALINGAM SUDHAKAR
For the petitioner
For the respondents
:
:
Mr. M. Rakesh, Advocate
Mr. Lenin Hijam, Dy. A.G.
Mr. L. Raju, Advocate
Date of Order
:
06.12.2019
ORDER
[1]
Heard Mr. M. Rakesh, learned counsel appearing for the petitioner;
Mr. Lenin Hijam, learned additional Advocate General for the State respondents
and Mr. L. Raju, learned counsel appearing for the respondent No. 2.
Page 1
[2]
The sole petitioner / villager of Chadong Village who engaged in
agriculture, shop attendant, has filed this writ petition primarily seeking the
following prayer :
“(ii) to issue a writ in the nature of Mandamus or any other order or
direction
directing
comprehensive
the
Respondent
Rehabilitation
and
to
implement
Resettlement
full
and
before
the
submergence of the Chadong and other affected villages as a result of
blockage of water flows of Thoubal River by the Mapithel Dam”
[3]
In respect of the Mapithel Dam, the Government of Manipur wanted
to augment the water resources in the State of Manipur and implement medium
and major irrigation projects, lift irrigation projects so as to manage the floods by
construction of dams and drainages etc. The Mapithel Dam of Thoubal
Multipurpose Project was conceived for a 66 meters high and 1074 meters long
as per approval of the Planning Commission of India in the year 1980. If the dam
is to be constructed, it would submerge several near about 11 villages. Since the
villages were likely to be submerged, the Government came up with the
proposal for resettlement of the people whose villages are likely to be
submerged. In paragraph 5 of the writ petition, the petitioner refers to the Expert
Review Committee’s proposal and Rehabilitation and Resettlement Plan, 1998.
Para 5 of the writ petition reads as follows :“5. That the “Expert Review Committee” conducted several exercises for
reviewing the already prepared Rehabilitation and Resettlement Plan.
However, before completing the process of the “Expert Review
Committee” the Respondents have entered into an agreement with the
affected villagers on 24th September 2011. According to the agreement
reached between the parties, the cost of dwelling house including granary,
toilet, kitchen, transportation, rehabilitation for headman and pastor was
Page 2
fixed at Rs. 16,00,000/-. The rehabilitation grant for common villagers like
the present Petitioner was fixed at Rs. 14,00,000/- (Rupees fourteen
lakhs). It has been clearly stated in Para 12 of the agreement that “Other
Terms and Conditions not indicated in the present memorandum of
Agreement but included in the approved Rehabilitation and Resettlement
Plan 1998 shall also apply for rehabilitation and resettlement of the above
two villages”. It means that the 14 lakh compensation was only for House,
Granary, Latrine, Kitchen, transportation and rehabilitation grant.
[4]
It is also pleaded in para 7 of the writ petition that out of about 230
households at Chadong Vilage, some have taken compensation and some
refused to take the compensation. Para 7 reads as follows:
“ 7. That there are more than 230 households at Chadong Village. Some
villagers have taken the compensation amount including the present
Petitioner. However, there are some villagers, who refused to collect the
compensation amount on the ground that the Respondents should
implement a more holistic Rehabilitation and Resettlement Plan at the new
resettlement sites.
[5]
The Rehabilitation and Resettlement Plan also provides for
construction of road, primary health centre, schools etc. According to the
petitioner, some of the measures stated in the Rehabilitation and Resettlement
Plan, 1998 have not been fully implemented. Copy of the Rehabilitation and
Resettlement Plan, 1998 has not been placed in this Court, but there is a
reference to that in para 5 of the writ petition extracted above.
[6]
The writ petition was filed in July, 2015. Reply affidavit of
respondent No. 2 was filed on 21.08.2015. Relevant para 3 reads as follows:
“3. i) 6(six) villages namely, Phayang, Louphong, Lamlai Khullen, Lamlai
Mongbung, Chadong and Lamlai Khunou will be submerged /
displaced due to the construction of Thoubal Multipurpose Project
and at present almost submerged. It is pertinent to mention that 2
(two) villages namely Phayang and Louphong which was directly
affected by the construction of the Dam had been rehabilitated and
Page 3
resettled during 1991 as per the Rehabilitation & Resettlement
Plan 1991 of the State Government after taking their consent and
giving proper compensation.
ii)
Regarding the submergence of 1215 hectare of land which include
595 hectare of forest land, 500 hectare of paddy field and 120
hectare of settlement land, in the upstream of the Dam, a
Memorandum of agreed terms and conditions was drawn up and
signed on 19.6.1993, between the chief/headman, representatives
of the affected villages and representatives of the Government of
Manipur. By specifying the rates of various classes of lands,
properties and other terms and conditions for Rehabilitation &
Resettlement of affected villagers/families, a Rehabilitation &
Resettlement plan was prepared based on the above Memorandum
of Agreed Terms and Conditions and the same was approved by
the Ministry of Welfare, T.D. Division, Govt. of India vide No.
20011/4/97-TDB dated 06.11.1997 and therefore, it is known as RR
Plan 1998.
iii) Accordingly, the Rehabilitation & Resettlement Programme for
Louphong and Phayang had been reviewed and additional
packages had also be paid as Higher Relief Assistance Package
during 2007.
iv)
During 2005, Mapithel Dam affected Villages Organisation
(MDAVO) started demanding for review of the R.R. Plan 1998 by
constituting an Expert Review Committee (ERC)
v)
To bring an amicable solution to the problems of Rehabilitation &
Resettlement Programme for the affected villages, the Govt. of
Manipur constituted an Expert Review Committee (ERC) during
January 2008 with Commissioner (IFC) as Chairman to review the
Rehabilitation & Resettlement Programmes for the affected
families/ villages due to the construction of the Thoubal
Multipurpose Project.
vi)
First meeting of ERC was held on 19.02.2008 and MDAVO
submitted terms of reference (TOR) for review of the existing
Rehabilitation & Resettlement Plan.
(vii) The village representatives walked out in the 5th meeting held on
22.4.2008 demanding among other to stop the construction
activities of the Project until a holistic R&R policy of Manipur
formulated through participatory process and acceptable to the
people of Manipur is framed. However, the Chairman and other
official members of the ERC opined that ERC has not been
Page 4
entrusted with the task of framing such a policy applicable to the
State of Manipur. The ERC has been constituted to review the RR
Plan 1998 and recommend for implementation to the villages
affected / to be affected due to the construction of Dam of Thoubal
Multipurpose Project.
viii) The State Government has revised and enhanced Rehabilitation &
Resettlement Package for the affected families in respect of
construction of residential buildings, dry low cost latrine, granary,
rehabilitation grant and grant-in-aid for construction of churches.
The revised Rehabilitation & Resettlement Programme has been
implemented for Lamlai Khullen as Ramrei Phase-I (95 families)
during the year 2008 and resettled at higher altitude within their
village.
ix)
Rehabilitation & Resettlement Packages for Lamlai Mongbung
(Kuki) Village (86 families) who left their village during the ethnic
clash during 1993 have also been paid during the year 2009. But,
the Rehabilitation & Resettlement Programme for the remaining 2
(two) villages namely (1) Chadong and (2) Lamlai Khunou were not
implemented due to the objection of the revised R&R Package of
2008 by the MDAVO.
xi)
The RR Package is for the construction of new building of 4 (four)
rooms kitchen, granary and latrine and rehabilitation grant. After
taking the RR Package, the affected villagers have to construct
their buildings at the new sites or anywhere as they like. But, the
villagers under the influence of undesirable elements did not
cooperate in handing over the land for resettlement site as well as
in construction of links roads rather they objected directly or
indirectly all the developmental works with threats hand in glove
with undesirable elements. However, the Project Authority has
constructed link roads and resettlement sites after taking the
consent of the village chiefs and under the tight security coverage
for the welfare of the Public at large. Even though, the resettlement
site is ready, no one comes to build their building at the site by
waiting for rainy season to get a reason to delay the construction of
the Dam. All the other facilities such as water supply, Electricity will
be arranged after their buildings have been constructed. So,
blaming to the project authority for water supply and electricity is
baseless. The new site for resettlement at the higher altitude is
their own choice defying the plan of the Project Authority but they
are now claiming for the scarcity of water. But the Department is
going to supply water by transportation for the time being.
Page 5
Necessary arrangement to supply water permanently is being taken
up. There is already electricity connection near the resettlement
site but require upgradation after the construction of their buildings
etc. The construction of Church, community hall should be
constructed by the villagers after taking the compensation amount
which has already been deposited to the D.C. Ukhrul. The
construction of Primary School, Dispensary etc. will be done
simultaneously when the affected villagers have resettled at the
new site, for which necessary land development works have
already completed. As some of the residences of the Chadong
Village have their second home at valley area, they don’t bother for
the new construction of building at the site.
xii) Many affected villagers who had already taken the RR Package
wanted to construct their house at the new site but they are not
allowed by the anti Dam group or undesirable elements on the
ground of distributing the plot in lottery system or on many flimsy
ground.
xiii) The Petitioner who has taken the RR Package long back under
beneficiary No. 189 did not come forward to construct his building
before monsoon but blaming the Project the Project Authority in the
name of water supply and electricity so as to delay the completion
of the Dam.
xiv) The plugging of the Diversion Channel is must as per the
construction schedule of the project under AIBP Funding. The
Project Authority had planned to complete the Rehabilitation &
Resettlement Plan of the Chadong Village, 1 (one) year ahead of
the completion of the Project. The Project Authority has disbursed
the RR Package for the construction of their new building during
2013-14. But, they are playing delaying tactic game not to shift to
the resettlement site in time and to obtain more monetary benefit.
xv) The plugging and filling of earth for the Diversion Channel cannot be
stopped at this juncture as reservoir has already been created
raising water level day by day. Full reservoir level may be achieved
by the end of August or 1st week of September and excess water
will flow over the spillway crest. So, the filing of earth should be
above the crest level by at least 2m in height so as not to be over
trapped the earth filled level otherwise dam may be overtopped
causing catastrophe to the Down Stream villages with serious and
numerous loss of human life, livestock, buildings and properties.
Therefore, there is no possibility for reducing water level or
stopping the ongoing construction of Dam at this stage.”
Page 6
[7]
From the statement made by the petitioner and the
respondents, it is clear that many villagers have already taken the
resettlement compensation and vacated. In this regard, it would be
appropriate to refer to para 8 &9 of the reply affidavit which read as follows:“8.
That, with reference to Paragraph No. 7 of the Writ Petition,
the answering deponent denies the averments made therein. Most
of the affected families have taken the compensation amount
including the present Petitioner except few villagers, as such,
Respondents had already implemented in a maximum holistic
manner regarding Rehabilitation and Resettlement Plan for the new
resettlement site. It is for the Petitioner who had already obtained
the R.R. Package to construct his house at the resettlement site,
only then he may prefer the Writ Petition or ventilate his grievances
if any to the Hon’ble Court or to the appropriate authority. In such
situation, his Writ Petition is premature.
9.
That, with reference to Paragraph No. 8 of the Writ Petition,
the answering deponent denies the averments made therein, and
the same is already explained in the foregoing Paragraph No. 3, 4,
5, 7 & 8 of my Affidavit-in-Opposition. After payment of R.R.
Package and preparation of resettlement sites, the authority is duty
bound to complete the construction of Thoubal Multipurpose
Project within the time bound/stipulated period in the interest of
public at large.
[8]
Therefore,
there
is
substantial
compliance
of
the
Rehabilitation and Resettlement Plan, 1998 but Mr. M. Rakesh, learned
counsel appearing for the petitioner pleads that Rehabilitation and
Resettlement Plan package has not been fully implemented. This is fact in
dispute.
[9]
The petitioner can point out any specific project or facility
which has been omitted to be completed in the rehabilitation package to the
respondent No. 1 and 3 who shall look into the grievance expressed and take
Page 7
remedial measures in respect of the Rehabilitation and Resettlement Plan,
1998, if there is any shortfall in the same.
[10]
The petitioner is given liberty to highlight this issue by way of
memorandum to respondent No. 1 & 3 within 4 (four) weeks from the date of
receipt of a copy of this order and decision will be taken by the authority
expeditiously.
[11]
Writ petition stands disposed of as above.
CHIEF JUSTICE
Sandeep
FR/NFR
Page 8
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review