6. [6] In view of the discussion ussion made hereinabove, the application is allowed. Delay D of 855 days in filing the present review application is hereby condoned, however, the applicant/appellant shall not be entitled to interest for the period for which tthey hey did not approach this Court. Court CM-2236 6-CI-2019 Learned counsel for the applicant/ appellant does not press the e application under Order 41 1 Rule 27 read with Section 151 CPC for adducing additional evidence e. Dismissed as withdrawn. RA-99-CI CI-2018 IN RFA-4002-2002 After hearing learned counsel for the parties and gone through the contents of the review application, the same is allowed in view of the fact that the applicant is entitled for award of similar market value as awarded in in favour of other identically placed landowners pertaining to same acquisition. Order dated 03.11.2015 is hereby recalled and the main appeal is taken up on board today itself. RFA-400 4002-2002(O&M) Both the counsels are ad idem that the issue involved in the present appeal which relates to acquisition pertaining to notification dated 24.07.1997 issued under Section 4 of the Act is 2026.02.23 15:37 I attest to the accuracy and integrity of this document RA-RF-9 99-CI-2018 (O&M) in/and RFA RFA-4002-2002 (O&M) [7] squarely covered by decision dated 21.11.2016 passed by a Coordinate Bench of this Court in Review Application No.17…
2. In view of the above, the present appeal is disposed of in terms of the decision dated 21.11.2016 passed by a coordinate Bench of this Court in Bhim Singh’s case (supra).
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
RA-RF-9
99-CI-2018 (O&M) in/and RFA
RFA-4002-2002 (O&M)
[1]
128(1)
IN THE HIGH COURT OF PUNJAB AND HARYANA AT
CHANDIGARH
*****
CM
M-2236-CI-2019;
CM
CM-3075-CI-2018 IN/AND
RA
RA-RF-99-CI-2018 IN/AND
RFA
RFA-4002-2002 (O&M)
Date of Decision: 1
19.02.2026
United Cold Storage and Ice Factory
…….
…….Applicant/ Appellant
Versus
State of Haryana and ors.
..….Respondents
CORAM:
HON'BLE MR. JUSTICE HARKESH MANUJA
Present:
Mr. Shailendra Jain, Sr. Advocate with
Mr. Rahul, Advocate
for the applicant/ appellant.
Mr. Abhinash Jain, DAG, Haryana.
Mr. Pritam Singh Saini, Advocate with
Ms.Surbhi Rana, Advocate for HSIIDC.
-.-
HARKESH MANUJA, J. (ORAL)
CM-3075
5-CI-2018
Prayer in the present application under Section 5 of
Limitation Act, is for condonation of delay of 855 days in filing the
present review application.
application
2.
Notice of the application stands issued vide order dated
18.03.2019 and in response thereof, learned counsel for HSIIDC had
filed reply.
SANJAY GUPTA
2026.02.23 15:37
I attest to the accuracy and
integrity of this document
RA-RF-9
99-CI-2018 (O&M) in/and RFA
RFA-4002-2002 (O&M)
3.
[2]
I have heard learned counsel for the parties and gone
through the contents of the application
application.
4.
Taking into account
count the fact that the present application
has been filed for seeking review of the order dated 03.11.2015
passed by a Coordinate Bench of this Court, based on order dated
21.11.2016 made in Review Application No.173
No.173-CI-2016 in RFARFA
3520-2006
2006 titled as Bhim
im Singh and ors. Vs. State of Haryana and
anr.,, relating to the same very acquisition proceedings, though
pertaining to other landowners. The judgment dated 03.11.2015 was
reviewed by a Coordinate Bench of this Court with the following
modifications:
modifications:“17.
To sum up, it is held that the for the land
abutting GT Road upto the depth of 880 feet,
the applicants-landowners
landowners shall be entitled to
compensation @ Rs.20,00,000/- per acre,
whereas for the land located beyond that, they
shall
be
entitled
to
compensat
compensation
ion
@Rs.14,00,000/
14,00,000/- per acre. The applicantsapplicants
landowners shall also be entitled to all statutory
benefits available under the Act.”
5.
Therefore, once the other similarly situated landowners
pertaining to the same acquisition proceedings have already been
held entitled for the enhanced amount of compensation pertaining to
Village Kundli to the tune of Rs.20,00,000/
Rs.20,00,000/- per acre for the land
SANJAY GUPTA
2026.02.23 15:37
I attest to the accuracy and
integrity of this document
RA-RF-9
99-CI-2018 (O&M) in/and RFA
RFA-4002-2002 (O&M)
[3]
abutting GT Road upto the depth of 880 feet
feet,, whereas for the land
located beyond that, they shall be entitled to compensation @
Rs.14,00,000/ per acre vide judgment dated 21.11.2016 passed by
Rs.14,00,000/this Court in Review Application No.173
No.173-CI-2016 in RFA-3520
35202006,, titled Bhim Singh and ors. Vs. State of Haryana and anr
anr.
6.
Thus, considering the principle of parity, it would be unjust
in case the present review application filed at the instance of
applicant/ appellant is declined on the ground of delay in filing the
same, as itit would also violate the principles of equity as well as their
claim of fair and just compensation. My aforesaid view is also derived
from a judgment passed by Hon’ble the Apex Court in case of
“Ningappa
Ningappa Thotappa Angadi vs. Special Land Acquisition Office
reported as 2020(19) SCC 599”
599” and also in view of the latest decision
of Hon’ble Supreme Court in Mohar Singh (Dead) through LRs and
ors. Vs. State of Uttar Pradesh Collector and ors
ors.,
., reported as
2023 INSC 1016. Paragraphs 9 to 11 of Ningappa’s case (supra)
(supr
and paragraph 12 of Mohar Singh’s
’s case (supra) are reproduced
hereunder:
hereunder:“Paragraphs 9 to 11 of Ningappa’s case
9. The afore-cited
cited view has been consistently
followed by this Court in a series of cases before and
after the decision in Dhiraj Singh's (dead) case
(supra). In Imrat Lal & Ors. v. Land Acquisition
Collector & Ors., 2014 14 SCC 133, it was observed
SANJAY GUPTA
2026.02.23 15:37
I attest to the accuracy and
integrity of this document
RA-RF-9
99-CI-2018 (O&M) in/and RFA
RFA-4002-2002 (O&M)
[4]
that the
he delay in filing the Special Leave Petition
cannot be the reason to deny just and fair
compensation to the claimants. This Court observed
that a liberal approach should be adopted in such like
matters. In Huchanagouda v. Assistant Commissioner
and Land Acquisition
cquisition Officer, 2019 SCC Online SC
990 also this Court condoned the delay and restored
parity in the matter of grant of compensation though
with a condition ‘that for the period of delay in filing
and in refiling the Special Leave Petitions, the
appellant
ant claimant(s) shall not be entitled to any
interest on the enhanced compensation and statutory
amount.’ 10. It is undeniable that this Court vide
judgment dated November 11, 2016 passed in C.A.
No. 2927/2010 (Ningappa Thotappa Angadi v.
Special Land Acquisition
isition Officer & Anr.) has set aside
the order of the High Court and restored the
compensation as was awarded by the Reference
Court. In the cited case, this Court held as follows:
‘We have heard the learned counsel for the
parties to some length and car
carefully
efully perused the
material on record. We are of the considered opinion
that the impugned judgment and order of the High
Court deserves to be set aside and judgment and
order passed by the Reference Court restored. We
say so because, this Court has in a si
similar
milar appeal
directed against the very same order set aside the
impugned judgment and restored the enhancement
granted by the Reference Court. We see no reason to
take a different view in the present case. We,
accordingly, allow this appeal and while setti
setting
ng aside
the impugned judgment insofar as the same relates to
the appellant, restore the judgment and order passed
SANJAY GUPTA
2026.02.23 15:37
I attest to the accuracy and
integrity of this document
RA-RF-9
99-CI-2018 (O&M) in/and RFA
RFA-4002-2002 (O&M)
[5]
by the Reference Court. The parties shall, however,
bear their own costs.’
11. The appellant(s) are also similarly placed
claimants. They are,, thus, entitled to seek parity and
claim the same amount of fair and just compensation
as has been awarded to other land owners. The
appellant(s) are, however, not entitled to seek interest
for the period for which they did not approach this
Court.”
Singh’s case
“Paragraph 12 of Mohar Singh
12.
Having heard learned Senior Counsel for the
parties and on perusal of the material placed on record,
we are satisfied that the appellants are entitled to seek
parity
with
their
co-villagers
in
the
grant
of
compensation for their acquired land. This Court has
consistently held in a catena of decisions that the
inordinate delay in filing appeal in compensatory
matters, per se, may not be fatal as the rights and
equities between the parties can be well balanced by
denying the statutory benefits, such as interest for the
delayed period. We are thus of the considered opinion
that the delay in filing the first appeal(s) could be
condoned subject to the condition that the appellants
would not be entitled to enure undue benefit for the
delayed period. We grant such indulgence in the
appellant’s favour also for the reason that a batch of first
appeals at the instance of other land owners was still
pending consideration before the High Court. All that the
High Court ought to have emphatically denied to the
late-comers was the benefit of interest including on the
solatium, under Section 34 of the Act for the period from
the date of passing of the award by the Reference Court
till the filing of the first appeals.”
SANJAY GUPTA
2026.02.23 15:37
I attest to the accuracy and
integrity of this document
RA-RF-9
99-CI-2018 (O&M) in/and RFA
RFA-4002-2002 (O&M)
6.
[6]
In view of the discussion
ussion made hereinabove, the
application is allowed. Delay
D
of 855 days in filing the present review
application is hereby condoned, however, the applicant/appellant
shall not be entitled to interest for the period for which tthey
hey did not
approach this Court.
Court
CM-2236
6-CI-2019
Learned counsel for the applicant/ appellant does not
press the
e application under Order 41
1 Rule 27 read with Section 151
CPC for adducing additional evidence
e.
Dismissed as withdrawn.
RA-99-CI
CI-2018 IN RFA-4002-2002
After hearing learned counsel for the parties and gone
through the contents of the review application, the same is allowed in
view of the fact that the applicant is entitled for award of similar
market value as awarded in
in favour of other identically placed
landowners pertaining to same acquisition. Order dated 03.11.2015 is
hereby recalled and the main appeal is taken up on board today itself.
RFA-400
4002-2002(O&M)
Both the counsels are ad idem that the issue involved in
the present appeal which relates to acquisition pertaining to
notification dated 24.07.1997 issued under Section 4 of the Act is
SANJAY GUPTA
2026.02.23 15:37
I attest to the accuracy and
integrity of this document
RA-RF-9
99-CI-2018 (O&M) in/and RFA
RFA-4002-2002 (O&M)
[7]
squarely covered by decision dated 21.11.2016 passed by a
Coordinate Bench of this Court in Review Application No.173--CI2016 in RFA-3520-2006, titled Bhim Singh and ors. Vs. State of
Haryana and anr.
anr
2.
In view of the above, the present appeal is disposed of in
terms of the decision dated 21.11.2016 passed by a coordinate
Bench of this Court in Bhim Singh’s case (supra).
3.
It is, however, made clear that the appellant shall not be
entitled to interest for the period for which it did not approach this
Court.
4.
Pending misc. application(s), if any, shall also stand
disposed of.
19.02.2026
.02.2026
sanjay
(HARKESH MANUJA)
JUDGE
Whether speaking/reasoned?
Whether Reportable?
SANJAY GUPTA
2026.02.23 15:37
I attest to the accuracy and
integrity of this document
Yes/No
Yes/No
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review