IN THE HIGH COURT OF DELHI AT NEW DELHI
%
Judgment reserved on: 27.03.2026
Judgment pronounced on: 04.04.2026
+
O.M.P. (COMM)
14396/2023
UNION OF INDIA
289/2023,
Through:
I.A.
14392/2023
&
I.A.
.....Petitioner
Mr. Rakesh Kumar, SPC with
Mr. Sunil, Adv.
versus
M/S ANAND AND COMPANY
Through:
.....Respondent
Mr. Kunwar Chandresh, Ms.
Poonam Prasad, Mr. Divyansh
Singh & Mr. George Lincoln,
Advs.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
JUDGMENT
1.
This petition is filed under Section 34 of the Arbitration and
Conciliation Act, 1996 (for short „the Act‟) challenging the arbitral
award dated 17.02.2023.
2.
The facts in brief are that the petitioner invited an e-tender for
construction of hundred Family Quarters (Type-II, III & IV) including
internal W/S, S/I and electrical works for ITBP 22nd Bn. Campus at
Chhawla, New Delhi. The bid of the respondent was accepted and a
Letter of Acceptance (for short „LOA‟) dated 20.06.2017 was issued.
An agreement (02/EE/AIMSPD/2017-18) was executed between the
parties to the lis. The stipulated date of commencement was
11.07.2017 and the time period for completion was twelve months i.e.
O.M.P. (COMM) 289/2023
Signed By:CHANCHAL
17:01:08
10.07.2018.
2.1
During execution of the contract, disputes arose between the
parties. The respondent approached the Engineer-in-Charge of CPWD
(hereinafter „EE‟) but the disputes were not resolved. Clause 25 of the
General Conditions of Contract (hereinafter „contract‟) was invoked
for forming a Dispute Resolution Committee (for short „DRC‟). On
failure to do the needful the respondent by notice dated 08.04.2021
initiated arbitration proceedings which culminated in the impugned
award.
3.
Learned counsel for the petitioner contends that the arbitrator
erred in directing the release of Rs.35,12,328/- withheld for failure of
the respondent to achieve the milestones. The submission is that
extension of time and rescheduling of milestones are two distinct
aspects. Moreover, extension of time is to be granted by the EE
whereas rescheduling of milestones is to be done by the
Superintending Engineer, CPWD (for short „SE‟). The respondent
failed to apply for rescheduling of the milestones under clause 5.3 of
the contract and in case of non-achievement of the milestones the
petitioner was entitled to withhold the amount to the extent of ten
percent of the tender value. Clause 2 of the contract is relied upon to
challenge the award of interest on the withheld amount.
3.1
It is submitted that there is a clerical error in awarding the
amount of Rs.71,45,578/- on account of release of pending final bills
and while doing so the amount already paid was not deducted.
3.2
The awarding of three percent difference on account of
O.M.P. (COMM) 289/2023
Signed By:CHANCHAL
17:01:08
difference between the Goods and Services Tax (for short „GST‟) and
Value Added Tax (for short „VAT‟) is canvassed to be based upon
assumed calculation and contrary to clause 38 of the contract where
under the GST paid is to be reimbursed. The arbitrator erred in
awarding the difference of three percent without proof that it was
deposited.
3.3
The refund of Rs.3,00,000/- penalty imposed for delay in
completing the sample flat is stated to have been allowed without
recording reasons and ignoring the terms and conditions of the
contract. Neither there was a provision for extending the time for
completion of the sample flat nor the time was extended.
3.4
The grant of loss of on-site and off-site expenses for the
prolongation period is stated to be against Section 73 of the Indian
Contract Act, 1872 (for short „Contract Act‟) and the law laid by the
Supreme Court in Kailash Nath Associates v. DDA, (2015) 4 SCC
136 and Unibros vs. All India Radio, 2023 SCC OnLine SC 1366.
The argument is that there was no proof of actual loss or damage
suffered and the arbitrator without any basis apportioned the expenses
depicted in the certificate issued by the Chartered Accountant (for
short „CA‟) and awarded the damages.
3.5
The interest awarded at the rate of nine percent is contended to
be on the higher side. The costs awarded of Rs.8,00,000/- to the
respondent are assailed being on the higher side and contrary to the
terms of the contract providing that the arbitration costs shall be
equally borne by both the parties.
O.M.P. (COMM) 289/2023
Signed By:CHANCHAL
17:01:08
4.
Per contra the delay in achieving the milestones was
attributable to the petitioner and for this reason the time was
repeatedly extended, yet the amount was withheld for nonachievement of the milestones. The contention is that under clause 5.4
of the contract the milestones should have been rescheduled without
filing of an application by the respondent. The award of interest on the
refund of the withheld amount is defended by stating that clause 2 of
the contract is not applicable to the facts of the case.
4.1
It is argued that from 01.07.2017, GST was levied and service
tax thereafter is included in GST. Submission is that clauses 37 and 38
of the contract provided that service tax shall be reimbursed and the
arbitrator rightly awarded the service tax portion of the contract
covered by GST.
4.2
The contention is that the sample flat was to be completed after
two months of casting of first floor slab and the delay in completion
was due to repeated revisions suggested by the petitioner. Moreover,
the petitioner failed to prove the actual loss or injury suffered due to
delay in completion of the sample flat and the arbitrator rightly relied
upon the decisions of the Supreme Court in Kailash Nath Associates
(supra) and Fateh Chand v. Balkishan Dass, 1963 SCC OnLine SC
49 to allow the claim.
4.3
The grant of damages for prolongation of the contract is
defended as having been granted relying upon a certificate issued by
the CA. Contention is that it is admitted position that the work which
was to be completed by 10.07.2018 was actually completed on
O.M.P. (COMM) 289/2023
Signed By:CHANCHAL
17:01:08
05.10.2019 i.e. after delay of 452 days. The submission is that a
reasonable amount in accordance with the settled principles of law
was awarded by the arbitrator.
4.4
The rate of interest and litigation costs awarded is supported by
stating that the discretion exercised by the arbitrator is on a sound
basis and no interference can be made within the restricted scope
under Section 34 of the Act.
5.
Heard learned counsel for the parties at length and perused the
relevant record with their able assistance. No other issue than those
noted above was pressed.
6.
The terms of the contract between the parties provide the time
stipulated for completion of the work and the milestones to be
achieved periodically. Clause 5 of the contract deals with the
extension of time and rescheduling of milestones. Clauses 5.3 and 5.4
of the contract are reproduced below:
“CLAUSE 5
5.3 Request for rescheduling of Mile stones and
extension of time, to be eligible for consideration, shall
be made by the Contractor (As per Appendix XVI) in
writing with supporting documents within fourteen
days of the happening of the event causing delay on the
prescribed form to the authority as indicated in
Schedule 'F'.
5.4 In any such case the authority as indicated in
Schedule 'F' may give a fair and reasonable extension
of time and reschedule the mile stones for completion
of work. Such extension or rescheduling of the
milestones shall be communicated to the Contractor by
the authority as Indicated in Schedule 'F' in writing,
O.M.P. (COMM) 289/2023
Signed By:CHANCHAL
17:01:08
within 3 months or 4 weeks of the date of receipt of
such request with all supporting documents
respectively failing which it will be deemed that
rescheduling of milestones have been approved.
Non application by the contractor for extension of
time/ rescheduling of the milestones shall not be a bar
for giving a fair and reasonable extension/ rescheduling
of the milestones by the authority as indicated in
Schedule „F‟ and this shall be binding on the
contractor.”
7.
It is an admitted fact that the time for completion of the project
was extended from time to time and delay in completion of the work
was not attributed to the respondent. The last extension was granted
up to 15.10.2019 vide letter dated 24.09.2019 and almost after one
year of the last extension of time, the penalty for non-achievement of
the milestones was apportioned from the withheld amount. The
contention of learned counsel for the petitioner that the respondent had
not applied for rescheduling of milestones is factually wrong. The
respondent vide letter dated 23.03.2018 applied for rescheduling of the
milestones to the EE and this letter was forwarded to the SE but was
not decided. Be that as it may, clause 5.4 of the contract provides that
non-filing of an application by the contractor for rescheduling of
milestones shall not be a bar for rescheduling the milestones. The
view taken by the arbitrator that once time was extended from time to
time, the milestones should have been rescheduled is a plausible and
calls for no interference.
8.
So far as the grant of interest on the amount withheld for non-
achievement of the milestones is concerned there is no discussion in
O.M.P. (COMM) 289/2023
Signed By:CHANCHAL
17:01:08
the award and is bereft of reasons. Clause 2 of the contract provides
for withholding of amount on failure of the contractor to achieve
milestones mentioned in schedule „F‟ or the rescheduled milestones in
terms of clause 5.4 of the contract. This amount is to be adjusted
against compensation levied at the time of final grant of extension of
time. The withholding is automatic without notice and in case the
contractor catches up with the progress the amount withheld has to be
released. On failure of the contractor to make up the delay the
amounts mentioned against the subsequent missed milestones shall
also be withheld. Clause 2 of the contract provides that no interest
whatsoever shall be paid on the withheld amount and the condition of
non-payment of interest on the withheld amount has no exceptions.
The granting of interest on the withheld amount is contrary to clause 2
of the contract and cannot be sustained.
9.
The clerical error while directing the release of the amount
pending from the final bill is conceded by the respondent and it is
admitted that the due amount was Rs.54,44,112/-. As there is no
modification of the award involved and it is only a clerical error to be
rectified, claim 2 awarded is corrected to Rs.54,44,112/10.
Clauses 37 and 38 of the contract dealing with the levy of taxes
and the conditions for reimbursement are reproduced below:
“CLAUSE 37
Levy/Taxes payable by Contractor
(i) Sales Tax/VAT (except Service Tax), Building and
other Construction Workers Welfare Cess or any other
tax or Cess in respect of this contract shall be payable
O.M.P. (COMM) 289/2023
Signed By:CHANCHAL
17:01:08
by the contractor and Government shall not entertain
any claim whatsoever in this respect. However, in
respect of service tax, same shall be paid by the
contractor to the concerned department on demand and
it will be reimbursed to him by the Engineer-in-Charge
after satisfying that it has been actually and genuinely
paid by the contractor.
(ii) The contractor shall deposit royalty and obtain
necessary permit for supply of the red bajri, stone,
kankar, etc. from local authorities.
If pursuant to or under any law, notification or order
any royalty, cess or the like becomes payable by the
Government of India and does not any time become
payable by the contractor to the State Government,
Local authorities in respect of any material used by the
contractor in the works, then in such a case, it shall be
lawful to the Government of India and it will have the
right and be entitled to recover the amount paid in the
circumstances as aforesaid from dues of the
contractor.”
“CLAUSE 38
Conditions for reimbursement of levy/taxes if levied
after receipt of tenders
(i) All tendered rates shall be inclusive of all taxes and
levies (except Service Tax) payable under respective
statutes. However, if any further tax or levy or cess is
imposed by Statute, after the last stipulated date for the
receipt of tender including extensions if any and the
contractor thereupon necessarily and properly pays
such taxes/levies/cess, the contractor shall be
reimbursed the amount so paid, provided such
payments, if any, is not, in the opinion of the
Superintending engineer (whose decision shall be final
and binding on the contractor) attributable to delay in
execution of work within the control of the contractor.
(ii) The contractor shall keep necessary books of
O.M.P. (COMM) 289/2023
Signed By:CHANCHAL
17:01:08
accounts and other documents for the purpose of this
condition as may be necessary and shall allow
inspection of the same by a duly authorized
representative of the Government and/or the Engineerin-Charge and shall also furnish such other
information/document as the Engineer-in-Charge may
require from time to time.
(iii) The contractor shall within a period of 30 days of
the imposition of any such further tax or levy or cess,
give a written notice thereof to the Engineer-in-Charge
that the same is given pursuant to this condition,
together with all necessary information relating
thereto.”
11.
Clause 37 of the contract provided that sales tax/VAT shall be
payable by the contractor but service tax paid by the contractor shall
be reimbursed on satisfaction of actual and genuine payment. As per
clause 38 of the contract, the tender rates are inclusive of all taxes
except service tax and in case of any future tax or levy or cess
imposed after the last stipulated date of receipt of tender i.e.
08.05.2017, the tax or levy or cess shall be reimbursed to the extent of
the amount paid. GST would fall within future tax levied after the last
date stipulated for receipt of tender and is to be reimbursed. No
evidence was produced to show that the amount of three percent
difference claimed was actually paid by the respondent. Service tax
was not leviable after the implementation of GST on 01.07.2017. The
arbitrator without any basis made a split of taxes levied under GST
and held that fifteen percent of the forty percent of the work
constituted a component of service tax. The finding is against public
policy as the service tax under Chapter V of the Finance Act, 1994
O.M.P. (COMM) 289/2023
Signed By:CHANCHAL
17:01:08
was repealed upon the introduction of GST with effect from
01.07.2017 and there was no question of service tax being levied
thereafter. The award of claim of Rs.35,12,329/- claimed as a
difference of three percent between the post-GST and pre-GST period
is unsustainable.
12.
The chart forming part of the contract provided for a penalty of
Rs.50,000/- per fortnight for delay in completion of the sample flat. It
is an admitted position that the sample flat was to be completed within
two months of casting of first floor slab and there was delay in
completing the sample flat. The arbitrator considered that the
hindrances causing delay between casting of first floor slab and
construction of the sample flat were not considered by the petitioner
and the respondent was not even given an opportunity to explain the
delay. The reliance was placed upon the decisions of the Supreme
Court in Kailash Nath Associates (supra) and Fateh Chand (supra)
to hold that in the absence of loss due to breach of contract the
imposition of penalty for delay in completion of sample flat cannot be
sustained. It is not a case set up even now that the petitioner had
substantiated the loss due to breach of contract. The view taken by the
arbitrator is plausible and calls for no interference.
13.
The respondent under Section 73 of the Contract Act claimed
loss of on-site and off-site expenses incurred due to prolongation of
the contract period. The law is well settled that for claiming damages
under Section 73 of the Contract Act the claimant has to prove the
actual loss suffered and in case it is not possible to prove loss, a
O.M.P. (COMM) 289/2023
Signed By:CHANCHAL
17:01:08
reasonable amount of damages is to be assessed. Reference is made to
the following judgments:
13.1 The Supreme Court in Unibros (supra) while dealing with a
claim for redressal of loss of profit made under Section 73 of the CA
arising from prolongation of the contract held:
“19. The law, as it should stand thus, is that for claims
related to loss of profit, profitability or opportunities to
succeed, one would be required to establish the
following conditions : first, there was a delay in the
completion of the contract; second, such delay is not
attributable to the claimant; third, the claimant's status
as an established contractor, handling substantial
projects; and fourth, credible evidence to substantiate
the claim of loss of profitability. On perusal of the
records, we are satisfied that the fourth condition,
namely, the evidence to substantiate the claim of loss
of profitability remains unfulfilled in the present case.”
13.2 The Supreme Court in Kailash Nath Associates (supra) held:
“43.6. The expression “whether or not actual damage
or loss is proved to have been caused thereby” means
that where it is possible to prove actual damage or loss,
such proof is not dispensed with. It is only in cases
where damage or loss is difficult or impossible to
prove that the liquidated amount named in the contract,
if a genuine pre-estimate of damage or loss, can be
awarded.”
13.3 The Supreme Court in State of Rajasthan v. Ferro Concrete
Construction (P) Ltd., (2009) 12 SCC 1 held:
“55.While the quantum of evidence required to accept
a claim may be a matter within the exclusive
jurisdiction of the arbitrator to decide, if there was no
evidence at all and if the arbitrator makes an award of
O.M.P. (COMM) 289/2023
Signed By:CHANCHAL
17:01:08
the amount claimed in the claim statement, merely on
the basis of the claim statement without anything more,
it has to be held that the award on that account would
be invalid. Suffice it to say that the entire award under
this head is wholly illegal and beyond the jurisdiction
of the arbitrator, and wholly unsustainable.”
13.4 The Division Bench of this court in Tower Vision India (P)
Ltd. v. Procall (P) Ltd., 2012 SCC OnLine Del 4396 held:
“16. Consequence for breach of the contract are
provided in Chapter VI of the Indian Contract Act,
1872, which contains three sections, namely, section 73
to section 75. As per section 73 of the Indian Contract
Act, the party who suffers by the breach of contract is
entitled to receive from the defaulting party,
compensation for any loss or damage caused to him by
such breach, which naturally arose in usual course of
things from such breach, or which the two parties knew
when they make the contract to be likely the result of
the breach of contract. This provision makes it clear
that such compensation is not to be given for any
remote or indirect loss or damage sustained by reason
of the breach. The underlying principle enshrined in
this section is that a mere breach of contract by a
defaulting party would not entitle the other side to
claim damages unless the said party has in fact suffered
damages because of such breach. Loss or damage
which is actually suffered as a result of breach has to
be proved and the plaintiff is to be compensated to the
extent of actual loss or damage suffered. When there is
a breach of contract, the party who commits the breach
does not eo instanti, i.e., at the instant incur any
pecuniary obligation, nor does the party complaining of
the breach becomes entitled to a debt due from the
other party. The only right which the party aggrieved
by the breach of the contract has is the right to sue for
damages. No pecuniary liability thus arises till the
O.M.P. (COMM) 289/2023
Signed By:CHANCHAL
17:01:08
court has determined that the party complaining of the
breach is entitled to damages. The court in the first
place must decide that the defendant is liable and then
it should proceed to assess what the liability is. But, till
that determination, there is no liability at all upon the
defendant. The courts will give damages for breach of
contract only by way of compensation for loss suffered
and not by way of punishment. The rule applicable for
determining the amount of damages for the breach of
contract to perform a specified work is that the
damages are to be assessed at the pecuniary amount of
difference between the state of the plaintiff upon the
breach of the contract and what it would have been if
the contract had been performed and not the sum which
it would cost to perform the contract, though in
particular cases the result of either mode of calculation
may be the same. The measure of compensation
depends upon the circumstances of the case. The
complained loss or claimed damage must be fairly
attributed to the breach as a natural result or
consequence of the same. The loss must be a real loss
or actual damage and not merely a probable or a
possible one. When it is not possible to calculate
accurately or in a reasonable manner, the actual
amount of loss incurred or when the plaintiff has not
been able to prove the actual loss suffered, he will be,
all the same, entitled to recover nominal damages for
breach of contract. Where nominal damages only are to
be awarded, the extent of the same should be estimated
with reference to the facts and circumstances involved.
The general principle to be borne in mind is that the
injured party may be put in the same position as that he
would have been if he had not sustained the wrong.”
(emphasis supplied)
14.
The only evidence produced by the respondent to support the
claim for damages was a certificate of expenses issued by the CA.
O.M.P. (COMM) 289/2023
Signed By:CHANCHAL
17:01:08
There was no evidence of actual loss suffered due to prolongation of
the contract. The certificate issued by the CA provides year-wise
expenses and head office expenses incurred but there is no
certification as to the quantification of loss suffered if any, due to the
extension of time period of the contract. In other words, there was no
proof of actual loss suffered by incurring additional expenses due to
extension of period of the contract. The expenses incurred after the
stipulated date of completion of the contract in itself are not evidence
of actual loss or damage suffered. It is not the case set up that the
actual loss or damage suffered cannot be quantified. The
quantification of damages by the arbitrator is based on assumptions
and is without any foundation. The compensation awarded is in
violation of Section 73 of the Contract Act and the law laid down by
the Supreme Court and cannot be sustained being against public
policy.
15.
The simple interest awarded at the rate of nine percent by the
arbitrator calls for no interference within the limited scope of
jurisdiction under Section 34 of the Act. No case is made out that the
interest awarded is excessive.
16.
Section 31A(3) of the Act bestows discretion upon the arbitrator
to determine costs considering the facts and circumstances of the case.
A reasonable figure has been quantified by the arbitrator taking into
consideration the various factors calling for no interference.
17.
The Supreme Court in Gayatri Balasamy v. ISG Novasoft
Technologies Ltd., (2025) 7 SCC 1 held that while an arbitral award
O.M.P. (COMM) 289/2023
Signed By:CHANCHAL
17:01:08
cannot be modified under Section 34 of the Act, a severable part of the
award may be set aside. The relevant paragraphs are quoted below:
“32. In the present controversy, the proviso to Section
34(2)(a)(iv) is particularly relevant. It states that if the
decisions on matters submitted to arbitration can be
separated from those not submitted, only that part of
the arbitral award which contains decisions on matters
non-submitted may be set aside. The proviso, therefore,
permits courts to sever the non-arbitrable portions of an
award from arbitrable ones. This serves a twofold
purpose. First, it aligns with Section 16 of the 1996
Act, which affirms the principle of kompetenzkompetenz, that is, the arbitrators' competence to
determine their own jurisdiction. Secondly, it enables
the Court to sever and preserve the “valid” part(s) of
the award while setting aside the “invalid” ones. [The
“validity” and “invalidity”, as used here, does not refer
to legal validity or merits examination, but validity in
terms of the proviso to Section 34(2)(a)(iv) of the 1996
Act.] Indeed, before us, none of the parties have argued
that the Court is not empowered to undertake such a
segregation.
33. We hold that the power conferred under the proviso
to Section 34(2)(a)(iv) is clarificatory in nature. The
authority to sever the “invalid” portion of an arbitral
award from the “valid” portion, while remaining within
the narrow confines of Section 34, is inherent in the
Court's jurisdiction when setting aside an award.
34. To this extent, the doctrine of omne majus continet
in se minus—the greater power includes the lesser—
applies squarely. The authority to set aside an arbitral
award necessarily encompasses the power to set it
aside in part, rather than in its entirety. This
interpretation is practical and pragmatic. It would be
incongruous to hold that power to set aside would only
mean power to set aside the award in its entirety and
not in part. A contrary interpretation would not only be
O.M.P. (COMM) 289/2023
Signed By:CHANCHAL
17:01:08
inconsistent with the statutory framework but may also
result in valid determinations being unnecessarily
nullified.
(emphasis supplied)
18.
The non-awarding of interest on refund of the withheld amount
for non-achievement of the milestones; the rectification of the amount
due for settlement of the final bill; the denial of three percent
difference in post-GST and pre-GST period; and the quashing of
awarding of damages under Section 73 of the Contract Act are
separable, not dependant on other claims awarded and are not
intricately connected with each other.
19.
In view of the above discussion, it is concluded as under:
A. The award directing release of the amount withheld for nonachievement of milestones is upheld.
B. The award of interest on the amount withheld for nonachievement of milestones is set aside.
C. The amount awarded towards the final bill is corrected to
Rs.54,44,112/-.
D. The award of three percent difference between the post-GST
and pre-GST period is set aside.
E. The grant of refund of penalty for delay in completion of the
sample flat is upheld.
F. The award of damages under Section 73 of the Contract Act on
account of prolongation of the contract is set aside.
G. The interest granted except on the amount withheld for nonachievement of milestones and the costs awarded are upheld.
O.M.P. (COMM) 289/2023
Signed By:CHANCHAL
17:01:08
20.
The petition is partly allowed. Pending applications stand
disposed of.
AVNEESH JHINGAN, J
APRIL 04, 2026
‘ha’
Reportable:- Yes
O.M.P. (COMM) 289/2023
Signed By:CHANCHAL
17:01:08
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review