IN THE HIGH COURT OF MANIPUR
AT IMPHAL
WP(C) No. 1066 of 2018
Thingujam Jotendro Singh, aged about 33
years, S/o Th. Bhubon Singh, a resident of Kiyam
Wangma Taba Makha Leikai, P.O. & P.S. Thoubal,
Thoubal District, Manipur – 795138.
……. Petitioner/s
– Versus –
1. The State of Manipur, represented by the Chief
Secretary, Government of Manipur, Old
Secretariat Building, P.O. & P.S. Imphal,
Imphal West, Manipur, PIN-795001.
2. The
Commissioner/Secretary
(DP),
Government of Manipur, Old Secretariat
Building, P.O. & P.S. Imphal, Imphal West,
Manipur, PIN-795001.
3. The
Commissioner/Secretary
Water
Resources,
Government
of
Manipur,
Secretariat Building, P.O. & P.S. Imphal,
Imphal West, Manipur, PIN-795001.
4. The
Commissioner/Secretary
(Works),
Government of Manipur, Secretariat Building,
P.O. & P.S. Imphal, Imphal West, Manipur,
PIN-795001.
5. The
Commissioner/Secretary
(PHE),
Government of Manipur, Secretariat Building,
P.O. & P.S. Imphal, Imphal West, Manipur,
PIN-795001.
6. The Chief Engineer, Water Resource,
Government of Manipur, Khuyathong, P.O. &
WP(C) No. 1066 of 2018
Page 1
P.S. Imphal, Imphal West, Manipur, PIN795001.
7. The Chief Engineer, PWD, Government of
Manipur, Khuyathong, P.O. & P.S. Imphal,
Imphal West, Manipur, PIN-795001.
8. The Chief Engineer, PHED, Government of
Manipur, Khuyathong, P.O. & P.S. Imphal,
Imphal West, Manipur, PIN-795001.
9. The Secretary, Manipur Public Service
Commission, North AOC, Imphal West, P.O. &
P.S. Imphal, Manipur-795001.
…Respondent/s
BEFORE
HON’BLE MR. JUSTICE M.V. MURALIDARAN
For the petitioner/s
:
Mr. I. Denning, Advocate.
For the respondent/s
:
Mr. H. Debendra, GA
Date of hearing &
:
14.11.2019
Order
ORDER
(ORAL)
[1]
This writ petition has been filed by the petitioner seeking writ
of mandamus directing the respondents to provide appointment to
the vacant posts of Assistant Engineer in PWD, IFCD (now Water
Resources) and Public Health Engineering Department more
particularly in one unfilled notified vacancy in the Water Resource
Department, as he has already claimed for such appointment within
WP(C) No. 1066 of 2018
Page 2
the validity period of 18 months of the combined select list dated
18.7.2014.
[2]
The case of the petitioner is that the 9th respondent issued an
Advertisement dated 7.5.2013 calling applications for filling up the
vacant
posts
of
Assistant
Department/Public Health
Engineer
Engineering
for
Public
Works
Department/IFCD (now
Water Resource) on direct recruitment basis. The petitioner applied
the said post. After completion of the written test as well as viva
voce, the 9th respondent notified the combined merit list of the
candidates vide notification dated 18.7.2014. The petitioner's name
was found under the heading “A Civil Engineering" at Serial No.37
with final marks of 442 as General category.
[3]
One of the candidates namely Roshan Kshetrimayum filed
W.P.No.33 of 2014 contending that he is entitled for relaxation of
upper age limit to the extent of the period of continuous service in
the post as Government servants. By an order dated 23.7.2014, this
Court directed the respondents not to fill up one of 41 posts of
Assistant Engineer without leave of the Court. As per the
recommendation of the 9th respondent, 3 candidates were appointed
to the post of Assistant Engineers (Civil) on regular basis and those
WP(C) No. 1066 of 2018
Page 3
3 candidates’ names appeared at Serial Nos.32, 34 and 35, belong
to General category. Further, the candidates whose names
appeared as Serial Nos.33 and 36 who belong to OBC (M) and ST
respectively were also appointed. The petitioner's name appeared at
Serial No.37 under the General category of the said combined merit
list dated 18.7.2014 and all those candidates whose names
appeared above the petitioner were already appointed.
[4]
On 21.12.2015, the petitioner submitted a representation
seeking to extend the validity of the combined merit list dated
18.7.2014 and further to provide appointment against those
vacancies which remained unfilled in any of the Departments
followed with another representation on 7.1.2016. Since the
respondents have not taken action on the representations of the
petitioner, he has filed W.P.No.30 of 2016 and the said writ petition
came to be disposed of by this Court on 30.1.2016 directing the
respondents to consider the representations dated 21.12.2015 and
7.1.2016.
[5]
In the meanwhile, W.P.No.33 of 2014 filed by Roshan
Kshetrimayum
was
allowed
on
6.6.2016
by
directing
the
respondents to offer appointment to him against the unfilled post of
WP(C) No. 1066 of 2018
Page 4
Assistant Engineer which falls under the unreserved category.
Aggrieved by the said order, the 9th respondent preferred W.A.No.59
of 2016. By the judgment dated 13.9.2018, the writ appeal came be
allowed, thereby the order dated 6.6.2016 passed in W.P.No.33 of
2014 was set aside.
[6]
It is stated that those candidates whose names appeared up
to Serial No.36 have already been provided appointment as per the
options exercised by them and those persons whose names
appeared at Serial Nos.32, 34 and 35 of the General category were
appointed recently against the General category. As such, in the
General category, the petitioner's position is next to the candidates
who were already appointed by the appointing authority. If any of the
notified vacancies which remained unfilled for such appointment, it is
the petitioner's turn to be appointed against the unfilled vacancies.
Hence, the petitioner has filed the present writ petition seeking the
above relief.
[7]
The second respondent filed counter stating that as per the
Office Memorandum dated 20.12.1995 issued by the Department of
Personnel & Administrative Reforms, Government of Manipur, all
waiting lists for direct recruitment for which Departmental Promotion
WP(C) No. 1066 of 2018
Page 5
Committees have been held more than a year back shall be deemed
to have been cancelled. The petitioner has submitted his
representation on 21.12.2015 while the DPC result was declared on
18.7.2014 i.e., more than one year back and any representation
submitted after expiry of the DPC need not be considered by the
Government.
[8]
It is stated that it would be wrong on the part of the petitioner
to assume automatic appointment merely on the ground that
persons above him in the merit list have already got appointment
and he is not eligible to fill up in the vacant position. It is further
stated that the petitioner cannot make a claim for the post merely on
the ground that one post still remains unfilled after the disposal of
W.A.No.59 of 2016 by this Court. Hence, prayed for dismissal of the
writ petition.
[9]
The learned counsel for the petitioner submitted that since
similarly situated persons were given appointment in the Department
of Public Health Engineering as per the option exercised by those
candidates from the combined merit list in question. As per the turn
on priority merit basis, one unfilled vacancy is lying in IFC
Department (now Water Resource Department). He would submit
WP(C) No. 1066 of 2018
Page 6
that the petitioner being the next candidate to the candidates who
were already appointed, he is entitled to get appointment to the post
of Assistant Engineer. However, the respondent authorities have not
considered
the
claim
of
the
petitioner
made
through
the
representations and the said representations are still pending
unattended by the respondents.
[10]
Per contra, the learned counsel for the State submitted that
the claim of the petitioner cannot be considered, as the
representation of the petitioner was on 21.12.2015 much after the
DPC result was declared on 18.7.2014 and any representation after
the expiry of DPC, need not be considered by the authorities; The
petitioner is not eligible to fill up in the vacant post and he cannot
take advantage of one post lying vacant.
[11]
I have considered the submissions made by the learned
counsel appearing on either side and also perused the materials
available on record.
[12]
The grievance of the petitioner is that by way of extending the
validity of the select list dated 18.7.2014, the candidates up to Serial
No.35 were appointed in the PHED Department in the General
category. Likewise other candidates of the other categories were
WP(C) No. 1066 of 2018
Page 7
also appointed whose names appeared above his Serial Number on
merit basis. Thus, it is the say of the petitioner that in the General
category, after Serial No.35, his name appeared at Serial No.37. As
such any vacancy of the General category arose, the petitioner is
entitled to be considered for appointment against such vacancy. In
this regard, the petitioner has submitted two representations dated
21.12.2015 and 07.01.2016 to the respondent authorities. Since the
respondent authorities have not considered the representations of
the petitioner, he has filed W.P.No.30 of 2016 before this Court.
[13]
By an order dated 20.01.2016, W.P.No.30 of 2016 came to be
disposed of by this Court. The order of this Court reads thus:
“
Heard Mr. I. Lalitkumar, learned senior counsel for
the petitioner. Mr. N. Ibotombi, learned Additional Advocate
General, Manipur for respondent Nos.1 to 5. Mr. Y.
Nirmolchand, learned counsel for respondent No.6 and Mr.
R.K. Deepak, learned counsel for respondent No.8.
In this petition, the petitioner who has been already
recommended for recruitment to the post of Assistant
Engineer against the vacancy unreserved category has
sought for appointment against the existing vacancy in
any of the departments of PWD, IFCD & PHED.
Mr. I. LaIitkumar, learned senior counsel for the
petitioner submits that the petitioner will be satisfied for
WP(C) No. 1066 of 2018
Page 8
the time being if a direction is issued to the respondents
to consider the representations submitted on 21.12.2015
and 7.01.2016.
In view of the above submissions, which is not
objected to by the learned counsel for the respondents,
the present writ petition is disposed of with the direction to
the
respondents
to
consider
the
representations
submitted by the petitioner on 21.12.2015 as well as
7.1.2016 and pass appropriate speaking order and
intimate the same to the petitioner.
The aforesaid exercise may be completed within a
period of three months.
With the above direction, the writ petition stands
disposed of.”
[14]
Admittedly, the representations of the petitioner have not
been considered and disposed of by the respondent authorities as
directed by this Court. Instead, through counter-affidavit, the second
respondent contended that any representation submitted after the
expiry of DPC, need not be considered by the Government. Nothing
has been produced by the respondent authorities to prove their
contention. When this Court directed the respondent authorities to
consider the representations of the petitioner, it is the bounden duty
WP(C) No. 1066 of 2018
Page 9
of the authorities concerned to obey the orders of this Court and to
pass a speaking order as aforesaid.
[15]
As per the combined recommended select list of the 9th
respondent’s notification dated 18.7.2014 for direct recruitment to
the posts of Assistant Engineer, the petitioner's name appeared at
Serial No.37 under Roll No.0332 in the General category by
securing 442 marks. The petitioner submitted his option in the PWD,
IFCD and PHED respectively on priority of such preferences.
[16]
The learned counsel for the petitioner submits that one seat
was reserved by this Court when a candidate in pursuance to the
Advertisement dated 07.05.2013 challenged the procedure and its
connected orders and the same is still lying vacant and remained
unfilled. He further submits that the petitioner could have been
appointed to such post, but due to operation of the interim orders of
Courts, the present petitioner was not appointed to such vacant
post. One post of Assistant Engineer (Civil) in the unreserved
category for direct recruitment was available in Water Resources
Department is evidenced from the letter of the Chief Engineer, Water
Resources
Department
addressed
to
the
Secretary
(WR),
Government of Manipur.
WP(C) No. 1066 of 2018
Page 10
[17]
The petitioner highlighted the instances in the same selection
procedure arising out of the said Advertisement, wherein some of
the candidates were appointed to the posts of Assistant Engineer in
various Departments after one year or more. The said fact has not
been rebutted and/or disproved by the respondent authorities. In
fact, the Deputy Director, IFC, Government of Manipur issued an
order dated 12.8.2015 whereby consequent upon the resignation of
one K.M. Marem Marino Maring, AE/IFCD with effect from 7.5.2015
appointed one Lunminthang Telien Kom, whose name appears at
Serial No.90 of the overall merit list recommended by the 9th
respondent to the post of Assistant Engineer, Civil, ST. However, in
the case on hand, as stated supra, despite direction of this Court in
W.P.No.30 of 2016, the respondent authorities have not considered
the claim of the petitioner and the plea of the respondent authorities
is that the representation submitted after the expiry of DPC is
without substance.
[18]
It is not the case of the respondent authorities that the
petitioner is not eligible and qualified for the post of Assistant
Engineer. The petitioner, who is eligible and qualified to fill up to the
post in question, is the most deserving candidate amongst the
WP(C) No. 1066 of 2018
Page 11
others after the last candidate who was appointed as Assistant
Engineer in pursuance of the notification dated 18.7.2014.
[19]
The contention of the respondents is that merely because the
name of the petitioner was included in the select list, he would not
get any right to claim appointment as matter of right. In support, the
learned counsel for the respondent authorities relied on the decision
in the case of All India SC & ST Employees' Association v. A. Arthur
Jeen, reported in (2001) 6 SCC 380.
[20]
In All India SC & ST Employees’ Association, supra, the
Hon'ble Supreme Court held:
"10. Merely because the names of the candidates were
included in the panel indicating their provisional selection,
they did not acquire indefeasible right for appointment even
against the existing vacancies and the State is under no
legal duty to fill up all or any of the vacancies as laid down by
the Constitution Bench of this Court, after referring to earlier
cases in Shankarsan Dash v. Union of India, (1991) 3 SCC
47, Para 7 of the said judgment reads thus:
“7. It is not correct to say that if a number of vacancies are
notified for appointment and adequate number of candidates
are found fit, the successful candidates acquire an
indefeasible right to be appointed which cannot be
legitimately
denied.
Ordinarily
the
notification
merely
amounts to an invitation to qualified candidates to apply for
recruitment and on their selection they do not acquire any
WP(C) No. 1066 of 2018
Page 12
right to the post. Unless the relevant recruitment rules so
indicate, the State is under no legal duty to fill up all or any
of the vacancies. However, it does not mean that the State
has the licence of acting in an arbitrary manner. The
decision not to fill up the vacancies has to be taken bona
fide for appropriate reasons. And if the vacancies or any of
them are filled up, the State is bound to respect the
comparative merit of the candidates, as reflected at the
recruitment test, and no discrimination can be permitted.
This correct position has been consistently followed by this
Court, and we do not find any discordant note in the
decisions in State of Haryana v. Subash Chander Marwaha,
(1974) 3 SCC 220, Neelima Shangla v. State of Haryana,
(1986) 4 SCC 268 or Jatinder Kumar v. State of Punjab,
(1985) 1 SCC 122.”
[21]
The petitioner has pointed out that pursuant to the letter
issued by the Under Secretary (IFC) Department, dated 16.9.2014,
23 persons to the posts of Assistant Engineer (Civil) in IFC
Department
were
appointed.
Similarly,
persons
were
recommended to the posts of Assistant Engineer (Civil) in PWD on
regular basis and 22 persons were recommended to the posts of
Assistant Engineer (Civil) in PHE Department. According to the
petitioner, he is eligible for direct recruitment to the post of Assistant
Engineer (Civil), which is available in three Departments. As per the
Advertisement dated 7.5.2013, there are 14 general seats in the
PHED and 13 general seats in the IFCD. Thus, the total number of
WP(C) No. 1066 of 2018
Page 13
seats for the General category for the post of Assistant Engineer
(Civil) is 27 in which the petitioner can be adjusted against the said
27 posts. Out of 14 in PHED, 13 unreserved candidates have been
appointed. Similarly, in IFCD, 12 unreserved candidates have been
appointed to the posts of Assistant Engineers (Civil). Thus, 25 posts
have been appointed as unreserved candidates (General) to those
vacant posts and 2 were to be kept unfilled.
[22]
The petitioner further pointed out that the number of
candidates who were appointed to the posts of Assistant Engineer
(Civil) in the Department of IFCD, PWD and PHED are 23 in IFCD; 7
in PWD and 22 in PHED. Altogether 42 were filled up by appointing
52 candidates in the year 2014 for the post of Assistant Engineer
(Civil) and as per the order dated 30.10.2015, 3 posts were filled in
PHE Department. Thus, the total seats appointed so far by the State
is 55 against the total post of 56 Assistant Engineers (Civil). Thus, 1
post of Assistant Engineer (Civil) remains vacant till now. The
aforesaid number of posts, filling up and the vacant remains unfilled
stated by the petitioner has not disputed by the respondent
authorities.
WP(C) No. 1066 of 2018
Page 14
[23]
According to the learned counsel for the respondent State,
ordinarily the life of a select list is one year and in the absence of
any notification extending the validity of such select list, no
appointment can be directed to be made from such select list. In
support, the learned counsel relied upon the decision in the case of
Man Singh v. Commissioner, Garhwal Mandal, Pauri and others,
reported in (2009) 11 SCC 448.
[24]
In Man Singh, supra, the Hon'ble Supreme Court held:
“14. Mr Krishnamorthi submits that Shri Mohan Lal is no
longer in service. That by itself may not be a ground,
particularly at this distance time, to direct appointment
of the appellant. Recruitment process started in the
year 1995. A select list was prepared. Ordinarily, the
life of a select list is one year. In absence of any
notification extending the validity of such select list, no
appointment can be directed to be made from such
select list.”
[25]
On a perusal of the order dated 25.11.2016 of the
Commissioner (Works) Government of Manipur, it is seen that on
the recommendation made by the 9th respondent, one Yumnam
Robin was appointed to the post of Assistant Engineer (Civil) in
PWD on regular basis by extending the validity of the selection
list/merit list. The said recommendation relates to the very same
WP(C) No. 1066 of 2018
Page 15
Combined Competitive Examination, 2013. Thus, it cannot be
contended by the respondent authorities that the representation
submitted by the petitioner after the expiry of DPC need not
considered by the Government. Since by extending the validity of
the select list, subsequent appointments came to be made by the
respondent authorities, the decision in Man Singh, supra, is not
applicable to the case of the respondents. Moreover, the instances
pointed out by the petitioner in the same selection arising out of the
same advertisement, wherein some of the candidates were
appointed to the posts of Assistant Engineer in various Departments
after one year or more has not been denied by the respondent
authorities.
[26]
Having regard to the submissions made by the learned
counsel for either parties and taking note of the fact that the
petitioner’s name found at Serial No.37 i.e., next to the candidates
who were already appointed and the fact remains that one post of
Assistant Engineer (Civil) in the unreserved category for direct
recruitment is available in Water Resource Department and the
petitioner is suitable for the said post, this Court is of the view that
the grievance of the petitioner is merit acceptance. Accordingly, his
candidature has to be considered by the respondent authorities.
WP(C) No. 1066 of 2018
Page 16
[27]
In the result,
a)
the writ petition is allowed;
b)
the respondent authorities are directed to
appoint the petitioner in the post of
Assistant
Engineer
(Civil)
in
the
Department of Water Resource;
c)
the said exercise shall be done within a
period of 8(eight) weeks from the date of
receipt of a copy of this order.
[27]
No costs.
JUDGE
-Larson
FR/NFR
WP(C) No. 1066 of 2018
Page 17
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review