The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
02. 03.11 gazette notification was made by the Respondents for acquiring 0.50 acres of land appertaining to the aforesaid plot in possession of the claimant petitioner for the purpose of laying down of gas pipe line for the use of Thermal Project in Palatana, Udaipur of the then South Tripura District, now Gomati District as per provision of section 3(1) of the Act and as per provision of Section 5(1)(2) of the Act objection was invited from the claimant petitioner against the aforesaid acquisition and the claimant petitioner submitted objection claiming compensation of Rs. 16,00,000/- for 160 numbers of rubber trees, Rs. 20,000/- for Tube Well and bamboo fencing and Rs. 6,25,000/- as cost of the acquired land. But the competent authority did not consider the aforesaid claim of the claimant petitioner and by order dt. 04.01.12 gave compensation amounting to Rs.1,47,000/- @Rs. 800 and Rs.900/- for 109 and 50 numbers of rubber trees respectively and Rs. 3000/- for the tube well and Rs.12,000/- for the bamboo fencing. The competent authority also gave Rs.4000/- as 10% of the cost of the acquired land. [3] The claimant petitioner being dissatisfied with aforesaid compensation amount claimed Rs.10,000/- x 160 nos of rubber trees = Rs.16,00,000/- and Rs.5,00,000/- per acre for the acquired land. [4] On the other hand the opposite parties contested this case by filing Written Objection an…
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
HIGH COURT OF TRIPURA
AGARTALA
CRP 34 of 2021
1. Oil and Natural Gas Corporation Ltd
Jiban Bharati Building, New Delhi-110001
2. The Chairman-cum-Managing Director
ONGC Ltd., 7th Floor Jiban Bharati Building,
New Delhi-110001
3. The Asset Manager
ONGC Ltd., Tripura Asset, Agartala,
Tripura (West) Pin – 799014
-----Petitioner
Versus
1. Sri Sadhan Debnath
S/O Lt. Mukunda Debnath
Resident of Radhanagar,
PO: Konaban, PS: Bishalgarh,
Dist: Sipahijala
-----Respondent
2. The Competent Authority (RoU),
The Oil & Natural Gas Corporation Limited
Quarter No.B-78,South Colony,
PO- Badharghat, PS-Amtali, Agartala
District-West Tripura, Pin-799014
---Pro-Respondent-Opposite Party
For Petitioner(s)
For Respondent(s)
Date of hearing
Date of pronouncement
Whether fit for reporting
: Mr. R. Dasgupta, Adv.
: Mr. P. Gautam, Adv.
Mr. Raju Datta, Adv.
: 22.03.2022
: 25.03.2022
: No
HON’BLE MR. JUSTICE T. AMARNATH GOUD
Judgment & Order
This is an application under Article 227 of the Constitution of
India against the judgment dated 20.11.2019 passed in Civil Misc (PMP)
38 of 2014 between Sri Sadhan Debnath, Claimant-petitioner and the Oil
and Natural Gas Corporation Limited and 3 others, whereby and
whereunder the learned Additional District Judge, Sipahijala, Bishalgarh,
fixed compensation for 110nos. of rubber trees in question of 8 to 10
years old @ Rs.9000 per tree and 50 nos of rubber trees of 16 to 20
years old @ Rs5000/- per tree. The petitioners also preferred this
application for exercising the supervisory jurisdiction of the Hon’ble High
Court against the Order passed by the learned Additional District Judge,
Sipahijala, Bishalgarh in Civil Misc.(PMP) No.38 of 2014 between Sri
Sadhan
Debnath
claimant-petitioner
and
the
Oil
&
Natural
Gas
Corporation Limited and 3 others respondents, whereby and whereunder
the learned Addl. District Judge, Sipahijal, Bishalgarh fixed compensaton
for 110 nos in question of Rubber Trees for 8-10 years old @ Rs9000/per tree and 50 nos of rubber trees for 16-20 years old @ Rs.5000/- per
tree in violation of the provisions of Petroleum & Minerals Pipelines Act,
1962 (P&MP Act, 1962) and the Petroleum & Minerals Pipelines
(Acquisition of Right of User in Land) Rules, 1962.
[2]
For the sake of brevity the parties are referred to as in the
cause title of Civil Misc (PMP) 38 of 2014. The genesis of the case is that
he is the possessor of the land under plot no.1418(p) under khatian
no.163 of Mouja Radhanagar measuring 0.50 acres of land and he was
enjoying the possession of the land by planting rubber trees and other
valuable trees including fruits by investing good amount of money. On
02.03.11 gazette notification was made by the Respondents for acquiring
0.50 acres of land appertaining to the aforesaid plot in possession of the
claimant petitioner for the purpose of laying down of gas pipe line for the
use of Thermal Project in Palatana, Udaipur of the then South Tripura
District, now Gomati District as per provision of section 3(1) of the Act
and as per provision of Section 5(1)(2) of the Act objection was invited
from the claimant petitioner against the aforesaid acquisition and the
claimant petitioner submitted objection claiming compensation of Rs.
16,00,000/- for 160 numbers of rubber trees, Rs. 20,000/- for Tube Well
and bamboo fencing and Rs. 6,25,000/- as cost of the acquired land. But
the competent authority did not consider the aforesaid claim of the
claimant petitioner and by order dt. 04.01.12 gave compensation
amounting to Rs.1,47,000/- @Rs. 800 and Rs.900/- for 109 and 50
numbers of rubber trees respectively and Rs. 3000/- for the tube well
and Rs.12,000/- for the bamboo fencing. The competent authority also
gave Rs.4000/- as 10% of the cost of the acquired land.
[3]
The claimant petitioner being dissatisfied with aforesaid
compensation amount claimed Rs.10,000/- x 160 nos of rubber trees =
Rs.16,00,000/- and Rs.5,00,000/- per acre for the acquired land.
[4]
On the other hand the opposite parties contested this case
by filing Written Objection and they stated that the compensation for the
aforesaid trees and the acquired land assessed by OP No. 4 was
accepted by the claimant petitioner as adequate, reasonable and
sufficient.
[5]
In view of the pleadings of the parties the following issues
were framed in connection with this case:
1) Is the case maintainable?
2) Is the case barred by Law of Limitation?
3) Is the case bad for non joinder and mis-joinder of
parties?
4) Is the compensation fixed by the competent authority
adequate and proper?
5) Is the petitioner entitled to get enhancement of
compensation; if so, to what extent?
[6]
The claimant petitioner Sri Sadhan Debnath adduced himself
as witness and he submitted examination in chief by affidavit in this case
and he was cross examined by the OP side. The claimant petitioner also
adduced some documents and those were marked as exhibits as follows:
1) Exhibit 1: Copy of Memorandum dt. 3.9.1996 of TFDPC.
2) Exhibit 2: Copy of assessment of compensation of the
rubber plantation of TRPC dt. 29.4.2008.
3) Exhibit 3: Copy of memorandum dt. 5.10.2010 of TRPCL.
4) Exhibit 4: Copy of calculation of capitalized value of a
rubber tree by the TRPCL dt. 02.11.2011.
5) Exhibit 5: Payment order dt. 12.04.11.
6) Exhibit 6: Power of Attorney.
7) Exhibit 7: Letter dt. 11.04.2012 of the Joint Rubber
Production Commissioner Mr. J. C. Das with cost benefit
analysis per rubber tree.
[7]
While deciding the issues No. 1, 2 and 3, the court below has
observed
that
these
three
issues
raises
question
regarding
maintainability of this case on technical ground. The claimant petitioner
fled the application under Section 10 of the Act being dissatisfied with
the compensation granted by the competent authority for damaging the
rubber trees. Section 10 of the Act talks about compensation and it says
that any person who has sustained damaged or loss due to laying down
of
the
pipeline
by
the
competent
authority
is
entitled
to
get
compensation from that competent authority and for such type of matter
the District Judge or equivalent is competent to determine the
compensation due to removal of trees, standing crops etc.
[8]
The OP side failed to adduce any document to substantiate
their contention that the claimant was duly intimated. Although they
adduced Exhibit 1 which is the payment receipt of award to the affected
people and it reveals that the claimant petitioner Sadhan Debnath at
serial No.18 received compensation of Rs.1,47,200/- on 9.1.12 but there
is no signature of the petitioner on the payment receipt. The OP side also
adduced another payment receipt regarding compensation for the
acquired land as Exhibit H and it reveals that the petitioner was given
Rs.4000/- as compensate for the acquired land on 9.1.12 and his
signature is also there but facts remains that as per the provision of Rule
5 of PMP Rules 1963 it is duty upon the competent authority to give
intimation of award to the petitioner in proper way and in the case in
hand no such intimation was given.
[9]
In this regard the Hon’ble High Court while disposing CRP
cases no. 12 of 2016, 142 of 2015, 50 of 2015, 54 of 2015, 54 of 2016
and 59 of 2016 by order and judgment dated. 29.09.2016 in para no. 37
gave specific observation that limitation to file application before the
District Judge for enhancement of compensation in terms of section
10(3) of the PMP Act will commence only on receipt of the limitation.
[10]
Therefore, in the instant case the limitation of 90 days
cannot be taken into consideration as the competent authority did not
give due intimation to the petitioner about the award.
[11]
So far non joinder of party is concerned the including of
ONGC Ltd. a Union Govt concerned as necessary party No.1, & 2
sufficient to hold that the Union Govt was duly made the party in this
case.
[12]
Therefore, it can be safely concluded that the present
application under section 10 of the Act is very much maintainable and it
is not barred by limitation or due to non joinder or mis-joinder of parties.
Accordingly, all the three issues are answered in affirmative.
[13]
While deciding the issues nos. 4 and 5, the court below has
observed that on perusal of the aforesaid documents it is found that the
value of one rubber tree was assessed depending on the age of the tree.
In the aged 8-10 years old and 50 nos. of trees were aged 16-20 years
old. On perusal of Exhibit 7 it is found that the value of a rubber tree
which is aged in between 8-10 years will
approximately be Rs.9000/-
per tree. Similarly a rubber tree aged in between 16-20 years will be
priced at Rs.5000/[14]
Therefore, the rate assessed by the competent authority as
compensation for the rubber tree was on the lower side and the
petitioner is entitled to get compensation @ Rs.9000/- x 110 nos of
rubber
trees
=
Rs.9,90,000/-
and
@
Rs.5000/-
x
trees
=
Rs.2,50,000/-, in total Rs.12,40,000/-.
[15]
So far cost of the acquired land is concerned, it is evident
from Exhibit H that Rs.4000/- @ 10% as cost of the land was given to
the petitioner as compensation and considering the nature and class of
the land as well as the location the court below was of the opinion that
the compensation of Rs.4000/- was adequate and need no enhancement.
Therefore, the issues no. 4 and 5 were also answered in affirmative.
[16]
Finally, by the order dated 20.11.2019, the court below has
observed in the following manner:
The
claimant
petitioner
is
entitled
to
get
Rs.12,40,000/- (Rupees Twelve lakh forty thousand) only
in total. The opposite parties are directed to pay the
aforesaid amount within a period of 45 days from today to
the claimant petitioners and the amount paid if any, shall
be deducted from the total compensation. If the opposite
parties fails to pay the aforesaid
amount within the
stipulated time the amount shall carry interest @ 9% per
annum from the date of expiry of 45 days till deposit of the
amount.
[17]
Aggrieved by the said judgment and order dated 20.11.2019,
the petitioners herein have approached this court filing the instant civil
revision petition.
[18]
Mr. R. Dasgupta, counsel for the ONGC-petitioners argued on
the point of limitation and jurisdiction and unreasonable fixation of
amount of compensation.
[19]
While discussing on the point of limitations, the counsel for
ONGC-petitioners has not placed anything on record to show that on
which date the copy of the award has been served on the claimants and
whether the limitation period of 90 days was within or after in filing of
the claim before the court below. Hence, the point on limitation is
negative.
[20]
While discussing on the point of jurisdiction, this court is of
the view that the District Judge under the Land Acquisition Act, 1984 is
empowered
to
entertain
the
claims
and
passing
an
award
of
compensation. But whereas in pursuant of the notification dated 24 th
July, 2018 the powers have been delegated from all District Judges to all
Additional District Judges for resolving the disputes relating to the
fixation of the compensation.
[21]
Further with regard to the separation of judicial districts this
court is of the opinion that wherever the dispute is falling in the judicial
district of the other judicial district, mere making an argument before
the court in a routine manner that the application cannot be entertained
on the grounds of courts having no jurisdiction cannot be accepted in all
pending cases. The ONGC- petitioners have not placed on record any
orders obtained by high court in the form of transfer of ONGC cases from
one district court to other district court having territorial jurisdiction.
Hence, no case on the point of jurisdiction. The Administrative
instructions of High Court of Tripura in respect of giving additional
responsibilities to lower judiciary is not relevant to the facts of the case
on the point of jurisdiction.
[22]
Hence, this court is of the view that the court below has
rightly assessed the loss sustained by the claimant and fixed fair
compensation.
[23]
In view of the above discussion, the civil revision petition
stands dismissed affirming the order dated 20.11.2019 passed in Civil
Misc (PMP) 38 of 2014 by the District Judge, West Tripura, Agartala.
JUDGE
Dipak
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review