The Oil and Natural Gas Corporation Limited vs Sri Santosh Debbarma and Anr

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Tripura High Court
Date
25 March 2022
Case No.
CRP 49/2021
Result
Dismissed
Bench
T. Amarnath Goud
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

05. 12.2019, the petitioners herein have approached this court filing the instant civil revision petition. [22] Mr. R. Dasgupta, counsel for the ONGC-petitioners argued on the point of limitation and jurisdiction and unreasonable fixation of amount of compensation. [23] While discussing on the point of limitations, the counsel for ONGC-petitioners has not placed anything on record to show that on which date the copy of the award has been served on the claimants and whether the limitation period of 90 days was within or after in filing of the claim before the court below. Hence, the point on limitation is negative. [24] While discussing on the point of jurisdiction, this court is of the view that the District Judge under the Land Acquisition Act, 1984 is empowered to entertain the claims and passing an award of compensation. But whereas in pursuant of the notification dated 24th July, 2018 the powers have been delegated from all District Judges to all Additional District Judges for resolving the disputes relating to the fixation of the compensation. [25] Further with regard to the separation of judicial districts this court is of the opinion that wherever the dispute is falling in the judicial district of the other judicial district, mere making an argument before the court in a routine manner that the application cannot be entertained on the grounds of courts having no jurisdiction…

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

HIGH COURT OF TRIPURA AGARTALA CRP 49 of 2021 1. Oil and Natural Gas Corporation Ltd Jiban Bharati Building, New Delhi-110001 2. The Chairman-cum-Managing Director ONGC Ltd., 7th Floor Jiban Bharati Building, New Delhi-110001 3. The Asset Manager ONGC Ltd., Tripura Asset, Agartala, Tripura (West) Pin - 799014 -----Petitioner-Opposite Parties Versus 1. Sri Santosh Debbarma S/o Lt. Bikram Debbarma, Resident of Konaban, Bishalgarh, PS: Bishalgarh Dist: Sepahijala. 2. Smt. Bishalaxmi Debbarma W/o- Sri Santosh Debbarma Resident of Konaban, Bishalgarh PS: Bishalgarh, Dist: Sepahijala. ---Respondent 3. The Competent Authority (RoU), The Oil and Natural Gas Corporation Limited Quarter No.B-78, South Colony, P.O-Badharghat P.S.-Amtali, Agartala, District- West Tripura Pin-799014 ---Pro-Respondent-Opposite Party For Petitioner(s) For Respondent(s) Date of hearing Date of pronouncement Whether fit for reporting : Mr. R. Dasgupta, Adv. : Mr. P. Gautam, Adv. Mr. Raju Datta, Adv. : 22.03.2022 : 25.03.2022 : No. HON’BLE MR. JUSTICE T. AMARNATH GOUD Judgment & Order This is an application under Article 227 of the Constitution of India against the judgment dated 05.12.2019 passed in Civil Misc (PMP) 01 of 2014 between Sri Santosh Debbarma & another, claimant- petitioner and the Oil and Natural Gas Corporation Limited and 3 others, whereby and whereunder the learned Additional District Judge, Sepahijala, Bishalgarh fixed compensation for 31 nos of Teak Trees @ Rs.2920/- per tree and fixed compensation for 141 nos of Rubber Trees @ Rs.3870/- in question. The petitioners also preferred this application for exercising the supervisory jurisdiction of the Hon’ble High Court against the Order passed by the learned Additional District Judge, Sepahijala, Bishlgarh, in Civil Misc (PMP) 01 of 2014 between Sri Santosh Debbarma and another claimant-petitioner and the Oil & Natural Gas Corporation Limited and 3 others, whereby and whereunder the learned Addl. District Judge, Sepahijala, Bishalgarh fixed compensation for 31 nos of Teak Trees @ 2980/- per tree and fixed compensation for 141 nos of Rubber trees for 12 years @ 3870/- per tree in violation of the provisions of Petroleum & Minerals Pipelines Act, 1962 (P & MP) Act, 1962) and the petroleum & Minerals Pipelines (Acquisition of Right of User in Land) Rules, 1962. [2] For the sake of brevity the parties are referred to as in the cause title of Civil Misc (PMP) 01 of 2014. Brief facts of the present case of the claimant is that the petitioners (respondents No.1 and 2 herein) are the owners and possessors of the land under plot no.201/3160/p of Khatian no.1287 of Moua Konaban measuring 1 acres 60 satak of land since 1980 and they were enjoying the possession of the land by planting rubber trees and other valuable trees including fruits by investing good amount of money. On 06.03.2013 gazette notification was made by the Respondents for acquiring the entire land appertaining to the aforesaid plot in possession of the claimant petitioners for the purpose of laying down of gas pipe line for the use of Thermal project in Palatana, Udaipur of the then South Tripura District, now Gomati District as per provision of Section 3(1) of the Act and as per provision of section 5(1)(2) of the Act objection was invited from the claimant petitioners against the aforesaid acquisition and the claimant petitioners submitted objection claiming compensation of Rs.16,45,500/- for 141 numbers of rubber trees and 31 numbers of Teak trees as well as compensation for the land @ Rs.5,00,000/- per kani but the competent authority did not consider the aforesaid claim of the claimant petitioners and by order dated 03.02.2012 gave compensation amounting to Rs.1,26,000/- @ Rs.800 x 141 nos of rubber trees = Rs. 1,12,800/-, Rs.800/- x 15 nos of Segun Trees = Rs12,000 and Rs.75 x 16 nos of Segun trees = Rs.1200/[3] The claimant petitioner being dissatisfied with aforesaid compensation amount claimed Rs.10,000 x 141 nos of rubber trees = Rs.14,10,000/- and Rs.7500 x 31 nos of Teak trees = Rs.2,25,000/- in total Rs.16,45,500/- only as compensation for the damages to the aforesaid trees. [4] On the other hand the opposite party contested this case by filing written objection and they stated that the compensation for the aforesaid trees assessed by Opposite party No.4 was accepted by the claimant petitioners as adequate, reasonable and sufficient. [5] In view of the pleadings of the parties the following issues were framed in connection with the case by the court below: 1. Is the case barred by Law of Limitation? 2. Is the case bad for non joinder and mis-joinder of parties? 3. Is the compensation assessed by the competent authority adequate and proper? 4. Is the claimant entitled to get enhancement of compensation; if so, to what extent? 5. What other relief or relieves to which the claimant is entitled? [6] The claimant petitioner Santosh Debbarma adduced himself as witness and submitted examination in chief by affidavit in this case and he was cross examined by the OP side. The claimant petitioners also adduced some documents and those were marked as exhibits as follows: Exhibit 1 : Copy of Memorandum dated 3.09.1996 of the TFDPC. Exhibit 2: copy of assessment of compensation of the rubber plantation of TRPCL dt. 29.04.2008. Exhibit 3: Copy of memorandum dt. 5.10.2010 of TRPCL. Exhibit 4: Copy of calculation of capitalised value of a rubber tree by the TRPCL dt. 02.11.2011. Exhibit 5: copy of Notification dt. 22.09.1999 of the Forest Department Govt. of Tripura. Exhibit 6: Letter dt. 11.04.2012 of the Joint Rubber Production Commissioner to Advocate Mr. J. C. Das with cost benefit analysis per rubber tree. Exhibit 7: Khatian No.1282. Exhibit 8 : Payment order dated 26.06.2012. [7] While deciding the issues no.1 & 2 the court below has observed that the claimant petitioners filed the application competent authority for damaging the rubber trees. Section 10 of the Act talks about compensation and it says that any person who has sustained damage or loss due to laying down of the pipeline by the competent authority is entitled to get compensation from the competent authority, and for such type of matter the District Judge or equivalent is competent to determine the compensation due to removal of trees, standing crops etc. [8] Rule 5 of the PMP (Acquisition of Right of user in land) Rules 1963 requires that the application before the District Judge for enhancement of compensation must be filed within 90 days of the receipt of intimation from the competent authority under Rule 4(3) of the aforesaid rules 1963. [9] The court below has further observed by the order dated 05.12.2019 that on bare perusal of the compensation order it is vivid that signature of the claimant petitioner were no taken as a proof that the order was passed in presence of the claimant petitioners. [10] At the same time it is mandatory upon the competent authority to give due intimation to the claimants about the award and from that date onward the period of 90 days will commence. [11] The Opposite party side failed to adduce any document to substantiate their contention that the claimants were duly intimated. There is no document from the side of Opposite party to establish that the petitioners were given a formal intimation about the compensation and as per the aforesaid rules it is mandatory upon the Opposite party side to give a formal intimation. [12] In this regard the Hon’ble High Court while disposing CRP cases no. 12 of 2016, 142 of 2015, 50 of 2015, 54 of 2015, 54 of 2016 and 59 of 2016 by order and judgment dated. 29.09.2016 in para no. 37 gave specific observation that limitation to file application before the District Judge for enhancement of compensation in terms of section 10(3) of the PMP Act will commence only on receipt of the limitation. [13] Therefore, it was further observed by the court below that the limitation of 90 days cannot be taken into consideration as the competent authority did not give due intimation to the petitioner about the award. [14] So far non joinder of party is concerned the including of ONGC Ltd. a Union Government concerned as necessary party No.1, & 2 sufficient to hold that the Union Government was duly made the party in this case. [15] Therefore, it can be safely concluded that the present application under section 10 of the Act is very much maintainable and the case in question is not barred by limitation or due to non joinder or mis-joinder of parties. Accordingly, all the two issues are answered in affirmative. [16] While deciding the issues nos. 3, 4 and 5, the court below has observed that the portion of land in dispute appertains to the plot No.201/3160 under Khatian No.1282 measuring 01 acre 60 satak of land and it was admitted by the opposite party that they issued notification for acquisition of the aforesaid land for the purpose of laying pipeline for the Palatana Project at Udaipur. [17] The opposite party making assessment regarding loss of different types of trees on that land came to conclusion by order dated 22.06.2012 that the claimant petitioners are entitled to get Rs.1,26,000/- in total with the break up of each of the trees as follows: @Rs.800/- 141 nos of rubber trees = Rs.1,12,800/- Rs. 800/- x 15 nos of Teak trees = Rs.12,000/- Rs.75/- x 16 nos of Teak Trees = Rs.1200/[18] The court below has further observed that on perusal of the aforesaid documents it is found that the value of one rubber tree was assessed depending on the age of the tree. In the case in hand the claimant petitioners in their application specifically stated that they started rubber plantation on the acquired land in the year 2001 and the land was acquired in the year 2013 which means that the rubber trees which were damaged were aged more than 12 years. On perusal of Exhibit 4 it is found that the value of a rubber tree which is aged 12 years has been assessed at Rs.3870/- per tree and court below was of the view that this rate is appropriate to compensate the petitioners for loss of his rubber trees during the acquisition. [19] In conclusion the claimant petitioners are entitled to get Rs.3870/- x 141 nos of rubber trees = Rs.5,45,670,/-. They are also entitled to get Rs.2980/- x 31 nos of Teak trees = Rs.92,380/-. Therefore the petitioners are entitled to get Rs.6,38,050/- as compensation. Accordingly, all the issues are answered in affirmative. [20] Finally by the order dated 05.12.2019, the court below has observed in the following manner: The claimant petitioners are entitled to get Rs.6,38,050/- (Rupees Six Lakh thirty eight thousand fifty) only in total. The Opposite Party is directed to pay the aforesaid amount within a period of 45 days from today to the claimant petitioners and the amount paid if any, shall be deducted from the total compensation. If the Opposite Party fails to pay the aforesaid amount within the stipulated time the amount shall carry interest @ 9% per annum from the date of expiry of 45 days till deposit of the amount. [21] Aggrieved by the said judgment and order dated 05.12.2019, the petitioners herein have approached this court filing the instant civil revision petition. [22] Mr. R. Dasgupta, counsel for the ONGC-petitioners argued on the point of limitation and jurisdiction and unreasonable fixation of amount of compensation. [23] While discussing on the point of limitations, the counsel for ONGC-petitioners has not placed anything on record to show that on which date the copy of the award has been served on the claimants and whether the limitation period of 90 days was within or after in filing of the claim before the court below. Hence, the point on limitation is negative. [24] While discussing on the point of jurisdiction, this court is of the view that the District Judge under the Land Acquisition Act, 1984 is empowered to entertain the claims and passing an award of compensation. But whereas in pursuant of the notification dated 24th July, 2018 the powers have been delegated from all District Judges to all Additional District Judges for resolving the disputes relating to the fixation of the compensation. [25] Further with regard to the separation of judicial districts this court is of the opinion that wherever the dispute is falling in the judicial district of the other judicial district, mere making an argument before the court in a routine manner that the application cannot be entertained on the grounds of courts having no jurisdiction cannot be accepted in all pending cases. The ONGC- petitioners have not placed on record any orders obtained by high court in the form of transfer of ONGC cases from one district court to other district court having territorial jurisdiction. Hence, no case on the point of jurisdiction. The Administrative instructions of High Court of Tripura in respect of giving additional responsibilities to lower judiciary is not relevant to the facts of the case on the point of jurisdiction. [26] Hence, this court is of the view that the court below has rightly assessed the loss sustained by the claimant and fixed fair compensation. [27] In view of the above discussion, the civil revision petition stands dismissed affirming the order dated 05.12.2019 passed in Civil Misc (PMP) 01 of 2014 by the Additional District Judge, Sepahijala District, Bishalgarh. JUDGE Dipak

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All Tripura HC judgments →