Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
Serial No. 06
Regular List
HIGH COURT OF MEGHALAYA
AT SHILLONG
Arb.A.No.1/2018 with
MC (Arb.A.) No.1/2018
Date of order: 31.03.2022
State of Meghalaya & ors
Vs. M/s Patel Engineering Private Limited
Coram:
Hon’ble Mr. Justice Sanjib Banerjee, Chief Justice
Hon’ble Mr. Justice W. Diengdoh, Judge
Appearance:
For the Appellants
For the Respondent
: Mr. A. Kumar, Advocate-General with
Ms. S Laloo, GA
Mr. AH Kharwanlang, GA
: Mr. A. Dholakia, Sr.Adv with
Mr. R. Dangwal, Adv
Ms. P. Prakash, Adv
JUDGMENT: (per the Hon’ble, the Chief Justice) (Oral)
The appeal is directed against a judgment and order dated March 29,
2018 on a challenge to an arbitral award dated December 9, 2010 in
proceedings under Section 34 of the Arbitration and Conciliation Act, 1996.
2.
The contract between the parties pertained to the construction of a
dam near Mawphlang. There is no dispute that the work has been completed.
In course of the execution of the contract, the work actually executed deviated
from what was contemplated under the contract in respect of some items of
work. Several clauses in the detailed contract provided for the mechanism to
deal with such a situation. The claims of the respondent contractor in this case
were in respect of the negative deviation in the work relating to three items, in
the sense that in each case a much higher quantum of work was contemplated
than the contractor was actually required to execute.
3.
Three principal grounds have been urged by the State to discredit the
award rendered by a tribunal of three retired High Court judges. According to
the State, the very acceptance of the claim on account of deviation is at
variance with the contract. In other words, the appellants question the authority
of the Arbitral Tribunal to travel beyond the bounds of the contract to
prescribe a remedy that was not contemplated in the contract. The second
count of attack is based on the amendment to Section 28 of the Contract Act,
1872. According to the appellants, the bid was submitted by the contractor in
this case on August 6, 1996 and the acceptance of the bid was communicated
to the contractor on August 20, 1996. On the rudimentary principle of offer
and acceptance and the formation of the contract thereupon, the State contends
that the substantive amendment of Section 28 of the Act of 1872 brought about
on January 8, 1997 would not govern the contractual terms. While on this
aspect, it may be noticed that the contract between the parties was executed on
April 22, 1997, more than three months after the relevant amendment was
incorporated in Section 28 of the Act of 1872. The final ground of challenge to
the arbitral award is in it providing for pendente lite interest despite the
relevant clause in the contract prohibiting the payment of interest on any
account whatsoever.
4.
On the first ground, the appellants refer, in particular, to clause 33 of
the general conditions of contract (GCC) which is intituled as “Deviation”.
Such clause covers various circumstances in which any deviation may occur
from the original design or drawing or the items of work contemplated to be
executed. The four major sub-clauses thereunder chart out the course of action
that would be followed by the parties qua revision of rates and charges as a
consequence of any deviation.
5.
Clause 33.1 permits the engineer-in-charge to call for any deviation
in the original specifications or drawings or the like as may be necessary for
the execution of the work. The clause specifies that such deviation or extra
work or additions or omissions or alterations or substitutions would be deemed
to be an integral part of the contract and it would not do for the contractor to
cite the addition or alteration or variation or omission to not perform the
contract. Clause 33.2 deals with the rates for the items of work as may be
required to be executed due to the deviation called for by the engineer. It is
necessary to see clause 33.2 in its entirety, except the detailed modalities
pertaining to the third limb thereof:
“33.2 The rates for such item of works as are required to be executed
due to deviations, as stated aforesaid shall be payable in the manner
as stated hereunder :
(i)
The rates already provided in the scheduled of
quantities, shall apply in respect of the same item(s) of work to
be executed due to variations.
(ii) The rates of such items, as far as practicable, shall be
derived from the quoted rates of analogous item(s) in the
schedule of quantities after actual observance at site. The
decision to select analogous item(s) shall be taken by the
Engineer-in-charge which shall be conclusive and binding on
the contractor.
(iii) Provided where analogous items are not available in the
schedule of quantities the rates for such items to be executed
shall be determined by the Engineer-in-charge on the basis of
actual analysed cost taking the following into consideration:
…”
6.
As indicated above, the details omitted to be quoted pertain to how,
in terms of clause 33.2(iii) of the GCC, certain parameters are to be taken into
account to ascertain the rates for such deviated items of work for which there
is nothing analogous in the agreed schedule of quantities to go by.
7.
It is also necessary to see amended clause 33.4 of the GCC as has
been set out at internal page 9 of the award under challenge:
33.4 (After amendment):“Both parties agreed that the contract rates shall be valid upto a
variation of + or – 30% (plus or minus thirty percent) of the
scheduled quantities of items in Schedule of Quantities as stipulated
in the tender documents with corrections agreed to during pre-bid
meeting stands. However, the last sentence that “No claim on
account of (-) minus variation in contract shall be entertained “is not
meaningful in view of the statement agreed at pre-bid meeting.”
8.
For the completeness of the discussion on such aspect, it may be
noticed that initially the relevant clause did not provide for additional payment
to the contractor for any negative deviation in any executed item of work, in
the sense that the contractor would be entitled to additional payment if there
was any positive deviation (extra work) above 30 per cent of the scheduled
work, but the contractor could not claim any additional amount for any
negative deviation (less work) in any executed item of work. This was later
modified to incorporate the additional charges to be applicable if the extent of
the deviation in the executed work was either above 30 per cent of the work
originally envisaged or even above 30 per cent less than the work originally
envisaged in respect of the particular item. Also, as a consequence of the
amendment, the embargo on the additional payment being claimed for
negative deviation stood removed as will appear from last three lines of the
amended clause above.
9.
According to the contractor, in respect of the three items of work, the
actual execution of work fell woefully short of the original quantum envisaged
under the contract. Accordingly, a claim was fashioned as per the table below:“Sl.No.
Description of Item
1.
Drilling holes of
minimum 75 mm dia
vertical or inclined in
all formation of
rock/concrete
by
rotary
method
including washing
with air and water
under pressure for
core drilling.
2.
M-15
Quantity
as
per
Schedule
of
Quantities
1430 M
[Schedule
Item
No.4.3.1
(a) + (b)]
Quantity
actually
executed
Quantity
Variation
executed
Limit
in % of
BOQ
Actual
Variation
145 M
10.14%
30%
89.86%
(+ plus or (-)
minus )
Minus
Variation
controlled 59100 M3
38864.08
65.76%
30%
34.24%
3.
10.
concrete with max
mm
size
aggregate for nonoverflow
section,
spillway
section,
bucket, training wall,
concrete
gravity
section (Zone C-1 as
indicated in the
drawing)
M-20,
controlled
concrete with 20 mm
max
size
of
aggregate
for
spillway
bridge
slabs, beam, parapet
and kerbs (Zone C-6
as indicated in the
drawing)
(Schedule
4 M3
(+ plus or (-)
minus )
Minus
Variation
Item No.
8.1.2)
650 M3
185.886
(Schedule M3
Item No.
8.1.3)
28.60%
30%
(+ plus or
Minus)
71.40%
(-)
Minus
Variation”
In respect of the deviation aforesaid, the contractor claimed a total
amount of Rs.4,47,45,787.00/- in principal as per a further table incorporated
in the statement of claims as follows:
“Item
No.
4.3.1
8.1.2
8.1.3
11.
Rate as
Per
Agreement
per M3
Rs. 2, 750
Rs. 2, 163
Rs. 3, 500
Rate
claimed by
Claimant
per M3
Rs. 5, 200
Rs. 3, 261
Rs. 12, 742
Quantity
In M3
Amount due
in Rs.
145.00
3,55,250.00
38864.08 4,26,72,764.00
185.86
17, 17,773.00
Total Rs. 4,47,45,787.00”
In dealing with such head of claim, the Arbitral Tribunal noticed that
there was no formula which was prescribed in the contract in respect of the
deviation of work greater than 30 per cent of the work originally envisaged,
whether on the negative or on the positive side. Clearly, such opinion of the
Arbitral Tribunal is unimpeachable as clause 33.4, indeed, does not provide for
a mechanism for calculation of the additional costs on an account of the vast
deviation in the execution of any item of work from what may have been
originally envisaged in respect thereof.
12.
The contractor reasoned before the Arbitral Tribunal that since the
price payable for the additional items of work which the contractor had to
execute in terms of the contract and at the behest of the engineer would have to
be determined in terms of clause 33.2 of the GCC, a similar basis for
ascertaining the additional payment that the contractor would be entitled to
should apply to the instances of deviation of more than 30 per cent in the
actual execution in respect of any item of work, whether on the negative or the
positive side. The contractor further claimed before the Tribunal that since
there could be no analogous or comparable work for the purpose of
determining the additional costs to be paid for the negative deviation of more
than 30 per cent in respect of any item of work, the assessment had to be made
in accordance with the guidelines and parameters detailed in the third limb of
clause 33.2 of the GCC.
13.
In discussing the claim, the Arbitral Tribunal first noticed the
amendment to clause 33.4 and, after a detailed discussion on the aspect, agreed
that the parameters in clause 33.2(iii) may have to be applied for determining
the rates that the contractor would be entitled to on account of any major
deviation in the work. In essence, the Arbitral Tribunal held that when a
contractor had quoted the rates upon anticipating a certain quantum of work to
be executed, if the actual quantum of work executed was much less than what
had been originally bargained for, the contractor had to be compensated on
account of mobilising extra men, masons, machines, equipment and material to
execute the larger chunk of work specified in the contract.
14.
The Arbitral Tribunal then observed that the uncovered costs had
also to be spread over the executed quantity and that would be the appropriate
approach. It was an aspect that the Arbitral Tribunal, in the backdrop of the
wide words of the arbitration clause in this case, was empowered to adjudicate
on and the same cannot be called into question in the limited scope of judicial
review available under Section 34 of the said Act.
15.
It must be appreciated, at this stage, that the appellants here have
challenged the award of the amount as claimed by the contractor both in
principle and as to the quantum awarded. As to the underlying basis for the
head of claim, the further contention of the appellants is that since clause 33.2
indicated how the rate of additional or altered work had to be determined, the
Arbitral Tribunal ought to have confined itself to such clause for the purpose
of determining, if at all, whether the contractor was entitled to any additional
sum. The State refers to the award and the reliance therein on the rates in such
regard determined by the Central Water Commission and the award is assailed
on the ground that the Arbitral Tribunal took irrelevant considerations into
account by seeking to apply the CWC guidelines pertaining to deviation rather
than confining the determination to within the scope of the contractual terms.
16.
The State’s contention in such regard is completely flawed. It is
evident from the award that the Assistant General Manager of the contractor
was examined in course of the arbitral reference and such official asserted that,
“the respondents had referred to the claims of the claimant in respect of
positive variation and extra works for fixation of rates to Central Water
Commission and new rates were arrived at by the respondents and the Central
Water Commission relying upon the guidelines of the Central Water
Commission on River Valley Projects ...”.
17.
The arbitral award went on to observe that the evidence of the
concerned official “virtually remains unassailed”. The Arbitral Tribunal then
reasoned as follows:
“... The crux of the argument of ... learned counsel for the
respondents centered around the question of payment of
compensation for negative variation. Since the price for positive
variation was received as per C.W.C. guidelines and amount paid,
the claim for negative variation prepared following the guidelines of
the same authority cannot be rejected unless errors in calculation is
(sic, are) pointed out. The respondents have not challenged the
details of calculation in Ext.C-IV/26. C-IV/27 and C-IV/28 in any
manner”.
18.
Thus, what is apparent from the award is that the principle on which
the Arbitral Tribunal treated the matter was that since for positive variation in
the quantum of work executed, the CWC guidelines had been resorted to by
the parties by abandoning the parameters indicated in clause 33.2(iii); the same
CWC guidelines ought to be applicable to the negative variation in work. It
was a possible view that fell within the domain of the Arbitral Tribunal and the
same cannot be questioned on the basis of any permissible ground under
Section 34 of the said Act.
19.
It must be added that it does not lie in the mouth of the appellants at
this stage to question the quantum awarded on such head of claim since,
admittedly, the appellants herein did not question the calculations furnished by
the contractor on the basis of CWC guidelines before the Arbitral Tribunal.
20.
There is no merit in the principal ground urged on behalf of the
appellants and considerable Court time has been wasted in such regard.
21.
As to the so called relinquishment of rights in terms of a clause of the
contract, the appellants refer to clause 39.1 of the GCC that speaks of a timelimit for claims to be made by the contractor. The relevant clause reads as
follows:
“39.1 Any claim raised by the contractor should have been registered
with the Engineer-in-charge and not before any subordinate authority
within 90 (ninety) days. He is precluded from raising any such claim
after the expiry of the above period”.
22.
In support of the appellants’ case that since the acceptance of the
offer in this case was completed prior to the amendment to Section 28 of the
Contract Act coming into effect on January 8. 1997, a judgment reported at
(2016) 9 SCC 720 (Union of India v. Indusind Bank Ltd) has been placed. The
judgment is instructive as it goes into various previous Law Commission
recommendations for the amendment of Section 28 of the Contract Act and the
ultimate amendment thereof. The judgment also dwelt on whether the
amendment was substantive or it was clarificatory or declaratory in nature. The
discussion in such regard concludes with the observation that it was a
substantive amendment that was brought about and, as a consequence, it would
operate prospectively since the amendment did not provide for any
retrospective operation thereof. However, the dictum in such case is confined
to the rule enunciated that a clause in any contract entered into subsequent to
the amendment to Section 28 of the Contract Act which falls foul of the
amended provision will be invalid, but a clause in any contract executed prior
to such statutory amendment will be governed by the unamended provision.
23.
Paragraph 24 of the report in Indusind Bank Ltd may be seen in the
present context:
“24. On a conspectus of the aforesaid decisions, it becomes clear that
Section 28, being substantive law, operates prospectively, as
retrospectivity is not clearly made out by its language. Being
remedial in nature, and not clarificatory or declaratory of the law, by
making certain agreements covered by Section 28(b) void for the
first time, it is clear that rights and liabilities that have already
accrued as a result of agreements entered into between parties are
sought to be taken away. This being the case, we are of the view that
both the Single Judge and the Division Bench were in error in
holding that the amended Section 28 would apply.”
24.
This second ground of challenge to the arbitral award may be dealt
with on the basis of a simple reference to the fact that the contract in this case
was executed between the parties on April 22, 1997, more than three months
after the statutory amendment came into effect. However, the additional
argument made here is that since the acts of offer and acceptance were
completed by August 20, 1996, the amended provision would not apply in this
case.
25.
The mere acceptance of an offer can lead to the formation of a
contract and the rights and obligations of the parties are somewhat determined
upon the acceptance of an offer. However, the exact rights and obligations of
the parties in, inter alia, how the work would be executed and what would be
regarded as executed terms and what other as executory terms are spelt out
only upon the formation of the detailed contract and its due execution. In this
case, the appellants’ argument may have been acceptable and the dictum in
Indusind Bank Ltd applied if the acceptance of the offer or any letter of intent
issued in August, 1996 contained the stipulation as in clause 39.1 of the GCC.
But that is not the appellants’ case. Such clause was contained in the contract
and, as such, it was only upon the parties executing the contract on April 22,
1997 that clause 39.1 of the GCC came to be born, so to say.
26.
Accordingly, the appellants’ second ground of challenge fails and, on
the basis of the dictum in Indusind Bank Ltd, it is held that since the contract in
this case was executed after Section 28 of the Contract Act was amended, it is
such amended provision which will govern the parties. Accordingly, clause
39.1 of the GCC would have to be read down or seen to be invalid as a
consequence of amended Section 28 of the Contract Act.
27.
As an aside, it is respectfully submitted that the dictum in Indusind
Bank Ltd, binding as it is under Article 141 of the Constitution, may be worth
revisiting. Of course, this may only be an academic exercise as more than a
quarter of a century has elapsed after the relevant amendment was introduced
in Section 28 of the Contract Act. There is no doubt that the ratio decidendi in
Indusind Bank Ltd. is that the “rights and liabilities that have already accrued
as a result of agreements entered into between parties” prior to the amendment
coming into effect would not be affected by the amendment of Section 28 of
the Contract Act. However, it is submitted that the more appropriate
consideration would be the date when the claim is made and such claim is
sought to be resisted on the ground of the relinquishment clause in the contract
between parties, irrespective of when the contract may have been entered into.
28.
Section 28 as amended in 1997 makes an agreement by which any
party thereto is absolutely restricted from enforcing his rights under or in
respect of any contract by usual legal proceedings or which limits the time for
enforcement of rights or which extinguishes the rights of any party or
discharges any party from any liability, under or in respect of any contract on
the expiry of a specified period so as to restrict any party from enforcing his
rights, void to such extent. That would imply that, irrespective of when the
contract between the parties is entered into, the relevant date would be when a
claim is asserted, whereupon the relinquishment clause in the agreement is
cited to deny the claim. It is not as if the entirety of the contract is voided by
Section 28 of the Contract Act; it is only such part of the contract which is a
derogation of the rule that is indicated in the provision, that is voided. If a
claim was made prior to January 8, 1997 and by virtue of a relinquishment
clause in the governing agreement, such claim could not have been made or
pursued, Section 28 of the Contract Act would not come into play. However, if
the claim was made subsequent to January 8, 1997 and the relinquishment
clause in an agreement executed prior to January 8, 1997 was cited to
relinquish the claim, the relinquishment will not apply to the extent it is at
variance with Section 28 of the Contract Act. The date of the execution of the
contract may not be of any significance. If the disability under a
relinquishment clause had fastened to a party prior to the amendment being
effected in Section 28 of the Contract Act, the amendment will not have any
effect. However, if the disability in terms of the relinquishment clause in the
contract does not fasten to the party prior to the amendment coming to the
effect, by virtue of the amendment, the relinquishment clause can no longer be
of any effect.
29.
The final limb of argument pertains to the award of interest. The
appellants have relied on paragraph 34 of the three-Judge Bench judgment in a
reference reported at (2016) 6 SCC 36 (Union of India v. M/s Ambica
Construction):
“34. Thus, our answer to the reference is that if the contract expressly
bars the award of interest pendente lite, the same cannot be awarded
by the arbitrator. We also make it clear that the bar to award interest
on delayed payment by itself will not be readily inferred as express
bar to award interest pendente lite by the Arbitral Tribunal, as ouster
of power of arbitrator has to be considered on various relevant
aspects referred to in the decisions of this Court, it would be for the
Division Bench to consider the case on merits.”
30.
Even without referring to any other material and on the basis of the
binding law as laid down at paragraph 34 of the judgment in Ambica
Construction, it is evident that there is no merit in the appellants’ suggestion
that by virtue of the relevant clause in the contract between the parties, no
interest could have been awarded in favour of the contractor.
31.
Clause 39.1 of the GCC, which is relevant for the present discussion,
provides as follows:
“36.1 No claim for interest or damages will be entertained by the
Department with respect to any money or balance which may be
lying with the Department owing to any dispute, difference or
misunderstanding between the Engineer-in-charge on the one hand
and contractor on the other or with respect to any delay on the part of
the Engineer-in-Charge in making periodical or final payments or in
any other respect whatsoever”.
32.
On a plain reading of such clause, it is apparent that the clause
prohibits payment of interest in certain specified cases and it also contains a
residuary limb in the words “or in any other respect whatsoever” that
ostensibly precludes the payment of interest on any account. However, the
dictum in Ambica Construction instructs that unless the payment of pendente
lite interest is specifically prohibited, a general bar of payment of interest will
not be interpreted to also include a prohibition as to pendente lite interest. The
principle of party autonomy permits the exclusion of several ordinary rights,
but such exclusion has to be express and specific and may not be easily
inferred unless unambiguously stated.
33.
In any event, the dictum in Ambica Construction has been interpreted
subsequently in a judgment reported at (2017) 14 SCC 323 (Ambica
Construction v. Union of India). Paragraphs 5 and 6 of the judgment are
relevant in the present context:
“5. The impugned order passed by the High Court dated 17-6-2005,
limited to the determination with reference to pendente lite interest,
has been assailed by the appellant, through the instant civil appeal.
During the course of hearing, it was not disputed, that the contractual
obligation between the parties expressly provided, that interest could
not be claimed, either on earnest money or on the security deposit,
and even on amounts payable to the claimant. The relevant clause
affirming the above position is extracted hereinbelow:
“(2) Interest on amounts. – No interest will be payable upon
the earnest money or the security deposit or amounts payable
to the contractor under the contract, but government securities
deposited in terms of sub-clause (1) of this clause will be
repayable with interest accrued thereon.”
The aforesaid clause has been relied upon by the learned counsel
representing the Union of India to contend, that when interest was
not payable even on the principal amount, there was no question of
the same being payable during the period the matter remained
pending for adjudication. It is therefore apparent, that the learned
counsel for the respondent, relied upon the contractual obligation
contained in the clause, extracted hereinabove, to counter the claim
of pendente lite interest and to support the impugned order passed by
the High Court.
6. The only contention advanced at the hands of the learned counsel
for the appellant, was based on the judgment of this Court in Union
of India v. Ambica Construction, wherein, having examined the legal
position declared by this Court by a Constitution Bench in Irrigation
Deptt., State of Orissa v. G.C. Roy, it was held as under: (Ambica
Construction case, SCC p.59, para 34)
“34. Thus, our answer to the reference is that if the contract
expressly bars the award of interest pendente lite, the same
cannot be awarded by the arbitrator. We also make it clear that
the bar to award interest on delayed payment by itself will not
be readily inferred as express bar to award interest pendente
lite by the Arbitral Tribunal, as ouster of power of arbitrator
has to be considered on various relevant aspects referred to in
the decisions of this Court, it would be for the Division Bench
to consider the case on merits.”
A perusal of the conclusions drawn by this Court in the above
judgment, rendered by a three-Judge Division Bench, leaves no room
for any doubt, that the bar to award interest on the amounts payable
under the contract, would not be sufficient to deny payment of
pendente lite interest. In the above view of the matter, we are
satisfied, that the clause relied upon by the learned counsel for the
Union of India, to substantiate his contention, that pendente lite
interest could not be awarded to the appellant, was not a valid
consideration, for the proposition being canvassed. We are therefore
satisfied, that the arbitrator, while passing his award dated 28-61999, was fully justified in granting interest pendente lite to the
appellant.”
34.
An ancillary ground asserted by the appellants is that interest has
been awarded at an exhorbitant rate of 15 per cent per annum.
35.
The award of interest at such high rate does not call for any
interference. First, in view of Section 31 of the Act of 1996, it is the
prerogative of the Arbitral Tribunal, subject to any agreement between the
parties, as to what should be the quantum of interest. Secondly, considering
that the contract in this case was of the year of 1996 and the dues have not
been cleared yet, a reasonable quantum has been awarded by way of interest
by the Arbitral Tribunal that does not shock the conscience of this Court for it
to be minded to interfere therewith.
36.
The other contention of the appellants is that the court of the first
instance failed to appreciate the matter in its proper perspective and merely
parroted the words of the Arbitral Tribunal in dealing with the legal issues
raised under Section 34 of the Act.
37.
In the light of the comprehensive discussion on all three grounds
urged by the appellants in challenging the award, as to whether appropriate
considerations were taken into account in the judgment and order impugned
pales into insignificance.
38.
The appellants have needlessly barked up the wrong tree in seeking
to challenge the arbitral award despite the same being eminently justified and
every limb of the adjudication and finding reflected therein being within the
authority of the Arbitral Tribunal.
39.
As it is, the scope of interference with an arbitral award is limited to
the few grounds available under Section 34 of the Act. Qualitatively, the
assessment under Section 34 of the Act is not as in a regular appeal. In
substance, the Court looks for errors of jurisdiction committed by the Arbitral
Tribunal rather than errors committed by an Arbitral Tribunal within the
bounds of its authority. The only exception is on account of patent illegality or
perversity of the kind that shocks the conscience of the Court.
40.
Ordinarily, the Arbitral Tribunal, particularly when, as in this case, it
has expansive authority to construe the contract in view of the wide words of
the arbitration agreement, if one of several possible views on an aspect is taken
by an arbitral tribunal, the Court will not intervene to supplant its view over
the Arbitral tribunal’s. At the same time, it must be kept in mind that an
Arbitral tribunal has only such authority as has been conferred by the
agreement of the parties; and, an arbitrator being a creature of an agreement
cannot act contrary to the terms of the agreement, particularly when the
arbitration clause is contained in the matrix contract itself. The plenary
authority available to a Court, by virtue of the Court being a part of the
sovereign scheme of dispensation of justice, is not available to an arbitrator.
41.
In the rarified atmosphere of an appeal from a failed challenge to an
arbitral award, the scope of interference is even more constricted. Unless the
Court of the first instance is found to have applied completely wrong tests and
the Arbitral Tribunal appears to have committed errors of jurisdiction or the
award results in manifest miscarriage of justice that would shock the
conscience of the appellate court, there is little room to interfere with an
arbitral award at this level.
42.
In the present case, the appellants do not meet the high benchmark
set for this Court to interfere with the arbitral award. Not only do the grounds
canvassed by the appellants not appeal to this Court, but also the reasons
furnished in support of the award and in dealing with the objections raised by
the appellants appear to be appropriate and satisfactory.
43.
For the reasons indicated hereinabove, there is no merit in the
appellants’ challenge to the arbitral award of December 9, 2010. Accordingly,
Arb.A.No.1 of 2018 and MC (Arb.A.) No.1 of 2018 are dismissed with costs
assessed at Rs 2 lakh; of Rs 1 lakh will be paid as a token amount to the
respondent contractor and the balance to the Meghalaya State Legal Services
Authority within a month for valuable Court time being needlessly wasted.
(W. Diengdoh)
Judge
(Sanjib Banerjee)
Chief Justice
Meghalaya
31.03.2022
“Lam DR-PS
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.