HIGH COURT OF TRIPURA
AGARTALA
CRP No.93/2024
Sri Samir Chakraborty, S/O.-Late Sunil Chakraborty, Village & P.O.Durjoynagar, P.S.-N.C.C., Agartala, District-West Tripura.
……… Petitioner(s).
VERSUS
Radiant Highrise Pvt. Ltd., A company incorporated under Indian Companies
Act, 1956, having its registered office at 3A Auckland Place, 9th Floor, P.S.Shakespeare Sarani, P.O.- Shakespeare Sarani, Kolkata - 700017, West Bengal.
Represented by Sri Pranab Kumar Ray, S/O.-Late Pramod Kumar Ray, resident
of Madhyapara, Banamalipur, P.O.-Agartala, P.S.-East Agartala, District-West
Tripura, Pin-799001.
(who has been authorized by the company under resolution dated 28-01-2021,
wherein, said Pranab Kumar Ray has been authorized to file and conduct and
represent the suit).
………Respondent(s).
For Petitioner(s)
: Mr. Biswanath Majumder, Advocate.
For Respondent(s)
: None.
HON’BLE THE CHIEF JUSTICE MR. APARESH KUMAR SINGH
Order
05/10/2024
Heard Mr. Biswanath Majumder, learned counsel appearing for
the petitioner.
2.
Title Suit No.17 of 2021 was instituted by the respondent under
Sections 14(3)(C), 34 and 37 of the Specific Relief Act, 1963 for enforcement
of the development agreement and also declaration that the development
agreement dated 21.06.2019 made between the plaintiff and the defendant are
binding and enforceable. Petitioner also sought a declaration that plaintiff is
entitled to construction of (G+4) storied RCC residential building over the land
mentioned in the development agreement and for enforcement of the contract.
The plaintiff also sought for perpetual injunction against the defendant. The
suit was valued at Rs.1,05,000/- and court fees were paid thereupon.
Thereafter, written statements have been filed and issues were also framed vide
order dated 09.01.2023. Plaintiff thereafter sought amendment of the plaint to
incorporate certain additional reliefs under Order VI Rule 17 read with Section
151 of the Civil Procedure Code, 1908 (CPC, for short) sometime in May,
2023 as it appears that the copy of the amendment application was received by
the other side on 19.05.2023.
3.
The plaintiff sought the following additional relief/prayer to be
added as para-VA at page-12 of the plaint:
"VA) Pass a decree declaring that the Plaintiff is entitled to get
Rs.27,33,929/- (Rupees Twenty Seven Lakhs Thirty Three Thousand Nine
Hundred & Twenty Nine) only which was incurred by the Plaintiff as preconstruction activities and compensation amounting to Rs.10,00,000/(Rupees Ten Lakhs) only in the event of cancellation of the Registered Joint
Venture Agreement vide no.1-3755 dated 21.06.2019 recorded in the Book
No.1, Vol. No.45, Page No.43-64 for the year 2019."
4.
Written objection was also filed by the defendant/petitioner herein
as it appears that copy thereof was received by the plaintiff on 11.08.2023. The
learned trial Court has by the impugned order dated 15.03.2024 allowed the
proposed amendment to incorporate the alternative relief so that it may prevent
multiplicity of suits. However, since the amendment was sought after framing
of the issues at the stage of evidence, plaintiff was directed to compensate the
defendant with a cost of Rs.3,000/- (rupees three thousand only). Thereafter,
defendant/petitioner was also allowed to file additional written statement as per
statement contained in the synopsis of the petition. After six months of the
passing of the impugned order on 15.03.2024, the present revision petition
under Article 227 of the Constitution of India has been filed on 25.09.2024 by
the defendant being aggrieved by the order allowing amendment of the relief
portion in favour of the plaintiff.
5.
Learned counsel for the petitioner submits that the amendment has
been proposed at a belated stage after framing of issues when evidence has
begun. The amendment intends to set up a new relief which would change the
very nature of the suit. He has also submitted that the prayer for injunction
made before the learned trial Court was rejected. At no point of time earlier,
the plaintiff thought it necessary to seek such amendment in the nature of an
alternative relief. The respondent would be highly prejudiced if the amendment
is allowed to sustain. Therefore, they have decided to assail it. Impugned order
may be set aside.
6.
I have considered the submission of learned counsel for the
petitioner and taken note of the materials placed on record. I have also gone
through the impugned order.
7.
As noted above, the instant suit has been preferred in the year
2021 under the Specific Relief Act for enforcement of a development
agreement dated 21.06.2019 made between the parties. It appears that plaintiff
had not sought for any compensation for breach of the agreement in the
original plaint. After framing of the issues, such a prayer in the nature of an
alternative relief has been prayed for which is permissible in terms of Section
21 sub-section (5) of the Specific Relief Act, 1963. Section 21 of the Act reads
as under:
"21. Power to award compensation in certain cases.-(1) In a suit for
specific performance of a contract, the plaintiff may also claim compensation
for its breach, [in addition to], such performance.
(2)
If, in any such suit, the court decides that specific performance
ought not to be granted, but that there is a contract between the parties which
has been broken by the defendant, and that the plaintiff is entitled to
compensation for that breach, it shall award him such compensation
accordingly.
(3)
If, in any such suit, the court decides that specific performance
ought to be granted, but that it is not sufficient to satisfy the justice of the
case, and that some compensation for breach of the contract should also be
made to the plaintiff, it shall award him such compensation accordingly.
(4)
In determining the amount of any compensation awarded
under this section, the court shall be guided by the principles specified in
Section 73 of the Indian Contract Act, 1872 (9 of 1872).
(5)
No compensation shall be awarded under this section unless
the plaintiff has claimed such compensation in his plaint:
Provided that where the plaintiff has not claimed any such
compensation in the plaint, the court shall, at any stage of the proceeding,
allow him to amend the plaint on such terms as may be just, for including a
claim for such compensation.
Explanation.-The circumstance that the contract has become
incapable of specific performance does not preclude the court from exercising
the jurisdiction conferred by this section."
8.
Proviso to Section 21(5) provides that where the plaintiff has not
claimed any such compensation in the plaint, the court shall, at any stage of the
proceeding, allow him to amend the plaint on such terms as may be just, for
including a claim for such compensation. The explanation thereto provides that
the circumstance that the contract has become incapable of specific
performance does not preclude the court from exercising the jurisdiction
conferred by this section.
9.
In terms of Order VI Rule 17 of the CPC, the Court may at any
stage of the proceedings allow either party to alter or amend his pleading in
such manner and on such terms as may be just, and all such amendments shall
be made as may be necessary for the purpose of determining the real questions
in controversy between the parties: provided that no application for amendment
shall be allowed after the trial has commenced, unless the Court comes to the
conclusion that in spite of due diligence, the party could not have raised the
matter before the commencement of trial.
10.
The proceedings of the title suit are not at a fag end. Immediately
after framing of the issues when the trial began, the plaintiff has sought for an
alternative relief by way of the proposed amendment filed on 19.05.2023. It is
permissible for the plaintiff to seek alternative relief unless the reliefs sought
for are self-destructive or inconsistent to each other. In a case for specific
performance of contract, if the Court decides that the specific performance
ought not to be granted, then the court may grant compensation for that breach.
Section 21(5) provides that no compensation shall be awarded under this
section unless the plaintiff has claimed such compensation in his plaint. In the
wake of this legal position, the learned trial Court has upon consideration of the
rival stand of the parties on the proposed amendment also taken into
consideration the decision rendered by the Apex Court in the case of Life
Insurance Corporation of India vrs. Sanjeev Builders Private Limited
reported in AIR 2022 SC 4256 which illustrates the conditions in which prayer
for amendment can be allowed. It further indicates that delay in applying for
amendment alone is not a ground to disallow the prayer. The amendment so
allowed would not change the nature of the suit or the cause of action or set up
an entirely new case, foreign to the case set up in the plaint.
In fact, if the amendment was not allowed, it may lead to
multiplicity of suits. Therefore, the learned trial Court considered it proper to
allow the proposed amendment, however, with a cost to compensate the
prejudice caused to the defendant as the amendment was proposed at the
evidence stage. Thereafter, the learned trial Court has also allowed the
defendant to file additional written statement. If the defendant/petitioner has
not filed additional written statement, as allowed by the learned trial Court, he
may be allowed opportunity to file the same within a reasonable time.
Moreover, petitioner has chosen to assail the impugned order six months
thereafter when the trial has further proceeded.
11.
In the wake of aforesaid circumstances and for the reasons
recorded hereinabove, this Court does not consider it proper to exercise
jurisdiction under Article 227 of the Constitution of India to interfere in the
matter.
12.
The instant revision petition is accordingly dismissed.
Pending application(s), if any, also stands disposed of.
(APARESH KUMAR SINGH), CJ
Pulak
DIPESH DEB
Date: 2024.10.07 14:40:23
+05'30'
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review