IN THE HIGH COURT OF MANIPUR
AT IMPHAL
W.P. (C) No. 906 of 2018
Shri Th. Nodichand Singh, aged about 72 years, Special
Class Contractor, R/o Thangmeiband Lourng Pural Leikai, P.OD.M College Campus & P.S – Lamphel, District: Imphal West,
Manipur-795001.
... Petitioner
- Versus 1. The State of Manipur, represented by the Commissioner
(Rural Development & Panchayati Raj), Government of
Manipur, Old Secretariat Complex, Babupara, P.O & P.S
Imphal, District: Imphal-West, Pin No. 795001.
2. The
Chief
Engineer,
Rural
Engineering
Department
th
(RED)/(MSRRDA), 4 Floor, Secured Office Complex,
North AOC, Imphal-795001, Manipur.
3. The Executive Engineer (PIU/ Imphal West) Rural Engineer
Department (RED)/(MSRRDA), 4th Floor, Secured Building
Office Complex, North AOC, Imphal-795001,Manipur
... Official respondents
4. M/S Manikchand & Co. Having its registered office at
Kwakeithel Mayaikoibi, Imphal represented by its Proprietor/
Manager, Ch. Jitendra Singh, aged about 58 years of
Kwakeithel Mayaikoibi, Imphal West-795001, Manipur.
… Private Respondent
With
W.P. (C) No. 267 of 2019
M/S Manikchand & Co. of Kwakeithel Mayaikoibi, Imphal
represented by its Proprietor/ Manager namely Ch. Jitendra
Singh aged about 58 of Kwakeithel Mayaikoibi, Imphal West,
Manipur, PIN No.795001
... Petitioner
W.P. (C) No. 906 of 2018 With
W.P (C) No. 267 of 2019
Contd…/-
[2]
- Versus 1. The
State
of
Manipur
represented
by
the
Commissioner(Rural Development & Panchayati Raj),
Government of Manipur, Old Secretariat
Babupara, Imphal West, Manipur, Pin.-795001
Complex,
2. The Chief Engineer, Rural Engineering Department
(RED)(MSRRDA) and its Office at 4th Floor, Secured Office
Complex, North AOC, Imphal-795001, Manipur.
3. The Project Director, Loktak Development Authority,
Government of Manipur and its Office at 4th Floor, Secured
Office Complex, North AOC, Imphal-795001, Manipur.
... Respondents
B E F O R E
HON’BLE MR. JUSTICE KH. NOBIN SINGH
For the petitioners
: Shri L. Anand, Advocate
For the respondents
: Shri Lenin Hijam, Addl. AG;
Date of Hearing
: 25-11-2019
Date of Judgment & Order
: 19-12-2019
JUDGMENT & ORDER
[1]
Heard Shri Ajoy Pebam, learned counsel appearing for the
petitioner in writ petition being WP(C) No. 267 of 2019 while Shri L. Anand,
learned counsel appearing for the petitioner in writ petition being WP(C)
No. 906 of 2018 and Shri Lenin Hijam, learned Addl. Government
Advocate appearing for the State respondents.
[2]
Since both the above writ petitions have arisen out of a similar
set of facts, the same are being decided and disposed by this common
judgment and order.
W.P. (C) No. 906 of 2018 With
W.P (C) No. 267 of 2019
Contd…/-
[3]
[3]
On 20-10-2014, the Chief Engineer, Manipur State Rural Roads
Development Agency (herein referred to as “the MSRRDA”) issued its first
NIT inviting item rate tender, through e-procurement for Pradhan Mantri
Gram Sadak Yojna (herein referred to as “the PMGSY”), from eligible
contractors for execution of various contract works including the PackageMNO 555. Due to certain reasons, the second NIT dated 27-12-2014 was
issued by the Chief Engineer, MSRRDA but it was cancelled by the
respondents and the bid process in respect of Package-MNO 555 was
repeated by issuing a third NIT date 18-01-2016 inviting item rate tender
through e-procurement for the Package-MN0 555.
[4]
Shri Th. Nodiachand Singh, the petitioner in WP(C) No.906 of
2018 and M/S Manikchand & Co, the petitioner in WP(C) No.267 of 2019
who are hereinafter referred to as the petitioner and the private
respondent, along with other contractors, participated in the e-tender in
respect of Package-MNO 555 for construction of the Road from “T03 to
Karang Part-II” under Wangoi Block of Imphal West District under the
guiding principles of the PMGSY. After the financial bid being opened, the
bid rank of the petitioner was at L1 while that of the private respondent was
at L4. Accordingly, the Chief Engineer, the respondent No.2 issued a letter
of acceptance dated 19-11-2016 and the work order dated 15-04-2017 in
favour of the petitioner, on the basis of which he started constructing the
earth work with due cognizance and permission of the competent authority
after investing huge money and effort.
W.P. (C) No. 906 of 2018 With
W.P (C) No. 267 of 2019
Contd…/-
[4]
[5]
Being aggrieved by the said letter of acceptance dated
19-11-2016 and the work order dated 15-04-2017, the private respondent
who was one of the bidders, approached this Court on 24-04-2017 by way
of a writ petition being WP(C) No.296 of 2017 challenging them on the
ground that the performance security and additional performance security
were furnished by the petitioner after the expiry of ten days as prescribed
in the NIT. This Court passed a judgment and order dated 08-08-2017
allowing the said writ petition and consequently, the letter of acceptance
dated 19-11-2016 and the work order dated 15-04-2017 were quashed and
set-aside. The said judgment and order dated 08-08-2017 passed by this
Court appears to have been challenged by the petitioner before the
Hon’ble Supreme Court by way of a petition for special leave to appeal
which was dismissed and accordingly, the official respondents issued a
work order dated 10-04-2018 in favour of the private respondent without
re-tendering the process in respect of the said package-MN0-555 as
contended by the petitioner.
[6]
The said work order dated 10-04-2018 was challenged by the
petitioner on the inert-alia grounds that while passing the judgment and
order dated 08-08-2017, this Court did not give any direction to the official
respondents for issuing the work order dated 10-04-2018 in favour of the
private respondent; that in terms of clause 8.15 of the tender documents,
the tender process shall be repeated where the performance security is not
furnished; that since the official respondents have reserved the right either
W.P. (C) No. 906 of 2018 With
W.P (C) No. 267 of 2019
Contd…/-
[5]
to accept or reject the bids, they ought to have cancelled the tender
process and initiated the process for re-tender and that the act of the
official respondents in issuing the work order without affording opportunity
to the petitioner is arbitrary, illegal and violation of Article 14 and 21 of the
Constitution of India. This writ petition was contested by the private
respondent by fling an affidavit-in-opposition stating that after the petitioner
having failed to get any relief from the Hon’ble Supreme Court, the official
respondents after, considering all the eligible bidders, issued the work
order in favour of the private respondent and moreover, this court while
passing the judgment and order dated 25-07-2017 did not interfere with the
NIT, as it was not challenged by it. It has further been stated that in respect
of a similar case being Package-MNO 936, although this Court quashed
the work order dated 21-03-2011, the official respondents awarded the
contract to Shri Khupkhohao Kilong who was the petitioner therein. The
PMGSY scheme being a flagship programme, the execution of the
work
was
to
be
completed
within
months
reckoning
from
17-04-2018. While the sad writ petition being WP(C) No.906 of 2018 was
pending for consideration, the private respondent filed an application being
MC No.327 of 2018 praying for permission to raise an objection as regards
the maintainability of the said writ petition.
[7]
After the work order dated 10-04-2018 being issued in its favour,
the private respondent started the execution of the work and while it was
executing the work, the respondent No.2 issued a letter dated 29-08-2018
W.P. (C) No. 906 of 2018 With
W.P (C) No. 267 of 2019
Contd…/-
[6]
directing it to stop construction of work which appears to have been issued
pursuance to a letter dated 25-08-2018 issued by the Project Director,
Loktak Development Authority wherein it is stated that the said proposed
road falls within the area of the Loktak Lake. Since the private respondent
had completed 80% of the work, it requested the respondent No.2 by way
of a representation dated 16-10-2018 requesting him to allow it to
complete the construction of work, followed by a legal notice dated
30-11-2018. But the respondent did not pay any heed to its representation
at all. It may be noted that the respondent No.2 wrote a letter dated
21-02-2019 to the Project Director, LDA clarifying that the Karang Yangbi
Road is not within the Core Zone of the Loktak Lake. But as the
respondent No.2 did not revoke its letter dated 29-08-2018, the private
respondent filed the writ petition being WP(C) No.267 of 2019 questioning
both the letter dated 25-08-2018 of the Project Director, LDA and the letter
dated 29-08-2018 issued by the respondent No.2.
[8]
During the course of the proceedings, it was brought to the notice
of this Court by the learned Addl. Advocate General that the dispute
between the Rural Engineering Department, Government of Manipur
and the Loktak Development Authority remained unresolved and on
30-04-2019, this Court expressed the need of having a resolution between
them for which the leaned Addl. Advocate General was granted time to find
an amicable solution. On 21-05-2019 when the matter was taken up for
consideration, it was submitted by the learned Addl. Advocate General that
W.P. (C) No. 906 of 2018 With
W.P (C) No. 267 of 2019
Contd…/-
[7]
although a meeting was held, the dispute could not be resolved by them. In
the meantime, a representation dated 13-05-2019 was submitted to the
Chief Engineer, RED by the private respondent stating that it was no
longer interested in the continuance of the execution of the work and a
prayer was made that the security deposit for a sum of Rs.51,90,000/- be
refunded and the pending bill for a sum of Rs.14,90,309/- be released in
the interest of justice. While granting further time to the Addl. Advocate
General, this Court observed that the Chief Engineer, RED was not
precluded from considering the said representation of the private
respondent. On 14-06-2019 when the matter was listed again, the counsel
appearing for the private respondent submitted that its representation was
not considered by the official respondents and therefore, the official
respondents were granted time till 05-07-2019 for disposal of the
representation. On 03-07-2019, the Chief Engineer, RED informed the
private respondent that since it could not drop the work in the middle of the
execution of the work, it would be better for it to wait for the solution. But
since the Rural Engineering Department and the Loktak Development
Authority having failed to resolve the dispute between them, this Court
passed an order dated 05-07-2019 observing that there was no point of
keeping the matter pending awaiting their resolution which is quite
uncertain and that the matter be listed on 22-07-2019 for disposal.
Thereafter, sufficient time was granted by this Court to the parties to
complete their pleadings and ultimately, the matters were heard on
25-11-2019.
W.P. (C) No. 906 of 2018 With
W.P (C) No. 267 of 2019
Contd…/-
[8]
[9.1]
It is not in dispute that the PMGSY is a flagship programme,
launched by the Government of India, which is to be implemented within a
time frame. In the present case, admittedly the work was to be executed in
12 months. The first NIT was issued on 20-10-2014 by the Chief Engineer,
RED in respect of the Package-MNO 555 which was cancelled and the
second NIT dated 27-12-2014 was issued which, too, was cancelled by the
official respondents and the third NIT date 18-01-2016 was ultimately
issued inviting item rate tender through e-procurement for the PackageMN0 555. It may be noted that the third NIT was issued after the expiry of
more than a year from the date of issuing the first NIT, leave alone the
completion of the work within a year. It is the Rural Engineering
Department, Government of Manipur which has to be careful and apply its
judicious mind. In other words, the officials of the Rural Engineering
Department who are responsible for the implementation of the PMGSY,
need to be sincere in the discharge of their duties and functions. If they fail
to do that, the implementation of such a welfare programme will be
rendered meaningless. It is the right time for the Rural Engineering
Department to be introspective; to examine minutely as to how many
works have been executed and completed by them in time and to stop
playing with the public money in the name of the execution of the works. If
the mistake is committed by the Rural Engineering Department only in this
case, it is understandable. But there are many packages in respect of
which many writ petitions have been filed before this Court challenging the
process of tender. This shows that the officials of the Rural Engineering
W.P. (C) No. 906 of 2018 With
W.P (C) No. 267 of 2019
Contd…/-
[9]
Department may have done it either due to lack of sincerity or incapability
to handle the work. In other words, the officials of the Rural Engineering
Department are incapable of handling the work or have done it deliberately
with hidden agenda being kept in mind. If the tender process is undertaken
by the Rural Engineering Department strictly in accordance with law and in
particular, the clauses contained in the tender documents, many of the
problems could have been avoided by it.
[9.2]
After the financial bid being opened, the petitioner being found to
be the L1, the respondent No.2 issued a letter of acceptance dated
19-11-2016 and the work order dated 15-04-2017 in favour of the
petitioner, on the basis of which he allegedly started constructing the earth
work. The private respondent challenged them by way of a writ petition
being WP(C) No.296 of 2017 on the ground that the performance security
and additional performance security were furnished by the petitioner after
the expiry of ten days as prescribed in the NIT. This Court vide its
judgment and order dated 08-08-2017 allowed the said writ petition
quashing the letter of acceptance dated 19-11-2016 and the work order
dated 15-04-2017. A petition for special leave to appeal preferred against it
before the Hon’ble Supreme Court was dismissed and accordingly, the
official respondents issued a work order dated 10-04-2018 in favour of the
private respondent which is being challenged by the petitioner. The private
respondent appears to have stared the work as contended by it. The
Project Director, LDA wrote a letter dated 25-08-2018 stating that the said
W.P. (C) No. 906 of 2018 With
W.P (C) No. 267 of 2019
Contd…/-
[10]
proposed road falls within the area of the Loktak Lake, on the basis of
which the respondent No.2 issued a letter dated 29-08-2018 directing the
private respondent to stop construction of work. The private respondent,
having completed 80% of the work, made a request vide its representation
dated 16-10-2018 requesting the official respondents to allow it to
complete the construction of work, followed by a legal notice dated
30-11-2018. Since the official respondents did not pay any heed to its
representation at all, the private respondent filed the writ petition being
WP(C) No.267 of 2019 questioning both the letter dated 25-08-2018 of the
Project Director, LDA and the letter dated 29-08-2018 issued by the
respondent No.2. From the aforesaid circumstances, it is seen that it is the
Rural Engineering Department, Government of Manipur and in particular,
its officials who are to be blamed for the said events. The process of
tender will have to be initiated and completed in terms of the tender
documents which contain various clauses. Had the clauses been followed
by them in their true spirit, the aforesaid litigation could have been avoided
by the Rural Engineering Department. It is unfortunate that although the
officials of the Rural Engineering Department were aware of the clause
that the performance security and additional performance security had
been furnished by the petitioner beyond ten days as prescribed in the NIT,
the respondent No.2 issued the letter of acceptance and the work order.
He ought not to have done that and before doing that, he could have
consulted the Law Department or the learned Advocate General for legal
advice as regards the interpretation of the various clauses contained in the
W.P. (C) No. 906 of 2018 With
W.P (C) No. 267 of 2019
Contd…/-
[11]
tender documents which he appears to have failed to do that. Interestingly,
after the said letter of acceptance and the work order having been
quashed by this Court and the appeal preferred before the Hon’ble
Supreme Court having failed, the respondent No.2 issued the work order in
favour of the private respondent which was the L4, probably, without
assigning any cogent reason, because of which its validity and correctness
is being challenged by the petitioner.
[9.3]
While the private respondent was executing the work, the
respondent No.2 issued a letter dated 29-08-2018 directing it to stop the
work. This letter dated 29-08-2018 was issued by the respondent No.2
pursuant to a letter dated 25-08-2018 of the Project Director, LDA. Thus, a
dispute arose between them with respect to the said road, for which the
private respondent cannot be said to be responsible at all. Before the
tender process being initiated, the Rural Engineering Department appears
to have not applied its mind. The dispute is between the State Government
and its statutory body and in other words, the dispute being between two
hands of the State Government, it ought to be resolved by them sitting
across the table without bringing it to the notice of this Court. It is an
internal problem of the State Government. Despite sufficient opportunities
being given by this Court to the State Government, it has failed to resolve it
and in other words, it has utterly failed to do its needful which is
unfortunate. It is the Rural Engineering Department which has created the
problem and therefore, it is the duty of the Rural Engineering Department
W.P. (C) No. 906 of 2018 With
W.P (C) No. 267 of 2019
Contd…/-
[12]
to find out a solution. Being fed up with the dispute between the State
Government and its statutory body, the private respondent has expressed
its desire to discontinue with the work. But its request was turned down on
the ground that the work could not be stopped in the middle of its
execution. On the one hand, the respondent No.2 did not permit the private
respondent to continue with the work and on the other hand, its request
was rejected. Of course, the work order issued in favour of the private
respondent is being challenged by the petitioner. In any case, the Rural
Engineering Department, Government of Manipur cannot blow hot and
cold at one time. The Rural Engineering Department being an institution, it
has to act fairly and reasonably and in the interest of the general public.
Since the dispute between the State Government and its statutory body is
not the subject in issue before this Court in the above writ petitions, it may
not be appropriate for this Court to make any observation thereon. But it
has no doubt a bearing on the issue involved herein and moreover, unless
it is resolved by the State Government at an early date, it will definitely
have a problem in complying with any order passed by this Court in the
matter. It is upto the State Government to take a decision but the
stalemate which cannot be allowed to continue without any resolution, will
not, in any case, be in the interest of the work but this Court will have to
decide the issue involved herein based on the materials available on
record.
W.P. (C) No. 906 of 2018 With
W.P (C) No. 267 of 2019
Contd…/-
[13]
[10]
Keeping in mind the peculiar facts and circumstances of the
present case, the above writ petitions stand disposed of with the following
directions:
(a) The State Government shall take appropriate and immediate
steps to ensure that the dispute between the Rural Engineering
Department and the Loktak Development Authority is resolved at
an early;
(b) The respondents and in particular, the respondent No.2, the
Chief Engineer, RED shall return to the private respondent, M/S
Manikchand & Co., the security deposit for a sum of
Rs.51,90,000/- deposited by it within three months from the date
of receipt of a copy of this judgment and order, failing which it
shall accrue interest @ 8% per annum till the date of return;
(c) The respondents and in particular, the respondent No.2, the
Chief Engineer, RED shall release the amount for the work done
so far by the private respondent, M/S Manikchand & Co., within
three months from the date of receipt of a copy of this judgment
and order after the same being worked out and verified from the
records;
(d) The respondents and in particular, the respondent No.2, the
Chief Engineer, RED shall release the amount for the work done
by the petitioner, Th. Nodiachand Singh, before the letter of
acceptance dated 19-11-2016 and the work order dated 15-042017 issued in his favour, within three months from the date of
W.P. (C) No. 906 of 2018 With
W.P (C) No. 267 of 2019
Contd…/-
[14]
receipt of a copy of this judgment and order after the same being
worked out and verified from the records;
(e) It is open to the State Government and in particular, the Rural
Engineering Department, to take appropriate steps for taking a
decision towards discontinuation of the work and take an
initiative for a fresh tender in respect of the remaining work.
JUDGE
FR/ NFR
A. Surjit
WAIKH Digitally
signed by
WAIKHOM
OM
TONEN MEITEI
TONEN Date:
2019.12.20
MEITEI 10:34:58
-08'00'
W.P. (C) No. 906 of 2018 With
W.P (C) No. 267 of 2019
Contd…/-
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review