Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
MAYAN Digitally signed
GLAMBA by
MAYANGLAMBA
M CHANU
M
NANDINI
CHANU Date: 2021.03.17
15:08:38 +05'30'
NANDINI
[1]
IN THE HIGH COURT OF MANIPUR
AT IMPHAL
W.P. (C) No. 799 of 2019
Seikhothang Haokip, aged about 77 years, S/o (Late)
Luntum Haokip, Chief of Mangbung Village, District Jiribam,
P.S. Jiribam, Manipur State.
…Petitioner
-VersusThe Chairman & Managing Director, Power Grid Corporation
of India Ltd., NERTS, Dongtieh, Lower Nongrah, Lapalang,
Shillong-793006,
Regd. Office: B-9, Qutab Institutional Area, Katwaria Sarai,
New Delhi-110016
CIN No.- L 40101DL1989GOI038121
… Respondent
B E F O R E
HON’BLE MR. JUSTICE KH. NOBIN SINGH
For the petitioner
:: Shri N. Biren, Advocate
For the Respondents
:: Shri Nitin Kheda, Advocate
Date of Hearing
:: 01-03-2021
Date of Judgment & Order
:: 17-03-2021
JUDGMENT AND ORDER
[1]
Heard Shri N. Biren, learned Advocate appearing for the
petitioner and Shri Nitin Khera, learned Advocate appearing on behalf
of the respondent.
[2]
By the instant writ petition, the petitioner has prayed for
issuing a writ of mandamus or any other appropriate writ to direct the
respondents to pay compensation in terms of the letter dated
W.P. (C) No. 799 of 2019
Contd…/-
[2]
15-10-2015 of the Government of India, Ministry of power, Shriram
Shakti Bhawan, Rafi Marg, New Delhi.
[3.1]
According to the petitioner, he is the Chief of the Mongbung
Village, Jiribam District, Manipur. Some Heavy Electric Towers were
erected/ installed passing through his village, agricultural land as well
as homestead land causing damages to about 320 sq.ft covering a
distance of 2 (two) kilometer. On account of the said heavy electric
towers being erected/ installed passing through his village, his villagers
were/ are unable to construct any kind of buildings including
Government offices, schools or private houses and on top of that, no
plantation of trees, rubbers, bamboos, agricultural crops, etc. thereon is
possible resulting in the helplessness of the villagers. The petitioner
approached the respondent/ authority concerned on many occasions
for payment of compensation for the lands affected by the said
installation of heavy electric towers but his application was never
considered by the respondent.
[3.2]
The petitioner learnt from the reliable sources that in respect
of the land owners/ chefs of the neighboring villages namely Talbung,
Mutugal, Phaital, Muktukhal,
Tarbung etc., certain amount of
compensation had been paid to them, while the same being denied to
the petitioner, although he is the owner of the said village, as is evident
from the attested map/ scale of the SDC, Jiribam, paying Hill
House Tax thereof. The petitioner submitted a representation dated
09-03-2018 to the authority concerned/ respondent for payment of
W.P. (C) No. 799 of 2019
Contd…/-
[3]
compensation and according to him, the amount of compensation
calculated by him came to be about Rs. 96,00,000/- (Rupees ninety-six
lakhs) only. Being aggrieved by the inaction on the part of the
respondent, the petitioner approached this Court by way of writ petition
being WP(C) No.498 of 2018 which was dismissed by this Court vide
its judgment and order dated 06-05-2019, the relevant portion of which
read as under:
“[10]
In the present case, the land of the petitioner was
not acquired at all and while erecting/ installing the
transmission line, certain damages were caused to his land
for which adequate compensation had already been paid to
him by the NEEPCO about thirty years ago. Therefore, in
view of the decision rendered by the Hon’ble Supreme
Court in Power Grid Corporation of India Limited Vs.
Century Textiles and Industries Ltd. case, the instant writ
petition is devoid of any merit and is liable to be dismissed
by this court. In case the petitioner feels that the
compensation granted earlier, was not sufficient or the
damages caused to his land stood aggravated in course of
time, it is open to him to approach the respondent No.4 for
redressal of his grievance so that the same can be
considered by it in accordance with law. In this regard, the
petitioner appears to have submitted a representation
dated 09-03-2018 to the State respondents who are not
concerned with the installation of the transmission line.
[11]
In view of the above and for the reasons stated
hereinabove, the instant writ petition is dismissed with no
order as to costs. It is open to the petitioner to submit a
representation to the respondent No.4 for redressal of his
grievance and in the event of such a representation being
submitted by him, the same shall be considered and
disposed of by the respondent No.4, as expeditiously as
possible, in accordance with law.”
W.P. (C) No. 799 of 2019
Contd…/-
[4]
[3.3]
In terms of the above judgment and order, the petitioner
submitted a representation dated 27-05-2019 to the respondent No.4
therein, who is the Chairman and Managing Director, Power Grid
Corporation of India who considered it and rejected the same on
31-07-2019. Being aggrieved by the rejection of his representation on
31-07-2019, the instant writ petition has been filed by him praying for
issuing a writ of mandamus in terms of the letter dated 15-10-2015
issued by the Government of India, Ministry of power, Shriram Shakti
Bhawan, Rafi Marg, New Delhi. According to the petitioner, the
respondent, while considering the representation, has failed to consider
the letter dated 15-10-2015 resulting in the violation of Article 300A of
the Constitution of India.
[4]
The instant writ petition is contested by the respondent by way
of an affidavit stating that the respondent is a company incorporated
under
the
Companies
Act,
but
has
been
notified
as
POWERGRID, a Central Transmission Utility which is authorized to
exercise all power vested in the Telegraph Authority. The transmission
line from Jiribam to Aizawl was handed over to it by the NEEPCO Ltd.
in the year, 1992 along with the records/ files which were typed and
handwritten on papers. From the said files, it was found that the SDO,
NEEPCO Ltd., wrote a letter dated 12-06-1987 to the ADDL. District
Maigistrate, Jiribam enclosing therewith a list of the names of the
affected land owners including that of the petitioner. After a joint survey
being conducted at that point of time, the damage relating to tree,
crop/surface etc. was assessed and the compensation thereof was
W.P. (C) No. 799 of 2019
Contd…/-
[5]
paid for which the petitioner signed an undertaking/ letter of
acceptance. In other words, the compensation was paid to the
petitioner without any objection being raised by him at that point of
time. This Court while passing the judgment and order dated
06-05-2019, observed that the land of the petitioner was not acquired
and that the compensation for the surface damage had been paid and
accepted by the petitioner. The instant writ petition has been filed by
the petitioner on the similar grounds and that too, on the basis of a
letter dated 15-10-2019 bringing forth a guideline which has no
relevance to the present case. The question of violation of the
provisions of Article 300A does not arise at all, as the petitioner has not
been deprived of his property.
[5]
On 26-09-2019 when the instant writ petition came up for
consideration, this Court issued notice to the respondent. After the
notice being served upon the respondent, it did file its counter affidavit,
the details of which are referred to hereinabove in the preceding
paragraph. On 11-02-2020, when this matter was listed, Shri N. Biren,
the learned counsel appearing for the petitioner submitted that no
rejoinder was required to be filed in the matter and accordingly, the
matter was directed to be listed on 17-03-2020 for disposal in the
category of admission. Due to COVID-19 pandemic, the instant writ
petition could not be disposed of in time as directed and on 14-10-2020
when the matter was taken up for consideration through video
conference, it was submitted by Shri Nitin Khera, learned counsel
appearing for the respondent that the guidelines as contained in the
W.P. (C) No. 799 of 2019
Contd…/-
[6]
letter dated 15-10-2020 would have no application to the case of the
petitioner for the reason that in terms of para 4 thereof, the State
Government had issued a Notification dated 28-03-2018. In view of his
submission, he was granted time to file an additional affidavit enclosing
therewith a copy of the Notification dated 28-03-2018 which he could
do it sometime in the month of December, 2020. Since a new
document was produced by the respondent, the petitioner was granted
some time to file a rejoinder thereto which was filed by the petitioner on
05-02-2021. After the pleadings were complete, this matter was taken
up for hearing on 01-03-2021.
[6]
In order to decide the issue involved herein, this Court deems
it appropriate to reproduce the letter dated 15-10-2015 and Notification
dated 28-03-2018 which read as under:
“No. 3/7/2015-Trans
Government of Manipur
Ministry of Power
Shram Shakti Bhawan
Rafi Marg, New Delhi – 110001
Dated, 15th October, 2015
To
1. Chief Secretaries/Administrators of all the States/UTs
(As per list attached)
2. Chairperson, CEA, New Delhi with the request to
disseminate the above guidelines to all the
stakeholders.
3. CMD, PGCIL, Gurgaon.
4. CEO, POSOCO, New Delhi.
5. Secretary, CERC, New Delhi.
6. CMD of State Power Utilities/SEBs.
W.P. (C) No. 799 of 2019
Contd…/-
[7]
Subject:-
Guidelines for payment of compensation
towards damages in regard to Right of
Way for transmission lines.
During the Power Ministers Conference held on April
9-10, 2015 at Guwahati with States/UTs, it has, inter alia,
been decided to constitute a Committee under the
chairmanship of Special Secretary, Ministry of Power to
analyse the issues related to Right of Way for laying of
transmission lines in the country and to suggest a uniform
methodology for payment of compensation on this count.
Subsequently, this Ministry had constituted a Committee with
representatives from various State Governments and others.
The Committee held several meetings to obtain the views of
State Governments on the issue and submitted its Report
along with the recommendations (copy of the Report is at
Annex-1).
2.
The Recommendations made by the Committee are
hereby formulated in the form of following guidelines for
determining the compensation towards “damages” as
stipulated in section 67 and 68 of the Electricity Act, 2003
read with Section 1C and 16 of Indian Telegraph Act, 1885
which will be in addition to the compensation towards normal
crop and tree damages. This amount will be payable only for
transmission lines supported by a tower base of 66 KV and
above, and not for sub-transmission and distribution lines
below 66 KV:(i) Compensation @ 85% of land value as determined by
District Magistrate or any other authority based on
Circle rate/ Guideline value/ Stamp Act rates for tower
base area (between four legs) impacted severely due
to installation of tower/pylon structure.
(ii) Compensation towards diminution of land value in the
width of Right of Way (RoW) Corridor due to laying of
transmission line and imposing certain restriction would
be decided by the States as per categorization/ type of
land in different places of States, subject to a
maximum of 15% of land value as determined based
on Circle rate/ Guideline value/Stamp Act rates;
W.P. (C) No. 799 of 2019
Contd…/-
[8]
(iii) In areas where land owner/ owners have been offered/
accepted alternate mode of compensation by
concerned corporation/Municipality under Transfer
Development Rights (TDR) policy of State, the licensee
/ Utility shall deposit compensation amount as per (i) &
(ii) above with the concerned Corporation/Municipality/
Local Body or the State Government.
(iv) For this purpose, the width of RoW corridor shall not be
more than that prescribed in the table at Annex-2 and
shall not be less than the width directly below the
conductors.
3.
Necessary action may kindly be taken accordingly.
These guidelines may not only facilitate an early resolution of
RoW issues and also facilitate completion of the vital
transmission lines through active support of State/UT
administration.
4.
All the States/UTs etc. are requested to take suitable
decision regarding adoption of the guidelines considering that
acquisition of land is a State subject.
Yours faithfully,
(Jyoti Arora)
Joint Secretary (Trans.)
Tele: 011-2371 0389
Copy, along with enclosure, forwarded to the following:
1. Secretaries of Government of India (Infrastructure
Ministries/ Deptt. Including MoEF – As per attached list)
2. Prime Minister’s Office (Kind Attn: Shri Nripendra Mishra,
Principal Secretary to PM)
3. Technical Director, NIC, Ministry of Power with the request
to host on the website of Ministry of Power.
....
Copy to P.S. to Hon’ble MoSP (IC)/ Secretary (Power)/ AS
(BNS)/ AS (BPP)/ All Joint Secretaries/ EA/All Directors/
DSs, Ministry of Power.
--And--
W.P. (C) No. 799 of 2019
Contd…/-
[9]
“GOVERNMENT OF MANIPUR
SECRETARIAT: POWER DEPARTMENT
….
N O T I F I C A T I O N
Dated, Imphal, the 28th March, 2018
No. 14/15/2017-Power: The Governor of Manipur is pleased
to notify the following methodology for payment of
compensation towards damages in regard to Right of Way for
transmission lines in accordance with the Guidelines of
Ministry of Power, Govt. of India, vide Ref. No. 3/7/2015Trans. Dated 15.10.2015 for maintaining uniformity in
compensation payment to the affected land owners during
construction of transmission lines. These guidelines of
payment methodology of compensation towards “damages”
as stipulated in Section 67 & 68 of the Electricity Act, 2003
read with Section 10 and 16 of Indian Telegraph Act, 1885
shall be in addition to the compensation towards normal crop
and tree damages. This amount will be payable only for
transmission lines supported by tower base of 66 KV and
above and not for sub-transmission and distribution lines
below 66 KV.
i.
Compensation @ 85% of the land value as determined
by District Magistrate or any other authority based on
Circle rate/Guideline value/Stamp Act rates for tower
base area (between four legs) impacted severely due to
installation of tower/ pylon structure.
ii.
Compensation towards diminution of land value in the
width of Right of Way (RoW) corridor due to laying of
transmission line and imposing certain restriction which
would be decided by the States as per categorization/
type of land in different places of States, subject to a
maximum of 15% of land value as determined based on
Circle rate/ Guidelines value/Stamp Act rates.
iii.
In areas where land owner/owners have been
offered/accepted alternate mode of compensation by
concerned corporation/ Municipality under Transfer
Development Rights (TDS) policy of State, the licensee/
Utility shall deposit compensation amount as per (i) &
W.P. (C) No. 799 of 2019
Contd…/-
[10]
(ii) above with the concerned Corporation/Municipality/
Local body or the State Government.
iv. For this purpose, the width of RoW corridor shall not be
more than that prescribed in table below and shall not
be less than the width directly below the conductors.
Table for RoW width for different voltage line*
Transmission voltage in KV
Width of Right of Way in
metres
66 KV
132 KV
220 KV
400 KV S/C
400 KV D/C
765 S/C
(Width delta configuration)
765 D/C
* Width of Right of Way is as per Ministry of Environment
& Forest (MoEF) guidelines dated 05.05.2014
These guidelines shall be effective from the date of issue
of notification for those new transmission line/ projects. This
notification shall not be applicable for i) existing transmission
lines which are already in service or completed portion of all
ongoing transmission lines, ii) maintenance of any existing
transmission line, iii) stringing of second circuit on the existing
Double Circuit transmission towers, iv) re-conducting/ restringing of aged transmission lines and v) repairing/
reconstruction of existing transmission towers etc.
This is issued with the approval of the Cabinet in its
meeting held on 12/03/2018 and in consultation with Law
Department and Finance Department, Govt. of Manipur.
By order etc.
(Rajani Ranjan Rashmi)
Chief Secretary (Power), Govt. of Manipur.
W.P. (C) No. 799 of 2019
Contd…/-
[11]
Copy to:
1. Secretary to Chief Minister, Manipur.
2. P.P.S. to Minister (Finance/Power/Revenue),
Government of Manipur.
3. The Joint Secretary (Trans.), Ministry of Power,
Government of India, Shram Shakti Bhawan, Rafi
Marg, New Delhi – 110001.
4. Managing Director (MSPCL/MSPDCL).
5. The Executive Director, NERTS, Power Grid Corp. of
India Ltd. (PGCIL), Dongtieh, Lower Nongrah,
Lapalang, Shillong 793006, Meghalaya.
6. Director, Printing & Stationery, Government of
Manipur, for publication in the State Gazette
Notification.
7. Guard File.”
[7]
From the perusal of the letter dated 15-10-2015, it is seen that
it is a letter addressed to all the State Governments through their Chief
Secretaries and other stakeholders informing that the Committee
constituted with representative from various State Governments and
others, had submitted its report and that its recommendations had been
formulated in the form of guidelines for determining compensation
towards ‘damages’ as stipulated in Section 67 and 68 of the Indian
Electricity Act, 2003 with Section 10 and 16 of the Indian Telegraph
Act, 1885. As many as four guidelines have been enumerated therein.
It is further seen from paragraph 4 of the said letter that all the States/
UTs etc. were requested to take suitable decision regarding adoption of
the guidelines considering that acquisition of land is a State subject.
This para 4 makes it very clear that the application of the guidelines as
enumerated in the letter, was not automatic and that they were required
to be adopted by the States/ UTs and others, for which the appropriate
W.P. (C) No. 799 of 2019
Contd…/-
[12]
decision ought to be taken by the States/ UTs in that regard. There is
no controversy about these guidelines formulated by the Government
of India. All that has been submitted by the counsel appearing for the
respondent, is that pursuant to the request made by the Government of
India as mentioned in para 4 of the letter, the Government of Manipur
had issued a Notification dated 28-03-2018 adopting the said
guidelines. It has further been submitted by him that the guidelines
have been made effective from the date of notification for those new
transmission lines/ projects and balance uncompleted portion of
ongoing transmission lines and that they will have no application to
existing transmission lines which are already in service. On perusal of
the said Notification, the submission of the counsel appearing for the
respondent has some force and merit. So far as the petitioner’s case is
concerned, the transmission line was erected/ commissioned in the
year, 1988, when his father was the chief of the village. The
observations made by this Court in the earlier writ petition being WP(C)
No.498 of 2018 as regards the facts and circumstances, are relevant
and will clearly demonstrate that the instant writ petition is devoid of
any merit and is accordingly liable to be dismissed. Para 7 and 8 of the
judgment and order dated 06-05-2019 read as under:
“[7]
The undisputed facts which have emerged from the
pleadings of the parties as aforesaid, are that the petitioner is
the Chief of the Mongbung Village as is evident from the
certificate dated 20-07-2015 produced by him along with
rejoinder affidavit. At the time when the transmission line was
commissioned/
W.P. (C) No. 799 of 2019
erected
on
01-09-1988 NEEPCO,
the
Contd…/-
[13]
petitioner’s father was the Chief of the said village. Prior to
the erection/ installation of the transmission line, a joint
inspection was conducted as is evident from the letter dated
12-06-1987 of the SDO (Elect), NEEPCO Ltd., Jiribam
addressed to the Addl. District Magistrate (I), Jiribam and
after the land of the petitioner being inspected, on 28-071987 tree, crop/ surface damage was assessed and the
evaluation of different fruits was also done. The petitioner
signed an undertaking/ letter of acceptance whereby he
agreed to the formula deduced by the NEEPCO, Jiribam for
the proportionate deduction from the claim in respect of the
transmission line. The compensation thereof was paid to the
petitioner without any objection being raised by him at that
point of time.
[8]
After about 30 years and that too, after the
petitioner having been declared as the Chief of the
Mongbung Village, claimed compensation in respect of the
damages caused to his land on the ground that he is entitled
to compensation under the provisions of Article 300-A. In
order to substantiate it, the learned counsel appearing for the
petitioner has relied upon various decisions of the Hon’ble
Supreme Court as mentioned hereinabove. But on perusal
thereof, it is seen that the facts of the said cases are not
identical to that of the present case and therefore, the same
will have no application at all. In the said cases, since the
land was acquired, the question of payment of compensation
did arise. But in the present case, the land of the petitioner
was not acquired at all by the respondent No.4. The learned
counsel appearing for the respondent No.4 made his
submission raising some relevant points-one, the land of the
petitioner was not acquired by the respondent No.4 except
the use thereof; two, so far as the damages caused to the
land are concerned, it was duly assessed by the concerned
authorities and the compensation thereof was paid,
thereafter, to the petitioner; three, the instant writ petitioner is
barred by delay and laches, as the same has been filed after
W.P. (C) No. 799 of 2019
Contd…/-
[14]
about thirty years from the day when the cause of action
arose; four, in the instant petition, the petitioner has
suppressed material facts as regards the payment of
compensation and five, the respondent No.4 which took over
the assets and liabilities of NEEPCO, is required to act in
accordance with the provisions of the Telegraph Act, 1885.
His submissions have some force and merit. Section 10 of
the Telegraph Act, 1885 reads as under:
“10. Power for telegraph authority to place and maintain
telegraph lines and posts-The telegraph authority may,
from time to time, place and maintain a telegraph line
under, over, along or across, and posts in or upon,
any immovable property:Provided that –
(a)
The telegraph authority shall not exercise the powers
conferred by this section except for the purposes of a
telegraph established or maintained by the Central
Government, or to be so established or maintained;
(b) The Central Government shall not acquire any right
other than that of user only in the property under, over,
along, across, in or upon which the telegraph authority
places any telegraph line or post; and
(c)
Except as hereinafter provided, the telegraph authority
shall not exercise those powers in respect of any
property vested in or under the control or management
of any local authority, without the permission of that
authority; and
(d) In the exercise of the powers conferred by this section,
the telegraph authority shall do as little damage as
possible, and, when it has exercised those powers in
respect of any property other than that referred to in
clause (c), shall pay full compensation to all persons
interested for any damage sustained by them by
reason of the exercise of those powers.”
W.P. (C) No. 799 of 2019
Contd…/-
[15]
[8]
In view of the above and for the reasons stated hereinabove,
the instant writ petition is dismissed with no order as to costs.
JUDGE
FR/NFR
Devananda
W.P. (C) No. 799 of 2019
Contd…/-
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review