IN THE HIGH COURT OF DELHI AT NEW DELHI
%
Judgment reserved on: 13.01.2026
Judgment pronounced on: 21.01.2026
+
O.M.P. (COMM) 337/2023
S AND S CONSTRUCTION CO
Through:
.....Petitioner
Mr. Kunwar Chandresh & Ms.
Poonam Prasad, Advs.
versus
UNION OF INDIA THROUGH E E B F D II
Through:
.....Respondent
Mr. Vikram Jaitley, CGSC with
Ms. Shreya Jaitley, Adv. with
Mr. Rakesh Kumar, EE, BFD
Bikaner CPWD.
CORAM:
HON'BLE MR. JUSTICE AVNEESH JHINGAN
JUDGMENT
1.
This petition is filed under Section 34 of the Arbitration and
Conciliation Act, 1996 (for short „the Act‟) challenging the arbitral
award dated 18.04.2023 (for short „the Award‟).
2.
The relevant facts are that the petitioner/claimant was awarded
a tender by the Executive Engineer, Border Fencing Division-II,
CPWD, New Delhi and the contract was entered on 04.06.2010. The
estimated cost of work was Rs.19,43,10,348/-. The petitioner
furnished a performance bank guarantee equivalent to five percent of
the tender amount. The work was to be completed within eight
months. The completion certificate mentioning the defects in the work
done was issued on 17.12.2019. Dispute between the parties in
O.M.P. (COMM) 337/2023
Signed By:CHANCHAL
16:49:07
compliance with Clause 25 of the General Conditions of Contract (for
short „the GCC‟) was referred to arbitration. The arbitrator was
appointed on 19.04.2022 and the proceedings culminated in the
impugned award. Out of the sixteen claims made by the petitioner,
seven were rejected. The counter-claims filed by the respondent
beyond the period prescribed under Section 23(4) of the Act were
rejected. Hence, the present petition.
3.
This petition is filed being aggrieved by the rejection of the
following claims.
S.No.
CLAIM NO.
CLAIM DESCRIPTION
1.
Claim No.1
2.
Claim No.3
3.
Claim No.4
4.
Claim No.5
5.
Claim No.6
6.
Claim No.7
7.
Claim No.12
Claim on account of illegally withheld
amount for non-sanctioning of deviation items
amounting to Rs.13,00,000/The claim of Rs.9,50,285/- for extra interest
recovered on Mobilization Advance for the
delay in work the beyond the stipulated date
of completion.
Claim of interest on account of amount
wrongfully
withheld
for
Milestones
amounting to Rs.16,93,470/Claim amounting to Rs.2,84,07,336/- for
damages due to rise in price for material other
than material covered under Clause 10CA
used in the work done during the extended
period (Claim amended to Rs.357,93,677 at
rejoinder stage).
Claim
of
damages
amounting
to
Rs.9,73,66,774/- on account of onsite and off
site overhead during prolongation of contract.
Claim amounting to Rs.7,45,40,000/- on
account of work done in R.D. 2.4 km to 27
km in the C/o ITBP Road from Nyu Sobla to
Sela Tedang.
Claim amounting to Rs 1,47,19,500/ on
account of non-payment for extra work
executed to restore the road connectivity after
disaster in June 2013.
O.M.P. (COMM) 337/2023
Signed By:CHANCHAL
16:49:07
4.
Learned counsel for the petitioner argued with regard to claim
no.1, that the withholding/deduction of Rs. 13,00,000/- was without
issuance of notice and further that no deduction could be made under
clause 17 of the GCC.
4.1
With regard to claim no.3, the submission is that the delay and
prolongation of the work was not attributed to the petitioner and the
interest of Rs.9,50,285/- was wrongly charged on the mobilisation
advance for the period of delay beyond the stipulated date of
completion. The argument is that the mobilisation advance was
invested in the project and not utilised by the petitioner.
4.2
Vis-a-vis claim no. 4, the argument is that the amount was
wrongly withheld for failure of the petitioner to complete the work
upto the stipulated milestones and the petitioner should be
compensated with interest. The submission is that once the time to
complete the work was extended, the milestone should have been
rescheduled. Grievance is that the claim was rejected by a nonspeaking award.
4.3
So far as claim no.5 is concerned, the grievance is that the
arbitrator erred in considering that the claim was not covered under
Clause 10CC of the GCC whereas the claim was made under Section
73 of the Indian Contract Act, 1872 (for short „the Contract Act‟).
Submission is that the reasons recorded by the arbitrator for rejection
of the claim are not tenable.
4.4
With regard to claim no.6, the contention is that the profit from
work done had no nexus with the on-site and off-site overheads
damages consequent to the prolongation of the contract. The claim
O.M.P. (COMM) 337/2023
Signed By:CHANCHAL
16:49:07
was made under Section 73 of the Contract Act and was not dependant
on existence of clause in GCC.
4.5
The contention for claim no.7 is that the amount of
Rs.7,45,40,000/- claimed for the work done on RD 24 Km to 27 Km
was erroneously rejected. The submission is that the scope of work of
the petitioner was for RD 0 Km to 10 Km but the work in question
was undertaken by the petitioner on asking of the respondent and yet
in spite of repeated requests joint inspection was not carried out to
verify the work done. The submission is that the measurements made
by the petitioner were head-wise and ought to have been accepted. It is
contended that while making payment of Rs.41,09,530/- the
respondent had not considered that the petitioner not only removed
debris from the road but also the material which later slid from the
slope of the hills.
4.6
Lastly, the rejection of the claim no.12 is challenged stating that
the payment of Rs.10,74,000/- directly made by the district
administration was for different work undertaken by the petitioner.
The grievance is that the unproved stand of the respondent that the
work was not done by the petitioner but got completed from another
agency was accepted.
5.
Per contra, there cannot be re-appreciation of evidence to
interfere with the findings recorded.
5.1
For claim no.1, the submission is that before making deductions
notice dated 11.12.2019 and reminder dated 17.01.2020 were issued
and vide communication dated 02.11.2020, the petitioner was asked to
deposit the expenditure incurred for removing the defects.
O.M.P. (COMM) 337/2023
Signed By:CHANCHAL
16:49:07
5.2
It is argued that the mobilisation advance was not a matter of
right but a loan taken by the petitioner at an agreed rate of interest
between the two parties and the interest was recovered for the period
the amount was utilised by the petitioner.
5.3
As per the respondent, no interest on the amount withheld on
account of non-completion of work upto the stipulated milestone
could be claimed as per clause 2 of the GCC. Moreover, the petitioner
never applied for rescheduling of the milestone. The delay in
completion of work was attributed to both parties and the extension of
time for completion of work was granted without any compensation.
5.4
The rejection of claim no.5 is defended.
5.5
The submission is that the petitioner failed to prove the actual
damages suffered due to prolongation of the contract, which is a sine
qua non for claiming damages under Section 73 of the Contract Act.
5.6
Learned counsel for the respondent submits that owing to the
failure of the petitioner to substantiate the actual work done, claim
no.7 was rejected.
5.7
Lastly, claim no.12 is refuted on the ground that the claim was
false and no work was done by the petitioner except for which the
consideration was paid by the district administration. Rather the rest
of the work was executed by another agency for which the counterclaim was filed, albeit rejected on technical ground.
6.
Heard the learned counsel for the parties at length and perused
the record. No other contention than those as noted above has been
pressed.
7.
The petitioner submitted that an amount of Rs.13,00,000/- was
O.M.P. (COMM) 337/2023
Signed By:CHANCHAL
16:49:07
wrongly withheld without issuing notice but the respondent proved
that after issuance of a notice dated 11.12.2019 and that the action was
taken under clause 17 of the GCC. It would be appropriate to
reproduce the said clause:“CLAUSE17 Contractor Liable for Damages, defects during
maintenance period
If the contractor or his working people or servants shall break,
deface, injure or destory any part of building in which they may
be working, or any building, road, road kerb, fence, enclosure,
water pipe, cables, drains, electric or telephone post or wires,
trees, grass or grassland, or cultivated ground contiguous to the
premises on which the work or any part is being executed, or if
any damage shall happen to the work while in progress, from
any cause whatever or if any defect, shrinkage or other faults
appear in the work within twelve months (six months in the case
of work costing Rs. Ten lacs and below except road work) after
a certificate final or otherwise of its completion shall have been
given by the Engineer-in-Charge as aforesaid arising out of
defect or improper materials or workmanship the contractor
shall upon receipt of a notice in writing on that behalf make the
same good at his own expense or in default the Engineer-inCharge cause the same to be made good by other workmen and
deduct the expense from any sums that may be due or at any
time thereafter may become due to the contractor, or from his
security deposit or the proceeds of sale thereof or of a sufficient
portion thereof. The security deposit of the contractor shall not
be refunded before the expiry of twelve months (six months in
the case of work costing Rs. Ten lacs and below except road
work) after the issue of the certificate final or otherwise, of
completion of work, or till the final bill has been prepared and
passed whichever is later.
Provided that in the case of road work, if in the opinion of the
Engineer-in-Charge, half of the security deposit is sufficient, to
meet all liabilities of the contractor under this contract, half of
the security deposit will be refundable after six months and the
remaining half after twelve months of the issue of the said
certificate of completion or till the final bill has been prepared
and passed whichever is later.
In case of Maintenance and Operation works of E&M services,
the security deposit deducted from contractors shall be refunded
within one month from the date of final payment or within one
O.M.P. (COMM) 337/2023
Signed By:CHANCHAL
16:49:07
month from the date of completion of the maintenance contract
which ever is earlier.”
From a reading of clause 17 of the GCC it is clear that in the event of
defect, shrinkage or other fault in the work within twelve months after
the issuance of final certificate the contractor had to make good the
defects upon receipt of a notice. In case of failure to do the needful the
Engineer in-charge shall get the defects rectified by other workmen
and deduct the expenses from the amount due to the contractor or
from the security deposit. The completion certificate dated 17.12.2019
was issued to the petitioner and the defects were mentioned therein.
The notice issued to the petitioner under clause 17 of the GCC and the
reminder was produced as Exhibit R-104 and Exhibit R-105
respectively. The communication to the petitioner to deposit the
expenditure incurred for removing the defects is Exhibit R-107. The
contention that the deduction was made without issuance of notice and
no deduction could be made under clause 17 of the GCC is illfounded.
8.
Under clause 10B (ii) and (iv) of the GCC the petitioner had an
option to get a mobilisation advance from the respondent, bearing an
interest rate of ten per cent per annum. The petitioner partially availed
this option. Interest was charged for the period the amount of
mobilisation advance was utilised. The arbitrator rightly rejected the
argument that interest should not have been charged for the period of
delay. It was noted that in the eventuality of not taking the
mobilisation advance petitioner would have made own investment.
Further the petitioner was well aware that the mobilisation advance
O.M.P. (COMM) 337/2023
Signed By:CHANCHAL
16:49:07
shall bear interest at a particular rate and was meant for mobilisation
of resources for the project only. Interest was charged only for the
period for which the mobilisation advance was utilized and not
thereafter.
9.
Claim no. 4, seeking interest on the amount withheld for not
achieving the milestone was rejected on two grounds. Firstly, that the
petitioner made no request for rescheduling of milestones and
secondly, that the claim of interest on the payment withheld is barred
under Clause 2 of the GCC. The contention that once the time for
completion was extended the milestone should have been rescheduled
need not be dilated upon in view of clause 2 of the GCC stipulating
that no interest is payable on the withheld amount. It is not the case
put forth that clause 2 was not applicable. So far as the submission
that claim was rejected by a non-speaking award, suffice to say that
the claim for interest was barred by clause 2 the GCC. The absence of
detailed reasons caused no prejudice to the petitioner and the
conclusion arrived at remains unaffected. The award calls for no
interference.
10.
Claim no.5, seeking damages under Section 73 of the Contract
Act due to rise in prices of material not covered under clause 10CA
was rejected for the failure of the petitioner to adduce evidence of the
actual damages suffered. The arbitrator considered the admission of
the petitioner that the claim was neither covered under clause 10CA
nor 10CC. The challenge to the other reasons recorded for rejecting
the claim need not be gone into, as one reason upheld for rejecting the
claim shall be sufficient. It would be apposite to note that actual
O.M.P. (COMM) 337/2023
Signed By:CHANCHAL
16:49:07
damage suffered was not proved for raising claim under Section 73 of
the Contract Act and only the head-wise calculation given by the
petitioner were relied upon which remained unsubstantiated. A person
making a claim under Section 73 of the Contract Act has to prove that
actual damage was caused. Reference in this regard be made to the
following judgment:10.1 The Supreme Court in Unibros vs. All India Radio 2023 SCC
OnLine SC 1366 held:“19. The law, as it should stand thus, is that for claims
related to loss of profit, profitability or opportunities to
succeed, one would be required to establish the
following conditions : first, there was a delay in the
completion of the contract; second, such delay is not
attributable to the claimant; third, the claimant's status
as an established contractor, handling substantial
projects; and fourth, credible evidence to substantiate
the claim of loss of profitability. On perusal of the
records, we are satisfied that the fourth condition,
namely, the evidence to substantiate the claim of loss of
profitability remains unfulfilled in the present case.”
(Emphasis Supplied)
11.
Claim no.6, for damages on account of on-site and off-site
overheads due to the prolongation of the contract also remained
unsubstantiated, the petitioner failed to submit proof of the actual
damages suffered. Another aspect to be considered is that the
petitioner was awarded a contract of approximately Rs.17 crores and
ultimately executed work of approximately Rs.30 crores. It was not
demonstrated that damage was suffered in spite of escalated price of
revised work, in this backdrop the arbitrator recorded that the
O.M.P. (COMM) 337/2023
Signed By:CHANCHAL
16:49:07
petitioner executed 1.78 times of the tendered value of the work and
earned profit therefrom. The argument that the claim was under
Section 73 of the Contract Act and that the arbitrator erred in holding
that there was no clause in the contract for compensating overhead
expenditure is of no avail, in view of failure of the petitioner to prove
the actual damages suffered. The head-wise calculation submitted by
the petitioner for making the claim by itself shall not be sufficient for
discharging onus of proving actual damage suffered.
12.
The claim of the petitioner for the work done on RD 24 Km to
27 Km was opposed by the respondent stating that no work was
actually done. The arbitrator recorded that in spite of sufficient
opportunities granted to the petitioner no document or evidence was
produced for proving the work done. There was no material on record
except the self-serving version of the petitioner. It was also taken into
account that no assessment of the ground level at the time of taking
over the work by the petitioner was carried out for enabling to verify
the work done on the spot. The contract provided that joint
measurement shall be undertaken by both the parties to verify the
work done but no such joint measurement was conducted. The work
was started by the petitioner in June, 2010. A letter informing
stoppage of work and requesting for joint inspection was issued on
17.06.2013 but by letter dated 22.06.2013, the petitioner informed the
respondent that due to natural calamity the petitioner suffered heavy
losses and site had become inaccessible. The clause for joint
measurement is reproduced below:“CLAUSE 6 – Measurements of work done
O.M.P. (COMM) 337/2023
Signed By:CHANCHAL
16:49:07
Engineer-in-Charge shall, except as otherwise provided,
ascertain and determine by measurement, the value in
accordance with the contract of work done.
All measurement of all items having financial value shall be
entered in Measurement Book and/or level field book so that a
complete record is obtained of all works performed under the
contract. All measurements and levels shall be taken jointly by
the Engineer-in-Charge or his authorised representative and by
the contractor or his authorised representative from time to time
during the progress of the work and such measurements shall be
signed and dated by the Engineer-in-Charge and the contractor
or their representatives in token of their acceptance. If the
contractor objects to any of the measurements recorded, a note
shall be made to that effect with reason and signed by both the
parties.
If for any reason the contractor or his authorised representative
is not available and the work of recording measurements is
suspended by the Engineer-in-Charge or his representative, the
Engineer-in-Charge and the Department shall not entertain any
claim from contractor for any loss or damages on this account. If
the contractor or his authorised representative does not remain
present at the time of such measurements after the contractor or
his authorized representative has been given a notice in writing
three (3) days in advance or fails to countersign or to record
objection within a week from the date of the measurement, then
such measurements recorded in his absence by the Engineer-inCharge or his representative shall be deemed to be accepted by
the Contractor.”
13.
The finding recorded by the arbitrator that actually the work
done was not proved by the petitioner needs no interference. Even at
this stage it is argued that the head-wise calculation given by the
petitioner should have been accepted. It cannot be lost sight of that the
district administration made payment to the petitioner but it was
claimed that more work was done than the amount paid but no
evidence to this effect was produced.
14.
The petitioner claimed that work was executed to restore the
road connectivity after the disaster in June, 2013 in Uttarakhand. For
O.M.P. (COMM) 337/2023
Signed By:CHANCHAL
16:49:07
the work done by the petitioner the district administration verified the
work by joint measurement of the State Government and the CPWD
and directly paid Rs. 10,74,000/- for the work executed. The claim
that the payment received directly was for a different work remained a
bald statement. On the other hand, the respondent withdrew the work
assigned to the petitioner and got it executed through another agency.
The counter-claim for recovery of expenses incurred for execution of
the work through another agency was rejected having been filed
beyond the limitation prescribed under the Arbitration Act. The
submission that the respondent failed to prove the execution of the
work through another agency does not enhance the case of the
petitioner. The petitioner claimed to have executed the work and had
to discharge the onus and the claimant has to stand on its own legs.
Negative onus cannot be cast upon the respondent to prove that the
work was not done by the petitioner.
15.
Learned
counsel
for
the
petitioner
submits
that
the
measurements furnished by the petitioner were not considered by the
arbitrator and the award is perverse, lack merits. The head-wise
measurement produced by the petitioner was not supported by
evidence or documentary proof and claim by itself is not an evidence
and its non-consideration shall not vitiate the award with perversity.
16.
The law is well settled that the scope of interference under
Section 34 is extremely limited. Every legal or factual error in the
award does not call for interference under Section 34 of the Act. There
cannot be re-appreciation of evidence. The challenge to the arbitral
award can only be on the grounds mentioned in Section 34 of the Act.
O.M.P. (COMM) 337/2023
Signed By:CHANCHAL
16:49:07
The award should not be interfered with until the conclusion arrived at
is perverse. Proceedings under Section 34 cannot be equated with
appellate jurisdiction and there can be no re-appreciation of evidence.
Interference is limited to the grounds specified under the Act,
including violation of public policy, fundamental principles of Indian
law or patent illegality going to the root of the matter. Errors of law or
fact revealed upon reassessment of the evidence shall not justify
setting aside an arbitral award unless it falls within the ambit of the
grounds mentioned under Section 34 of the Act. Reference be made to
the following judgements of the Supreme Court:
16.1 The apex court in Sepco Electric Power Construction
Corporation Vs. GMR Kamalanga Energy Ltd. 2025 INSC 1171
recently emphasized held:
“97……..Therefore, it appears that even if the arbitrator‟s
legal or factual reasoning is faulty, the courts ought to
ideally refrain from interfering with an award until an error
of law is evident from the award itself or in a document
that forms an integral component thereof.”
16.2 The Supreme Court in Ramesh Kumar Jain vs. Bharat
Aluminium Company Limited 2025 SCC OnLine SC 2857 held as
under:
“28. The bare perusal of section 34 mandates a narrow
lens of supervisory jurisdiction to set aside the arbitral
award strictly on the grounds and parameters enumerated
in sub-section (2) & (3) thereof. The interference is
permitted where the award is found to be in contravention
to public policy of India; is contrary to the fundamental
policy of Indian Law; or offends the most basic notions of
morality or justice. Hence, a plain and purposive reading
O.M.P. (COMM) 337/2023
Signed By:CHANCHAL
16:49:07
of the section 34 makes it abundantly clear that the scope
of interference by a judicial body is extremely narrow. It
is a settled proposition of law as has been constantly
observed by this court and we reiterate, the courts
exercising jurisdiction under section 34 do not sit in
appeal over the arbitral award hence they are not
expected to examine the legality, reasonableness or
correctness of findings on facts or law unless they come
under any of grounds mandated in the said provision. In
ONGC Limited. v. Saw Pipes Limited14, this court held
that an award can be set aside under Section 34 on the
following grounds:“(a) contravention of fundamental
policy of Indian law; or (b) the interest of India; or (c)
justice or morality, or (d) in addition, if it is patently
illegal.”
16.3 In Consolidated Construction Consortium Limited Vs.
Software Technology Parks of India (2025) 7 SCC 757 it was held
as under:
“46. Scope of Section 34 of the 1996 Act is now well
crystallized by a plethora of judgments of this Court.
Section 34 is not in the nature of an appellate provision. It
provides for setting aside an arbitral award that too only
on very limited grounds i.e. as those contained in Subsections (2) and (2-A) of Section 34. It is the only remedy
for setting aside an arbitral award. An arbitral award is
not liable to be interfered with only on the ground that the
award is illegal or is erroneous in law which would
require re-appraisal of the evidence adduced before the
arbitral tribunal. If two views are possible, there is no
scope for the court to re-appraise the evidence and to take
the view other than the one taken by the arbitrator. The
view taken by the arbitral tribunal is ordinarily to be
accepted and allowed to prevail. Thus, the scope of
interference in arbitral matters is only confined to the
extent envisaged Under Section 34 of the Act. The court
exercising powers Under Section 34 has perforce to limit
O.M.P. (COMM) 337/2023
Signed By:CHANCHAL
16:49:07
its jurisdiction within the four corners of Section 34. It
cannot travel beyond Section 34. Thus, proceedings
Under Section 34 are summary in nature and not like a
full-fledged civil suit or a civil appeal. The award as such
cannot be touched unless it is contrary to the substantive
provisions of law or Section 34 of the 1996 Act or the
terms of the agreement.”
16.4 In PSA Sical Terminals Pvt Ltd. vs. The Board of Trustees of
V.O. Chidambranar Port Trust Tuticorin And Others (2023) 15
SCC 781 it was held:
“38. Before that, it will be apposite to refer to the
judgment of this Court in MMTC Ltd. [MMTC Ltd. v.
Vedanta Ltd., (2019) 4 SCC 163 : (2019) 2 SCC (Civ)
293] , wherein this Court has revisited the position of law
with regard to scope of interference with an arbitral
award in India. It will be relevant to refer to the following
observations of this Court in MMTC Ltd. [MMTC Ltd. v.
Vedanta Ltd., (2019) 4 SCC 163 : (2019) 2 SCC (Civ)
293] : (SCC pp. 166-67, paras 11-14)
“11. As far as Section 34 is concerned, the position is
well-settled by now that the Court does not sit in
appeal over the arbitral award and may interfere on
merits on the limited ground provided under Section
34(2)(b)(ii) i.e. if the award is against the public policy
of India. As per the legal position clarified through
decisions of this Court prior to the amendments to the
1996 Act in 2015, a violation of Indian public policy,
in turn, includes a violation of the fundamental policy
of Indian law, a violation of the interest of India,
conflict with justice or morality, and the existence of
patent illegality in the arbitral award. Additionally, the
concept of the “fundamental policy of Indian law”
would cover compliance with statutes and judicial
precedents, adopting a judicial approach, compliance
with the principles of natural justice, and Wednesbury
[Associated Provincial Picture Houses Ltd. v.
O.M.P. (COMM) 337/2023
Signed By:CHANCHAL
16:49:07
Wednesbury Corpn., (1948) 1 KB 223 (CA)]
reasonableness. Furthermore, “patent illegality” itself
has been held to mean contravention of the substantive
law of India, contravention of the 1996 Act, and
contravention of the terms of the contract.
12. It is only if one of these conditions is met that the
Court may interfere with an arbitral award in terms of
Section 34(2)(b)(ii), but such interference does not
entail a review of the merits of the dispute, and is
limited to situations where the findings of the arbitrator
are arbitrary, capricious or perverse, or when the
conscience of the Court is shocked, or when the
illegality is not trivial but goes to the root of the matter.
An arbitral award may not be interfered with if the
view taken by the arbitrator is a possible view based on
facts. (See Associate Builders v. DDA [Associate
Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC
(Civ) 204] . Also see ONGC Ltd. v. Saw Pipes Ltd.
[ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705] ;
Hindustan Zinc Ltd. v. Friends CoalCarbonisation
[Hindustan Zinc Ltd. v. Friends Coal Carbonisation,
(2006) 4 SCC 445] ; and McDermott International Inc.
v. Burn Standard Co. Ltd. [McDermott International
Inc. v. Burn Standard Co. Ltd., (2006) 11 SCC 181] )
14. As far as interference with an order made under
Section 34, as per Section 37, is concerned, it cannot
be disputed that such interference under Section 37
cannot travel beyond the restrictions laid down under
Section 34. In other words, the court cannot undertake
an independent assessment of the merits of the award,
and must only ascertain that the exercise of power by
the court under Section 34 has not exceeded the scope
of the provision. Thus, it is evident that in case an
arbitral award has been confirmed by the court under
Section 34 and by the court in an appeal under Section
37, this Court must be extremely cautious and slow to
disturb such concurrent findings.””
O.M.P. (COMM) 337/2023
Signed By:CHANCHAL
16:49:07
(Emphasis Supplied)
17.
The view taken by the arbitrator is plausible, not vitiated by
patent legality, perversity or conflict in public policy of India and no
case is made out for interference by this Court under Section 34 of the
Act.
18.
The petition is dismissed. All pending applications stand
dismissed.
AVNEESH JHINGAN, J.
JANUARY 21, 2026
Ch
Reportable:- Yes
O.M.P. (COMM) 337/2023
Signed By:CHANCHAL
16:49:07
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review