Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
Page No.# 1/8
GAHC010284412025
undefined
THE GAUHATI HIGH COURT
(HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Case No. : PIL/5/2026
RAJON ALI BORBHUIYA AND ANR
S/O- FEAJUL ALI BARBHUIYA, VILL. BARUNGA PT- I, P.O.- TIKAR
BURUNGA, DIST. CACHAR, ASSAM.
2: RAJU SINGHA
S/O- RAI MOHAN SINGHA
VILL. BURUNGA PT- II
P.O.- TIKAR BURUNGA
DIST. CACHAR
ASSA
VERSUS
THE UNION OF INDIA AND 12 ORS
TO BE REPRESENTED BY THE SECRETARY TO THE GOVERNMENT OF
INDIA, MINISTRY OF ENVIRONMENT, FOREST AND CLIMATE CHANGE,
INDIRA PARYAVARAN BHAWAN JORBAGH ROAD, NEW DELHI-110003.
2:THE STATE OF ASSAM
TO BE REPRESENTED BY THE COMMISSIONER AND SECRETARY TO THE
GOVERNMENT OF ASSAM
MINISTRY OF ENVIRONMENT
FOREST AND CLIMATE CHANGE
DISPUR
GUWAHATI-781006.
3:THE DIVISIONAL FOREST OFFICER
CACHAR
SILCHAR
P.O- SILCHAR
DIST- CACHAR
ASSAM. PIN - 788001.
4:THE COMMISSIONER
Page No.# 2/8
INDUSTRIES AND COMMERCE
ASSAM
UDYOG BHAWAN
BAMUNIMAIDAM
GUWAHATI- 21.
5:THE GENERAL MANAGER
DISTRICT INDUSTRIES AND COMMERCE CENTRE
CACHAR
SONAI ROAD
SILCHAR
P.O.- SILCHAR
DIST- CACHAR
ASSAM. PIN - 788001.
6:THE FUNCTIONAL MANAGER
DISTRICT INDUSTRIES AND COMMERCE
CACHAR
SILCHAR
ASSAM. PIN-788001
7:THE REGIONAL EXECUTIVE ENGINEER
POLLUTION CONTROL BOARD
SILCHAR
P.O- SILCHAR
DIST- CACHAR
ASSAM
PIN-788001.
8:THE DISTRICT COMMISSIONER
CACHAR
SILCHAR
P.O- SILCHAR
DIST- CACHAR
ASSAM. PIN-788001.
9:THE JOINT DIRECTOR OF HEALTH SERVICES
CACHAR
SILCHAR
P.O.- SILCHAR
DIST- CACHAR
ASSAM. PIN- 788001.
10:THE DISTRICT AGRICULTURAL OFFICER
P.O- SILCHAR
DIST- CACHAR
ASSAM. PIN-788001
Page No.# 3/8
11:THE MEMBER SECRETARY
STATE ENVIRONMENT IMPACT ASSESSMENT AUTHORITY
ASSAM
BAMUNIMAIDAM
GUWAHATI-21.
12:THE DIRECTOR
STAR CEMENT NORTH EAST LIMITED
REG. OFFICE KHALIEHRIAT
P.O.- KHALIEHRIAT
DIST.- JANTIA HILLS
MEGHALAYA
PIN- 793200.
13:THE MANAGER
STAR CEMENT NORTH EAST LIMITED
VILL- BURUNGA PT- II
P.O.- TIKAR BURUNGA
DIST. CACHAR
ASSAM
PIN-788001
Advocate for the Petitioner
: MR. P K DEKA, MR F A LASKAR,MR A MALEK
Advocate for the Respondent : DY.S.G.I., SC. AGRICULTURE,SC, PCB,GA, ASSAM,SC,
HEALTH,SC, FOREST
BEFORE
HONOURABLE MR. JUSTICE KALYAN RAI SURANA
HONOURABLE MRS. JUSTICE SUSMITA PHUKAN KHAUND
ORDER
Date : 09.02.2026
(K.R. Surana, J)
Heard Mr. P.K. Deka, learned counsel for the petitioners and Ms. S. Sarma,
learned Standing Counsel, Health Department for respondent No.9, Mr. S.
Baruah, learned counsel, Pollution Control Board, Assam for respondent Nos. 7
& 11 (SEIAA), Ms. R.B. Bora, learned Junior Government Advocate for
respondent Nos. 5, 6 and 8 and Mr. D. Gogoi, learned counsel for respondent
Page No.# 4/8
Nos. 2 and 3.
2.
Aggrieved at the setting up of an industry under the name of Star Cement
Northeast Limited at Village- Burunga, Pt- II, in the district of Cachar, the
petitioners have filed this PIL seeking the following reliefs:
(a) Directing the Respondent authorities to hold an Independent
enquiry into the matter and on being satisfied, close down the setup of the Cement Factory owned by the Star Cement North East
India Limited located at Burunga, in the district of Cachar;
(b) Directing the Respondent authorities to consider the petition
dated 08.12.2025 submitted before the Respondent No. 8 and
(c) In the interim, it is also prayed that Your Lordships may further
be pleased to direct the Respondent authorities to immediately halt
the functioning of the said the Cement Factory owned by the Star
Cement North East India Limited located at Burunga, in the district
of Cachar, till disposal of the instant Public Interest Litigation in the
interest of justice.
3.
The case of the petitioners is that they are local inhabitants of the
concerned village and the villagers are adversely affected due to illegal setting
up of a cement factory which would be a threat to the health of the local
inhabitants and would also adversely affect agriculture and the environment. It
is also projected that about 5000 people are residing in this village in the vicinity
Page No.# 5/8
of the cement factory and these site is close to several government
establishments including railway station, hospital, markets, schools, places of
worship, students’ hostels and is highly densely inhabited. It is also projected
that the land on which the industry has been set up was an agricultural land
and ignoring the larger public interest, the cement factory was established in
such land. The petitioners have questioned how the respondent Nos. 12 and 13
could have obtained permission for conversion of agricultural land for matter of
setting up the cement factory.
4.
The petitioners have filed successive RTI applications before various
authorities on 07.03.2024, 12.09.2024, 13.02.2025 and 25.06.2025 to which
various authorities had given their RTI reply. The petitioners have made a
complaint before the Minister of Environment, Forest and Climate Change, New
Delhi, by complaint dated 29.08.2025 against the setting up of the cement
plant. Copies of the said complaints have also been submitted before the
Ministry of Environment, Government of Assam, and the State Human Rights
Commission.
5.
The grievance of the petitioners is that the industry has been set up
illegally. It is also projected that the petitioner No.1 had approached this Court
earlier by filing WP(C)/6811/2025 and the learned Single Judge by order dated
08.12.2025, was of the view that the issue raised in the said petition was more
in the nature of public interest litigation and accordingly, the petitioners had
proposed to withdraw the petition and file the present PIL.
6.
It is also projected in the PIL that the petitioners have no personal
interest in the matter, and they are not guided by self-gain or gain of any
person, institution, or body and there was no motive other than public interest
in filing public interest litigation
Page No.# 6/8
7.
The learned Standing Counsel for the State Environment Impact
Assessment Authority has submitted that in respect of operation of factory
and/or industry in the State of Assam, which includes a cement factory, there
are several environmental factors and parameters for an industry to operate.
Accordingly, it is submitted that the authorities, at any point of time during the
operation of the industry, would be empowered to take appropriate steps if
there is any violation of the parameters and/ or conditions under which the
environment clearance (EC) is issued.
8.
The learned Standing Counsel, Environment Department also endorses the
same view as exposed by the learned Standing Counsel for the SEISS.
9.
It is observed from the documents annexed to this PIL that the petitioner
No.1 has filed an application under the RTI Act to several authorities and that
the State Environment Impact Assessment Authority (‘SEIAA’ for short) on an
RTI application dated 25.06.2025, seeking
for information about the
environment impact assessment report, had provided a reply dated 29.07.2025,
had mentioned that the Environment Impact Assessment Report is a big
volume, and therefore, the petitioner was requested to download the report by
tracking online proposal ‘Parivesh, 2.0 portal’.
10.
The learned Counsel for the petitioner made a statement in the writ
petition that the petitioner had tried to access the said web-portal to download
the said report, but the portal could not be traced out. On the said submission,
the Court visited the website and found the Parivesh portal in the website of the
SEIAA, Assam.
11.
The learned Standing Counsel for the Environment Department, in the
meantime, has also opened up the said portal and the Environment Impact
Assessment Report could be assessed, which was shown Court and to the
Page No.# 7/8
learned counsel for the petitioners.
12.
There is no doubt that the Environment Impact Assessment Report in
respect of the said cement factory is available in public domain in the website of
the portal of SEIAA. It was expected of the petitioners to make their own
assessment of the environmental damage which the area would suffer due to
functioning of the industry. However, without making their own effort, the
petitioners in the prayer –(a) of the PIL,
has requested for holding an
independent inquiry into the matter, and if satisfied, close down the cement
factory.
13.
In the considered opinion of the Court, as the Environment Impact
Assessment report is available in the web portal, linked to the website of SEIAA,
Assam, it was for the petitioners to project as to why the said environment
impact assessment report should not be accepted as correct projection of the
environmental aspect of the locality where the industry is set up and/ or what
nature of adverse environment impact would be made if the cement factory is
allowed to operate. Accordingly, it is the considered opinion of this Court to
refrain from making inquiry, as the petitioners, who could have accessed the
report and informed the Court about any adverse environmental impact, having
elected not to do so. Had any environment damage been done, the petitioners
would have annexed photograph to highlight the same, which has not been
done.
14.
From the statements made in paragraph- 4 and 10 of the PIL, it appears
that the industry against the complaint has already been set up. The petitioners
claim that the factory was illegally constructed, as such, against illegal
construction, the petitioners has filed a complaint before the Assam Human
Rights Commission. We refrain from examining the said complaint, which has
Page No.# 8/8
been filed before a statutory authority. The authorities who had given the
construction permission have not been moved to project that the construction
permission was illegally granted.
15.
Therefore, as there is no material in the record to arrive at a finding that
the Pollution Control Board of Assam and/or the Industries and Commerce
Department of the Government of Assam, including the Commissioner of
Industries and Commerce, cannot take an appropriate steps if setting of the
concerned industry does not comply with the conditions imposed by the
Pollution Control Board.
16.
There is no material in this Public interest litigation to enable the Court to
assume that the setting of the cement industry has impacted the environment in
any manner, or it has caused pollution which is higher than the norms
prescribed by the Pollution Control Board, Assam, the Court does not find any
reason to issue notice in this public interest litigation.
17.
Accordingly, as no grounds have been set up by which it can be presumed
that the concerned Star Cement North East India Limited factory has caused any
damage to the environment due to pollution or otherwise by construction of the
same, this PIL stands dismissed without causing notice on the respondents.
18.
As the matter is being dismissed at the motion stage, there shall be no
order as to costs.
JUDGE
Comparing Assistant
JUDGE
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?