IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment reserved on:17.10.2025
Judgment pronounced on: 22.01.2026
+
O.M.P. (COMM) 595/2020, I.A. 12441/2020, I.A. 12442/2020, I.A.
12443/2020, I.A. 1083/2024
PALI HILLS BREWERIES PRIVATE LIMITED
Through:
.....Petitioner
Mr. Kirtiman Singh, Sr. Adv with Mr.
Varun Rajawat, Adv., Mr Arjun
Chopra,
Adv.
and
Mr.
Maulik
Khurana, Adv.
versus
CARLSBERG INDIA PRIVATE LIMITED
Through:
....Respondent
Mr. Dr. Maurya Vijay Chandra Adv.
and Mr. Manu Prabhakar, Adv.
CORAM:
HON'BLE MR. JUSTICE JASMEET SINGH
JUDGMENT
1.
This is a petition filed under Section 34 of the Arbitration and
Conciliation Act, 1996 (“1996 Act”) seeking to set aside the Arbitral
Award dated 15.09.2020 passed in the matter of “Carlsberg India Pvt.
Ltd. v. Pali Hills Breweries Pvt. Ltd.” wherein out of the 7 claims
preferred by the respondent before the Arbitral Tribunal (“Tribunal”)
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
claim Nos. 1 being liquidated damages and 7 being interest were
allowed, claim Nos. 2 and 3 were rejected and claim Nos. 4, 5 and 6
were not pressed. The Tribunal further rejected all 5 counter claims of
the petitioner.
2.
The challenge in the present petition is to the extent of award of claim
No. 1 and rejection of counter claim Nos. 1, 3 and 4.
FACTUAL BACKGROUND
3.
The respondent (claimant before the Tribunal) is a manufacturer of beer
and the petitioner (respondent before the Tribunal) owns a brewery in
the State of Jharkhand. The parties entered into a Contract Brewing and
Packaging Agreement (“Agreement”) dated 11.12.2015 (“effective
date”).
4.
As per clause No. 14.1 of the Agreement, the petitioner was to provide a
Bank Guarantee (“BG”) of Rs. 3,00,00,000/- within 15 days of the
effective date as a security for CIPL equipment i.e. the 3G labeler and
pull off crowner.
5.
The respondent on 01.02.2016 asked the petitioner for submission of
BG in terms of Clause No. 14.1 of the Contract. The petitioner
thereafter vide emails dated 02.02.2016 and 16.02.2016 sought
extension of time to submit the BG.
6.
The petitioner‟s banker delayed in approving the petitioner‟s proposal
for the BG. Therefore, in order to minimise the delay, petitioner
proposed the issuance of post-dated cheques as a security for CIPL
equipment. The respondent vide email dated 17.06.2016 accepted the
said proposal and amended the BG requirement. The petitioner in
pursuance thereof, issued post-dated cheques to the tune of Rs. 24
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
crores as agreed between the parties inter se.
7.
The respondent, who was to provide the CIPL equipment, did not
provide the same even after submission of the post dated cheques.
Thereafter, the respondent invited the petitioner for training of the
CIPL equipment, more specifically the 3G Labeler at Parag Brewery,
Kolkata. The petitioner after inspecting the Labeler at Parag Brewery,
vide email dated 05.10.2016, requested the respondent not to send the
said Labeler as the same was not in a good condition.
8.
The respondent supplied the said CIPL equipment, i.e. the pull off
crowner and the 3G Labeler on 10.10.2016 and 16.10.2016
respectively.
9.
The petitioner commenced the brewing process. However, as per the
petitioner the 3G Labeler provided by the respondent was defective and
no bottling of the product could take place with the said Labeler. The
same was pointed out by the petitioner in email dated 05.11.2016 and
thereafter on 15.12.2016 the petitioner requested the respondent for
replacement of switch mode power supply of the 3G Labeler which was
allegedly in a burnt condition. The petitioner repeatedly requested the
respondent to replace the 3G Labeler.
10. As per the petitioner, the petitioner was ready to start the contract
manufacturing on 25.10.2016 but due to delay in providing the 3G
Labeler, the start date was deferred to January, 2017. Thereafter, as
well, the petitioner on multiple occasion informed the respondent about
the jamming/ breakdown of the 3G Labeler. The petitioner also
informed the respondent about the decline in production and labour
issues emerging from the said breakdown.
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
11. In August, 2017, the liquor industry in the State of Jharkhand was taken
over by the State Government and the number of retail shops reduced
from 1470 to approximately 300.
12. Owing to the said policy changes and the deterioration of petitioner‟s
financial condition, the petitioner, vide email dated 22.08.2017,
requested the respondent for deletion of clause No. 8, being the
exclusivity clause, of the Agreement, wherein the petitioner could only
exclusively brew and package finished products for the respondent.
13. The dispute arose when in response to the aforesaid communication the
respondent denied all the allegations and refused to recognise the policy
changes. Thereafter, the petitioner again on two other occasions
informed the respondent about the breakdown of 3G Labeler. When the
petitioner did not hear from the respondent with regard to his request of
deletion of clause No. 8, the petitioner terminated the Agreement as per
clause No. 3.2. Pursuant to this the petitioner requested the respondent
to remove its material from petitioner‟s premises. The respondent
raised various monetary claims and invoked Arbitration vide legal
notice under Section 21 of the 1996 Act.
14. The Arbitral Tribunal passed the impugned Award dated 15.09.2020
and awarded claim Nos. 1 and 7 of the respondent and rejected all the
counter claims of the petitioner. The findings of the Tribunal read as
under:
“Claim No. 1
75. The Claimant is entitled to an Award of Rs.25 Lakhs in
accordance with Clause 4.3 of the Agreement. This is the
amount considered to be reasonable by both the parties and
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
the Tribunal has found that although there was a novation
and modification of the Agreement in June 2016, the
Claimant agreed to the modification without waiving any
rights under the Agreement. Before 17 June 2016 there is no
evidence that the Claimant accepted any performance from
the Respondent although after 24 April, the originally
stipulated time period - 135 days for achieving the Start Date
had expired.
….
Counter Claim No.1:
111. The details in relation to Counter Claim No.1 have been
set out at paragraph 33 above. This Counter Claim No.1 is
for electricity charges incurred by the Respondent to
"preserve" the Products. The period during which the
Respondent, as claimed, incurred these charges is October December 2016. The Tribunal has already found that the
Respondent
was
largely
responsible
for
delays
in
achievement of the Start Date. The Respondent is, therefore,
not entitled to any damages for the pre-Start Date period. On
this basis, Counter Claim No.1 is rejected.
Counter Claim No. 3:
112. Counter Claim No.3 is for an amount of Rs.60,000/towards rent for space occupied by "CIPL Equipment"
between October 2017 and April 2018. There appears to be
no dispute between the parties that CIPL Equipment had
been removed by April 2018. In fact, the minutes of meetings
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
held on 18 May 2019 and 19 May 2018 signed by
representatives of both sides also confirms this fact.
According to the Respondent, the 3G Labeller should have
been removed in October 2017. The Respondent relies on
Clause 20.1.3 which provides as follows:
“20.1.3 Return all CIPL Equipment installed at the Site
within 5 (five) Business Days of termination of this
Agreement subject to Contract Brewer obtaining all
applicable approvals under Applicable Laws. In the
event Contract Brewer fails to return CIPL Equipment,
CIPL will have the right to encash the bank Guarantee
furnished by the Contract Brewer. Further the Contract
Brewer will also be liable to pay, a delay penalty of INR
50,000 (Indian Rupees Fifty Thousand only) per day for
the period of such delay. It is agreed between the
Parties that immediately after obtaining approvals
under Applicable Laws, if any, or termination of the
Agreement, as the case may be the Contract Brewer will
give unfettered access to CIPL and its nominated
representatives to the Site for dismantling, packaging
and transportation of CIPL Equipment. The Parties
agree that CIPL shall be responsible for dismantling,
packaging and transportation of CIPL Equipment out of
Site within 15 (fifteen) Business Days of getting access
to the Site. Any delay by CIPL to dismantle and remove
CIPL Equipment inspite of Contract Brewer fulfilling its
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
obligation to give unfettered access to the Site, the
penalty payable by the Contract Brewer in terms of this
Clause shall stand nullified. Further, it is agreed
between the Parties that in the event that CIPL is unable
to dismantle and remove CIPL Equipment within 15
(fifteen) Business Day time period set out above, then
CIPL shall pay the Contract Brewer a penalty of INR
10,000/- per month for each month of delay. CIPL shall
not unreasonably delay dismantling, packaging and
transportation of CIPL Equipment.”
113. Clause 20.1.3 makes it clear that access to the site is to
be provided by Respondent for "dismantling, packaging and
transportation of CIPL Equipment out of Site" within 15 days
from "getting access to the site". The Respondent has not
produced any evidence as to when access to site was
provided by the Respondent. As such, this claim is
inconsistent with Clause 20.1.3 of the Agreement and,
therefore, rejected.
114. In any case, the notice of termination of 9 October 2017
itself mentions that according to the Respondent, the
termination was under Clause 3.2 of the Agreement. It is not
the Respondent's case that before 9 October 2017 any notice
of termination was served. In terms of Clause 3.2, six months
notice is required to be provided. Taking that into account,
the 6 month period after 9 October 2017 came to an end only
in early April 2018. As such also, Clause 20.1.3, which had to
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
be read harmoniously with Clause 3.2 of the Agreement,
cannot assist the Respondent. Counter Claim No.3 is,
therefore, rejected.
Counter Claim No.4:
115. Counter Claim No.4 is also a claim for rent / charges.
However, this is not for CIPL equipment but for broken glass.
The case advanced by the Respondent in support of this
counter claim is summarized at paragraph H at page 41 of
Respondent's Written Submissions. The basis on which this
counter claim has been made is not indicated. Moreover,
there is no evidence as to what loss at all the Respondent has
suffered on account of broken glass. It is also unclear to the
Tribunal as to how the Respondent is suggesting that the
"broken glass .....belong to the Claimant". As such, the
Tribunal is not persuaded to make any award in favour of the
Respondent towards this counter claim also. Counter Claim
No.4 is, therefore, also rejected.”
SUBMISSIONS ON BEHALF OF THE PETITIONER
15. Mr. Kirtiman Singh, learned senior counsel for the petitioner, opposes
the present Award. The petitioner challenges the Award to the extent of
the award of claim No. 1 and the rejection of counter claim No. 1, 3 and
4.
Submissions with respect to Claims of the respondent
Erroneous and contradictory findings of the Tribunal in relation to
evidence related to delay and reasonable compensation provided
under Clause No. 4.3 of the Agreement appear to treat the said
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
compensation as ‘pre-estimate’ only on the basis of word ‘fair’
16. He submits that the Tribunal has rendered erroneous and contradictory
findings as regards the party responsible for the delay. Even though the
Tribunal correctly came to a finding that the time has ceased to be the
essence of the Agreement, de hors the amendment or novation of the
Contract, claim No. 1 was erroneously allowed by the Tribunal on the
ground that the respondent had reserved its rights vide communication
dated 17.06.2016. Reliance is placed on Welspun Specialty Solutions
Ltd. v. ONGC Ltd.1
17. He further submits that the parties knowingly digressed from the
stipulated timelines under the Agreement. This is evident from the fact
that even after the expiry of the original timelines, no further dates were
specified by the parties inter se. It is significant to mention that the
respondent itself failed to seek the furnishing of the BG from the
petitioner within fifteen days of the effective date, i.e., on or before
26.12.2015. Such conduct, ex facie, demonstrates forbearance on the
part of the respondent and clearly indicates that strict adherence to the
timelines stipulated in the Agreement were neither insisted upon nor
treated as mandatory. Therefore, respondent reserving its right has no
consequence.
18. The learned counsel for the petitioner further submits that no debit note
was ever issued by the respondent qua the alleged claims, as per the
requirements under clause No. 13.5 of the Agreement. The respondent
also did not issue any notice of breach or raise any contemporaneous
correspondence alleging delay in the start date. It is, therefore, evident
Digitally Signed
By:MAYANK
18:37:48
(2022) 2 SCC 382.
O.M.P. (COMM) 595/2020
that claim No. 1 is a mere afterthought, raised only after disputes had
arisen between the parties.
19. Without
prejudice,
it
is
submitted
that
pursuant
to
the
amendment/novation of the Agreement dated 17.06.2016, the
respondent itself failed to discharge its contractual obligations for a
period of approximately four months, and only thereafter supplied a
defective and faulty 3G Labeler. Consequently, any delay post
17.06.2016 is ipso facto attributable to the respondent alone. In fact, not
only the delay in delivery of CIPL equipment but also it being defective
was admitted by the respondent in email dated 05.12.2016.
Accordingly, no liability on account of delay can be fastened upon the
petitioner.
20. It is also submitted that the Tribunal has expressly recorded a finding
that the petitioner was ready to commence Contract Manufacturing by
the end of September 2016, ipso facto, the delay thereafter is
attributable to the respondent. Except, the Tribunal has failed to
consider that on the petitioner‟s specific plea that the start date for
commencement of production ought to have been 25.10.2016, and that
it was shifted to 03.01.2017 solely on account of the respondent
supplying a defective 3G Labeler. The Tribunal has mechanically
accepted the respondent‟s assertion that the start date was 03.01.2017,
without
dealing
with
the
petitioner‟s
aforesaid
contention.
Consequently, the finding recorded by the Tribunal is not only
contradictory to its own earlier findings, but is also perverse.
21. He further submits that the Tribunal relied on the word „fair‟ used in
clause No. 4.3 of the Agreement to award claim No. 1 to the tune of
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
Rs.25 lakhs. The respondent never pleaded before the Tribunal that the
losses suffered by it were because of the delay in start date. Moreover,
the proof of loss cannot be dispensed with just because a clause in the
contract stipulates that liquidated damages are fair or reasonable
pre-estimate of purported losses. Reliance is placed on Kailash Nath
Associated v. DDA 2 and the position was reaffirmed in Indian Oil
Corpn. Ltd. v. Fiberfill Engineer 3 and Constucciones Y Auxiliar De
Ferrocarriles v. Delhi Airport Metro Express (P) Ltd.4
22. He points out that Section 74 of the Contract Act, 1872 (“ICA”) a party
claiming breach and seeking compensation is entitled to succeed only
upon proving actual loss or damage. Placing reliance on Kailash Nath
Associates (supra) where it is held that the proof of loss is a sine qua
non for liquidated damages where it is possible to prove actual damage
or loss and where damage or loss is impossible to prove then the
liquidated amount stipulated in the contract can be awarded if it is a
genuine pre-estimate of damage or loss. He submits that liquidated
damages contemplated by clause No. 4.3 of the Agreement do not
amount to genuine pre-estimate as they are in the nature of loss of
profits for which proving losses are a sine qua non. The Tribunal gave a
categorical finding that the respondent has not suffered any loss.
Submissions with respect to Counter Claims
23. At the outset, the petitioner submits that the respondent‟s contention
that the counter claims were not pressed is wholly erroneous and
misconceived. The petitioner has, both in the pleadings and during the
(2015) 4 SCC 136.
2024 SCC OnLine Del 8133
2025 SCC OnLine Del 1974.
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
course of arbitral proceedings, specifically advanced submissions in
support of the counter claims and has consistently pressed the same in
terms of the averments made and the reliefs sought. Any assertion that
the petitioner had no intention to press the counter claim is, therefore,
devoid of merit and liable to be rejected. Accordingly, the petitioner
submits the following assailing and challenging the rejection of the
counterclaims by the Tribunal.
No finding with respect to petitioner’s plea for start date being
25.10.2016 and rejection of counter claim No. 1
24. The learned counsel for the petitioner submits that it was specifically
averred before the Tribunal that the start date should have been
25.10.2016 instead of 03.01.2017 as averred by the respondent as the
petitioner has commenced the operations along with daily tank report to
the respondent. This is evident from the email dated 25.10.2016. It was
the CIPL Equipment, which was provided by the respondent itself, was
the faulty since the inception which thereby led to some delay.
Consequently, the respondent delayed the start date to be 03.01.2017.
25. The petitioner claimed electricity charges incurred in preserving the
products from October to December, 2016 to the tune of Rs.
09,05,157/- and the same was rejected by the Tribunal only on the
ground that the petitioner was largely responsible for the delays,
without even returning a finding on the petitioner‟s specific plea on the
start date. The same is perverse and the Award is liable to be set aside.
Misinterpretation of clause No. 20.1.3 and findings contrary to the
evidence with respect to counter claim No. 3
26. The learned senior counsel for the petitioner, challenging the Award on
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
the rejection of counter claim No. 3, submits that as per clause No.
20.1.3 the Agreement provides that the respondent would be
responsible for dismantling, packaging and transportation for CIPL
equipment after the expiration or termination of Agreement. In case of
default of the same the respondent would be liable to pay Rs. 10,000 per
month for each month delay. It is admitted by CW1 Jushil Kharbanda,
in the cross examination, that the respondent had not removed the CIPL
equipment from the premises of the petitioner and the same was
removed atleast until April of 2018. Despite this, the Tribunal has
erroneously found that there is no dispute between the parties as the
CIPL equipment had been removed in April of 2018. The Tribunal has
ignored the evidence on record in rendering the said finding. Moreover,
the claim No. 3 was valued at Rs. 10,000 per month and not on 60,000/as recorded by the Tribunal.
27. It is also submitted that the Tribunal erred in finding that no evidence
has been placed on record to show as to when the access to the site was
provided to the respondent. The Tribunal ignored the evidence on
record and more specifically communications dated 01.11.2017 and
24.04.2018 wherein the petitioner asked the respondent to collect the
CIPL equipment from the site.
Erroneous rejection of counter claim No. 4
28. The learned counsel for the petitioner submits that Rs. 40,000/- per
month were claimed as the respondent has not removed the broken
glass lying in the petitioner‟s brewery. The Tribunal has misdirected
itself and rejected counterclaim No. 4 on the ground that it is unclear as
to how the broken glass belonged to the respondent.
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
Limitation
29. The petitioner submits that the respondent, in its written submissions,
has for the first time contended that the present petition is barred by
limitation on the ground that it was allegedly not served upon the
respondent within the period prescribed by the statute. It is respectfully
submitted that the objection as to limitation has been raised at an
extremely delayed stage, in the written submissions filed at the stage of
conclusion of final arguments. The respondent admittedly failed to
raise any such objection for a considerable period of nearly five years
since the filing of the present petition. Having acquiesced in the
proceedings and participated therein without demur, the respondent is
now estopped from raising the plea of limitation at this advanced stage,
and the said objection is liable to be rejected on this ground alone.
30. It is further submitted that the objection of limitation raised by the
respondent is without merit. The impugned Award was passed on
15.09.2020. The present petition was filed on 11.12.2020, defects were
pointed out on 14.12.2020, and the petition was re-filed on 17.12.2020.
The Hon‟ble Supreme Court, in Cognizance for Extension of
Limitation, In re,5 excluded the COVID-19 period for computation of
limitation and held that where limitation would have expired between
15.03.2020 and 28.02.2022, a fresh period of ninety days would be
available from 01.03.2022. Accordingly, in the present case, the
limitation stood extended till 01.06.2022. The petition was listed on
22.12.2020.
SUBMISSIONS ON BEHALF OF THE RESPONDENT
Digitally Signed
By:MAYANK
18:37:48
(2022) 3 SCC 117.
O.M.P. (COMM) 595/2020
31. Dr. Maurya Vijay Chandra, learned counsel for the respondent,
supports the Award and states that there is no perversity, patent
illegality or violation of public policy that calls for interference of this
Court.
32. At the outset, the learned counsel, submits that the present petition is
barred by limitation, as the same was not served upon the respondent
within the statutory period of three months. No application seeking
condonation of delay has been filed. Consequently, the filing of the
petition is liable to be construed as non-est in the eyes of law. It is
further submitted that since the challenge to the counterclaims was not
pressed before the Court, no reply is being tendered to submissions with
respect to counter claims prior to the oral arguments.
33. He further submits that the only surviving issue for consideration is
whether liquidated damages could have been granted. He places
reliance on Kailash Nath (supra) and more specifically on paragraph
No. 43.
34. He points out that the Tribunal, even though does not, mention the
above judgment, but it is evident from the reasoning of the Tribunal that
there is a reflection of the relevant part of the ratio as quoted above.
35. He submits that the Tribunal recorded a finding that the Start Date was
achieved beyond the stipulated period and that such delay was
attributable to the financial distress of the petitioner. The Tribunal
further held that the petitioner was ready for Contract Manufacturing
only by the end of September 2016. The Tribunal also found that the
parties had agreed that, in the event of delay for any reason whatsoever,
liquidated damages would be payable by the petitioner, such amount
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
being a genuine pre-estimate of damages. It was further noted that the
respondent had expressly reserved its right to claim such damages vide
communication dated 17.06.2016, despite its efforts to salvage the
project amid the petitioner‟s financial distress.
36. It is submitted that mere attempts to salvage and implement the project
cannot amount to a waiver of the contractual stipulation on liquidated
damages, particularly where the right to claim such damages has been
expressly reserved.
37. He further submits that such findings of fact, contractual interpretation,
and application of law cannot be lightly interfered with by this Hon‟ble
Court in exercise of jurisdiction under Section 34 of the 1996 Act. The
findings returned by the Tribunal are cogent, commercially appropriate,
and definitely plausible, and do not offend the public policy of India.
An Arbitral Award cannot be subjected to a piecemeal or
hyper-technical scrutiny under Section 34 of the 1996 Act. The alleged
contradiction relied upon by the petitioner arises from picking up
observation out of context and does not warrant interference with the
Award. To set out the scope of Section 34 of the 1996 Act, amongst
others, reliance is placed on Associate Builders v. DDA 6 ,
SsangyongEngg. & Construction Co. Ltd. v. NHAI 7 , Delhi Airport
Metro Express (P) Ltd. v. DMRC8.
38. He also submits that the Court does not sit in appeal over an Arbitral
Award. An interpretation of law or fact, being a possible and plausible
view, cannot be interfered with under Section 34 of the 1996 Act. The
(2015) 3 SCC 49.
(2019) 15 SCC 131.
(2022) 1 SCC 131.
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
findings of fact borne out of pleadings and returned by the Arbitrator
are required to be accepted, the Arbitrator being the ultimate judge of
the quantity and quality of evidence relied upon in making the Award.
39. Thus, it is submitted by the learned counsel for the respondent that the
Tribunal, after duly considering the evidence on record, the contractual
provisions and their interpretation has rightly awarded a sum of Rs. 25
lakhs in favour of the respondent, along with interest at the rate of 8%
per annum on the awarded amount from the date of the award till
realization.
ANALYSIS AND FINDINGS
40. I have heard the learned counsel for the parties and perused the material
on record.
41. Before delving into the objections raised by the parties in the present
case, it is relevant to mention the scope of interference under Section 34
of the 1996 Act. Section 34 of the 1996 Act provides for limited
grounds for interference. The Court cannot act as an appellate authority
or re-appreciate the evidence or interfere with the plausible findings of
the Arbitrator. The Court may only interfere with the findings of the
Arbitrator only on grounds expressly provided under the said Section
i.e. unless the impugned Award is shown to suffer from patent
illegality, perversity, or contravention of the fundamental policy of law,
no interference is warranted.
42. In Consolidated Construction Consortium Ltd. v. Software
Technology Parks of India9, the Hon‟ble Supreme Court has observed
as under:
Digitally Signed
By:MAYANK
18:37:48
(2025) 7 SCC 757.
O.M.P. (COMM) 595/2020
“46. Scope of Section 34 of the 1996 Act is now well
crystallised by a plethora of judgments of this Court. Section
34 is not in the nature of an appellate provision. It provides
for setting aside an arbitral award that too only on very
limited grounds i.e. as those contained in sub-sections (2)
and (2-A) of Section 34. It is the only remedy for setting aside
an arbitral award. An arbitral award is not liable to be
interfered with only on the ground that the award is illegal or
is erroneous in law which would require re-appraisal of the
evidence adduced before the Arbitral Tribunal. If two views
are possible, there is no scope for the court to re-appraise the
evidence and to take the view other than the one taken by the
arbitrator. The view taken by the Arbitral Tribunal is
ordinarily to be accepted and allowed to prevail. Thus, the
scope of interference in arbitral matters is only confined to
the extent envisaged under Section 34 of the Act. The court
exercising powers under Section 34 has per force to limit its
jurisdiction within the four corners of Section 34. It cannot
travel beyond Section 34. Thus, proceedings under Section
34 are summary in nature and not like a full-fledged civil suit
or a civil appeal. The award as such cannot be touched
unless it is contrary to the substantive provisions of law or
Section 34 of the 1996 Act or the terms of the agreement.”
43. With the scope of Section 34 of the 1996 Act in mind, I shall now deal
with the rival contentions.
44. At the outset, the learned counsel for the respondent raises an objection
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
as to limitation wherein he contends that the present petition is barred
by limitation as the same was not sent to the respondents within the
statutory period of 3 months. The petitioner contended that the petition
is well within the limitation as the Award was passed on 15.09.2020.
The present petition was filed on 11.12.2020, defects were pointed out
on 14.12.2020, and the petition was re-filed on 17.12.2020.
45. In Cognizance for Extension of Limitation (supra), the Hon‟ble
Supreme Court has held as under:
“5. Taking into consideration the arguments advanced by the
learned counsel and the impact of the surge of the virus on
public health and adversities faced by litigants in the
prevailing conditions, we deem it appropriate to dispose of
MA No. 21 of 2022 with the following directions:
5.1. The order dated 23-3-2020 [Cognizance for Extension of
Limitation, In re, (2020) 19 SCC 10 : (2021) 3 SCC (Cri)
801] is restored and in continuation of the subsequent orders
dated 8-3-2021 [Cognizance for Extension of Limitation, In
re, (2021) 5 SCC 452 : (2021) 3 SCC (Civ) 40 : (2021) 2 SCC
(Cri) 615 : (2021) 2 SCC (L&S) 50] , 27-4-2021 [Cognizance
for Extension of Limitation, In re, (2021) 17 SCC 231 : 2021
SCC OnLine SC 373] and 23-9-2021 [Cognizance for
Extension of Limitation, In re, 2021 SCC OnLine SC 947] , it
is directed that the period from 15-3-2020 till 28-2-2022
shall stand excluded for the purposes of limitation as may be
prescribed under any general or special laws in respect of all
judicial or quasi-judicial proceedings.
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
5.2. Consequently, the balance period of limitation
remaining as on 3-10-2021, if any, shall become available
with effect from 1-3-2022.
5.3. In cases where the limitation would have expired during
the
period
between
15-3-2020
till
28-2-2022,
notwithstanding the actual balance period of limitation
remaining, all persons shall have a limitation period of 90
days from 1-3-2022. In the event the actual balance period of
limitation remaining, with effect from 1-3-2022 is greater
than 90 days, that longer period shall apply.”
46. The perusal of the above shows that the period from 15.3.2020 to
28.2.2022 is required to be excluded for the purpose of calculating
limitation. The judgment also mandates that irrespective of the
limitation period available, limitation of 90 days from 01.03.2022 shall
be available. Since, the Award is dated 15.09.2020 and the petition is
filed on 11.12.2020, the petition is well within the period of limitation.
47. On merits, the Tribunal, while deciding whether time is the essence of
the Agreement, observed that owing to the modification in the
requirements of the Agreement, the time did not continue to remain the
essence of the contract. The said finding of the Tribunal reads as under:
“64. When the Agreement was executed, all timelines were
clearly identified. Time was clearly of the essence. However,
the question is: did time continue to remain of the essence of
the Agreement? The answer, in short, is in the negative.
65. Neither party avoided the contract after the expiry of 135
days from the Effective Date. Neither the Claimant nor the
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
Respondent proceeded, after 24 April 2016 on the basis that
time was of the essence of the Agreement.
66. It is well settled that when time is of the essence in a
contract and a party, instead of avoiding the contract, after
the time agreed expires, accepts belated performance of an
obligation (originally intended to be performed in a
time-bound manner), it would render ineffective the express
provision relating to time being of the essence of contract.
The law laid down by the Supreme Court on Section 55 of the
Contract Act can be summarized as follows: Time, when
specified, is ordinarily the essence of contract. However,
intention to make time of the essence must be expressed
unmistakably and whether time is of the essence is to be
gathered from the terms of the contract. After extension of
time, it cannot be said, albeit, ordinarily, that time remains
the essence of the contract.
67. In any case, conduct of parties and surrounding
circumstances should be examined to determine whether time
is of the essence of the contract.”
48. Further, on the issue of the award of liquidated damages by the
Tribunal, the petitioner contended that the Tribunal has given a
categorical finding that there is no loss suffered by the respondent yet
the pre-estimate damages were awarded, whereas the contention of the
respondent is that the damages were to be awarded in the terms of the
clause No. 4.3 of the Agreement which provided that for any reason
whatsoever if the start date is delayed, the petitioner shall pay to the
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
respondent an amount of Rs. 25 lakhs. Clause No. 4.3 of the Agreement
reads as under:
“Unless otherwise waived by CIPL in writing, in the event
the Contract Brewer is unable to achieve such Start Date for
any reason whatsoever, then the Contract Brewer shall pay
CIPL an amount of INR 2,500,000 (Indian Rupees two
million five hundred thousand only). Contract Brewer
acknowledges that this Clause is fair since delay in achieving
Start Date shall adversely impact CIPL’s expected sales in
Territory and CIPL would have also lost the opportunity to
achieve these expected sales through alternative tie-up
arrangements.”
(emphasis supplied)
49. The finding of the Tribunal on the said issue reads as under:
“70. As to the Claimant's entitlement to reasonable
compensation, Clause 4.3 of the Agreement is a complete
answer. However, before discussing the issue of Claimant's
entitlement, some preliminary points must be noted.
71. First, Clause 4.3 applies upto Start Date. As such, Claim
No.2 which is premised on Clause 4.3 applying only for a
“reasonable time” of 14 days deserves rejection on this short
point. The Tribunal is bound to apply the terms of the
Agreement. No evidence, whether oral or documentary, can
be looked into in order to find out what the Agreement means
or, in other words, to interpret the Agreement.
72. Second, reasonable compensation provided for in Clause
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
4.3 appears to be a pre-estimate which the parties agreed to
and is capped at Rs.25 Lakhs (Rupees Two Million Five
Hundred Thousand Only). This is because the Claimant, as is
plain from the language used, took into account the losses
that would be caused in relation to achieving the “expected
sales”.
73. Third, the attempt of the Respondent to rely on the
answers of CW-4and to contend that the figure of Rs. 25
Lakhs is in effect a penalty does not assist the Respondent.
The Tribunal needs to only consider the terms of the
Agreement. The language used in Clause 4.3, makes it
abundantly clear that the Respondent acknowledges that the
amount of Rs.25 Lakhs is “fair”. No oral evidence whether it
is led by the Claimant or the Respondent can be used to
interpret a contractual provision which is otherwise
completely clear, as already mentioned above.”
50. It is a settled principle of law that whether time is of the essence of the
Contract has to be inferred after examining the contract as a whole and
the surrounding circumstances.
51. There is no challenge to the finding that the time was not the essence of
the contract.
52. It is also observed that even though, the Agreement was amended and
time no longer remained the essence of the Agreement, the respondent
retained the right to claim the damages. The same is evident from the
email dated 17.06.2016, which reads as under:
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
53. The provisions for damages under the Agreement can be bifurcated into
two parts. One being before start date and the other being after start
date. The penalty for delay before the start date, would be compensated
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
by the petitioner, as per the clause No. 4.3 and after the start date the
damages will be calculated as per the 6th schedule of the Agreement.
The Agreement clearly sets out a different framework governing levy
of damages into two distinct phases, namely, (i) the period prior to the
Start Date, and (ii) the period subsequent to the Start Date. In so far as
the period prior to the Start Date is concerned, any delay in the contract
is governed under Clause No. 4.3, which provides for genuine
pre-estimates payable by the petitioner for delay in start date.
Conversely, once the start date is achieved, the computation and levy of
damages are governed exclusively by the mechanism prescribed under
Schedule 6 of the Agreement. The said is evident from the finding of
the tribunal:
“79. The first basis on which the Claimant has made this
claim is
that
Clause 4.3
only covers
reasonable
compensation for reasonable time (of around 2 weeks) after
24 April 2016. According to the Claimant, the inordinate
delay of 254 days was never contemplated by the parties. As
such, the Claimant's case is that it is entitled to liquidated
damages of Rs.25 Lakhs in accordance with Clause 4.3 and
also entitled to general damages characterized as claims for
loss of production and / or loss of profits in accordance with
the mechanism provided in Schedule 6 to the Agreement.
80.The Tribunal finds that Schedule 6 applies after Start
Date is achieved and not before. Thus, Claim No.2 which is
made in respect of delays before achievement of Start Date
cannot be advanced on the basis of Schedule 6.
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
….
83. Claim No.2, to the extent that the Tribunal can
understand from a mere reading of pages 302 and 303 of the
documents filed with the SOC, is on the basis of "minimum
commitment". That, in turn, appears to be based on Schedule
6 to the Agreement. As indicated above, Schedule 6 only
applies post achievement of Start Date. As to the period
following the Start Date, the Tribunal finds that the Claim
No.2 cannot be entertained for two reasons: (a) that the
Claimant's own pleaded case is confined to the losses upto
the Start Date; and (b) in any case for the period following
the achievement of Start Date, according to the Claimants,
the minimum monthly commitment was not met.”
54. In the present case the start date was originally contemplated as
24.04.2016. The Tribunal has held that the delay in start date upto
22.06.2016 is attributable to the petitioner and thereafter it is
attributable to both the parties. The said finding of the tribunal reads as
under:
“63. On analyzing the factual evidence, referred to above,
the Tribunal finds that the Start Date was delayed for reasons
attributable to both the Claimant and the Respondent. Whilst,
the Respondent was responsible for the delays upto 22 June
2016, the Claimant and Respondent were both responsible
for delays between 16 October 2016 and 16 December 2016
and in fact, it is for reasons attributable to both parties that
the Start Date was not achieved immediately after 22 June
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
2016. Despite this being the position, in so far as the claims
are concerned, in the Tribunal's view, nothing, save and
except as indicated below, turns on the delay in achievement
of the Start Date.”
55. The wordings of clause No. 4.3 i.e.“Contract Brewer acknowledges
that this Clause is fair since delay in achieving Start Date shall
adversely impact CIPL’s expected sales” makes it evident that the
petitioner itself agreed that Rs. 25 lakhs are a genuine pre-estimate of
losses that will occur if there is delay in start date. Moreover, the
respondent reserved the right to claim any such damages.
56. It is pertinent to mention that while deciding claim No.2 of the
respondent, where the respondent claimed Rs. 11,53,62,390 on account
of failure of the respondent to produce the required cases per month and
inordinate delay of 240 days in achieving the start date, the Tribunal has
dealt with the said claim on both the footing, i.e. period of delay in
achieving the start date and period of delay following the start date.
Based on the evidence led by CW4, Mr. Mahajan, the Tribunal
observed the following:
“90. It is well settled that an award for damages can only be
made if there is evidence that the party claiming damages
had suffered actual loss. The Claimant has relied on the
evidence of Mr. Gaurav Mahajan CW4. Mr. Mahajan, in his
affidavit, has stated as follows:
“4. I say that during the period where PHB was unable
to start production and later were under-producing
during the period January 2017 to September 2017, and
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
non-production from October 2018 onwards. CIPL
could not import any substantial quantity of the SKUs
from plants in other states as their production capacity
was tied up for the respective markets in anticipation of
timely production by PHB. Augmentation of production
capacity in beer industry in short period of time is very
difficult. Once it became clearer that PHB is not able to
meet its contractual obligations towards CIPL, it
started exploring the possibility of sourcing the
products from nearby breweries. Despite CIPL's best
efforts it could manage to import only limited volume of
the products from the nearby states. Further CIPL this
effort of supplying from outside the state of Jharkhand
resulted in higher cost of transportation and duties and
reduced profits per case.”
91. Mr. Mahajan's own evidence was that the Claimant could
only manage to import "limited volume" of the Product. No
evidence was provided as to what limited volume was and no
supporting documents were produced before the Tribunal. As
such, irrespective of all the points mentioned above, the
Tribunal does not find any evidence of the Claimant having
suffered any actual loss. The Claimant is, thus, not entitled to
any Award for Claim No.2 for this reason also.”
(emphasis supplied)
57. Upon perusal of the above statement, it can be observed from the said
finding of the Tribunal that irrespective of the statement of Mr.
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
Mahajan the Tribunal could not find any evidence of actual loss
irrespective of anything stated by him. However, as is evident from the
above discussion the fact of the respondent having suffered no actual
loss is post the start date. Thus, the said findings of claim No. 1 and
claim No. 2 are on different footings, thus, cannot be relied upon to
conclude that there was no loss suffered by the respondent.
58. In this regard, Section 74 of the ICA which pertains to the genuine
pre-estimate damages, is relevant and reads as under:
“Section 74: Compensation for breach of contract where
penalty stipulated for
When a contract has been broken, if a sum is named in the
contract as the amount to be paid in case of such breach, or if
the contract contains any other stipulation by way of penalty,
the party complaining of the breach is entitled, whether or
not actual damage or loss is proved to have been caused
thereby, to receive from the party who has broken the
contract reasonable compensation not exceeding the amount
so named or, as the case may be, the penalty stipulated for.
Explanation.- A stipulation for increased interest from the
date of default may be a stipulation by way of penalty.
Exception.- When any person enters into any bail-bond,
recognizance or other instrument of the same nature, or,
under the provisions of any law, or under the orders of the
Central Government or of any State Government, gives any
bond for the performance of any public duty or act in which
the public are interested, he shall be liable, upon breach of
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
the condition of any such instrument, to pay the whole sum
mentioned therein.
Explanation.- A person who enters into a contract with
Government does not necessarily thereby undertake any
public duty, or promise to do an act in which the public are
interested.”
59. The law regarding Section 74 of ICA was crystallised in the case of
Kailash Nath (supra). The relevant paragraphs read as under:
“43. On a conspectus of the above authorities, the law on
compensation for breach of contract under Section 74 can be
stated to be as follows:
43.1. Where a sum is named in a contract as a liquidated
amount payable by way of damages, the party complaining of
a breach can receive as reasonable compensation such
liquidated amount only if it is a genuine pre-estimate of
damages fixed by both parties and found to be such by the
court. In other cases, where a sum is named in a contract as a
liquidated amount payable by way of damages, only
reasonable compensation can be awarded not exceeding the
amount so stated. Similarly, in cases where the amount fixed
is in the nature of penalty, only reasonable compensation can
be awarded not exceeding the penalty so stated. In both
cases, the liquidated amount or penalty is the upper limit
beyond
which
the
court
cannot
grant
reasonable
compensation.
43.2. Reasonable compensation will be fixed on well-known
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
principles that are applicable to the law of contract, which
are to be found inter alia in Section 73 of the Contract Act.
43.3. Since Section 74 awards reasonable compensation for
damage or loss caused by a breach of contract, damage or
loss caused is a sine qua non for the applicability of the
section.
43.4. The section applies whether a person is a plaintiff or a
defendant in a suit.
43.5. The sum spoken of may already be paid or be payable in
future.
43.6. The expression “whether or not actual damage or loss
is proved to have been caused thereby” means that where it
is possible to prove actual damage or loss, such proof is not
dispensed with. It is only in cases where damage or loss is
difficult or impossible to prove that the liquidated amount
named in the contract, if a genuine pre-estimate of damage
or loss, can be awarded.
43.7. Section 74 will apply to cases of forfeiture of earnest
money under a contract. Where, however, forfeiture takes
place under the terms and conditions of a public auction
before agreement is reached, Section 74 would have no
application.”
60. It is an established law that for the applicability of Section 74 of the
ICA, loss or damage is a sine qua non but the loss need not be proved
and in the cases where a genuine pre-estimate is stipulated in the
Agreement the Court may award reasonable amount not exceeding the
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
penalty so stipulated.
61. Upon a careful perusal of clause No. 4.3 of the Agreement, it is evident
that the contract itself recognizes that any delay in the achieving the
Start Date would result in loss to the respondent. The parties have
expressly agreed that, in the event the petitioner fails to achieve the start
date for any reason whatsoever, the petitioner would be liable to pay a
fixed sum of Rs. 25 lakhs as genuine pre-estimated and agreed
damages. The said stipulation clearly reflected by the use of word
“fair”. The parties‟ intention to quantify the consequence of such delay
in advance, binds the petitioner accordingly.
62. Thus, the Tribunal is right in holding that since there were delays on
part of the petitioner in achieving the start date till 22.06.2016 and
thereafter, delay being attributable both the petitioner and the
respondent, the petitioner is liable to pay the sum of Rs. 25 lakhs.
63. The Tribunal is a creature of contract and is bound by the
circumscribing limits of the terms of the Contract. It is upon the
Tribunal to interpret the terms of the contract. The Tribunal, in the
present case, has interpreted the amount of Rs. 25 lakhs as reasonable
compensation. The said finding is a plausible finding. This Court, is
restricted by Section 34 of the 1996 Act to interfere with the plausible
findings of the Arbitrator, even if another conclusion is possible or
better.
64. At this juncture it would be relevant to distinguish the judgment of
Hon‟ble Supreme Court in Kailash Nath (supra) relied on by the
petitioner. The judgement clearly states that the loss is an essential
requirement to award damages in Section 74 of the ICA. The party
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
complaining the breach of the contract must suffer from actual loss
apart from the mere breach of contract or legal injury. In the present
case, clause No. 4.3 clearly states that delay in achieving the start date
by the petitioner would cause loss to the respondent as due to the delay
the respondent‟s expected sales in the said territory would be impacted.
Hence, the parties clearly agree that any delay in start date would cause
loss to the respondent, they further agreed that an amount of Rs.
25,00,000/- is a genuine pre-estimate of loss that will be suffered by the
respondent on account of such delay. Thus, it cannot be said that there
was no loss suffered by the respondent.
65. The judgement in Construcciones Y Auxiliar De Ferrocarriles (supra)
relied by the petitioner is also distinguishable as in that case the
respondent had failed to aver and prove loss. In the present case the
parties in the contract have already agreed that delay in achieving start
date itself causes loss to the respondent. The reason for the loss is also
encapsulated in the said clause which is that the respondent would lose
its expected sales and would not be able to achieve the expected sales
via alternative tie up arrangements.
66. Hence, I am unable to agree with the arguments advanced by the
learned senior counsel for the petitioner against the findings with
respect to claim No. 1. Consequently, the Award to the extent of claim
No. 1 is upheld.
67. With respect to the counter claim No. 1, i.e. rejection of electricity
charges, the Tribunal came to a finding that the delays in achieving the
start date were majorly attributable to the petitioner until 22.06.2016
and thereafter to both the petitioner and the respondent. Thus, it would
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
be apposite to conclude that if the petitioner is responsible for a part of
the delay, the respondent should not be held liable to pay the electricity
charges for preserving the products. Therefore, the finding that the
petitioner is not entitled to charge electricity charges from October to
December 2016 is a plausible finding. The findings of the Tribunal
have already been reproduced in paragraph No. 14 and are not being
again reproduced again for brevity.
68. With respect to counter claim No. 3, as per clause No. 20.1.3, the
petitioner was to provide unfettered access to the respondent to
dismantle the machinery. Clause 20.1.3 reads as under:
“20.1.3 return all CIPL Equipment installed at the Site
within 5 (Five) Business Days of termination of this
Agreement subject to Contract Brewer obtaining all
applicable approvals under Applicable Laws. In the event
Contract Brewer fails to return CIPL Equipment, CIPL will
have the right to encash the bank Guarantee furnished by the
Contract Brewer. Further the Contract Brewer will also be
liable to pay, a delay penalty of IN 50,000 (Indian Rupees
Fifty Thousand only) per day for the period of such delay. It
is agreed between the Parties that immediately after
obtaining approvals under Applicable Laws, if any, or
termination of the Agreement, as the case maybe. the
Contract Brewer will give unfettered access to CIPL and its
nominated representatives to the Site for dismantling,
packaging and transportation of CIPL Equipment, The
Parties agree that CIPL shall be responsible for dismantling,
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
packaging and transportation of CIPL Equipment out of Site
within 15 (fifteen) Business Days of getting access to the Site.
Any delay by CIPL to dismantle and remove CIPL Equipment
inspite of Contract Brewer fulfilling its obligation to give
unfettered access to the Site, the penalty payable by the
Contract Brewer in terms of this Clause shall stand nullified.
Further. it is agreed between the Parties that in the event that
CIPL is unable to dismantle and remove CIPL Equipment
within 15(fifteen) Business Day time period set out above,
then CIPL shall pay the Contract Brewer a penalty of INR
10,000/- per month for each month of delay. CIPL shall not
unreasonably
delay
dismantling,
packaging
and
transportation of CIPL Equipment”
(emphasis supplied)
69. The Arbitral Tribunal, with respect to the counter claim No. 3 has stated
as under:
“112. Counter Claim No.3 is for an amount of Rs.60,000/towards rent for space occupied by "CIPL Equipment"
between October 2017 and April 2018. There appears to be
no dispute between the parties that CIPL Equipment had
been removed by April 2018. In fact, the minutes of meetings
held on 18 May 2019 and 19 May 2018 signed by
representatives of both sides also confirms this fact.
113. Clause 20.1.3 makes it clear that access to the site is to
be provided by Respondent for "dismantling, packaging and
transportation of CIPL Equipment out of Site" within 15 days
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
from "getting access to the site". The Respondent has not
produced any evidence as to when access to site was
provided by the Respondent. As such, this claim is
inconsistent with Clause 20.1.3 of the Agreement and,
therefore, rejected.
114. In any case, the notice of termination of 9 October 2017
itself mentions that according to the Respondent, the
termination was under Clause 3.2 of the Agreement. It is not
the Respondent's case that before 9 October 2017 any notice
of termination was served. In terms of Clause 3.2, six months
notice is required to be provided. Taking that into account,
the 6 month period after 9 October 2017 came to an end only
in early April 2018. As such also, Clause 20.1.3, which had to
be read harmoniously with Clause 3.2 of the Agreement,
cannot assist the Respondent. Counter Claim No.3 is,
therefore, rejected.”
70. The Tribunal has come to a finding that the respondent has not
produced any evidence as to when the site was provided by the
respondent. The said finding is contrary to material on record namely
the communications dated 01.11.2017 and 24.04.2018 of the petitioner
which reproduced as under:
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
71. A perusal of two communications clearly show the petitioner duly
provided access to the site but it was the respondent who failed to
remove the CIPL equipment.
72. It was only on 18.05.2018, the respondent held a meeting with the
petitioner wherein the respondent stated that the equipment can‟t be
removed until it is reinstalled and run online. The minutes of the said
meeting are reproduced as under:
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
73. The machine was not reinstalled and run online to check the operational
ability and was not removed from the premises of the petitioner atleast
until 16.03.2019. The same is evident from the cross examination dated
06.03.2019 of Mr. Jushil Kharbanda, Manager- Engineering and
Projects Manufacturing Operations, Carlsberg India Private Limited.
He, upon asking if the CIPL equipment has been removed, gave an
answer in the negative. The same is reproduced as under:
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
(emphasis supplied)
74. The said cross examination was totally ignored by the Tribunal while
considering the counter claim No. 3. The reasoning of the Tribunal for
the rejection of Award is, as reproduced, namely:
i.
That the petitioner has not produced any evidence as to when
access to the site to remove the CIPL equipment was provided.
ii.
That the 6 months period, after notice of 09.10.2017 came to an
end in April 2018 and there is no dispute between the parties that
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
the equipment was removed by April, 2018.
75. Both the reasons are incorrect and contrary to record. It is evident that
the petitioner gave access to site for removal of equipment on
01.11.2017 and subsequently on 24.04.2018. Despite the notice of
09.10.2017, the equipment was not removed at least till 06.03.2019.
76. Hence, the burden of rental obligation, for the acts of the respondent,
cannot be put upon the petitioner. No prudent person can arrive at the
said findings in view of the documents available on record.
77. For the said reasons this finding of the Arbitrator is to be interfered with
and is liable to be set aside. This court is of the view that the findings
with respect to counter claim No. 3 are contrary to the evidence on
record and thus is set aside to that limited extend. Reliance is placed on
PSA Sical Terminals (P) Ltd. v. V.O. Chidambranar Port Trust10,
wherein the Hon‟ble Supreme Court held that an Award contrary to the
vital evidence is liable to be set aside as the said decision would be
perverse and patently illegal.
78. While interpreting Section 34 of the 1996 Act, the Hon‟ble Supreme
Court in Gayatri Balasamy v. ISG Novasoft Technologies Ltd.11, held
that the court though does not sit as a court of appeal under Section 34
of the 1996 Act but if the findings of the Court are severable, the court
has the power to sever and modify a portion of Award. The relevant
paragraphs read as under:
“43. Equally, Section 34 limits recourse to courts to an
application for setting aside the award. However, Section 34
Digitally Signed
By:MAYANK
18:37:48
(2023) 15 SCC 781. Ref paragraph Nos. 41 and 42.
(2025) 7 SCC 1.
O.M.P. (COMM) 595/2020
does not restrict the range of reliefs that the Court can grant,
while remaining within the contours of the statute. A different
relief can be fashioned as long as it does not violate the
guardrails of the power provided under Section 34. In other
words. the power cannot contradict the essence or language
of Section 34. The Court would not exercise appellate power,
as envisaged by Order 41 of the Code of Civil Procedure,
1908 (hereinafter referred to as "the Code").
44. We are of the opinion that modification represents a more
limited, nuanced power in comparison to the annulment of an
award, as the latter entails a more severe consequence of the
award being voided in toto.
Read in this manner, the limited and restricted power of
severing an award implies a power of the Court to vary or
modify the award. It will be wrong to argue that silence in the
1996 Act, as projected, should be read as a complete
prohibition.
45. We are thus of the opinion that the Section 34 Court can
apply the doctrine of severability and modify a portion of the
award while retaining the rest. This is subject to parts of the
award being separable, legally and practically, as stipulated
in Part II of our Analysis.”
79. Hence, counter claim No. 3 can be interfered while retaining the rest of
the findings of the Tribunal as the findings are severable.
80. The petitioner in Statement of Defence has substantiated the counter
claim No. 4, which reads as under:
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
“Counter Claim no.4- The claimant has refused to remove
the broken glass from the Respondent brewery and thus the
Excise Department, Ramgarh has also send a notice to the
respondent to remove such broken glass. This is capturing a
large portion of the premise of the respondent and thus a
claim of Rs 40,000/- per month for each month delay is
charges herewith.”
81. I am of the view that the finding returned by the Tribunal does not call
for interference. The Tribunal has held that the petitioner failed to
establish that the broken glass in question either belonged to the
respondent or that the respondent was under any contractual or legal
obligation to clear the same. This conclusion is a plausible one, as the
petitioner, both in the pleadings and during the course of arguments, did
not place on record any material to demonstrate that the broken glass
was belonging to the respondent or that the respondent was responsible
for its removal. Further, the petitioner has also failed to adduce any
evidence to show that any loss was actually suffered on account of the
alleged broken glass. In the absence of proof, the rejection of counter
claim No. 4 by the Tribunal cannot be said to be perverse. The findings
pertaining to counter claim No. 4 have already been extracted in
paragraph No.14 and are not being reproduced again for the sake of
brevity.
CONCLUSION
82. In view of the aforesaid discussion, this court does not find merit in the
challenge to the Award except for the rejection of counter claim No. 3.
Thus, the Award is set aside only to the extent of counter claim No.3.
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
83. The petition is disposed of with pending applications, if any.
JASMEET SINGH, J
JANUARY 22, 2026/(MU)
Digitally Signed
By:MAYANK
18:37:48
O.M.P. (COMM) 595/2020
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review