Page No.# 1/8
GAHC010263652018
2026:GAU-AS:15711
THE GAUHATI HIGH COURT
(HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Case No. : WP(C)/8193/2018
NIRUTPOL GOSWAMI
S/O. LT. BHARAT CHANDRA GOSWAMI, VILL. SARUMATARIA, P.O. AND P.S.
DISPUR, GUWAHATI-781006, DIST. KAMRUP (M), ASSAM.
VERSUS
THE STATE OF ASSAM AND 4 ORS.
REP. BY THE COMM. AND SECY. TO THE GOVT. OF ASSAM, REVENUE
DEPTT., DISPUR, GUWAHATI-06, ASSAM.
2:THE SECRETARY
TO THE GOVT. OF ASSAM
GENERAL ADMINISTRATIVE DEPTT.
DISPUR
GHY.-06.
3:THE DY. COMMISSIONER
KAMRUP (M)
DIST. KAMRUP (M)
ASSAM.
4:THE ADDL. DY. COMMISSIONER (REVENUE)
KAMRUP (M)
ASSAM.
5:THE CIRCLE OFFICER
DISPUR RENENUE CIRCLE
KAMRUP (M)
ASSAM
Page No.# 2/8
BEFORE
HON’BLE MR. JUSTICE DEVASHIS BARUAH
For the Petitioner(s)
: Mr. R. Phukan, Advocate
For the Respondent(s)
: Mr. J. Handique, Jr. GA, Assam
: Ms. G. Hazarika, SC, Revenue
·
Date on which Judgment was reserved
: NA
·
Date of Pronouncement of Judgment
: 14.10.2026
·
Whether the pronouncement is of
the Operative Part of the Judgment
: Yes
·
Whether the full Judgment has been
Pronounced
: NA
JUDGMENT AND ORDER (ORAL)
Heard Mr. R. Phukan, the learned counsel appearing on behalf
of the Petitioner and Ms. G. Hazarika, the learned Standing counsel
appearing on behalf of the Respondent No.1. I have also heard Mr.
J. Handique, the learned Junior Government Advocate appearing
on behalf of the Respondent Nos. 2 to 5.
2.
The Petitioner herein has approached this Court being
aggrieved by the inaction on the part of the respondent authorities
in not granting settlement of the land to the Petitioner, and on the
other hand, threatening to evict the Petitioner from the said land.
Page No.# 3/8
3.
The case of the Petitioner herein is that he is in possession of
a plot of land measuring 1 Katha 5 Lechas covered by Dag No.132
situated
at
Village
Sarumataria
under
Beltola
Mouza
by
constructing dwelling houses since the year 1999.
4.
The Petitioner herein purchased the possessory right in the
year 1999 over a plot of land admeasuring 1 Katha 5 Lechas
covered by Dag No.132 situated at Village Sarumataria under
Beltola Mouza and had constructed a dwelling house since the date
of purchase. The said land admittedly was a Government land and
under such circumstances, the purchase so made in the year 1999
from another person has no relevance except the same may be
seen as regards the possession of the Petitioner for collateral
purposes. The Land Advisory Committee recommended the name
of the Petitioner along with nine others for settlement of land.
5.
It transpires that the Land Advisory Committee held a meeting
on 24.10.2005, i.e. almost after 6 years from the date of
application so filed by the Petitioner. In the said meeting of Land
Advisory Committee, the proposal for settlement of land in favour
of the Petitioner was discussed and it was recommended that the
plot of land measuring 1 katha 5 lechas covered by Dag No.132 for
settlement vide the Resolution No.28. This aspect of the matter
Page No.# 4/8
would be seen from the communication issued by the Deputy
Commissioner, Kamrup (Metro), Guwahati dated 17.01.2006 to the
Secretary to the Government of Assam, Revenue (Settlement)
Department.
6.
It is the further case of the Petitioner that his settlement
application continued to be pending in spite of recommendation
given by the Land Advisory Committee. But in respect to the same
Dag Number, there has been certain settlement issued in favour of
various persons of land measuring around 18 Lechas. The
Petitioner along with others thereafter submitted a representation
for
consideration
representation
of
dated
their
settlement
26.12.2016.
proposal
However,
vide
the
neither
the
representation was considered nor the settlement proposal of the
Petitioner was allowed for which the Petitioner has approached this
Court by filing the instant writ petition.
7.
It is the further case of the Petitioner that on one hand the
Respondent Authorities are not taking steps for granting settlement
to the Petitioner though 27 years have passed by pursuant to the
submission of the application, and on the other hand, the
Petitioner was under threat of being evicted from the said land.
Page No.# 5/8
8.
It appears from the record that this Court vide an order dated
30.11.2018 had issued notice, and in the interim, it was directed
that the Petitioner shall not be evicted from the land in question.
The said order continued to be holding the field till date.
9.
It is also relevant to take note of that an affidavit-in-
opposition was filed by the Respondent No.4, i.e. the Additional
Deputy Commissioner, Kamrup (Metro), Guwahati. Surprisingly
nothing has been stated in the said affidavit-in-opposition save and
except stating that in the remark column of the ‘Chitha’ it is written
“as reserved for ‘Capital’ in favour of the GAD in Dag No.132
(old)/35 (new) of Village-Sarumataria under Beltola Mouza”. It was
mentioned that the Petitioner is in possession of Government land
of Dag No.132(old)/35 (new) covering an area of 3.34 Are of
village Sarumataria under Beltola Mouza by constructing RCC
building. There is not a single whisper in the said affidavit-inopposition as regards the settlement proposal of the Petitioner.
10. I have heard the learned counsel for the parties and perused
the materials on record. It transpires from the above that the
Petitioner had submitted an application for settlement in the month
of year, 1999. The said application was submitted upon proper
verification through the Lat Mondal wherein it has been mentioned
Page No.# 6/8
that the Petitioner has been in occupation over the said land from
the year 1999. It further transpires that the Petitioner’s application
was taken up by the Land Advisory Committee after the period of 6
years in the year 2005 and there was a recommendation being
made as could be seen from the communication issued by the
Deputy Commissioner, Kamrup (Metro), Guwahati to the Secretary
to the Government of Assam, Revenue (Settlement) Department
dated 17.01.2006 enclosed as Annexure-3 to the effect that the
plot of land measuring 1 Katha 5 Lechas was recommended to be
settled in favour of the Petitioner. In spite of that, the Respondent
Authorities did not decide the settlement application of the
Petitioner whereas it is also seen from the record, more
particularly,
from
Annexure-7
that
the
Additional
Deputy
Commissioner, Kamrup (Metro) Guwahati had also written to the
Settlement Authority, Guwahati regarding issuance of land patta in
respect to the same Dag being Dag No.132 in respect to other
persons.
11. This Court also finds it relevant that there has been no denial
by the Respondent Authorities to all these documents save and
except only stating in the affidavit-in-opposition that the said land
has been mentioned in the Remark Column of the ‘Chitha’ as
“reserved for ‘Capital’ in favour of the GAD” and the Petitioner was
Page No.# 7/8
in possession of the land in question by constructing RCC building.
12. Taking into account the above, this Court is of the firm view
that the Petitioner has a legitimate expectation for consideration of
his application for settlement and the non-consideration of the
Petitioner’s application by the concerned Respondent Authorities
violates the mandate of Article 14 of the Constitution.
13. It further transpires from the present land policy of the year
2019 as has been pointed out by Ms. G. Hazarika, the learned
Standing counsel appearing on behalf of the Revenue and Disaster
Management that it is also the policy of the Government of Assam
to settle land in favour of landless people of an area measuring 1
Katha 5 Lechas. That being the policy and the application of the
Petitioner being pending since the year 1999, this Court directs the
Respondent Authorities and more particularly the Commissioner &
Secretary to the Government of Assam, Revenue and Disaster
Management Department as well as to the Deputy Commissioner,
Kamrup (Metro), Guwahati to take a decision on the application
filed by the Petitioner seeking settlement of a plot of land
measuring 1 Katha 5 Lechas in Dag No.132 as per the extant
policy. The said decision be taken within a period of 6 (six) months
from the date a certified copy of the instant judgment is served
Page No.# 8/8
upon the Commissioner & Secretary to the Government of Assam,
Revenue and Disaster Management Department as well as the
Deputy Commissioner, Kamrup (Metro), Guwahati.
14. Mr. R. Phukan, the learned counsel appearing on behalf of the
Petitioner submits that if the Petitioner is not in the meantime
protected, the Respondent Authorities would evict the Petitioner.
15. Taking into account that there is a specific direction by this
Court to the concerned Respondent Authorities to consider and
decide the settlement application of the Petitioner, this Court
directs the Respondent Authorities not to take any coercive action
against the Petitioner till the outcome of the settlement application
is duly intimated to the Petitioner.
16. In view of the above observation and direction, the instant
writ petition stands disposed of.
Bijoy
Saha
Bijoy Saha
Date: 2026.10.15
18:08:42 +05'30'
Comparing Assistant
JUDGE
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review