The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
4. The Executive Engineer, Division No.IV, Manipur. Minor Irrigation Department …..Respondents HON’BLE MR. JUSTICE M.V MURALIDARAN For the petitioner : Mr. M.Devananda, learned Advocate. For the respondents : Mr. Lenin Hijam, Learned Deputy AG. Date of Hearing : 30.04.2019. Date of Order : 30.05.2019. JUDGMENT & ORDER [1] Heard Mr.MDevananda, learned counsel for the petitioner and heard also Mr. Lenin Hijam, learned Deputy AG for the respondents. Page |2 [2] This writ petition has been filed by the petitioner seeking to quash the order dated 11.07.2016 passed by the second respondent and to direct the respondents to conduct verification of the works completed by the petitioner in view of the order dated 30.03.2016 passed in W.P.(C) No. 242 of 2016 by affording the petitioner an opportunity and also direct the respondents to pay a sum of Rs.11,77,866/-. [3] The case of the petitioner is that the fourth respondent issued Work Orders dated 08.08.2008 to the petitioner for (i) construction of P/dam at Mare paddy field at KhamasomPhyngrel for Rs. 6,74,780/- and (ii) construction of P/W a/c Pharang River at SihaiKahaophung for Rs. 5,03,086/- of Minor Irrigation Department, Manipur after according administrative approval of the Government of Manipur. The petitioner had executed the work and after completion of the work, bills were not settled by the respondent authorities though the Exec…
30. 03.2016, this Court disposed of the writ petition directing the second respondent or his authorised Executive Engineer to verify the undisputed outstanding bill amounts within a period of three months from the date of Page |3 receipt of copy of the order and after verification of the undisputed bill amounts payable to the petitioner, the same shall be released in favour of the petitioner in accordance with seniority in completion of work. However, after a lapse of four months from the date of passing order in W.P.(C) No. 242 of 2016, the second respondent passed the impugned order stating that the works were started only after the expiry of schedule dates of completion of the works and no application for extension of time was received from the petitioner and thus the Work Orders lapsed automatically. Aggrieved by the same, the petitioner has filed the writ petition. [4] Resisting the writ petition, respondent Nos. 1, 2 and 4 have filed affidavit-in-opposition stating that no agreement was found in respect of the work alleged by the petitioner. It is stated that the progress of the work was recorded in the measurement book, however, the measurement were not signed by the contractor or his representatives. It is further stated that the work was started after the expiry of the scheduled date of completion of the work that fell on 10.8.2009.According to the respondents 1, 2 and 4 t…
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
Page |1
MEITEI
DN: c=IN, o=Personal,
2.5.4.20=2bc3ef4c6029fd1a0cfbe18d082a
c7da00d8c6db68269dfc15ecbc396f6a038
0, postalCode=795005, st=MANIPUR,
serialNumber=dd340facd2eaa2357c38c3f
421b62b4b4ad51d4bef35837928d4ebab
4f6a3736, cn=WAIKHOM TONEN MEITEI
Date: 2019.05.31 14:51:27 +05'30'
IN THE HIGH COURT OF MANIPUR
AT IMPHAL
W.P. (C) No 633 of 2016
Murphy Thumrah Contractor aged about 47 Years, S/O (late)
Daniel Thumrah, resident of Tribal Colony Type-I-25, New
Checkon, P.O. Imphal, P.S. Porompat, Imphal East District,
Manipur.
... Petitioner
- Versus 1. The State of Manipur represented by Commissioner (MI),
Government of Manipur.
2. The Chief Engineer, Minor Irrigation Department, Manipur.
3. The Principal Secretary(Finance) Government of Manipur.
4. The Executive Engineer,
Division No.IV, Manipur.
Minor
Irrigation
Department
…..Respondents
B E F O R E
HON’BLE MR. JUSTICE M.V MURALIDARAN
For the petitioner
:
Mr. M.Devananda, learned Advocate.
For the respondents
: Mr. Lenin Hijam, Learned Deputy AG.
Date of Hearing
: 30.04.2019.
Date of Order
: 30.05.2019.
JUDGMENT & ORDER
[1]
Heard Mr.MDevananda, learned counsel for the petitioner and
heard also Mr. Lenin Hijam, learned Deputy AG for the respondents.
Page |2
[2]
This writ petition has been filed by the petitioner seeking to
quash the order dated 11.07.2016 passed by the second respondent and
to direct the respondents to conduct verification of the works completed
by the petitioner in view of the order dated 30.03.2016 passed in W.P.(C)
No. 242 of 2016 by affording the petitioner an opportunity and also direct
the respondents to pay a sum of Rs.11,77,866/-.
[3]
The case of the petitioner is that the fourth respondent issued
Work Orders dated 08.08.2008 to the petitioner for (i) construction of
P/dam at Mare paddy field at KhamasomPhyngrel for Rs. 6,74,780/- and
(ii) construction of P/W a/c Pharang River at SihaiKahaophung for Rs.
5,03,086/- of Minor Irrigation Department, Manipur after according
administrative approval of the Government of Manipur. The petitioner had
executed the work and after completion of the work, bills were not settled
by the respondent authorities though the Executive Engineer, Minor
Irrigation Division No.IV, Minor Irrigation Department prepared the final
payment of bill amount of Rs.11,77,866/- and forwarded the liability
statement/list of outstanding bills to the second respondent/Chief
Engineer, Minor Irrigation Department.
Since the second respondent
failed to settle the undisputed amounts, the petitioner approached this
Court by filing W.P(C) No. 242 of 2016 praying inter alia for a direction to
the respondents to pay the total sum of Rs.11,77,866/-. By an order dated
30.03.2016, this Court disposed of the writ petition directing the second
respondent or his authorised Executive Engineer to verify the undisputed
outstanding bill amounts within a period of three months from the date of
Page |3
receipt of copy of the order and after verification of the undisputed bill
amounts payable to the petitioner, the same shall be released in favour of
the petitioner in accordance with seniority in completion of work.
However, after a lapse of four months from the date of passing order in
W.P.(C) No. 242 of 2016, the second respondent passed the impugned
order stating that the works were started only after the expiry of schedule
dates of completion of the works and no application for extension of time
was received from the petitioner and thus the Work Orders lapsed
automatically. Aggrieved by the same, the petitioner has filed the writ
petition.
[4]
Resisting the writ petition, respondent Nos. 1, 2 and 4 have
filed affidavit-in-opposition stating that no agreement was found in respect
of the work alleged by the petitioner. It is stated that the progress of the
work was recorded in the measurement book, however, the measurement
were not signed by the contractor or his representatives. It is further
stated that the work was started after the expiry of the scheduled date of
completion of the work that fell on 10.8.2009.According to the
respondents 1, 2 and 4 the first running account bills amounting to Rs.4,
91, 139/- and Rs.3,53,045/- for the works were submitted by the then
Assistant Engineer contrary to the claim of the petitioner that the work
was executed during the stipulated time and bills for final payment
amounting to Rs.11,77,866/- were prepared by the Executive Engineer
and forwarded to the second respondent. On 8.8.2008, the Executive
Engineer issued letter of acceptance of the tender floated by the
Page |4
petitioner in respect of the works in question. It is stated that no relevant
information for submission of application for extension of time was
available on record. Moreover, the verification reveals that no direction
was given for inclusion of the petitioner in the internal department process
and no role of the petitioner was required under the construction and
prayed for dismissal of the writ petition.
[5]
Assailing the impugned order, the learned counsel for the
petitioner submitted that the main ground for rejection of the petitioner’s
claim for payment of the entitled undisputed bill amounts for the works
completed is not tenable in the eye of law and the order impugned was
passed arbitrarily. He would submit that the respondents cannot deny
and/or dispute the fact that work Orders were issued to the petitioner after
completing all formalities such as the execution of agreement. The
learned counsel further submitted that the impugned order was issued to
forfeit the petitioner the undisputed bill amounts for the works completed.
[6]
Per
contra,
the
learned
Junior
Government
Advocate,
reiterating the ground for rejection of the petitioner’s claim, submitted that
in the absence of agreements which are enforceable by law, the Work
Orders being part of the agreement become null and void and not
enforceable by law. The learned Junior Government Advocate further
submitted that the works were started only after the expiry of the
scheduled dates of completion of the works that fell on 10.08.2009 and no
application seeking extension of time was received from the petitioner
and therefore, the Work Orders were lapsed automatically. Contending
Page |5
so, the learned Junior Government Advocate prayed for dismissal of the
writ petition.
[7]
I have considered the submissions made by the learned
counsel appearing on either side and also perused the materials available
on record.
[8]
The grievance of the petitioner is that despite completion of the
work awarded and executed by him, the respondent authorities without
assigning any valid ground declined to settle the undisputed bill amounts
and had passed the impugned order arbitrarily.
[9]
The respondents contended that no formal agreements were
concluded and in the absence of valid agreements, the Work Orders
issued to the petitioner become null and void. In the impugned order
itself, the second respondent stated that works were started only after the
expiry of the schedule dates of completion of works and no application for
extension of time was received. When the respondents stated that no
agreements were existing between the respondents and the petitioner,
how they can say that works started only after the expiry of the schedule
dates. The respondents cannot approbate and reprobate. Nothing has
been produced by the respondents to show that after the expiry of the
schedule dates, the works were completed.
[10]
Stating that despite the works being completed, bills were not
settled, the petitioner approached this Court by filing writ petition in
Page |6
W.P(C) No. 242 of 2016 for payment of the undisputed bill amounts. By
the order dated 30.03.2016, this Court passed the following order:
“In the above factual backdrop, this writ petition is
disposed of with the following directions:(i)
(ii)
(iii)
The claim of the petitioner for payment of
undisputed bills amount have to be verified by the
Chief Engineer or the Executive Engineer
authorised by the Chief Engineer.
The said verification should be completed within a
period of 3(three) months from the date of receipt
of certified copy of this order; and
After verification of the undisputed bills amount
payable to the petitioner, the same shall be
released in favour of the petitioner in accordance
with seniority in completion of works”.
With the above directions, the writ petition is
disposed of.
[11]
As against the order dated 30.03.2016 passed in W.P.(C) No.
242 of 2016, the respondents have not preferred any appeal and the said
order attained finality. However, after a lapse of four months, the
impugned order came to be passed stating inter alia that the Government
of Manipur has decided that no payment shall be made to the petitioner in
respect of the works viz.,(i) construction of P/dam at Mare paddy field at
KhamasomPhyngrel and (ii) construction of P/W a/c Pharang River at
SihaiKahaophung.
[12]
As rightly argued by the learned counsel for the petitioner, the
respondents cannot deny the fact that Work Orders were issued to the
petitioner after completing all formalities and the petitioner had also
executed the works. Though the respondents contended that works were
started after the expiry of the scheduled dates, as stated supra, nothing
Page |7
has been produced to establish the same and moreover such ground has
never been taken in the liability certificate issued execution of the work
orders.
[13]
The contention of the respondents that in the absence of
agreements, which are enforceable in law, the Works Orders being part of
the agreements become null and void and not enforceable by law is
unsustainable. When this Court earlier passed an order in W.P.(C) No.
242 of 2016 directing the respondents to release the undisputed bill
amount to the petitioner after verification, contrary to the said direction,
the second respondent, after prolonged period of four months, cannot
reject the claim of the petitioner raising a plea that no agreements subsist.
It is not know as to why such plea was never taken at the first instance by
the respondents in the earlier round of litigation and nothing in this regard
has been recorded in the earlier order.
[14]
Having issued Work Orders in favour of the petitioner for
construction of P/dam at Mare paddy field at KhamasomPhyngrel and
construction of P/W a/c Pharang River at SihaiKahaophung and having
executed the works by the petitioner and also the progress of the work
having been recorded in the measurement books maintained by the
respondent authorities, the respondents cannot contend that the works
were started only after the expiry of scheduled dates of completion of the
works.
Page |8
[15]
On a perusal of the impugned order, it is seen that the second
respondent without proper application of mind to the facts of the case on
hand, rejected the claim of the petitioner and thus, the impugned order
cannot be sustained in the eye of law and the same is liable to be set
aside and the respondent authorities are bound to settle the undisputed
bill amounts due to the petitioner forthwith.
[16]
In the result, the writ petition is allowed, thereby setting aside
the impugned order dated 11.07.2016 passed by the second respondent.
The respondent authorities are directed to settle the undisputed bill
amounts viz., Rs. 11,77,866/- to the petitioner as ordered in W.P.(C) No.
242 of 2016 within a period of twelve weeks from the date of receipt of a
copy of this order. No Costs.
JUDGE
FR/NFR
John Kom
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review