HIGH COURT OF JAMMU &KASHMIR AND LADAKH
AT JAMMU
…
WP(C) No. 958/2023
Uploaded on: 11.08.2026
Mohd Shafi Chopan, Age 65
years S/o Habib Chopan, R/o
Sumber, Tehsil Ramban District
Ramban.
…….Petitioner(s)
Through: Mr. M. Nadeem Bhat, Advocate
Vs.
1. The Union Territory of
Jammu and Kashmir through
its Commissioner/Secretary
to Government, Revenue
Department, Civil Secretariat,
Srinagar/Jammu.
2. Deputy
Ramban.
Commissioner,
3. Collector Land Acquisition
(Railway) Additional Deputy
Commissioner, Ramban.
…..Respondent(s)
Through: Ms. Sagira Jaffer, Advocate vice
Ms. Monika Kohli, Sr. AAG
CORAM: HON’BLE MR. JUSTICE RAJNESH OSWAL, JUDGE
ORDER
10.08.2026
1.
The petitioner has filed the present petition seeking a direction to the
respondents, more particularly respondent No. 3, to release the
compensation in favour of the petitioner, as already assessed by
respondent No. 3 in terms of the award dated 06.09.2012, in respect of
land measuring 2 kanals 12 marlas, comprising Survey No. 340, 11
kanals 09 marlas, comprising Survey No. 338, and 01 kanal 16 marlas,
comprising Survey No. 343, measuring a total of 15 kanals 16 marlas,
situated at Village Sumber, Tehsil and District Ramban
2.
It is stated that the father of the petitioner was in cultivating possession
of the land mentioned above and, after his death, the said land devolved
upon the petitioner. The land is stated to be ancestral in nature and in the
possession of the petitioner’s forefathers since 1960. It is further stated
that the petitioner’s land was acquired by the respondents for the
construction of a railway track at Village Sumber, vide award dated
06.11.2022, and the compensation payable to the petitioner was assessed
at Rs. 14,27,725/-. However, the awarded amount has not been released
in favour of the petitioner till date. It is further stated that the petitioner is
a “person interested” within the meaning of Section 3(b) of the Land
Acquisition Act and that, in terms of Government Order No. 434 of
1966, proprietary rights were required to be conferred upon persons who
were in cultivating possession of State land. However, the concerned
Tehsildar did not attest the mutation in favour of the petitioner. In
paragraph 12 of the petition, the petitioner has relied upon the judgment
of the Division Bench of this Court passed in LPA No. 153/2020, titled
Krishan Singh v. UT of J&K and others, in support of his case.
3.
The respondents have filed their objections, wherein they have set out
the chronology of events, commencing from the issuance of notice under
Section 4 of the Land Acquisition Act up to the passing of the award. It
is, however, stated that the assessment of the fruit-bearing trees has been
WP(C) No. 958/2023
carried out and compensation equivalent to 40% of the value of the fruitbearing trees existing on the State land has already been deposited in the
bank account of the petitioner, whereas the remaining 60% of the
compensation in respect of the fruit-bearing trees existing on the State
land is to be deposited under State Revenue Head 0029. It is further
stated that the petitioner is not entitled to any compensation, as the land
is recorded as State land in the revenue records.
4.
Learned counsel for the petitioner, in support of his submissions, has
relied upon the judgment of this Court passed in WP(C) No. 1855/2011,
titled Gain Chand/Singh v. UT of J&K and others, to contend that, in an
identical matter, this Court had allowed the writ petition and directed the
respondents therein to pay compensation to the petitioner therein in
accordance with the award.
5.
Learned counsel appearing for the respondents submits that the petitioner
is an unauthorized occupant of the State land and, therefore, has no right
to claim compensation in respect thereof.
6.
Heard learned counsel for the parties and perused the record.
7.
Admittedly, the petitioner is in possession of the State land. As per the
apportionment statement, the petitioner has been found to be in
possession of State land measuring 11 kanals 09 marlas, comprising
Survey No. 338; 02 kanals 12 marlas, comprising Survey No. 340; and
01 kanal 16 marlas, comprising Survey No. 343. The apportionment
statement also assesses the compensation payable in respect of the
aforesaid land to the petitioner.
WP(C) No. 958/2023
8.
The sole contention raised by the respondents for denying the
compensation so assessed in terms of the award and the apportionment
statement is that the petitioner, being an unauthorized occupant of the
State land, is not entitled to receive any compensation in respect thereof.
9.
The issue is no longer res integra. It is well settled that a person in
possession of the acquired land is a “person interested” and is entitled to
receive compensation in respect of such land in accordance with the final
award, notwithstanding the fact that he may not be the owner thereof or
that the land is recorded as State land. In the judgment relied upon by the
petitioner in Gain Chand/Singh (supra), this Court directed the
respondents to release the compensation to the petitioner therein in
accordance with the award, after placing reliance upon the judgment
rendered by the Division Bench in LPA No. 153/2020, titled Krishan
Singh and another v. Union Territory of J&K and others, decided on
21.08.2021, and after taking note of paragraphs 6, 7 and 8 thereof. The
paragraphs 6, 7 and 8 of the said judgment are reproduced hereunder:
“6 From a perusal of the award` passed in the instant case and
the apportionment statement prepared by the Collector Land
Acquisition, Gool, it is abundantly clear that the compensation
has been worked out by the Collector in the name of the
appellants, who have been found to be in cultivating possession
thereof. No doubt, the State is the owner of the State land, but as
is held by the Hon‟ble Supreme Court in the case of Sharda
Devi (supra) that the Government, not being a person interested
within the meaning of Section 3(b) of the Act, has no right to
compensation payable for the land owned and possessed by it.
To be precise, the State land cannot be made subject matter of
acquisition at the instance of and for the benefit of the
Government. Otherwise also, the award passed by the
Collector Land Acquisition, Gool in the instant case has
become final and the respondents have not challenged the
same. It, thus, does not lie in the mouth of the respondents
to say that the appellants, though named in the
apportionment statement to receive the compensation,
should be denied the compensation on the ground that they
WP(C) No. 958/2023
are not the owner of the land acquired, but were only found
to be in cultivating possession.
7 This Court considered similar question in case titled
‘Krishana vs. State of Jammu and Kashmir and ors’ (OWP
No. 1101/2016) and, after relying upon several judgments of
this Court as well as the Apex Court, concluded that the person
in possession of the land is a ‘person interested’ and entitled
to compensation of the acquired land as per the final award,
even though he may not be owner of the property and the
land is a State land. It is not in dispute that the appellants
have been in long continuous possession of the land and
have, therefore, acquired sufficient interest in the land to
claim compensation.
8 For facility of reference, the observations of this Court in
paragraph 22 of the judgment rendered in the case of Krishana
(supra) are reproduced hereunder:
“This is exactly the position in the present case, where
while making the award, the Collector itself determined the
compensation in respect of the aforesaid State land
recognizing the tenancy/possession of the petitioner.
Therefore, the compensation that has been determined
under the award in respect of the land in question is for the
person interested namely, the petitioner. Thus, it can safely
be concluded that the petitioner is the person interested
entitled to the compensation of the acquired land as per the
final award dated 20.03.2012 to the tune of Rs. 85,388/-,
Even though he may not be the owner of the property and
the land is that of the State simply on the basis even though
he may not be the owner of the property and the land is
that of the State simply on the basis of his long possession
which is not in dispute”.
(emphasis added)
10.
The aforesaid judgment of the Division Bench was assailed before the
Hon’ble Supreme Court, however, the Special Leave Petition came to be
dismissed vide order dated 21.11.2024.
11.
Thus, the respondents cannot seek to deny the petitioner the
compensation duly assessed by respondent No. 3-Collector merely on
the ground that the petitioner was in unauthorized occupation of the State
land, particularly when the award determining the compensation has not
been assailed by the Union Territory of Jammu and Kashmir.
12.
In view of the above, the present petition is disposed of by directing the
respondent No. 3 to release the compensation in favour petitioner
WP(C) No. 958/2023
assessed by respondent No. 3, within a period of eight weeks alongwith
interest @ 6% per annum from date of receipt of this order till the actual
compensation is released.
(Rajnesh Oswal)
Judge
Jammu
10.08.2026
Karam Chand
Whether approved for reporting:
KARAM CHAND
2026.08.10 21:53
I attest to the accuracy and
integrity of this document
WP(C) No. 958/2023
Yes/No
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review