The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
08. 01.2014 passed by the appellate court in Misc. Appeal No.1 of 2013 and the order dated 03.06.2013 as delivered in Civil Misc. No.26 of 2013 [in T.S.EXE(T) 14 of 2011]by the Civil Judge, Senior Division, South Tripura, Udaipur are set aside but without disturbing the status and post execution. It is further directed that the executing court (the Civil Judge, Senior Division, Gomati, Udaipur) shall appoint a Survey Commissioner with reference to: Whether the decreetal land as described in the Schedule-A in the application being Civil Misc. 26 of 2013 [arising from T.S.EXE(T) 14 of 2011] is part and parcel of the land as described in the Schedules-B and C of the said application on the status of land as described in the Schedules-B and C land ante execution?
14. While surveying those aspects as emerged, the Survey Commissioner shall take aid of the settlement map prepared during the survey and settlement operation and identify the land according to the map and the record of rights. For that purpose, all necessary records be inspected by the Survey Commissioner. That apart, he can take aid of the records maintained in the Tehashil or to its superior office. The executing court shall issue such letter of appointment within a period of 30(thirty) days from the date when a copy of this order be received by him. It is specifically mentioned here that the executing court is given liberty to appoint the Survey knowing person working under the Directorate of Settlement and Land Records or any Senior Surveyor working in the office of the Deputy Collector of the concerned jurisdiction. The cost of the Survey shall be borne by the appellants herein. After receipt of the Survey Commissioner’s report the parties will be entitled to all the rights as described under Order 26 of the CPC and thereafter, the executing court shall decide whether to accept the Survey Commissioner’s report or not. If the Survey Commissioner’s report is found to have any defect in that case further Survey Commissioner may be appointed by the executing court. If from the report, it is evident that the Schedules-B and C land are part and parcel of the Schedule-A land and the…
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
HIGH COURT OF TRIPURA
AGARTALA
RSA 16 of 2014
1. Md. Manu Mia,
son of late Dastur Mia
2. Md. Jahir Hossain,
son of Md. Manu Mia
3. Md. Ahid Mia,
son of late Chhattar Mia
4. Md. Mafij Mia,
son of late Jahar Ali
5. Md. Ashab Mia,
son of Md. Omar Ali
-all are residents of Village-East Gakulpur,
P.O. Gakulpur, P.S. R.K. Pur, Udaipur,
District : Gomati, Tripura
----Appellant(s)
Versus
1. Smt. Laxmi Datta,
wife of late Prafulla Datta
2. Md. Taiyab Ali,
son of Md. Rustam Ali
3. Md. Omed Ali,
son of Md. Rustam Ali
-all are residents of Village- East Gakulpur,
P.O. Gakulpur, P.S. R.K. Pur, Udaipur,
District : Gomati, Tripura
----Respondent(s)
For Appellant(s)
:
Mr. D.K. Daschoudhury, Advocate
For Respondent(s)
:
Mr. S. Mahajan, Advocate
Whether fit for
Reporting
:
NO
HON’BLE MR. JUSTICE S. TALAPATRA
Judgment & Order
11.06.2018
Heard
Mr.
D.K.
Daschoudhury,
learned
counsel
appearing for the appellants as well as Mr. S. Mahajan, learned
counsel appearing for the decree-holder, the respondent No.1.
None appears for the remaining respondents, despite due notice
from this court.
2.
This is an appeal under Section 100 of the CPC against
the judgment and order dated 08.01.2014, delivered in Civil Misc.
Appeal No.01 of 2013 by the District Judge, South Tripura,
Udaipur. By the said appeal, the order dated 03.06.2013 delivered
in Civil Misc. 26 of 2011 [arising from T.S.EXE(T) 14 of 2011] by
the Executing Court [the Civil Judge, Senior Division, South
Tripura, Udaipur] was challenged and by the impugned order
dated 08.01.2014, the first appellate court affirmed the said
judgment dated 03.06.2013. This appeal was admitted on the
following substantial question of law :
“When the report by the Survey Commissioner has
observed that the decretal land cannot be identified
by the description of the land as provided in the
decree whether executing court was correct in
allowing the execution of the decree by dispossessing
the appellants from the land on the basis of the
identification made by the decree holder?”
3.
For purpose of appreciating the said substantial
question as formulated by the order dated 28.07.2014, it would
be apposite to lay down the essential fact leading to the impugned
order. At the time of executing the decree, as obtained by the
respondent No.1, it was the claim of the present appellants that
they were evicted from their lawful possession. When they were
evicted, they filed an application under Order 21, Rules 97 to 106
read with Section 144 and 151 of the CPC for setting aside the
said execution and for restoration of their possession over the
land as described in Schedule-B and Schedule-C of the said
application.
4.
According to the appellants, the Schedule-A land is
the decretal land which is a distinct land from the land as
described in the Schedule-B and the Schedule-C. The Schedule-A
land pertains to C.S. plot No.141(p), hal plot No.3204 of RS
khatian No.975 measuring 0.20 acre under mouja R.K. pur RF.
But the appellants have been dispossessed while executing the
said decree as passed in T.S. 48 of 2009 vide execution case
No.EXE(T) 14 of 2011 from their possession over the land
pertaining to plots No.1411 (p) and 1548 (p) corresponding to RS
plot No.3261/3756 of khatian No.7321/1 under mouja R.K.pur RF
measuring 0.06 acre [so far the appellants No.1 and 2 are
concerned] and 0.08 acre [so far the appellants No. 3 and 5 are
concerned]. Similarly, the appellant No.4 has been dispossessed.
According to the appellant No.4, from his allotted land pertaining
to C.S. plots No.B/45, 1411/1548(p) corresponding to RS plots
No.3261/3557/5174 measuring 0.05 acre under mouja R.K. pur
RF he has been dispossessed. The said land was allotted to him by
the allotment case No.21 of 1997.
5.
they
The appellants in their said application had stated that
were
illegally
dis-possessed
from
the
said
land
on
16.12.2011 by demolishing their home stead, huts etc. Therefore,
they have claimed the loss and damages to the extent of
Rs.1,75,000/- so far the appellant No.1 is concerned, Rs.75,000/-
so far the appellant No.2 is concerned, Rs.1,00,000/- so far the
appellant Nos. 3 and 4 is concerned and Rs.50,000/- so far the
appellant No.5 is concerned. Before the decree was executed,
according to the appellants two Survey Commissions were
appointed. Since the second Survey Commission was appointed,
the report of the first Survey Commission was suppressed and
declared not accepted by the Executing Court. The second Survey
Commission’s report was submitted on 17.12.2011.
6.
According to the appellants, they were dispossessed
evicted from their land as described in the Schedule-B and the
Schedule-C on 16.12.2011 and thereafter, on 20.12.2011 when
the order of execution under Section 50 was passed in the said
execution case on 15.05.2012, according to them, the cause of
action arose and when the appellants obtained the certified copy
of the judgment and decree delivered in T.S.48 of 2009 they
came to know about the perspective facts. Thus, the executing
court has observed that any application to be filed under Rule 99
of Order 21 of the CPC has to be filed within thirty days, but the
said application was filed on 05.07.2012 and it was registered as
Civil Misc. 26 of 2012.
7.
The
respondent
No.1
herein
and
the
original
defendants were represented in the proceeding and the plaintiff
decree holder, the respondent No.1 herein filed the objection
against the said petition contending that the appellants did not
have any legal footing to possess the land of the decree holder
and hence, they were liable to be evicted and there was no
requirement of recalling the order of the execution case by way of
restoring their possession. It is apparent on the face of the
objection that the claim of the plaintiff-decree holder is related
only to the decretal land, not the adjoining land. Her impression
was that the appellants were possessing her land and for recovery
of which the said decree was passed. It was by way of execution,
her land has been recovered and handed over to her and the
formal order closing the execution proceeding was passed by the
Execution Court. Only thereafter, the said application under Rule
99 read with Section 101 of the order 21 CPC was filed by the
aggrieved appellants. The court below for purpose of determining
the said application, treating that as if it were a suit, framed the
following issues:
“i. Whether the Judgment and Decree passed in Case
No. Title Suit 48 of 2009 dated 27.08.2010 and
31.08.2010 passed by this Court are not binding on
the present petitioners and
ii. Whether present suit was a collusive suit and
hence, the present decree is un-enforceable and non
executable ?
iii. Whether the decreetal land in Case No. Title Suit
48 of 2009 is un-identifiable and untraceable having
no existence?
iv. Whether the plaintiff-petitioners are entitled to be
resisted with the possession of the Schedule B and
Schedule C land of the petition?
v. Whether the plaintiff-petitioners are entitled for
any other costs, damages and compensation?”
8.
In this regard and to make the narrative precise, this
court would observe that at the outset Mr. D.K. Daschoudhury,
learned counsel appearing for the appellants has made a
statement which is very categorical that over the decretal land
which has been described in the Schedule-A of the said application
filed under Rule 99 read with Section 101 of Order 21 of the CPC,
the appellants do not have any claim whatsoever. It thus clearly
implies that so far the judgment and decree passed in Case
No.T.S. 48 of 2009, the appellants do not have any opposition,
they are wholly concerned with the recovery of the possession of
the Schedule-B and the Schedule-C land.
9.
From a reading of the order dated 03.06.2013
delivered in Civil Misc.26 of 2012 by which the said application
was finally decided, it appears that no issue had been framed to
identify whether the Schedule-B and Schedule-C land are part and
parcel of the Schedule-A land or the Schedule-A land vis-a-vis the
Schedule-B and Schedule-C land is separate and distinct land. If
the Schedule-B and the Schedule-C land are not part and parcel
of the Schedule-A land, there cannot be any amount of doubt,
without without even determining the status of the appellants that
the said execution was grossly wrong and it required to be
interfered with. But in any case if it is found that the Schedule-B
and the Schedule-C land are part and parcel of the Schedule-A
land, then the question of status of the appellants may be
relevant for a remote case declaring the character under what
authority they were possessing the land or how they came into
the
possession.
Whether
they
came
into
the
possession
constructively or they were in the real possession over the
Schedules-B and C land. Further, whether they would be allowed
to continue in the said land can also be determined by the
executing court after giving them the appropriate opportunity. In
the present case, the appellants have set in a legal action. If it is
found that they were possessing the suit land illegally and they
cannot show any document of holding that land, they can be
treated as the trespassers over the land. In that case, they cannot
resist the execution of the land if further it is shown that their
trespass is after passing of the decree. But the first and foremost
factor to be considered is that the executing court while
determining the application being Civil Misc.26 of 2012, ought to
have framed a issue to determine the relation between the
Schedule-A land and the Schedule-B and C land. But that was not
so done and without doing so, the executing court while
determining the said application has observed as under:
“On perusal of Exhibit-5, it reveals that the process
server on 16.12.2011 along with the bailiff and the
Survey Commissioner reached the decretal land and
they accordingly, measured the decretal land
properly by giving a specific identification mark
around the decretal land and gave the possession of
the decretal land to the plaintiff-decree holderrespondent properly and the decree was executed
properly by the process server. On over all perusal of
the Exhibit-5 from the Process Server’s Report dated
09.11.2011, it reveals that the plaintiff-petitioners of
this case were living in the decretal land in three
houses. Also on perusal of the Process Server’s
Report dated 17.12.2011, there is no mentioning of
the plaintiff-petitioners of this case in the decretal
land as the decree was executed properly in presence
of
the
plaintiff-decree
holder-respondent
and
Judgment Debtor-defendant-respondents of that case
and at that time the plaintiff-petitioners of the
present petition were not found in the decretal land
as it is clear from the Process Server’s Report. No
objection was also raised on behalf of the plaintiffpetitioners of this case at the time of execution of the
decretal land on 16.12.2011. There was no iota of
evidence in the Process Server’s Report about
presence of the plaintiff-petitioners over the decretal
land on 16.12.2011. Even if it is believed that the
plaintiff-petitioners were found living on the decretal
land on 05.11.2011. But there was no whereabouts of
the plaintiff-petitioners on the next date, i.e., on
16.12.2011, the day on which the decree was
executed properly. If as per the plaintiff-petitioners’
case the report of Process Server dated 09.11.2011 is
believed to be true then the Report of the Process
Server dated 17.12.2011 is also believed to be true.
The plaintiff-petitioners cannot be allowed to put
forward the submission that the Report dated
09.11.2011 is true one and the Report dated
17.12.2011 is wrong one. The plaintiff-petitioners
cannot be allowed to take benefit of the Report which
supports their case and reject the report which goes
against them. Hence, Exhibit-5 though supports the
plaintiff-petitioners’ case to some extent but it
cannot be said to have supported the plaintiffpetitioners’ case fully as the plaintiff-petitioners of
the present petition did not raised any objection
during execution of the decree and there is no
evidence that on what basis and under what rights
the plaintiff-petitioners were possessing the decretal
land.”
Having observed thus, the said process was discarded
and
being
aggrieved,
the
appellants
herein,
filed
the
miscellaneous appeal and the said appeal as stated was dismissed
and the [judgment and order] in the miscellaneous appeal has
been questioned in this appeal.
10.
Mr. D.K. Daschoudhury, learned counsel appearing for
the appellants has categorically submitted that the appellants are
poor persons and they migrates from one place to another in
search of their livelihood and on the day of execution, they could
not resist the proceeding. When they found that they were
dispossessed from their land, they took initiative to collect the
documents. In the process of collection of those documents, they
wasted substantial part of the time. However, Mr. Daschoudhury,
learned counsel has fairly submitted that the date of delivery of
the documents cannot be treated as the day of cause of action.
But lack of knowledge and the days wasted for collection of the
certified copy are liable to be discounted in terms of the Limitation
Act because this is an application, not strictly a suit and moreover
in the event of institution of suit, this days are to be excluded for
obvious reason as they were taken completely aback because
there were not made parties in the suit, outcome of which is the
decree that has been executed by evicting them and demolishing
their homestead etc.
11.
Mr. S. Mahajan, learned counsel appearing for the
respondents has quite succinctly submitted that there cannot be
any amount of doubt that the appellants were squatting over the
decreetal land and as such, they have been evicted. From the
Process Server’s Report prepared on the date of execution, it
would be clearly apparent that even the appellants were not
present on the day of execution. They are attempting to make out
a case which is not borne in the records and as such, no
interference is required.
12.
But
when
this
court
proposed
that
since
Mr.
Daschoudhury, learned counsel has made a categorical statement
that over the decreetal land which has been described in the
Schedule-A of the application under Rule 99 and 101 Order 21 of
the CPC then appellants do not have any claim, if the decreetal
land as described in the Schedule-A vis-à-vis the Schedules-B and
C of the said application are identified to the effect that whether
the decree holder-respondent will have any objection
or not.
Even this court has indicated that the status-quo as on today shall
be maintained till such survey is carried out. Mr. Mahajan, learned
counsel has agreed to the proposition and as such, there is a
consensus between the counsel for the parties to the extent that a
survey may be carried out for proper identification of the
decreetal land as described in the Schedule-A of the said
application being Civil Misc.26 of 2012 and the land described in
the Schedules-B and C ascribed there.
13.
For
this
purpose,
the
impugned
order
dated
08.01.2014 passed by the appellate court in Misc. Appeal No.1 of
2013 and the order dated 03.06.2013 as delivered in Civil Misc.
No.26 of 2013 [in T.S.EXE(T) 14 of 2011]by the Civil Judge,
Senior Division, South Tripura, Udaipur are set aside but without
disturbing the status and post execution. It is further directed that
the executing court (the Civil Judge, Senior Division, Gomati,
Udaipur) shall appoint a Survey Commissioner with reference to:
Whether the decreetal land as described in the
Schedule-A in the application being Civil Misc. 26 of
2013 [arising from T.S.EXE(T) 14 of 2011] is part
and parcel of the land as described in the
Schedules-B and C of the said application on the
status of land as described in the Schedules-B and C
land ante execution?
14.
While surveying those aspects as emerged, the
Survey Commissioner shall take aid of the settlement map
prepared during the survey and settlement operation and identify
the land according to the map and the record of rights. For that
purpose, all necessary records be inspected by the Survey
Commissioner. That apart, he can take aid of the records
maintained in the Tehashil or to its superior office.
The
executing
court
shall
issue
such
letter
of
appointment within a period of 30(thirty) days from the date
when a copy of this order be received by him. It is specifically
mentioned here that the executing court is given liberty to appoint
the Survey knowing person working under the Directorate of
Settlement and Land Records or any Senior Surveyor working in
the office of the Deputy Collector of the concerned jurisdiction.
The cost of the Survey shall be borne by the appellants herein.
After receipt of the Survey Commissioner’s report the parties will
be entitled to all the rights as described under Order 26 of the
CPC and thereafter, the executing court shall decide whether to
accept the Survey Commissioner’s report or not. If the Survey
Commissioner’s report is found to have any defect in that case
further Survey Commissioner may be appointed by the executing
court. If from the report, it is evident that the Schedules-B and C
land are part and parcel of the Schedule-A land and then this
proceeding shall be closed and no further proceeding will be
allowed to be carried out by either of the parties. But if it is found
that the Schedules-B and C land are distinctly separate from the
Schedule-A land then the Schedules-B and C land shall be
released forthwith by the executing court and the due action shall
be taken to restitute that land to the appellants . If it is found that
any part of the Schedule-B and Schedule-C land has been taken
over at the time of execution, that part shall be demarcated by
the Survey Commissioner and the executing court shall recover
those parts from the respondent No.1 and handover to the
appellants.
15.
For purpose of avoiding any sort of confusion, it is
clearly observed that the parties will be bound by the Survey
Commissioner’s report. Till the executing court takes a decision on
the basis of the Survey Commissioner’s report, statusquo as on
today
shall
be
Commissioner’s
maintained.
report
holds
In
the
event,
the
that
the
Schedule-B
Survey
and
the
Schedule-C land has been recorded without proper scrutiny, in
that case damage can be determined by the Civil Court.
In the result, this appeal is allowed to the limited
extent as stated above.
Draw the decree accordingly.
Send down the records thereafter with a copy of this
judgment and order.
JUDGE
Sabyasachi B
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review