Page No.# 1/11
GAHC040009002024
THE GAUHATI HIGH COURT
(HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
(ITANAGAR BENCH)
Case No. : IA(C)/67/2026
M/s Woodhill Shivam (Joint Venture)
Age: 0
Occupation :
Address:OU 522
5th Floor
Esplanade Commercial Development
Unit No. 32
Rasulgarh
Bhubaneswar
Orissa 751010
VERSUS
Vijay Jamoh and 7 Ors
Age: 0
Occupation :
Address:Son of Tasing Jamoh
presently residing at D Sector
Naharlagun
PO and PS Naharlagun
Papumpare District
Arunachal Pradesh
2:Doge Lona
Age: 30
Occupation :
Address:Son of Jomi Lona
presently residing at Polo colony Naharlagun
PO and PS Naharlagun
Papumpare District
Arunachal Pradesh
3:The State of Arunachal Pradesh
Page No.# 2/11
Age: 0
Occupation :
Address:represented by the Chief Secretary
Govt of Arunachal Pradesh
Itanagar
4:The Chief Secretary
Age: 0
Occupation :
Address:Govt of Arunachal Pradesh
Itanagar
5:The Commissioner/ Secretary
Age: 0
Occupation :
Address:PWD
Govt of Arunachal Pradesh
Itanagar
6:The Chief Engineer (Highway Zone)
Age: 0
Occupation :
Address:PWD
Govt of Arunachal Pradesh
Itanagar
7:The Executive Engineer
Age: 0
Occupation :
Address:Naharlagun Highway Division
PWD
Nirjuli
Papumpare District
Arunachal Pradesh
8:The Secretary
Age: 0
Occupation :
Address:Govt of India
Ministry of Road Transport and Highways
Transport Bhawan
1 Parliament Street
New Delhi 110001
-----------Advocate for : Rakesh Dubey
Advocate for : Dicky Panging appearing for Vijay Jamoh and 7 Ors: Advocate ,
,
Page No.# 3/11
,
,
,
,
, appearing for 2,
3,
4,
5,
6,
7,
8, respectively.
Linked Case- PIL No. 11/2024
Vijay Jamoh and Anr
Son of Tasing Jamoh, presently residing at D Sector, Naharlagun, PO
and PS Naharlagun, Papumpare District, Arunachal Pradesh
2:
Doge Lona
Age:
Occupation :
Son of Jomi Lona
presently residing at Polo colony Naharlagun
PO and PS Naharlagun
Papumpare District
Arunachal Prades
VERSUS
The State of AP and 7 Ors
represented by the Chief Secretary, Govt of Arunachal Pradesh,
Itanagar
2:The Chief Secretary
Age: 0
Page No.# 4/11
Occupation :
Govt of Arunachal Pradesh
Itanagar
3:The Commissioner/ Secretary
Age: 0
Occupation :
PWD
Govt of Arunachal Pradesh
Itanagar
4:The Chief Engineer (Highway Zone)
Age: 0
Occupation :
PWD
Govt of Arunachal Pradesh
Itanagar
5:The Executiv Engineer
Age: 0
Occupation :
Naharlagun Highway Division
PWD
Nirjuli
Papumpare District
Arunachal Pradesh
6:The Secretary
Age: 0
Occupation :
Govt of India
Ministry of Road Transport and Highways
Transport Bhawan
1 Parliament Street
New Delhi 110001
7:M/s Woodhill Shivam (Joint Venture)
Age: 0
Occupation :
OU 522
5th Floor
Esplanade Commercial Development
Unit No. 32
Rasulgarh
Bhubaneswar
Orissa 751010
Page No.# 5/11
8:M/s T K Consortium Pvt Ltd
Age: 0
Occupation :
Model Village Naharlagun
Papumpare District
Arunachal Prades
Advocate for the Petitioner : Dicky Panging, Rosy c Lowangcha,Tokge
Darin,Kirmar Ado,Marge D,Daina Tamuk
Advocate for the Respondent : GA (AP), Eddie Payeng,R Dubey,Kamal Saxena,Rajiv
Cheri,Kirmani Lollen,Tao Tarin,A T Tara,J Likha,DSGI,Marto
Kato,SC(Highway),Rintu Saikia
BEFORE
HONOURABLE MR. JUSTICE ROBIN PHUKAN
HONOURABLE MR. JUSTICE BUDI HABUNG
ORDER
17.03.2026
(ROBIN PHUKAN, J)
Heard Mr. R. Dubey, learned counsel for the applicant/respondent No. 7.
Also heard Mr. D. Panging, learned counsel for the opposite party Nos. 1 & 2;
Mr. N. Ratan, learned Additional Advocate General for the opposite party Nos. 3,
4 & 5; Mr. R. Saikia, learned Standing Counsel for the opposite party Nos. 6 & 7
and Mr. M. Kato, learned Deputy Solicitor General of India, for the opposite
party No. 8.
2.
Mr. Dubey, learned counsel for the applicant submits that this interlocutory
application has been preferred by the applicant/respondent No. 7 in the PIL No.
11/2024; for issuing direction to the respondent authorities not to proceed
further with the termination of the contract in question, till the completion of the
extension period of the contract; i.e., till 31.07.2026.
Page No.# 6/11
2.1. Mr. Dubey, further submits that the applicant/respondent No. 7 has been
executing the work of 4-Laning of Itanagar to Banderdewa Section of NH-415,
from Km 40+430 to Km 51-735 (Pkg-B) on EPC Mode, which was awarded on
26.11.2020, and the period of completion of the work is extended up to
31.07.2026.
2.2
It is the further submission of Mr. Dubey that the PIL No. 11/2024, was
instituted by the opposite party Nos. 1 & 2, alleging tardy progress of work,
which was awarded to the applicant/respondent No. 7.
2.3 Drawing the attention of this Court to the order, dated 11.02.2026, passed
by this Court in the PIL No. 11/2024, especially, to paragraph Nos. 4, 5, 6 & 7;
Mr. Dubey submits that in the said paragraphs, this Court has observed that“This matter has come up on numerous occasions and this Court
vide an order dated 24.12.2025 had recorded that the work has to
be completed within 31.07.2026 beyond which, no extension is
required to be given. It may be mentioned that the schedule date
of completion was 07.12.2024 and from that date, more than a
year has passed.
On a specific query made to the learned counsel for the
Department along with the Officer, who is present as well as
Shri R. Dubey, learned counsel for the respondent No. 7, a
response has been given which would be practically impossible to
complete the work by the extended deadline on 31.07.2026.
Taking
into
consideration
the
aforesaid
facts
and
circumstances and the importance of the matter which has got
immense public interest, this Court is of the opinion that the
Department be given a liberty to take all further steps for
timely completion of the work by ensuring that the standards are
maintained.
The actions taken by the Department are to be apprised to this
Page No.# 7/11
Court by the next date.”
2.4
It is the further submission of Mr. Dubey, that on the basis of another
order, dated 22.01.2026, the PWD Department has filed an affidavit, responding
to the issue raised by the respondent No. 7 and though, a copy of the same was
not served upon the respondent No. 7, it could be gathered from the submission
on their behalf that they were seeking liberty to proceed with the termination of
the contract in question and after the order of this Court, dated 11.02.2026,
passed in PIL No. 11/2024; the Chief Engineer, Highway Division, PWD,
Arunachal Pradesh, Itanagar, issued a notice of intention to terminate the
contract in question, dated 13.02.2026; to the applicant. Though, the order,
dated 24.12.2025, does not lay down that any extension beyond 31.07.2026,
cannot be granted as a matter of course and would depend upon various
factors, as per contractual terms and that, the perspective of the public interest,
which was been espoused in the present proceeding, will not be served by
terminating the contract of the applicant/respondent No. 7, and rather, it would
cause more harm to the public interest; and within 31 st July, 2024, the applicant
has programmed to execute major portion of the work and that termination will
cause huge loss to the working period, the plant and machineries, as well as the
manpower of the applicant, and the applicant would become idle; and that, as
per the estimate/scheduled program, the entire work of the flyover can be
completed within the outer limit of 31.03.2027, and this does not mean that the
applicant is seeking extension at this stage, till 31.03.2027; and therefore, Mr.
Dubey submits that the applicant/respondent No.7 may be allowed to work till
31.07.2026, as per the extension of time granted and extending upon its
performance, the authorities can consider as to whether, in terms of the
contract, the applicant would be entitled for further extension of time or not.
Page No.# 8/11
2.5
Mr. Dubey, also submits that there was lapse on the part of the State
respondents in handing over the land for construction of the flyover and the
road and also, in respect of payment of arrear bills and unless, the bills are paid
in time, the applicant is not in a position to execute the work; and since, time
has been granted till 31.07.2026, the applicant/respondent No. 7 may be
allowed to continue his work till then.
3.
Mr. D. Panging, learned counsel for the opposite party Nos. 1 & 2 submits
that since, this is PIL, the petitioner is no longer required to file any response
and by bringing the public cause to the notice of this Court, the petition has
done its job.
4.
Per contra, Mr. Ratan, learned Additional Advocate General for the opposite
party Nos. 3, 4 & 5, submits that the State respondents have filed written
objection against the interlocutory application. Referring to the Order of this
Court, dated 24.12.2025; submits that in the said order, this Court was pleased
to direct that no further extension, beyond 31.07.2026; shall be granted, as a
matter of course and further, referring to the Order, dated 11.02.2026, he
submits that this Court has categorically made a observation that to a specific
query made to the learned counsel for the Department and also, Mr. R. Dubey,
learned counsel for the respondent No. 7, a response has been given that it
would be practically impossible to complete the work by extending the deadline,
till 31.07.2026 and vide said order and also considering the importance of the
matter, which got immense public interest; this Court had granted the
department liberty to take further steps for timely completion of work by
ensuring that the standard is maintained. He further submits that the Chief
Engineer, Highway Division, PWD, Arunachal Pradesh, Itanagar, vide letter, dated
13.02.2026, has notified the applicant/respondent No. 7; about the intention to
Page No.# 9/11
terminate, under Clause 23.1 (ii) of the EPC Contract Agreement, in respect of
4-Laning of Itanagar to Banderdewa Section of NH-415; and that since, it would
be practically not possible to complete the project within the deadline of
31.07.2026, and also, in view of the immense public interest involved in the
project; allowing the applicant to continue the work till 31.07.2026, would not
espouse the public interest and under such circumstances, the Department is
under obligation to complete the project as soon as practicable and with a view
to achieve the same, it has issued termination notice and therefore, he has
contended to dismiss this application.
5.
The learned Standing Counsel for the respondent/opposite parties also
subscribed the submission of Mr. Ratan.
6.
Having heard the submissions of the learned counsel for both the parties,
we have carefully gone through the application and documents placed on record
and also, perused the orders, passed by this Court on 24.12.2025, 22.01.2026
and
11.02.2026;
and
the
written
objection
filed
by
the
opposite
party/respondent Nos. 3, 4 & 5.
7.
It appears that on 11.02.2026, to a specific query put to the learned
counsel for the Department and to Mr. R. Dubey, learned counsel for the
respondent No. 7; a response has been given that it would be practically
impossible to complete the work by the extended deadline, on 31.07.2026 and,
vide said order, liberty was also granted to the Department to take further steps
for timely completion of the work, by ensuring that the standards are
maintained. And it appears that pursuant to the said order of granting liberty to
the Department, the Department has issued notice to the applicant herein,
notifying the intention to terminate the contract, under Clause 23.1 (ii) of the
Page No.# 10/11
EPC Contract Agreement.
8.
We have also taken note of the fact that the contract was awarded to the
applicant on 26.11.2020, and the completion period was 36 months, ending on
07.12.2024; and the same has been extended till 31.07.2026, by an order of this
Court.
9.
Further, we have taken note of the fact, from the order, dated 24.12.2025,
that as on 24.12.2025; the physical progress was about 48.32% and financial
progress was about 45.36%; and that 85 pillars, out of 149 pillars, had been
erected till then, i.e., 24.12.2025. And, from the cumulative physical progress
report, with effect from April 2025 to February 2026, as reflected in the para No.
20, of the objection, filed by the State respondent/opposite parties; indicates
that cumulative physical progress is only 50.63% and the financial progress is
46.92%; and in the remark column, it is reflected that the progress is critically
slow. This being the position, by no stretch of imagination, it can be expected
that the work will be completed within the extended period, i.e., 31.07.2026;
unless any miracle happens. And this fact is also apparent from the candid
statement made by the learned counsel for the Department and also by the
learned counsel for the applicant/respondent No. 7, that it would be practically
impossible to complete the work within the extended deadline, on 31.07.2026.
10. We have also taken note of the submission made by Mr. Dubey, in respect
of the difficulties in timely completion of the project and having weighed the
same against public interest involved in the project; and the balance is found to
be tilted in favour of the latter. Moreover, from the statement made in the para
No. 7 of the objection, it appears that the applicant has already invoked the
arbitration clause of the agreement and instituted an arbitration proceeding,
Page No.# 11/11
being Arbitration No. 1/2026, before the Court of the learned District Judge,
Yupia; and vide order, dated 05.03.2026, the learned District Judge, Yupia, has
granted interim relief to the applicant, by restraining the respondent authorities
from terminating the contract and encashing the bank guarantee, dated
23.12.2020; for an amount of Rs. 5,12,60,000/-, or regarding payment of bill
and other issues,
any coercive measures, till returnable date. Thus, his
grievance will be addressed in the said proceeding. Such issues cannot be
addressed in this PIL.
11. We are of the view that the paramount consideration at this stage, is the
completion of the project as soon as practicable, otherwise, public interest will
be seriously prejudiced. If, in view of the liberty granted by this Court, to the
respondent authorities, to take such steps for early completion of the project,
vide order, dated 11.02.2026; and if the authority has decided to terminate the
contract with the applicant herein, to take further such action, which will enable
the State respondent to complete the project early, then there is no question of
granting further time to the applicant up to 31.07.2026; to complete the work,
which, in the own words of the applicant, is virtually impracticable and as such,
we are of the considered opinion that it would not serve the public interest.
12. In that view of the matter, we find this interlocutory application devoid of
merit and accordingly, the same stands dismissed.
JUDGE
Comparing Assistant
JUDGE
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review