IN THE HIGH COURT OF MANIPUR
AT IMPHAL
W.P.(C) No. 32 of 2020
M/S Simplex Projects Ltd. through its Director Office at 19, Nellie
Sengupta Sarani 3rd Floor, Kolkata – 700087.
...Petitioner
-Versus1. State of Manipur through its Chief Secretary, Secretariat,
Manipur.
2. Public Works Department though its Chief Engineer
Manipur, Khuyathong Imphal – 795001.
3. The Executive Engineer, Office at Executive Engineer
Building Division No. 1 PWD, Manipur Khuyathong Imphal
– 795001.
...Respondents
B E F O R E
HON’BLE MR. JUSTICE KH. NOBIN SINGH
For the respondents
:: Shri S.D. Singh, Advocate asstd. by
Shri T. Momo Singh, Advocate
:: Shri N. Kumarjit, A.G. asstd. by
Date of hearing
Date of judgment & order
Shri P. Tamphamani, Advocate
:: 21-02-2020
:: 06-03-2020
For the petitioner
JUDGMENT AND ORDER
[1]
Heard Shri S.D Singh, learned Advocate assisted by Shri T.
Momo Singh, learned Advocate appearing for the petitioner and Shri N.
Kumarjit Singh, learned AG assisted by Mr. P. Tamphamani, learned
Advocate for the respondents.
W.P. (C) No. 32 of 2020
Contd.../-
[2]
[2]
By the instant writ petition, the petitioner has prayed for issuing
a writ of certiorari or any other appropriate writ to quash and set aside the
NIT dated 28-12-2019 issued by the respondent No.2; to issue a writ of
mandamus or any other appropriate writ directing the respondents not to
proceed with the said NIT; to declare Clause No.1.2.5 of NIT as illegal,
violative of the rights of the petitioner, ultra vires and null and void; to
issue a writ of mandamus or any other appropriate writ to direct the
respondents to grant an opportunity to the petitioner to participate in the
bid and to issue a writ of mandamus or any other appropriate writ
directing the respondents to continue with the execution of the work
awarded to the petitioner by quashing and setting aside the termination
letter dated 02-11-2019.
[3.1]
Facts and circumstances as narrated by the petitioner in the
writ petition are, in short, that on 18-02-2010, the respondents issued the
NIT for the work known as “Construction of Capital Complex (Civil
Secretariat Component) at Mantripukhri, Imphal”. The petitioner being
eligible, participated in the bid along with other bidders. The Technical Bid
was opened on 15-06-2010 and since only two bidders were found to be
eligible, their Financial Bids which were scheduled to be opened on
25-06-2010, were duly opened on 25-06-2010 itself.
[3.2]
The respondent No.2 vide its letter dated 06-07-2010 informed
the petitioner that it was found to be the lowest bidder and requested the
petitioner to attend office on 08-07-2010 for negotiation on rates quoted
W.P. (C) No. 32 of 2020
Contd.../-
[3]
by it. On 08-07-2010 the respondents wrote a letter to the petitioner,
being the lowest bidder, for negotiation. After the negotiation being held,
the total value of the contract was fixed at Rs. 282.60 crores. A meeting
of the Tender Committee was held on 28-08-2010 and pursuant to a
decision taken by the respondents based on the minutes of the meeting,
a letter of intent was issued on 05-10-2010 in favour of the petitioner.
[3.3]
As per the Letter of Intent dated 05-10-2010 issued in favour of
the petitioner, the period for execution of the said works fixed at 36 (thirtysix) months from the date of execution of the agreement between the
parties which occurred on 18-10-2010 and accordingly, the original period
for execution of the works was scheduled to expire on 17-10-2013. The
contract was a lump sum contract meaning thereby that in the aforesaid
contract value, the petitioner was required to execute the work as
emerged from the scope of the works for the project in question
consisting of three buildings including its ancillary works. For completion
of the project, it was necessary that the final drawings were to be made
available by the respondents which engaged the consultant namely, M/s
Design Academy, Interior Design from Bangalore for the purpose of
preparing the drawings, designs etc. and to process the approval thereof
and to take other steps to supply the final drawings to the petitioner for
execution of the works.
[3.4]
As required under the terms and conditions, the petitioner
submitted the Bank Guarantee towards the performance of the contract
W.P. (C) No. 32 of 2020
Contd.../-
[4]
being 5% of the contract value. The completion of the project was fully
dependent on the performance of the contractual obligations by both the
parties. The occurrence of the natural calamity or civil war commotion,
Indian Labour Permit (ILP), National Highway/ State Highway/ road
blockages, bandhs, strikes etc. have always been treated as force mejure
and the parties would be absolved from the performance of the
contractual
obligations
and
the
delay
owing
to
the
aforesaid
circumstances.
[3.5]
The respondents were totally unable to supply the drawings
even after the expiry of 16 (sixteen) months out of 36 (thirty six) months
of the contractual period. The petitioner made it clear to the respondents
that due to non-availability of the drawings and other hurdles created, it
was becoming difficult for the petitioner to plan properly for execution of
the work. The respondents failed to issue permits for outside labourers
which caused a lot of delay and consequently, works were adversely
affected. From the letters exchanged between the parties with effect from
13-02-2012 to 18-09-2012 and in particular, letters dated 26-03-2012,
06-04-2012 & 09-04-2012 of the respondents, it is evident that the
respondents admitted their failure for supplying the drawings. The
petitioner was made to appoint the same consultant by the respondents,
as it was the agreed one between the parties. The letter dated
18-09-2012 was written by the respondents to the extent of shifting the
responsibility of the petitioner relating to the preparation of drawings but
W.P. (C) No. 32 of 2020
Contd.../-
[5]
the liability to approve the same and to issue final drawings for execution
remained with them.
[3.6]
After the execution of the works having been commenced, the
changes in the specification were made by the respondents overlooking
the terms and conditions of the contract on various grounds. In this
regard, various letters dated 06-05-2013, 07-10-2013, 06-12-2013 and
01-02-2014 were written by the respondents to the petitioner calling upon
it to carry out the changes of specifications resulting in the delay and the
requirement of making more expenditure.
[3.7]
The petitioner raised bills from time to time, as the respondents
were obligated to make the payment thereof as per the terms and
conditions of the contract. However, the respondents without any
justification and without disclosing it to the petitioner, used to make
deduction from the bills and there had been inordinate delay in making
the payments which had resulted in the delay of the execution of works.
The petitioner vide its letters dated 05-08-2013 and 06-08-2013, called
upon the respondents to make arrangement of CDA for Rs.100 crores as
the petitioner would be in a position to complete the works within the said
period.
[3.8]
The occurrence of various contingencies prevented the
petitioner from executing the works which cannot be attributed to the
petitioner but the State/ respondents had the responsibility to control the
situation which it failed resulting in the failure to perform their contractual
W.P. (C) No. 32 of 2020
Contd.../-
[6]
obligations. The spiralling and cascading effect also affected the original
scope of work for various other infrastructure works, some of which were
within the original contract agreement specifically like land development
and land scapping, internal road, horticulture, boundary wall etc and
others as mentioned in the additional specifications for works adopted for
construction of civil secretariat, capital complex Imphal significantly
changed in proportion to the new catchment area. Such increase had a
significant bearing on the cost escalation of the project and the time over
run which need to be incorporated by the respondents for a fair
understanding of the project.
[3.9]
As the work could not be completed within three years, the
petitioner made the application for extension of time as provided under
the contract. The mere perusal of the contemporaneous documents and
the fact relating to the execution of the work, would make it very clear that
the petitioner did not get the opportunity to execute the works and only
the work for a value of Rs.120 crores out of Rs.280.60 crores, could be
executed during the original period. Due to the execution of extra works,
the contract value got increased to the extent of Rs.350 crores. In fact,
the petitioner had executed, by now, the works for a total value more than
Rs.260 crores which constituted about 75% of the entire work. The
petitioner was granted extension of time, from time to time, and the last
being the extension of time made upto 18-04-2017. The petitioner applied
for further extension which had not been formally granted by the
respondents but the petitioner was permitted to continue the work which
W.P. (C) No. 32 of 2020
Contd.../-
[7]
needed to be regularised by the respondents. The reason for such
extension of time was due to the failure on the part of the respondents to
perform their contractual obligations and the force majeure circumstances
like bands, blockade, ILP etc.
[3.10]
The details of the communications exchanged between the
parties for the period from 18-10-2013 to 18-04-2017 would clearly
demonstrate the true and correct facts relating to the increase in the
scope of the work including various instructions issued to the petitioner to
use specification of higher/ superior mix in order to fulfil the requirements
of the respondents in future which was never the scope of the work. In
addition thereto, there were various correspondences between the parties
with regard to electrical and electronic deviations as is evident from the
letter dated 25-06-2015 of the Chief Engineer who forwarded the estimate
for allocation of additional fund.
[3.11]
The petitioner submitted interim/ ad-hoc bills towards the
expenditure as made by the petitioner on the basis of the formula
provided in CPWD for a sum of Rs.19.5 crores. At that time, huge interest
was charged by the respondents. In case the payment would have been
made timely by the respondents, the petitioner would not have lost crores
of rupees on account of interest charged by the respondents. The
petitioner vide its letter dated 22-07-2017 submitted deviation statement
and statement of extra item along with a detailed analysis for approval for
a sum of Rs.33.58 crores and 34.81 crores respectively to the
W.P. (C) No. 32 of 2020
Contd.../-
[8]
respondents. In a meeting held between the parties, the minutes of the
meeting were prepared and one of the minutes of the meeting dated
05-07-2017 which had been termed as memo of understanding, the
petitioner had made clear endorsement that all variations, deviations and
other pending approvals should be given in the month of July, 2017 for
capital complex except CCTV camera. Although the petitioner was ready
and willing to execute the works, the respondents were not in a position
to perform their contractual obligations.
[3.12]
After the memo of understanding being signed between the
parties, the petitioner submitted work programmes for the balance work of
the civil secretariat project. The petitioner had been requesting the
respondents to take corrective steps and permit it to complete the work
without any obstruction and hindrance. But the respondents wrote various
letters mentioning incorrect facts and making allegations against the
petitioner to the effect that the petitioner had failed to perform its
contractual obligations and had abandoned the project. The petitioner
received five show cause notices for which replies had been given
making it clear that the respondents were not justified in issuing them and
the delay was not attributable to it. The allegation that the petitioner had
abandoned the project was specifically denied for the reason that
consumable materials including lifts, DG sets, panels etc. were/ are lying
at the site. In a meeting held with the Chief Secretary on 26-10-2017, the
relevant issues were pointed out to the respondents including the one
relating to release of payments. But the payment of Rs.20 crores as
W.P. (C) No. 32 of 2020
Contd.../-
[9]
assured in the meeting was not released by the respondents. The internal
correspondence between the Executive Engineer and the Chief Engineer
would demonstrate it. The further meeting was held on 28-01-2018 with
the Chief Secretary regarding the release of various payments due
payable to the petitioner regarding other contracts as well. When the
respondents failed to take appropriate steps to release the payment
towards deviated/ extra items, the petitioner wrote a letter dated
05-05-2018 followed by another letter dated 23-05-2018 addressed to the
respondents. However, the respondents started writing letters to the
effect that nothing was payable to the petitioners. The respondents
started acting contrary to the settlement and decision arrived at in the
meetings as aforesaid, followed by show cause notices including the 6th
show cause notice dated 09-08-2018, for which replies had been given by
the petitioner. On 31-08-2018, the petitioner wrote a letter to the Chief
Secretary requesting him for the release of payments. However, a news
item appeared in the local newspaper that coercive action would be taken
against the petitioner and being aggrieved by it, the petitioner filed an
arbitration petition being Art. Pet (J2) No.1 of 2018 before this Court
wherein this Court vide its order dated 08-10-2018 directed that the status
quo be maintained by the parties. During the pendency of the said
arbitration petition, a meeting was held to resolve the issue amicably
and accordingly, the respondents withdrew the termination letter dated
27-09-2018 with the condition that the work should be completed by
February, 2019 and that the performance Bank Guarantee be revalidated
W.P. (C) No. 32 of 2020
Contd.../-
[10]
on or before 06-11-2018. Thereafter, the respondent No.2 wrote a letter
dated 06-11-2018 to the petitioner to increase the manpower and to
submit a work schedule and in reply thereto, the petitioner wrote a letter
dated 11-11-2018 requesting the respondents to grant extension upto
30-06-2019 and also to comply with the terms of the MOU dated
27-10-2018 by releasing the payments and maintaining the cash flow in
the project for its timely completion. On 12-11-2018, the arbitration
petition was disposed recording the terms of the minutes of the meeting
as agreed between the parties and the withdrawal of the termination
order.
[3.13]
Since no action was taken by the respondents to perform their
contractual obligations, the petitioner wrote a letter dated 19-11-2018
followed by another letter dated 26-11-2018 requesting the respondents
to comply with MOU dated 27-10-2018. The respondent No.1 vide its
letter dated 03-12-2018 granted provisional extension. Although the
petitioner commenced the work, the respondents failed to release the
payments in favour of the petitioner. As a reminder, the petitioner wrote a
letter dated 07-12-2018 followed by a letter dated 04-01-2019 enclosing
therewith 29th RA bill for a sum of Rs.2.35 crores. The respondents vide
their letter dated 21-02-2019 forwarded a sanctioned copy of the extra
item statement for the works worth of Rs.37 crores. Even after a lapse of
more than five months, the respondents failed to act as per the MOU
dated 27-10-2018 but asked the petitioner to complete the works of three
blocks. Thereafter, the respondents vide their letter dated 28-03-2019
W.P. (C) No. 32 of 2020
Contd.../-
[11]
refused to entertain the escalation bill by referring to the terms and
conditions of the contract. A show cause notice dated 04-06-2019 was
issued alleging the apprehension that the work would not be completed
by the petitioner within the time agreed, to which a reply dated
11-06-2019 was given by the petitioner. Another show cause notice dated
18-09-2019 was issued and in the reply dated 25-09-2019, it was stated
by the petitioner that the delay was not attributable to it. In an unmindful
and unreasonable manner, another show cause notice dated 17-10-2019
was issued without adverting to the facts as communicated by the
petitioner which submitted its reply dated 25-10-2019 highlighting various
reasons causing the delay. However, the respondents, in an arbitrary
manner, terminated the contract vide its letter dated 02-11-2019
overlooking their own failure in performing their part of the contractual
obligations.
[3.14]
Thereafter, the respondents issued the NIT dated 28-12-2019
for execution of the balance and additional work arising out of the
contract, the technical bid of which was opened on 06-01-2020. Being
aggrieved by it, the instant writ petition was filed by the petitioner. On
17-01-2020 when the writ petition was listed for consideration, this Court,
while issuing notice to the respondents, granted interim relief in favour of
the petitioner to the effect that the financial bids should not be opened till
the next date, which has now been extended till the pronouncement of
the judgment and order.
W.P. (C) No. 32 of 2020
Contd.../-
[12]
[4]
The instant writ petition was contested by the respondents by
filing an affidavit-in-opposition on their behalf stating that there is no
irregularities in the NIT, as it is a self-composite one with full details of
volume and particulars of works to be executed. In the minutes of the 1st
State Level Empowered Committee, it was resolved that the petitioner
must complete the work by 28-02-2019 and moreover, in the revocation
notice, it was conveyed that the work must be completed by 28-02-2019
failing which necessary action would be taken against it. As per the terms
of the contract, the security deposit bank guarantee must be valid which
the petitioner failed to renew during the 1 year long period provided to
complete the work which is indirect breach of the terms of the contract.
The petitioner has caused unmindful delay and utter negligence on its
part resulting in below par work progress and heavy burden on the public,
the Government and the State Exchequer. Since the work remained
incomplete even after granting a whole 1 year with full cooperation, the
contract was terminated by the State Government. In the termination
notice, the schedule date for joint measurement was indicated but since
no one reported to the work agency, the measurement was carried out by
the Department. The NIT was floated with due approval from the
competent authority wherein there was no increase of work. All the
pending liabilities as per approved payment schedule have been cleared
and there is no outstanding liability. There is no question of blacklisting
the petitioner and as it failed to execute the work, the petitioner was
simply debarred from executing the balance work. In the 2 nd MOU, the
W.P. (C) No. 32 of 2020
Contd.../-
[13]
deadline for completion was indicated with the requirement for
submission of work programme. On petitioner’s failure to meet the
milestone, a show cause was served upon it. In the 3rd and 4th review
meeting of the State Level Empowered Committee, the petitioner failed to
turn up which had shown their non-seriousness to complete the work.
The petitioner failed to meet its work schedule resulting in innumerable
problems to the State Government which has adversely affected the
public, namely social as well as economic burden on the people of the
State. The various claims made by the petitioner towards delay in making
payments had shown that it became financially unsound with the result
that it could not execute the project and that even the validity of the
bank guarantee could not be renewed. The various force majeure
contingencies as contended by the petitioner, are questionable but
assuming their existence, the petitioner was given sufficient time to
complete the project.
[5]
In the rejoinder affidavit, it has been stated by the petitioner that
in the termination notice, it was stated that there would be final
measurement of work executed by the petitioner but no such
measurement was done by the respondents at any point of time. In this
regard, a letter dated 07-01-2020 was written to the respondents. Unless
and until the balance work was specified, it would not be appropriate to
say that the bid for the balance work was invited. There was no
quantification of items and the documents referring to the drawings, are
not sufficient to provide information relating to balance work and the
W.P. (C) No. 32 of 2020
Contd.../-
[14]
action was taken by the respondents to cause serious prejudice to the
rights of the petitioner. Since huge magnitude of work had been executed
by the petitioner, it is mandatory for the respondents to mention clearly
the balance work in the NIT documents. The period of one year which
has been specified in the NIT, is sufficient to indicate discriminatory
attitude of the respondent, when the petitioner prayed for six months for
completing the work. The respondents are trying to cause a serious loss
to public exchequer due to their illegal acts namely wrong estimation of
the costs. The petitioner has reiterated the averments made in the writ
petition, while denying the averments made in the counter affidavit except
those which are matter of records.
[6]
From the aforesaid pleadings, two main issues have arisen for
consideration by this Court-one, whether the letter dated 02-11-2019
issued by the Executive Engineer, Building Division No.1, PWD, Manipur
terminating the contract is legally valid and two, whether the NIT dated
28-12-2019 issued by the Executive Engineer is bad in law being violative
of the provisions of Article 14 of the Constitution of India, since it has
been issued without determination and specification of the balance work
which the petitioner has allegedly failed to complete it.
[7.1]
As regards the first issue, it has been submitted by the counsel
appearing for the petitioner that the NIT dated 18-02-2010 was issued
relating to the construction of Capital Complex (Civil Secretariat) at
Mantripukhri, Imphal. The respondents issued the letter of intent dated
W.P. (C) No. 32 of 2020
Contd.../-
[15]
05-10-2010 which was acknowledged by the petitioner vide its letter
dated 08-10-2010 and consequently, the agreement was executed on
18-10-2010 wherein the period for completion of the project was fixed up
as three years. The works could not be completed in time due to various
reasons which were not attributable to the petitioner, as is evident from
the minutes of the meeting held on 27-10-2018 and the letter dated
29-10-2018 which are on record. As the time was not the essence of
contract, the period for completion of the project was extended from time
to time. The non-completion of the project in time was due to patent and
illegal actions inviting tender prejudicial to the rights of the petitioner after
the contract being terminated on 02-11-2019 in a malafide manner. There
is no clause in the agreement conferring authority upon the respondents
to terminate the contract. The contract was terminated without
considering the averments made in the replies to the show cause notices
resulting in the violation of the principles of natural justice. The actions of
the respondents were unreasonable which have led to the violation of
Article 14 and 19 of the Constitution of India. In support of his contention,
he has relied upon the decision rendered by the Hon’ble Supreme Court
in Re: Special Reference No.1 of 2012, (2012) 10 SCC 1 which has
approved the law laid down in Srilekha Vidyarthi Vs. State of UP &,
(1991) 1 SCC 212. On the other hand, it has been submitted by the
learned Advocate General that the petitioner was unable to complete the
work in time. The time was extended on several occasions but the
petitioner failed to complete the work even after 7th extension of time
W.P. (C) No. 32 of 2020
Contd.../-
[16]
being granted which remained valid upto 18-04-2017. The respondents
had no option but to terminate the contract. In an arbitration petition, this
Court passed an interim order granting status quo. In order to resolve the
issue amicably, a meeting was held on 27-10-2018 wherein it was agreed
for early completion of the work and the termination of contract was
withdrawn by the respondents. But the petitioner failed to complete the
work till October, 2019, because of which the contract was terminated
after due notice being given to the petitioner. It has further been
submitted by him that there is no ground for challenging the termination of
contract as well as the NIT for the reason that it is the petitioner who has
failed to complete the work even in nine years from the date of signing
the agreement. The replies given by the petitioner to the show cause
notices were unsatisfactory and therefore, the contract was terminated so
that the completion of the work could be entrusted to another contractor.
Relying upon some of the decisions of the Hon’ble Supreme Court, it has
been submitted by him that since the disputed question of facts has
arisen in the matter, the same cannot be decided by this Court in exercise
of its power conferred under Article 226 of the Constitution of India.
[7.2]
A contract is nothing but an understanding arrived at between the
parties who are competent to execute it under the provisions of the India
Contract Act, 1872. Section 37 of the Contract Act provides that the
parties to a contract must perform or offer to perform their respective
promises, unless such performance is dispensed with or excused under
the provisions of the Act or any other law. In other words, both the parties
W.P. (C) No. 32 of 2020
Contd.../-
[17]
are bound to perform their contractual obligations as per the terms and
conditions agreed upon between them. If either of the parties fails to
perform its contractual obligations or has breached the contract, it is open
to the other party to terminate the contract. In other words, a contract can
be terminated and once it is terminated, its consequences ought to follow.
Section 73 of the Contract Act provides for the consequences of the
breach of the contract and it provides that when a contract has been
broken, the party who suffers by such breach is entitled to receive
compensation for any loss or damage caused to him. In the present case,
Clause 3 of the contract empowers the Engineer-in-charge to determine
the contract in any of the cases mentioned therein. The validity and
correctness of the termination of contract can be agitated before the
appropriate forum as provided in the agreement or before the civil court
for passing appropriate order. While resolving the issue by the
appropriate forum, if one of the parties is found to have breached the
contract, the other party is entitled to receive compensation for any loss
or damage caused to him. On perusal of the rival contentions as
aforesaid and the materials on record, this Court is of the view that the
contention of the learned Advocate General that the disputed questions of
facts cannot be decided by this Court in exercise of its power under
Article 226 of the Constitution of India, has substance and merit. Such
question shall be left to be decided by the appropriate forum. In the
present case, the documents are voluminous and the technical expertise
would be needed to decide the disputed question of facts. At the same
W.P. (C) No. 32 of 2020
Contd.../-
[18]
time, this Court is not equipped with the technical knowledge and
expertise for doing the needful. Moreover, there is a clause in the
agreement to the effect that in the event of any dispute being arisen out
of the contract between the parties, the same can be referred to
arbitration. In other words, since the contract has been terminated by the
respondents, it is open to the petitioner to invoke the arbitration clause in
the manner as provided therein. This Court has expressed no opinion as
regards the validity and correctness of the termination of the contract.
[8.1]
So far as the second issue is concerned, it may be noted that
the validity and correctness of the NIT is being questioned by the
petitioner on the ground of malafide and unreasonable. Before considering
this issue, this Court deems it appropriate to re-visit the principles laid
down by the Hon’ble Supreme Court in matters relating to award of
contract. In Tata Cellular Vs. Union of India, (1994) 6 SCC 651
wherein two main issues-one, relating to the scope of judicial review and
two, relating to selection being vitiated by arbitrariness, which are
relevant for the cases also, were considered and decided by the Hon‟ble
Supreme Court. In matters relating to contracts wherein one of the
parties is the public authority, the question to be asked is, have the
guidelines been laid down, if so laid down, have they been observed?
The Hon‟ble Supreme Court, after referring to its earlier decisions,
summarised the principles which are the broad grounds subject to
addition of further grounds in course of time. The Hon‟ble Supreme
Court held:
W.P. (C) No. 32 of 2020
Contd.../-
[19]
“69. A tender is an offer. It is something which invites and is
communicated to notify acceptance. Broadly stated, the
following are the requisites of a valid tender:
1. It must be unconditional.
2. Must be made at the proper place.
3. Must conform to the terms of obligation.
4. Must be made at the proper time.
5. Must be made in the proper form.
6. The person by whom the tender is made must be able and
willing to perform his obligations.
7. There must be reasonable opportunity for inspection.
8. Tender must be made to the proper person.
9. It must be of full amount.
70. It cannot be denied that the principles of judicial review
would apply to the exercise of contractual powers by
Government bodies in order to prevent arbitrariness or
favouritism. However, it must be clearly stated that there are
inherent limitations in exercise of that power of judicial review.
Government is the guardian of the finances of the State. It is
expected to protect the financial interest of the State. The right
to refuse the lowest or any other tender is always available to
the Government. But, the principles laid down in Article 14 of
the Constitution have to be kept in view while accepting or
refusing a tender. There can be no question of infringement of
Article 14 if the Government tries to get the best person or the
best quotation. The right to choose cannot be considered to be
an arbitrary power. Of course, if the said power is exercised
for any collateral purpose, the exercise of that power will be
struck down.
71. Judicial quest in administrative matters has been to find the
right balance between the administrative discretion to decide
matters whether contractual or political in nature or issues of
social policy; thus they are not essentially justiciable and the
need to remedy any unfairness. Such an unfairness is set
W.P. (C) No. 32 of 2020
Contd.../-
[20]
right by judicial review.
88. We may now look at some of the pronouncements of this
Court including the authorities cited by Mr Ashoke Sen. Fasih
Chaudhary v. Director General, Doordarshan was a case in
which the Court was concerned with the award of a contract
for show of sponsored TV serial. At p. 92 in paragraphs 5 and
6 it was held thus:
“ It is well settled that there should be fair play in action in a
situation like the present one, as was observed by this Court
in Ram & Shyam Co. v. State of Haryana. It is also well
settled that the authorities like Doordarshan should act fairly
and their action should be legitimate and fair and
transaction should be without any aversion, malice or
affection. Nothing should be done which gives the
impression of favouritism or nepotism. See the observations
of this Court in Haji T.M. Hassan Rawther v. Kerala
Financial Corpn. While, as mentioned hereinbefore, fair play
in action in matters like the present one is an essential
requirement, similarly, however, “free play in the joints‟ is
also a necessary concomitant for an administrative
body functioning in an administrative sphere or quasi
administrative sphere as the present one. Judged from that
standpoint of view, though all the proposals might not have
been considered strictly in accordance with order of
precedence, it appears that these were considered fairly,
reasonably, objectively and without any malice or ill-will.”
94. The principles deducible from the above are:
(1) The modern trend points to judicial restraint in administrative
action.
(2) The court does not sit as a court of appeal but merely
reviews the manner in which the decision was made.
(3) The court does not have the expertise to correct the
administrative decision. If a review of the administrative
decision is permitted, it will be substituting its own decision,
without the necessary expertise which itself may be fallible.
W.P. (C) No. 32 of 2020
Contd.../-
[21]
(4) The terms of the invitation to tender cannot be open to
judicial scrutiny because the invitation to tender is in the
realm of contract. Normally speaking, the decision to accept
the tender or award the contract is reached by process of
negotiations through several tiers. More often than not,
such decisions are made qualitatively by experts.
(5) The Government must have freedom of contract. In other
words, a fair play in the joints is a necessary concomitant
for an administrative body functioning in an administrative
sphere or quasi-administrative sphere. However, the
decision must not only be tested by the application of
Wednesbury principle of reasonableness (including its other
facts pointed out above) but must be free from arbitrariness
not affected by bias or actuated by mala fides.
(6) Quashing decisions may impose heavy administrative
burden on the administration and lead to increased and
unbudgeted expenditure”.
In Air India Ltd. Vs. Cochin International Airport Ltd. &
ors., reported in (2000) 2 SCC 617 wherein it has been held that the law
relating to award of a contract has been settled by the Hon‟ble Supreme
Court, the relevant para 7 of which is as under:
“7. The law relating to award of a contract by the State, its
corporations and bodies acting as instrumentalities and
agencies of the Government has been settled by the decision
of this Court in Ramana Dayaram Shetty v. International Airport
Authority of India, Fertilizer Corpn. Kamgar Union (Regd.) v.
Union of India, CCE v. Dunlop India Ltd., Tata Cellular v. Union
of India, Ramniklal N. Bhutta v. State of Maharashtra and
Raunaq International Ltd. v. I.V.R. Construction Ltd. The award
of a contract, whether it is by a private party or by a public
body or the State, is essentially a commercial transaction. In
W.P. (C) No. 32 of 2020
Contd.../-
[22]
arriving at a commercial decision considerations which are
paramount are commercial considerations. The State can
choose its own method to arrive at a decision. It can fix its own
terms of invitation to tender and that is not open to judicial
scrutiny. It can enter into negotiations before finally deciding to
accept one of the offers made to it. Price need not always be
the sole criterion for awarding a contract. It is free to grant any
relaxation, for bona fide reasons, if the tender conditions
permit such a relaxation. It may not accept the offer even
though it happens to be the highest or the lowest. But the State,
its corporations, instrumentalities and agencies are bound to
adhere to the norms, standards and procedures laid down by
them and cannot depart from them arbitrarily. Though that
decision is not amenable to judicial review, the court can
examine the decision-making process and interfere if it is found
vitiated by mala fides, unreasonableness and arbitrariness. The
State, its corporations, instrumentalities and agencies have the
public duty to be fair to all concerned. Even when some defect
is found in the decision-making process the court must exercise
its discretionary power under Article 226 with great caution
and should exercise it only in furtherance of public interest
and not merely on the making out of a legal point. The court
should always keep the larger public interest in mind in order to
decide whether its intervention is called for or not. Only when it
comes to a conclusion that overwhelming public interest
requires interference, the court should intervene.”
In Jagdish Mandal Vs. State of Orissa, reported in (2007)
14 SCC 517, the decision in Tata Cellular case (supra) was referred
to and relied upon with the following observations:
“This Court also noted that there are inherent limitations in the
W.P. (C) No. 32 of 2020
Contd.../-
[23]
exercise of power of judicial review of contractual powers.
This Court also observed that the duty to act fairly will vary in
extent, depending upon the nature of cases, to which the said
principle is sought to be applied. This Court held that the
State has the right to refuse the lowest or any other tender,
provided it tries to get the best person or the best quotation,
and the power to choose is not exercised for any collateral
purpose or in infringement of Article 14.”
In Maa Binda Express Carrier Vs. North-East Frontier
Railway, reported in (2014) 3 SCC 760, the Hon‟ble Supreme Court has
held that the submission of tender is no more than making an offer
which the State or its agencies are under no obligation to accept and the
bidders in the tender cannot insist that their tenders should be accepted
simply because a given tender is the highest or the lowest. It has
further been held that the only enforceable right that a bidder has, is to
examine by the court whether the aggrieved party has been treated
unfairly or discriminated against to the detriment of the public interest. In
Rishi Kiran Logistics Private Ltd. Vs. Board of Trustees of Kandla
Port Trust & anr., reported in (2015) 13 SCC 233, the decision of the
Hon‟ble Supreme Court in Tata Cellular Case (supra), has been
followed with the observation that a lucid enunciation on the scope of
judicial review of administrative action, that too in tender matters can be
found therein.
[8.2]
From the aforesaid decisions of the Hon’ble Supreme Court, it
is seen that the law, as regards the matters relating to award of
W.P. (C) No. 32 of 2020
Contd.../-
[24]
contracts involving a public authority, is no longer res integra. There is
no need of multiplying the decisions rendered by the Hon‟ble Supreme
Court in this regard and suffice it to say that the court’s power of judicial
review of administrative action is limited to the extent indicated in the
decisions mentioned hereinabove. But an exception has been carved
out that though a decision relating to matter of contract is not amenable
to judicial review, the court can examine the decision-making process
and interfere if it is found vitiated by malafides, unreasonableness and
arbitrariness. The principles of judicial review would apply to the
exercise of contractual powers by the Government bodies in order to
prevent arbitrariness or favouritism. In other words, the principles laid
down in Article 14 of the Constitution have to be kept in view while
accepting or refusing a tender. Article 14 of the Constitution being
anathema to any malafide, unreasonable and arbitrary action of the
Government or its instrumentalists, strikes at their roots.
[8.3]
It has been submitted by Shri S.D. Singh, learned counsel
appearing for the petitioner that while terminating the contract, it has been
stated that final measurement of the work executed by the petitioner
would be done but it was not done at all leading to illegality, arbitrariness
and prejudicial to the rights of the petitioner. The invitation of the tender
without final measurement is a malafide action. In other words, without
the balance work being ascertained and determined, the invitation of
tender is untenable and completely bad in law liable to be quashed and
set aside. In support of his contention, he has relied upon the decision
W.P. (C) No. 32 of 2020
Contd.../-
[25]
rendered by the Hon’ble Supreme Court in Mahabir Auto Stores & ors
Vs. Indian Oil Corporation & ors., (1990) 3 SCC 752 and Special
Reference No.1 of 2012, (2012) 10 SCC 1. Combating his contention
and relying upon the decisions rendered by the Hon’ble Supreme in
Michigan Rubber (India) Ltd. Vs. State of Karnataka, (2012) 8 SCC
216; Montecarlo Ltd Vs. National Thermal Power Corporation Ltd.,
(2016) 15 SCC 272; Afcons Infrastructure Ltd Vs. Nagpur Metro Rail
Corp. Ltd. & anr, (2016) 16 SCC 818 and JSW Infrastructure Ltd Vs.
Kakinada Seaports Ltd. & ors, (2017) 4 SCC 170, it has been submitted
by the learned Advocate General that there is no ground to challenge the
terms and conditions of the NIT.
[8.4]
In
Mahabir
Auto
Stores
case
(supra)
wherein
the
discontinuation of the supply of lubricants by the IOC without giving any
intimation to the appellant was challenged on the ground of arbitrariness,
the Hon’ble Supreme Court held:
“12. It is well settled that every action of the State or an
instrumentality of the State in exercise of its executive power,
must be informed by reason. In appropriate cases, actions
uninformed by reason may be questioned as arbitrary in
proceedings under Article 226 or Article 32 of the Constitution.
Reliance in this connection may be placed on the observations
of this Court in Radha Krishna Agarwal v. State of Bihar. It
appears to us, at the outset, that in the facts and circumstances
of the case, the respondent company IOC is an organ of the
State or an instrumentality of the State as contemplated under
Article 12 of the Constitution. The State acts in its executive
power under Article 298 of the Constitution in entering or not
entering in contracts with individual parties. Article 14 of the
W.P. (C) No. 32 of 2020
Contd.../-
[26]
Constitution would be applicable to those exercises of power.
Therefore, the action of State organ under Article 14 can be
checked. See Radha Krishna Agarwal v. State of Bihar at p.
462, but Article 14 of the Constitution cannot and has not been
construed as a charter for judicial review of State action after
the contract has been entered into, to call upon the State to
account for its actions in its manifold activities by stating
reasons for such actions. In a situation of this nature certain
activities of the respondent company which constituted State
under Article 12 of the Constitution may be in certain
circumstances subject to Article 14 of the Constitution in
entering or not entering into contracts and must be reasonable
and taken only upon lawful and relevant consideration; it
depends upon facts and circumstances of a particular
transaction whether hearing is necessary and reasons have to
be stated. In case any right conferred on the citizens which is
sought to be interfered, such action is subject to Article 14 of
the Constitution, and must be reasonable and can be taken only
upon lawful and relevant grounds of public interest. Where
there is arbitrariness in State action of this type of entering or
not entering into contracts, Article 14 springs up and judicial
review strikes such an action down. Every action of the State
executive authority must be subject to rule of law and must be
informed by reason. So, whatever be the activity of the public
authority, in such monopoly or semi-monopoly dealings, it
should meet the test of Article 14 of the Constitution. If a
governmental action even in the matters of entering or not
entering into contracts, fails to satisfy the test of
reasonableness, the same would be unreasonable. In this
connection reference may be made to E.P. Royappa v. State of
Tamil Nadu, Maneka Gandhi v. Union of India, Ajay Hasia v.
Khalid Mujib Sehravardi, R.D. Shetty v. International Airport
Authority of India and also Dwarkadas Marfatia and Sons v.
Board of Trustees of the Port of Bombay. It appears to us that
rule of reason and rule against arbitrariness and discrimination,
rules of fair play and natural justice are part of the rule of law
applicable in situation or action by State instrumentality in
W.P. (C) No. 32 of 2020
Contd.../-
[27]
dealing with citizens in a situation like the present one. Even
though the rights of the citizens are in the nature of contractual
rights, the manner, the method and motive of a decision of
entering or not entering into a contract, are subject to judicial
review on the touchstone of relevance and reasonableness, fair
play, natural justice, equality and non-discrimination in the type
of the transactions and nature of the dealing as in the present
case.
20. Having regard to the nature of the transaction, we are of the
opinion that it would be appropriate to state that in cases where
the instrumentality of the state enters the contractual field, it
should be governed by the incidence of the contract. It is true
that it may not be necessary to give reasons but, in our opinion,
in the field of this nature fairness must be there to the parties
concerned, and having regard to the large number or the long
period and the nature of the dealings between the parties, the
appellant should have been taken into confidence. Equality and
fairness at least demands this much from an instrumentality of
the State dealing with a right of the State not to treat the
contract as subsisting. We must, however, evolve such process
which will work.”
In Srilekha Vidyarthi case (supra), the question was as to
whether the circular was amenable to judicial review and if so, is it liable
to be quashed as violative of Article 14 of the Constitution of India, being
arbitrary? The Hon’ble Supreme Court held:
“24. The State cannot be attributed the split personality of Dr Jekyll
and Mr Hyde in the contractual field so as to impress on it all
the characteristics of the State at the threshold while making a
contract requiring it to fulfill the obligation of Article 14 of the
Constitution and thereafter permitting it to cast off its garb of
State to adorn the new robe of a private body during the
subsistence of the contract enabling it to act arbitrarily subject
only to the contractual obligations and remedies flowing from it.
W.P. (C) No. 32 of 2020
Contd.../-
[28]
It is really the nature of its personality as State which is
significant and must characterize all its actions, in whatever
field, and not the nature of function, contractual or otherwise,
which is decisive of the nature of scrutiny permitted for
examining the validity of its act. The requirement of Article 14
being the duty to act fairly, justly and reasonably, there is
nothing which militates against the concept of requiring the
State always to so act, even in contractual matters. There is a
basic difference between the acts of the State which must
invariably be in public interest and those of a private individual,
engaged in similar activities, being primarily for personal gain,
which may or may not promote public interest. Viewed in this
manner, in which we find no conceptual difficulty or
anachronism, we find no reason why the requirement of Article
14 should not extend even in the sphere of contractual matters
for regulating the conduct of the State activity.
In Natural Resources Allocation Case (Spl. Reference No.1
of 2012) (supra), the Hon’ble Supreme Court, after referring to its earlier
decisions on the issue relating to the doctrine of arbitrariness towards
nature of equality, examined the provisions of Article 14 of the
Constitution of India, held:
“107. From a scrutiny of the trend of decisions it is clearly perceivable
that the action of the State, whether it relates to distribution of
largesse, grant of contracts or allotment of land, is to be tested
on the touchstone of Article 14 of the Constitution. A law may
not be struck down for being arbitrary without the pointing
out of a constitutional infirmity as McDowell case has said.
Therefore, a State action has to be tested for constitutional
infirmities qua Article 14 of the Constitution. The action has to
be fair, reasonable, non-discriminatory, transparent, noncapricious, unbiased, without favouritism or nepotism, in pursuit
of promotion of healthy competition and equitable treatment. It
should conform to the norms which are rational, informed with
W.P. (C) No. 32 of 2020
Contd.../-
[29]
reasons and guided by public interest, etc. All these principles
are inherent in the fundamental conception of Article 14. This is
the mandate of Article 14 of the Constitution of India.
Whether “auction” a constitutional mandate.”
In Michigan Rubber case (supra) wherein the Karnataka State
Road Transport Corporation floated a tender for supply of tyres, tubes
and flaps specifying certain pre-qualification criteria which came to be
challenged and thereafter, the pre-qualification criteria were modified.
The said pre-qualification criteria were challenged in the High Court which
dismissed it. When the matter was carried to the Hon’ble Supreme Court,
it laid down the principles. Paragraph 23 and 35 read as under:
“23. From the above decisions, the following principles emerge:
(a) The basic requirement of Article 14 is fairness in action by
the State, and non-arbitrariness in essence and substance is
the heartbeat of fair play. These actions are amenable to the
judicial review only to the extent that the State must act
validly for a discernible reason and not whimsically for any
ulterior purpose. If the State acts within the bounds of
reasonableness, it would be legitimate to take into
consideration the national priorities;
(b) Fixation of a value of the tender is entirely within the purview
of the executive and the courts hardly have any role to play
in this process except for striking down such action of the
executive as is proved to be arbitrary or unreasonable. If the
Government acts in conformity with certain healthy
standards and norms such as awarding of contracts by
inviting tenders, in those circumstances, the interference by
courts is very limited;
(c) In the matter of formulating conditions of a tender document
and awarding a contract, greater latitude is required to be
conceded to the State authorities unless the action of the
W.P. (C) No. 32 of 2020
Contd.../-
[30]
tendering authority is found to be malicious and a misuse of
its statutory powers, interference by courts is not warranted;
(d) Certain preconditions or qualifications for tenders have to be
laid down to ensure that the contractor has the capacity and
the resources to successfully execute the work; and
(e) If the State or its instrumentalities act reasonably, fairly and
in public interest in awarding contract, here again,
interference by court is very restrictive since no person can
claim a fundamental right to carry on business with the
Government.
35. As observed earlier, the Court would not normally interfere with
the policy decision and in matters challenging the award of
contract by the State or public authorities. In view of the above,
the appellant has failed to establish that the same was contrary
to public interest and beyond the pale of discrimination or
unreasonable. We are satisfied that to have the best of the
equipment for the vehicles, which ply on road carrying
passengers, the 2nd respondent thought it fit that the criteria for
applying for tender for procuring tyres should be at a high
standard and thought it fit that only those manufacturers who
satisfy the eligibility criteria should be permitted to participate in
the tender. As noted in various decisions, the Government and
their undertakings must have a free hand in setting terms of the
tender and only if it is arbitrary, discriminatory, mala fide or
actuated by bias, the courts would interfere. The courts cannot
interfere with the terms of the tender prescribed by the
Government because it feels that some other terms in the
tender would have been fair, wiser or logical. In the case on
hand, we have already noted that taking into account various
aspects including the safety of the passengers and public
interest, CMG consisting of experienced persons, revised the
tender conditions. We are satisfied that the said Committee had
discussed the subject in detail and for specifying these two
conditions regarding pre-qualification criteria and the evaluation
criteria. On perusal of all the materials, we are satisfied that the
W.P. (C) No. 32 of 2020
Contd.../-
[31]
impugned conditions do not, in any way, could be classified as
arbitrary, discriminatory or mala fide.
In Afcons Infrastructure Ltd case (supra), the Hon’ble
Supreme Court held:
“15. We may add that the owner or the employer of a project, having
authored the tender documents, is the best person to
understand and appreciate its requirements and interpret its
documents. The constitutional courts must defer to this
understanding and appreciation of the tender documents,
unless there is mala fide or perversity in the understanding or
appreciation or in the application of the terms of the tender
conditions. It is possible that the owner or employer of a project
may give an interpretation to the tender documents that is not
acceptable to the constitutional courts but that by itself is not a
reason for interfering with the interpretation given.”
In Montecarlo Limited case (supra) wherein the issue was as
to whether the appellant meets the qualification criteria as provided under
the heading echnical criteria that occurs in clauses 7.1 and 7.2 of QR.
Referring to it earlier decisions including that of Afcons Infrastructure
limited, the Hon’ble Supreme Court held:
“26. We respectfully concur with the aforesaid statement of law. We
have reasons to do so. In the present scenario, tenders are
floated and offers are invited for highly complex technical
subjects. It requires understanding and appreciation of the
nature of work and the purpose it is going to serve. It is
common knowledge in the competitive commercial field that
technical bids pursuant to the notice inviting tenders are
scrutinised by the technical experts and sometimes third-party
assistance from those unconnected with the owner’s
organisation is taken. This ensures objectivity. Bidder’s
expertise and technical capability and capacity must be
assessed
by
W.P. (C) No. 32 of 2020
the
experts.
In
the
matters
of
financial
Contd.../-
[32]
assessment, consultants are appointed. It is because to check
and ascertain that technical ability and the financial feasibility
have sanguinity and are workable and realistic. There is a multiprong complex approach; highly technical in nature. The
tenders where public largesse is put to auction stand on a
different compartment. Tender with which we are concerned, is
not comparable to any scheme for allotment. This arena which
we have referred requires technical expertise. Parameters
applied are different. Its aim is to achieve high degree of
perfection in execution and adherence to the time schedule.
But, that does not mean, these tenders will escape scrutiny of
judicial review. Exercise of power of judicial review would be
called for if the approach is arbitrary or mala fide or procedure
adopted is meant to favour one. The decision-making process
should clearly show that the said maladies are kept at bay. But
where a decision is taken that is manifestly in consonance with
the language of the tender document or subserves the purpose
for which the tender is floated, the court should follow the
principle of restraint. Technical evaluation or comparison by the
court would be impermissible. The principle that is applied to
scan and understand an ordinary instrument relatable to
contract in other spheres has to be treated differently than
interpreting and appreciating tender documents relating to
technical works and projects requiring special skills. The owner
should be allowed to carry out the purpose and there has to be
allowance of free play in the joints.”
There is no or can be no any dispute between the parties as
regards the principles laid down by the Hon’ble Supreme Court in the
above decisions but on perusal thereof, it is seen that they are not
different from that of the law laid down in Tata Cellular case which was
followed in some of the subsequent decisions as mentioned in the
preceding para. Moreover, the decision rendered by the Hon’ble Supreme
W.P. (C) No. 32 of 2020
Contd.../-
[33]
Court in Tata cellular case has been referred to and relied upon in
Montecarlo Limited and Afcons Infrastructure Limited cases.
[8.5]
In the present case, the NIT impugned herein, is not the one in
respect of a new project, the execution of which has to commence from
the very beginning but it is the one issued in respect of the balance work
which remains allegedly incomplete after a major portion of the work
being executed by the petitioner. Therefore, what is the balance work,
needs to be understood by both the parties. The work for which the
agreement was signed between the parties is the construction of Capital
Complex (Civil Secretariat) at Mantripukhri. It is not in dispute that
although a major portion of the work has been completed, the work
remains incomplete even after a lapse of more than nine years.
According to the petitioner, the reasons for non-completion of the work
cannot be attributed to it because the respondents have failed to perform
their contractual obligations and in particular, the release of amounts. On
the other hand, according to the respondents, it is the petitioner which
has failed to execute the work in time, when the work was to be
completed in three years from the date of execution of the agreement. In
the termination letter, it has been stated that a joint measurement of the
balance work be held on 08-11-2019, failing which the measurement shall
be done by the respondents. According to the petitioner, no measurement
has been conducted at all, for which it has relied upon its letter dated
07-01-2020 addressed to the Executive Engineer wherein it has been
stated that no staff members of the PWD came for any such inspection
W.P. (C) No. 32 of 2020
Contd.../-
[34]
on the stipulated date. The stand of the respondents, is that since no one
from the petitioner appeared on the said date, the measurement was
done by the respondents. But no material has been brought on record by
the respondents to show the factum of measurement of the balance work
for the reason that it has not disclosed as to when the measurement was
held and who did it. What is the report of the officials who have conducted
the measurement and their finding as regards the major portion of the
work being completed and the balance work which remains incomplete.
Since the State Government being an institution, its stand or for that
matter, the averment made in the affidavit shall be based on documents
maintained by it and the mere saying that it was measured by it, is not
enough. In the absence of such materials or documents, its stand cannot
be countenanced by this Court. The State Government appears to have
taken a decision for issuing the said NIT in respect of the balance work
based on the information available only in its file which is unfair and
unreasonable. The determination of the exact balance work at the site is
a must and it is very much important and crucial which will have a bearing
on the issue relating to the validity and correctness of the termination of
the contract and its consequence as regards the computation of the
quantum of compensation/ damages. Therefore, the issuance of the NIT
in respect of the alleged balance work is unreasonable and illegal, on the
basis of which the instant writ petition can be disposed of setting aside
the NIT.
W.P. (C) No. 32 of 2020
Contd.../-
[35]
[9.1]
There are other ancillary issues-one, relating to the validity and
correctness of Clause 1.2.5 of the contract and two, the averment made
in the termination letter dated 02-11-2019 stating that the petitioner is not
allowed to participate in the process of tender in respect of the balance
work. The first issue relates to Clause 1.2.5 as contained in the bidding
documents to the effect that the contractor/ firm who has been earlier
disqualified/ blacklisted/ works terminated by the Central Government or
the State Government on any of the grounds mentioned therein, shall be
barred from bidding for the work which, in fact, need not be decided by
this Court in view of the observations made by this Court in the preceding
para. However, since the submissions have been made by the counsels
appearing for the parties with respect to the said issue, this Court
proposes to consider it. The clause 1.2.5 reads as under:
“1.2.5: The contractor/ Firm who had been earlier disqualified/
blacklisted/ works terminated by any Central Government/ State
Government Agencies because of fraudulent practice/ poor/
unprofessional like performance etc., shall be barred from
bidding for the work.”
On perusal of the said clause, it is absolutely clear that it is not
intended to apply to the petitioner only. It is a general clause applicable to
all bidders. It is nowhere mentioned therein that it would apply to the
petitioner only and therefore, there is nothing wrong incorporating it in the
tender documents. On top of that, it may be noted that the Hon’ble
Supreme Court, in a catena of decisions, has held that in matter relating
to formulating conditions of a tender document and awarding a contract,
W.P. (C) No. 32 of 2020
Contd.../-
[36]
greater latitude is required to be given to the State authorities. In other
words, it is the State authorities which have to be given greater latitude to
take decision relating to the terms and conditions to be incorporated in
the contract.
[9.2]
The second ancillary issue relates to the averment made in the
termination letter dated 02-11-2019 that the petitioner is not allowed to
participate in the process of tender in respect of the balance work. The
idea behind it appears to be that since the petitioner has failed to
complete the work in nine years, it need not be given further opportunity
to do the needful. A dispute has admittedly arisen between the parties but
in any case, the fact remains that the contract has been terminated by the
respondents and until and unless it is declared bad in law by an
appropriate forum, it will remain in operation and therefore, this Court is of
the view that there is nothing wrong in it. The decision of the respondents
appears to have been taken on that basis only. It does not amount to
blacklisting for which certain procedure is to be followed by the
respondents and it is a decision taken by the State Government in the
present case only in view of the peculiar facts and circumstances. The
petitioner cannot claim as of right to continue business with the State
Government, when the State Government is not satisfied with its
performance. If the petitioner is of the view that the decision of the State
Government in terminating the contract is incorrect, unfair and
unreasonable, it is open to seek redressal of its grievances as provided
under the contract including the claim for compensation or damage.
W.P. (C) No. 32 of 2020
Contd.../-
[37]
[10]
For the reasons stated hereinabove, the instant writ petition is
allowed in part and the NIT dated 28-12-2019 (date wrongly typed as 2801-2019) is quashed and set aside with the following directions;
(a) The respondents and in particular, the respondent No.3, shall
carry out the measurement of the balance work of the project
called “Construction of Capital Complex (Civil Secretariat
Component)
at
Mantripukhri,
Imphal”
which
remains
incomplete at the site within a week from the date of receipt of a
copy of this judgment and order;
(b) The respondents shall inform the petitioner, in advance, about
the date and time on which the measurement of the balance
work will be commenced;
(c) The petitioner shall extend full co-operation to the respondents
in the measurement of the balance work and in the event of the
full co-operation not being extended by the petitioner without
any cogent reason, the respondents are at liberty to proceed
with the measurement of the balance work in the absence of
the petitioner;
(d) After the measurement of the balance work being carried out by
the respondents in the manner as stated above, the petitioner
shall remove all its belongings including the machineries,
consumable items etc. within a period of fifteen days from the
date of completion of the measurement of the balance work and
W.P. (C) No. 32 of 2020
Contd.../-
[38]
shall not disturb the balance work being undertaken by any
person duly appointed by the respondents;
(e) After the measurement of the balance work being ascertained
and determined by the respondents, it is open to them to issue
a fresh NIT in respect of the balance work so ascertained and
determined;
(f)
Keeping in mind the importance and the requirement of the
secretariat building in the interest of the general public, an
endeavour shall be made by the respondents to ensure that the
balance work is completed with a reasonable time.
JUDGE
FR/NFR
Dhakeshori
WAIKHOM
TONEN MEITEI
WAIKHOM TONEN MEITEI
Date: 2020.03.06 13:22:00
+05'30'
W.P. (C) No. 32 of 2020
Contd.../-
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review