Judgments
LegalFirms.in Judgments · legalfirms.in/judgments/m-s-ratnagiri-impex-pvt-ltd-vs-joydeep-roy-barman-and-ors-20180706/ · Printed 28 Nov 2026
Civil

M/S Ratnagiri Impex Pvt. Ltd vs Joydeep Roy Barman and Ors

Add to a compilation

Keep judgments in folders, mark the paragraphs you rely on, and print a compilation with an index. It comes with the Research and Advocate Pro judgment plans and with a campus licence. Sign in · See the plans

Court
Tripura High Court
Date
6 July 2018
Case No.
CRP 90/2017
Result
Dismissed
Bench
S. Talapatra
Cite this judgment
Citation
Link for your website or blog
Cite the court's own record or the law report in court filings.

The court's order

The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.

22. Having taken note of the fact and circumstances as narrated in the impugned order and as available in the records, this court is not inclined to set aside the impugned order and accordingly this petition stands dismissed. There shall be no order as to costs. Moumita

Filed under

Code of Civil Procedure, 1908 Order VIII Rule 1, Code of Civil Procedure, 1908

The law this judgment cites

Opens the section on Law Maker (lawmaker.in), our sister site for law students.

Full Judgment Text

Text read from the judgment PDF published on the High Court's eCourts portal, through the Indian High Court Judgments open data set (Dattam Labs, CC BY 4.0). The court's own copy is the authoritative text.

HIGH COURT OF TRIPURA AGARTALA CRP No.90 of 2017 M/s. Ratnagiri Impex Pvt. Ltd., a company registered under the provisions of the Companies Act, 1956, having its registered office at “Annapurna House”, 1/G, Seventh Cross, Guddadahalli, Mysuru Road, Bangaluru- 560 026, represented by its Director [Shri Chandra Mohan S.A.] ----Petitioner(s) Versus 1. Shri Joydeep Roy Barman, son of Shri Samir Ranjan Barman, carrying on the business as the sole proprietor under name and style of “M/s. J. Deep Chemicals & Fertilizers, No.38, Akhaura Road, P.O. Agartala, District: West Tripura 2. Shri Dipam Bora also known as Dipam Jyoti Bora, carrying on business under name and style of M/s. Aditya Oil Engines, as the sole proprietor thereof having its office at Plot 4A, Neel Kamal Apartments, near SBI, Kahilipara Road, Guwahati – 781 006 3. * 4. * 5. Shri Pravin Baruah, carrying-on business under name and style of “PS Enterprise”, having its office at 4A, Neel Kamal Apartments, near SBI, Kahilipara Road, Guwahati – 781 006 ----Respondent(s) *As per Hon’ble Courts order dated 18.05.2018, passed in IA No.1 of 2018, the names of respondents No.3 & 4 has been deleted from the array of the parties. For Appellant(s) : Mr. T. K. Deb, Adv. For Respondent(s) : Mr. S. M. Chakraborty, Sr. Adv. Whether fit for Reporting : YES/NO HON’BLE MR. JUSTICE S. TALAPATRA Judgment & Order 06/07/2018 Heard Mr. T. K. Deb, learned counsel appearing for the petitioner as well as Mr. S. M. Chakraborty, learned senior counsel appearing for the respondent No.1. Despite notice none appears for the respondent No.2. It has been stated by Mr. Deb, learned counsel appearing for the petitioner that even the notice has been issued by the substituted service on publication of the same in the newspaper which has adequate circulation in the place where the respondent No.2 was last reported to have resided. 02. By means of this petition, the petitioner has challenged the order dated 01.08.2017 delivered in M.S. 27 of 2014 by the Civil Judge, Senior Division, Court No.4, West Tripura, Agartala. In order to appreciate the challenge, it will be apposite to lay the essential fact at the outset. The respondent No.1 instituted a suit being Money Suit No.27 of 2014 in the court of the Civil Judge, Senior Division, Court No.4, West Tripura, Agartala for realization of a sum of Rs.2,34,81,316/- as damage for complete non-cooperation of the defendant-petitioner resiling from their obligation as recorded by the Memorandum of Understanding (MOU). According to the plaintiff-respondent, the defendant-petitioner had deliberately neglected to make supply of 31 power paddy threshers within the time being fully aware that the plaintiff had to complete such supply as per the indent within seven days from 26.03.2013. 03. The plaintiff-respondent made the repeated calls to expedite the process for supply as indented by the Government of Assam. But later on, after about three months the plaintiff-respondent came to know that another supply order dated 26.03.2013 was issued for 42 Power Paddy Threshers and those agricultural equipments were supplied by the defendant-petitioner at Guwahati without any intimation to the plaintiff. The plaintiff-respondent had no occasion to inspect those 42 equipments or to verify the records to ascertain when those were received at Guwahati. The plaintiff was kept in complete dark in regard the said delivery. However, the said 42 power paddy threshers were illegally billed in the name of the plaintiff-respondent as the franchise of the defendant No.1, [the petitioner herein] in collusion with the defendants No.3 & 4. 04. On 30.03.2013 the Directorate of Agriculture, Government of Assam gave the supply order of 2022 manually operated single row conoweeders for an aggregate consideration of Rs.31,44,210/-. The delivery under the said order was to be completed within 15(fifteen) days from the date of issue of the indent. The plaintiff-respondent having a copy of the said supply order issued by the said directorate of Agriculture, Government of Assam had placed the requisition without delay to the defendant-petitioner for supply of the indented products implement the as order the plaintiff-respondent dated 30.03.2013. The was to plaintiff- respondent had contacted the defendant No.3 and requested him for an early dispatch of the required numbers of conoweeders, specified in the order. 05. The plaintiff-respondent, despite his several attempts to comply with the said order dated 30.03.2013, could deliver only 681 numbers of conoweeders lying in his stock at Agartala. That stock was purchased for retail sale for its office. The same was under compelling circumstances dispatched from Agartala on 24.06.2013 and received by the defendant-petitioner, but till the day of filing the suit the plaintiff-respondent was not abreast of the fact whether the said quantity of conoweeders dispatched by him from his stock had been delivered by the defendant-petitioner or his representative to the concerned directorate or not. The plaintiff-respondent has not received any payment till date of filing the suit from the Directorate of Agriculture, Government of Assam against the supply of the said quantity of conoweeders. 06. On 15.06.2013, the Government of Assam placed another supply order for supplying 1246 conoweeders for an aggregate consideration of Rs.19.37,530/-. Having received the said supply order the plaintiff through the defendant No.3 had placed the requisition to the defendant No.1. But the defendant-petitioner and the defendant No.3 did not supply nor did take any step for supply of the said equipments to the plaintiff-respondent as per the supply order dated 15.06.2013. As a result, the plaintiff-petitioner has failed to execute the order and suffered the cancellation of the said order causing him irreparable loss business and reputation in the suit. He has quantified the loss. 07. On 01.10.2013, there was a teleconference between the plaintiff-respondent and the respondents No.3 & 4 [who are stuck off at the instance of the petitioner] on the issue of liquidation of the stock against rotary tillers, paddy thrashers and brush cutters. One Shabana Kausar, the Executive Secretary of the defendant-petitioner 05.10.2013 forwarded an electronic mail recording on the minutes of the discussion as held on 01.10.2013, but the plaintiff-respondent has alleged that that was a clear attempt to shield their fault and breach. Hence, the plaintiff- respondent had replied the said communication by refuting the allegations as leveled against the plaintiff-respondent. 08. On 12.11.2013, again the principal defendant- petitioner had apprised the plaintiff-respondent that he had received two demand drafts on 05.11.2013 being draft No.659724 dated 30.08.2013 for Rs.28,350/- and the draft No.659820 dated 24.10.2013 for Rs.28,350/- only. Another demand draft dated 11.11.2013 being draft No.802211 dated 31.10.2013 for Rs.28,350/-. But the plaintiff-respondent has in reply stated that he had no information of such business transaction and he has not raised any bill for payment against the indenting Directorate. The references have been made elaborately how from the non-cooperation and irresponsible acts of the principal defendant-petitioner, the plaintiff- to make respondent has suffered loss. 09. The plaintiff-respondent had rearrangement for maintaining the office and the other operating staffs. Only for the office, the plaintiff-respondent had to spend the sum of Rs.16,831/- per month. That apart, (i) from 06.03.2013 to 30.07.2014 the plaintiff-respondent has spent Rs.52,740/- as the office rent, (ii) electricity bills from March, 2013 to December, 2013, @ Rs.400/- X 10 months = 4000/-, (iii)Ware houses rent from 18.04.2013 to 30.07.2014 =Rs.1,41,777/-, (iv) Staff expenses from March 2013 to July 2014 @ 28,500 X 17 months = 4,84,500/- and (v) for miscellaneous expenses it has been estimated @ Rs.33,940/-. Further, the plaintiff had to incur a further sum of Rs.4,53,317/- towards rent and maintaining the office and the staff as aforesaid. 10. Based on this narrative of claim, the plaintiff- respondent has urged this court to direct the defendantrespondent refund the money that he has spent for the business and the damages he has suffered for failure of execution of the supply order. Finally, the principal defendantpetitioner has been withdrawing its business operation from the area of operation where the plaintiff-respondent is carrying on his business without any reason, whereas the plaintiff-respondent had been earning from the said business. Thus, the plaintiff-respondent has quantified the damage at Rs.2,34,81,316/- for realization of which the plaintiff- respondent has filed the suit. The defendant did not file the written statement but challenged the order dated 01.08.2017 (Annexure-9) in this court in respect of rejection of the plaint for lack of jurisdiction of the court of the Civil Judge, Senior Division, Court No.4, West Tripura, Agartala. 11. It is an admitted fact that the principal defendant- petitioner did not get any order staying the proceeding of the Money Suit of 27 of 2014 in the relevant period. As consequence thereof, as recorded in the impugned order that after lapse of the statutory period the defendant filed his written statement along with a petition under Order VIII Rule 1 & 2 of the CPC for accepting the written statement of the defendant No.1 stating the reason of delay in filing the written statement. Since the written statement has been filed by the petitioner, for accepting the written statement the defendant No.1-petitioner did not file any other petition seeking extension of the time for filing the written statement. Even it has been urged that the order dated 21.11.2015 be set aside inasmuch as by the order dated 21.11.2015, the petition for accepting the written statement was rejected earlier. No further action was resorted to challenge the order dated 21.11.2015. But suddenly without any leave the said written statement was filed. By the impugned order, the court below has refused to accept the said written statement. 12. On 28.02.2017, after more than a year that petition under Section 151 of the CPC for accepting the written statement filed by the defendant No.1 was filed in M.S 27 of 2014 for setting aside the order dated 21.11.2015. By the impugned order dated 01.08.2017, the Civil Judge, Senior Division, Court No.4, West Tripura, Agartala has observed that the case was fixed for filing of the examination-in-chief by the plaintiff-respondent and as per the order dated 20.06.2017 the plaintiff-respondent had filed the examination-in-chief. On that day the defendant No.1 came up with the said petition for accepting the written statement which had been seriously objected by the plaintiff-respondent. 13. The defendant No.1-petitioner by the said petition dated 17.12.2016 filed under Order VIII Rule 1 & 2 read with Section 151 of the CPC had urged for accepting the written statement filed by the defendant No.1 [the petitioner herein]. On 21.02.2015, the principal defendant-petitioner by filing another petition had challenged the maintainability of the suit for lack of jurisdiction. After due hearing, by the order dated 27.07.2015, the said petition was rejected. 14. The defendants were directed to file the written statement by 22.08.2015. The defendant No.1 has finally taken a plea that the order of rejection dated 27.07.2015 was communicated to the defendant No.1 only on 07.10.2015. In the meanwhile, the previous engaged counsel expressed his inability to deal with the case. In such circumstances, the defendant No.1-petitioner prayed for the certified copies of the order dated 27.07.2015 and 24.08.2015. It was decided on 30.10.2015 that the revision petition would be filed against the order dated 27.07.2015 and accordingly after appointing a new counsel on 02.02.2016 a revision petition was filed before this court against the order dated 27.07.2015 which was registered as CRP No.69 of 2016. 15. On 17.12.2016, the defendant No.1 had submitted the written statement. However, the petition for accepting the written statement was filed on 28.02.2017. The plaintiffrespondent has contested the petition by filing the written objection on 19.08.2016. It was assertively contended in the said objection that the said petition was not maintainable. The Civil Judge, Senior Division has observed in the impugned order that the lack of communication cannot be accepted in the age of electronic mail for such a long time. The conduct of the defendant-petitioner demonstrates a clear dereliction or lax. Thereafter, the Civil Judge, Senior Division has further observed as follows: “If this version is believed to be true then how could the same counsel of the defendant No.1 & 4 come down with the time petition praying for time on 19.11.2015 and submitted before this Court that they are trying to obtain the stay order against the order dated 27.07.2015. This fact is found reflected in the order dated 19.11.2015. So, the assertions made by the defendant No.1 are blatant lie only to delay the proceeding plaintiff. Moreover, all the assertions made in the petition by defendant No.1 have been filed without any basis or cogent proof. As per the petition the defendant No.1 also challenged the order dated 27.07.2015 by filing Civil Revision Petition before Hon’ble High Court of Tripura.” 16. It has been also observed strangely that when the revision petition in respect of maintainability of suit was pending, how could the petition be floated before the Civil Judge on 17.12.2016 to accept the written statement. On 21.11.2015 by a full-fledged order, the Civil Judge, Senior Division rejected the petition for extending the time filed on 15.10.2015 and 19.11.2015. It is admitted that no further action was taken from those orders. 17. The defendants No.1 & 4 have thus lost their opportunity of filing the written statement inasmuch as the statutory period of filing the written statement had lapsed as per Order VIII, Rule 1 of the CPC. Now without setting aside the order dated 21.11.2015 how the court of the Civil Judge, Senior Division could set aside or recall the order dated 21.11.2015. Even the court cannot accept the written statement of the defendant No.1-petitioner filed without leave or allow the petition of the defendant No.1 petitioner dated 17.12.2016. To overcome that substantive fraud, the defendant No.1 petitioner again on 28.02.2017 came up with a petition urging to set aside the order dated 21.11.2015. The said order dated 21.11.2015 was passed by the Civil Judge, Senior Division on merit after hearing the parties. Unless the court below finds the cogent grounds to review the said order, it cannot be set aside by a stroke of pen. The judicial discretion is not that wide. Definitely, the court has the power to review its own order within the limited scope as provided under Section 114 read with Order 47 Rule 1 of the CPC. The Civil Judge has observed that the order cannot be set aside under the circumstances as emerged the question therefore is whether in the backdrop or in the context of explanation as given by the petitioner for setting aside the orders, the Civil Judge, Senior Division could have allowed the prayer made by the defendant-petitioner. To nourish his inference, the Civil Judge has referred to the decision of the apex court in Kailash vs. Nanhku & Ors. reported in (2005) 4 SCC 480 where the apex court has observed that three things are clear, firstly, a careful reading of the language in which Order VIII, Rule 1 has been drafted. It casts an obligation on the defendant to file the written statement within 30 days from the date of service of summons on him and within the extended time, if allowed, falling within 90 days. The provision does not deal with the power of the court and also does not specifically take away the power of the court to take the written statement on record though filed beyond the time as provided for. Secondly, the nature of the provision contained in the Order VIII, Rule 1 is procedural. It is not a part of the substantive law. Thirdly, the object behind Order VIII, Rule 1 in the present shape is to curb the mischief of unscrupulous defendants adopting dilatory tactics, delaying the disposal of cases. The object is to expedite the hearing and not to scuttle the same. The process of justice may be speeded up and hurried but the fairness which is a basic element of justice cannot be permitted to be buried. The similar legal position has been reiterated in Salem Advocates Bar Association, Tamilnadu vs. Union of India reported in 2005(6) SCC 344. 18. In Sushila Jain Corporation reported in vs. AIR Rajasthan RAJ, Financial 2115, the Rajasthan High Court has observed that if the Court is satisfied that the ground alleged prima facie reasonable and bona fide, then, without making much fuss over it, the court should extend the time. If, on the other hand, the request is not bona fide and un-reasonable, the Court would be justified, and may indeed be under a duty to refuse such a request. No hard and fast rule can be laid down for determining whether a particular request is bona fide or not. Such a request has to be dealt with on its merits in the circumstances of the case. The Civil Judge, Senior Division has observed that the defendant had clearly demonstrated lax and gross negligence on their part by not filing the written statement. Hence, no indulgence can be granted for filing the written statement. Accordingly, he had rejected the prayer. 19. Mr. T. K. Deb, learned counsel appearing for the defendant No.1-petitioner has submitted that for the supervening circumstances, the defendant No.1 petitioner could not file the reply. But, it is noted that there is no satisfactory explanation for such a long delay. Mr. Deb, learned counsel has also relied a decision of this court in Bijoy Krishna Acharjee and Ors. vs. Shri Mithun Sharma & Ors. [Judgment and order dated 23.02.2017 delivered in Civil Revision Petition 85 of 2016]. 20. This court having referred to Kailash (supra) has allowed the written statement to be filed by overlooking the delay, but subject to a cost of 20,000/-. There cannot be any amount of controversy in respect of the position of law that the time-limit set up by Order VIII Rule 1 of the CPC is not absolute, it circumstances can also where be the waived defendant in the was appropriate prevented by circumstances which was beyond their control or which is as such incidental, and its delay is not condoned, there would be serious prejudice. In Bijoy Krishna Acharjee (supra), this court has observed as follows: “In the instant case, I have the sneaking suspicion that the respondents are not serious in defending their case, and are merely interested in delaying the disposal of the suit. However, for the time being, I prefer to give them the benefit of doubt so that they are not left defenceless even before the commencement of the trial but this shall be subject to payment of deterrent and compensatory cost. In this view of the matter, I refrain from interfering with the impugned order with the rider indicated above.” With due humility, the said observation has not curved out a precedent finding this court to follow it. The defendant No.1 petitioner has failed to make out a case of exceptional nature for exercising the inherent power to allow the defendant petitioner file his written statement after such inordinate and un-explained delay. 21. Mr. S. M. Chakraborty, learned senior counsel appearing for the respondent No.1 has submitted that even the petition was not seriously drafted inasmuch as their prayer for extension of time for filing the written statement was earlier rejected, but no action therefrom was taken or carried out by the defendant-petitioner. 22. Having taken note of the fact and circumstances as narrated in the impugned order and as available in the records, this court is not inclined to set aside the impugned order and accordingly this petition stands dismissed. There shall be no order as to costs. JUDGE Moumita

This page is for informational and research purposes only and does not constitute legal advice. Consult a qualified advocate for advice specific to your situation.

Is your name in this judgment and should it be masked, or is something on this page wrong? Request a review

All Tripura HC judgments →