The court's order
The closing paragraphs of the judgment, in the court's own words. The reasons are in the full text below.
2. From perusal of the record and the General Conditions of contract forming part of the agreement executed between the employer and the contractor, it appears that Clause 25 of the agreement provides as under:“CLAUSE-25 Settlement of Disputes & Arbitration Except where otherwise provided in the contract all questions and disputes relating to the meaning of the specifications, design, drawings and instructions here-in-before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim right matter or thing whatsoever in any way arising out of or relating to contract, designs, drawings, specifications, estimates, instructions, orders or these conditions or otherwise concerning the works or execution or failure to execute the same whether arising during the progress of the work or after the cancellation, termination, completion or abandonment thereof shall be dealt with as mentioned hereinafter. (i) If the contractor considered any work demanded of him to be outside of the requirements of the contract, or dispute any drawings, record or decision given in the Patna High Court CWJC No.18551 of 2025(5) dt.23-02-2026 4/7 writing by the Engineer-in-Charge on any matter in connection with or arising out of the contract or carrying out of the contract or carrying out of the work, to be unacceptable, he shall promptly within 7 days request …
3. In view of the aforesaid, the petitioner shall be at liberty to avail the remedy available under Clause 25 of the Agreement. While invoking the remedy under Clause 25, the petitioner shall be at liberty to raise all permissible grounds in accordance with law.
4. Accordingly, with the aforesaid liberty, the present application stands disposed of.
Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.18551 of 2025
======================================================
M/s Khushee Construction through its Partner, namely Rajeev Kumar @
Rajeev Ranjan Kumar, aged about 37 years (Male), son of Virendra Singh,
resident of village- Rampur, Dumra, P.S.-Maranchi, District- Patna.
1.
... ... Petitioner
Versus
The State of Bihar through the Principal Secretary, Public Health
Engineering Department, Government of Bihar, Patna.
2.
The Principal Secretary, Public
Government of Bihar, Patna.
Health
Engineering
Department,
3.
The Engineer-in-Chief-cum- Special Secretary, Public Health Engineering
Department, Government of Bihar, Patna.
4.
The Chief Engineer, Design, Public Health Engineering Department,
Government of Bihar, Patna.
5.
The Chief Engineer (Zonal), Public Health Engineering Department, Purnea
Zone, Purnea.
6.
The Superintendent Engineer, Public Health Engineering Department,
Purnea Circle, Madhepura.
7.
The Executive Engineer, Public Health Engineering Division Purnea, Bihar.
8.
The Executive Engineer, Public Health Engineering Division Dhamdaha,
Bihar
... ... Respondents
======================================================
Appearance :
For the Petitioner
:
For the Respondents
:
Mr. Vikas Kumar, Advocate
Mrs. Aradhana Kumari, Advocate
Mr. Akash Deep, Advocate
Mr. Addl.Advocate General-3
======================================================
CORAM: HONOURABLE MR. JUSTICE SUDHIR SINGH
and
HONOURABLE MR. JUSTICE RAJESH KUMAR VERMA
ORAL ORDER
(Per: HONOURABLE MR. JUSTICE SUDHIR SINGH)
23-02-2026
In the present writ petition, the petitioner has prayed
for the following relief(s):“(i) For quashing of office order no. 176, 178 to
all
dated
28.08.2025
contained
in
respective memo no. 2788, 2800 to 05 all dated
Patna High Court CWJC No.18551 of 2025(5) dt.23-02-2026
2/7
28.08.2025 issued by the Executive Engineer,
Public Health Division, Purnea, whereby and
where-under altogether 7 agreements i.e SBD
No. 149, 147, 146, 143, 142, 140 and 148 of
2019-20 for "Design, Construction, Supply,
Testing, commissioning of Water supply Scheme
with Electric Driven Pumps and Iron Removal
Treatment
Plant
having
Technology
(Adsorption/ Nano Technology) of CSIR or
certified by CSIR or any other Technology
endorsed/ approved by GOI in the Iron effected
Habitations under different wards/ Panchayat
under different Blocks in the Purnea division,
District-Purnea of Bihar on turnkey basis with 3
month Trial Run after Commissioning and
comprehensive operation and maintenance of 60
months after successful completion of Trial Run
Period under Mukhyamantri Nishchay (Quality
Affected)" (herein after to be referred as 'the
work in question'), has been terminated and
security money has also been forfeited along
with decision has been taken to recommend the
higher officials to blacklist the registration of
the petitioner without issuance of any showcause notice and affording any opportunity of
hearing to the petitioner.
(ii) For direction to the respondent authorities
to allow the petitioner to complete the work
pursuant to aforesaid agreements as mentioned
in sub-para- (i) as petitioner has completed
almost more than 90% of work in the
ward/panchayat of the work in question.
Patna High Court CWJC No.18551 of 2025(5) dt.23-02-2026
3/7
(iii) For any other appropriate relief/reliefs on
the facts and circumstances of the present case
for which the petitioner is found entitle too.”
2. From perusal of the record and the General
Conditions of contract forming part of the agreement executed
between the employer and the contractor, it appears that Clause
25 of the agreement provides as under:“CLAUSE-25
Settlement of Disputes & Arbitration
Except where otherwise provided in the contract
all questions and disputes relating to the
meaning of the specifications, design, drawings
and instructions here-in-before mentioned and
as to the quality of workmanship or materials
used on the work or as to any other question,
claim right matter or thing whatsoever in any
way arising out of or relating to contract,
designs, drawings, specifications, estimates,
instructions, orders or these conditions or
otherwise concerning the works or execution or
failure to execute the same whether arising
during the progress of the work or after the
cancellation,
termination,
completion
or
abandonment thereof shall be dealt with as
mentioned hereinafter.
(i) If the contractor considered any work
demanded of him to be outside of the
requirements of the contract, or dispute any
drawings, record or decision given in the
Patna High Court CWJC No.18551 of 2025(5) dt.23-02-2026
4/7
writing by the Engineer-in-Charge on any
matter in connection with or arising out of the
contract or carrying out of the contract or
carrying out of the work, to be unacceptable, he
shall promptly within 7 days request the
Superintending Engineer in writing for the
written instruction of decision. Thereupon, the
Superintending Engineer shall give his written
instructions of decision within a period of fifteen
days from the receipt of the contractor's letter. If
the Superintending Engineer fails to give his
instructions or decision in writing within the
aforesaid period or if the contractor is
dissatisfied with the instructions or decision of
the Superintending Engineer, the contractor
may, within 15 days of the receipt of
Superintending Engineer's decision, appeal to
the Chief Engineer who shall afford an
opportunity to the contractor to be heard, if the
later so desires, and to offer evidence in support
of his appeal. The Chief Engineer shall give his
decision
within
days
of
receipt
of
contractor's appeal. If the contractor is
dissatisfied with this decision, the contractor
shall within a period of 30 days from receipt of
the decision, give notice to the Chief Engineer
for appointment of arbitrator failing which the
said decision shall be final binding and
conclusive and not referable to adjudication by
the arbitrator.
(ii) Except where the decision has become final,
binding and conclusive in terms of Sub Para (i)
Patna High Court CWJC No.18551 of 2025(5) dt.23-02-2026
5/7
above disputes or difference shall be referred
for adjudication through arbitrator appointed
by Engineer-in-Chief or the administrative head
of the said PHED. If the arbitrator so appointed
is unable or unwilling to act or resign his
appointment or vacates his office due to any
reason whatsoever another sole arbitrator shall
be appointed in the manner aforesaid. Such
person shall be entitled to proceed with the
reference from the stage at which it was left by
his predecessor.
It is a term of this contract that the party
invoking arbitration shall give a list of disputes
with amounts claimed in respect of each such
dispute along with the notice for appointment of
arbitrator and giving reference to the rejection
by the Chief Engineer of the appeal.
It is also a term of this contract that no person
other than a person appointed by such
Engineer-in-Chief or the administrative head of
the department as aforesaid should act as
arbitrator and if for any reason that is not
possible, the matter shall not be referred to
arbitrator at all. It is also a term of this contract
that if the contractor does not make any demand
for appointment of arbitrator in respect of any
claims in writing as aforesaid within 45 days of
receiving the intimation from the Engineer-inCharge that the final bill is ready for payment,
the claim of the contractor shall be deemed to
have been waived and absolutely barred and the
Government shall be discharged and released of
Patna High Court CWJC No.18551 of 2025(5) dt.23-02-2026
6/7
all liabilities under the contract in respect of
these claims.
The
arbitration
accordance
shall
be
the
provisions
with
conducted
of
in
the
Arbitration and Conciliation Act, 1996 (26 of
1996) or any statutory modifications or reenactment thereof and the rules made there
under and for the time being in force shall apply
to the arbitration proceeding under this clause.
It is also a term of the contract that if any fees
are payable to the arbitrator these shall be paid
equally by both the parties.
It is also a term of the contract that the
arbitrator shall be deemed to have entered on
the reference on the date the issues notice to
both the parties calling them to submit their
statement of claims and counter statement of
claims. The venue of the arbitration shall be
such place as may be fixed by the arbitrator in
his sole discretion. The fees, if any, of the
arbitrator shall, if required to be paid before the
award is made and published, be paid half and
half by each of the parties. The cost of the
reference and of the award (including the fees, if
any, of the arbitrator) shall be in the discretion
of the arbitrator who may direct to any by whom
and in what manner such costs or any part
thereof shall be paid and fix or settle the amount
of costs to be so paid.
All arbitration shall be held at PATNA and at no
other place.”
Patna High Court CWJC No.18551 of 2025(5) dt.23-02-2026
7/7
3. In view of the aforesaid, the petitioner shall be at
liberty to avail the remedy available under Clause 25 of the
Agreement. While invoking the remedy under Clause 25, the
petitioner shall be at liberty to raise all permissible grounds in
accordance with law.
4. Accordingly, with the aforesaid liberty, the present
application stands disposed of.
5. Pending application(s), if any, shall also stand
disposed of.
(Sudhir Singh, J.)
(Rajesh Kumar Verma, J.)
Gaurav Kumar,
Ibrar/-
U
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review