IN THE HIGH COURT OF JUDICATURE AT PATNA
Letters Patent Appeal No.1185 of 2024
In
Civil Writ Jurisdiction Case No.18226 of 2013
CNR No. BRHC011156592024
======================================================
1.
The State of Bihar through the Principal Secretary, Water Resources
Department, Government of Bihar, Patna.
2.
The Engineer-In-Chief, Water Resources Department, Government of Bihar,
Patna.
3.
The Chief Engineer, Water Resources Department, District- Purnea.
4.
The Superintending Engineer, Water Resources Department, Government of
Bihar, Patna.
5.
The Executive Engineer, Drainage and investigation Division, Kishanganj.
6.
The Assistant Engineer, Drainage and investigation Division, Kishanganj.
7.
The Junior Engineer, Drainage and investigation Division, Kishanganj.
... ... Appellant/s
Versus
Birat Construction Pvt. Ltd. through the Managing Director, Santosh Kumar
having itsd Principle Office at Basantpur, Near Court Colony, Virpur, P.O.Virpur, P.S. Virpur, District- Supaul.
... ... Respondent/s
======================================================
Appearance :
For the Appellant/State :
For the Respondent
:
Dr. Bipin Chandra, SC-28
Mr. Alok Ranjan, Advocate
Mr. Akash Chaturvedi, Advocate
======================================================
CORAM: HONOURABLE MR. JUSTICE PRABHAT KUMAR SINGH
and
HONOURABLE MR. JUSTICE RANA VIKRAM SINGH
ORAL ORDER
(Per: HONOURABLE MR. JUSTICE PRABHAT KUMAR SINGH)
06-11-2026
Heard learned counsel for the appellants-State and
learned counsel appearing on behalf of the respondent.
2. The present Letters Patent Appeal has been
Patna High Court L.P.A No.1185 of 2024(15) dt.06-11-2026
2/13
preferred against the judgment dated 30.08.2024 passed by the
learned Single Judge in C.W.J.C. No. 18226 of 2013 whereby
the writ petition filed by the respondent-writ petitioner was
allowed, the respondent was held entitled to payment for the
work executed under Agreement No. 36 F2 dated 19.03.2012,
and the appellants were directed to delete its name from the
blacklist.
3. The brief facts necessary for adjudication of the
present appeal are that the Water Resources Department,
Government of Bihar invited a tender bearing NIT No. 2/201112 for construction of porcupines on the right bank of the
Kankai River near village Purandaha, District Kishanganj.
Pursuant thereto, an agreement dated 19.03.2012 was executed
between the respondent-writ petitioner and the concerned
Executive Engineer. The work related to construction of
porcupines for a length of 300 metres.
4. The case of the appellants-State is that, in terms of
the tender, estimate and agreement, the respondent was required
to construct porcupines in two rows over a length of 300 metres.
However, instead of executing the work in the prescribed
manner, the respondent constructed porcupines in a single row
over a length of 600 metres, thereby deviating from the
Patna High Court L.P.A No.1185 of 2024(15) dt.06-11-2026
3/13
approved estimate and the terms of the agreement. It is further
the case of the appellants that the respondent was repeatedly
instructed by the departmental authorities to execute the work in
accordance with the agreement, but it failed to comply with
such directions. The appellants also contend that the work was
incomplete and of poor quality, that no corresponding entry was
made in the Field Measurement Book and consequently, no bill
could be passed for payment. It is their further case that, after
issuance of a show-cause notice dated 09.12.2013 and
consideration of the reply submitted by the respondent, the
department passed the order dated 30.01.2014, contained in
Memo No. 505, blacklisting the respondent under Rule 11(ka)
(a) of the Bihar Contractor Registration Rules, 2007.
5. Per contra, learned counsel appearing for the
respondent submits that the work was executed in accordance
with the instructions of the departmental engineers. It is
submitted that, owing to disturbances at the work site, the
departmental
engineers,
after
deliberation,
directed
the
respondent to construct the porcupines in a single row over a
length of 600 metres instead of constructing them in two rows
over 300 metres. The work was completed within the stipulated
period and was within the knowledge of the concerned
Patna High Court L.P.A No.1185 of 2024(15) dt.06-11-2026
4/13
Executive Engineer. It is further submitted that the qualitycontrol report dated 10.07.2012 issued by the Chief Engineer
found the quality of the work satisfactory. Subsequently, the
Superintending Engineer, by his review report dated 16.03.2013,
also appreciated the work executed by the respondent, found the
single-row arrangement successful and effective in the
prevailing river conditions, and recommended release of
payment. Despite the aforesaid departmental findings, the
appellants withheld the payment and proceeded to blacklist the
respondent.
6. We have considered the rival submissions and
perused the materials available on record. The principal issue
which arises for consideration is whether the construction of
porcupines in a single row over 600 metres, instead of in two
rows over 300 metres, constituted an unauthorised deviation
from the contractual terms so as to justify withholding of
payment and blacklisting of the respondent. Learned counsel for
the appellants has placed considerable reliance upon the
estimate and the departmental letter bearing No. 506 dated
17.02.2012. It is contended that the estimate formed an integral
part of the tender and the agreement and clearly stipulated
construction of porcupines in two rows over a length of 300
Patna High Court L.P.A No.1185 of 2024(15) dt.06-11-2026
5/13
metres. According to the appellants, the respondent was,
therefore, bound to execute the work strictly in accordance with
the said specification.
7. There can be no dispute with the general
proposition that the parties to a contract are bound by its terms
and that a Court cannot rewrite the contractual obligations
undertaken by them. However, before the aforesaid principle
can be applied, it must first be established what the actual
contractual
obligation
was
and
whether
the
particular
specification sought to be enforced by the appellants formed
part of the tender and the agreement executed between the
parties.
8. The learned Single Judge, upon consideration of the
materials available on record, specifically noticed that the
requisite specifications were not shown to have been
incorporated either in the agreement executed between the
parties or in the tender notification. The learned Single Judge
had also called upon the State authorities to furnish the relevant
details, but no proper documents were placed before the Court
to establish the alleged contractual requirement of construction
in two rows.
9. The appellants, in the present appeal, have
Patna High Court L.P.A No.1185 of 2024(15) dt.06-11-2026
6/13
reiterated that the estimate formed part of the agreement.
However, a mere assertion in the memorandum of appeal cannot
take the place of the contractual document itself. The appellants
were required to demonstrate from the relevant tender and
agreement documents that the particular specification relied
upon by them was an enforceable term of the contract. In the
absence of such material being demonstrated, the finding
recorded by the learned Single Judge cannot be said to be
perverse or contrary to the record.
10. There is another significant aspect of the matter
which cannot be overlooked. The respondent has consistently
maintained that the change in the manner of execution was not
made unilaterally or for its own convenience, but was
necessitated by disturbances at the site and was undertaken upon
the intervention and instructions of the departmental authorities.
In this regard, the review report dated 16.03.2013 submitted by
the Superintending Engineer assumes considerable significance.
The said report, as noticed by the learned Single Judge, records
that the work near village Purandaha was interrupted on account
of insecurity, personal enmity and disputes between two
communities. It further records that, upon intervention of senior
officials and in coordination with the regional officials, the work
Patna High Court L.P.A No.1185 of 2024(15) dt.06-11-2026
7/13
was completed in a single row over almost double the original
length and that the said arrangement was within the knowledge
of the Executive Engineer. The review report further records
that, having regard to the prevailing condition of the river, the
single-row arrangement appeared to be successful, useful and
effective.
On
that
basis,
the
Superintending
Engineer
recommended that the payment of the respondent should not be
withheld.
11. Thus, the departmental review does not support
the appellants' assertion that the respondent had, on its own,
departed from the contractual arrangement without the
knowledge or intervention of the departmental authorities.
Rather, the report indicates that the altered manner of execution
was undertaken in the prevailing site conditions with the
intervention
of
senior
departmental
officials
and
was
subsequently found useful and effective by the competent
departmental authority. The appellants have also contended that
the respondent was repeatedly directed to execute the work in
two rows and that it failed to comply with such directions.
However, the respondent's specific case before the writ Court
was that the communications dated 03.05.2012, 26.06.2012 and
09.07.2012 were received together on 13.07.2012, whereas the
Patna High Court L.P.A No.1185 of 2024(15) dt.06-11-2026
8/13
work had already been completed on 15.05.2012. The appellants
have not demonstrated from the materials placed before the writ
Court that the aforesaid communications were duly served upon
the respondent before completion of the work or that the
respondent deliberately disobeyed any subsisting direction of
the competent departmental authority.
12. In any event, the subsequent review report dated
16.03.2013, which specifically takes note of the circumstances
in which the work was executed and recommends release of
payment, is a material departmental document which could not
have been brushed aside merely on the basis of the appellants'
subsequent allegation of unauthorised deviation. The contention
of the appellants regarding absence of entries in the Field
Measurement Book also does not, by itself, justify denial of
payment for work which has been physically executed and
subsequently examined by the departmental authorities. It is true
that measurement and verification of the work are necessary for
processing a contractor's bill. However, the absence of an entry
in the Field Measurement Book cannot be treated as conclusive
proof that no work was executed, particularly when the
department's own review report acknowledges the execution of
the work, assesses its effectiveness and recommends payment to
Patna High Court L.P.A No.1185 of 2024(15) dt.06-11-2026
9/13
the respondent.
13. The appellants were required to examine the work
executed, verify the quantity and determine the amount payable
in accordance with the contractual terms. A deficiency in the
departmental measurement records cannot be used to defeat an
otherwise established claim for payment, especially when the
department itself had the responsibility to maintain and verify
such records.
14. We also find that the learned Single Judge has
taken note of the quality-control report dated 10.07.2012 issued
by the Chief Engineer, which found the quality of the work
satisfactory. The review report dated 16.03.2013 further records
that the single-row arrangement was successful, useful and
effective in the prevailing river conditions.
15. The appellants have alleged that the work was
incomplete and of poor quality and have also referred to an
inspection by the departmental flying squad. However, the
existence of such allegations cannot, by itself, displace the
findings contained in the aforesaid departmental reports. The
appellants have not demonstrated any cogent material which
would render the findings of the quality-control report and the
subsequent review report unreliable or establish that the work
Patna High Court L.P.A No.1185 of 2024(15) dt.06-11-2026
10/13
executed by the respondent was wholly unacceptable.
16. So far as the order of blacklisting dated
30.01.2014 is concerned, it is well settled that blacklisting a
contractor entails serious civil consequences and has a direct
bearing upon its right to participate in future government
contracts. Such an order must, therefore, be supported by a
legally sustainable basis and must satisfy the requirements of
fairness and proportionality.
17. In the present case, the principal allegation against
the respondent is that it deviated from the prescribed manner of
execution by constructing the porcupines in a single row over
600 metres instead of in two rows over 300 metres. However, as
noticed above, the appellants have not satisfactorily established
that the specification sought to be enforced was an unambiguous
and binding contractual condition. Further, the departmental
review report records the circumstances in which the work was
executed, acknowledges the intervention of senior officials and
recommends payment after finding the work successful and
effective.
18. In such circumstances, the mere fact that a showcause notice was issued and a reply was submitted by the
respondent would not, by itself, establish the legality of the
Patna High Court L.P.A No.1185 of 2024(15) dt.06-11-2026
11/13
ultimate decision to blacklist it. The substantive basis for taking
such an extreme action must also be sustainable. Once the
principal allegation of unauthorised deviation is not established
from the contractual documents and is further rendered doubtful
by the subsequent departmental review, the action of
blacklisting the respondent cannot be sustained merely on the
basis of the appellants' assertions.
19. The reliance placed by the appellants upon the
judgment of the Hon'ble Supreme Court in the case of
Rajasthan State Industrial Development and Investment
Corporation and Another v. Diamond and Gem Development
Corporation and Another, reported in (2013) 5 SCC 470, does
not advance their case any further.
20. There can be no quarrel with the proposition that
contractual terms are required to be interpreted in accordance
with their language and that a Court cannot create a new
contract between the parties. However, the aforesaid principle
does not dispense with the requirement of first establishing the
actual terms of the contract. In the present case, the learned
Single Judge has not rewritten the agreement or substituted a
different contractual obligation. The learned Single Judge has
examined whether the appellants had established the particular
Patna High Court L.P.A No.1185 of 2024(15) dt.06-11-2026
12/13
specification on the basis of which the respondent was sought to
be penalised and has also considered the subsequent
departmental assessment of the work.
21. The decision relied upon by the appellants,
therefore, does not warrant interference with the findings
recorded by the learned Single Judge.
22. On an overall consideration of the materials, we
find that the learned Single Judge has taken note of the relevant
contractual dispute, the absence of proper documentary material
establishing the specific requirement relied upon by the
appellants and more importantly, the departmental review report
dated 16.03.2013 recommending release of payment after
finding the work successful and effective.
23. The appellants have not been able to demonstrate
any perversity in the appreciation of the materials by the learned
Single Judge or any error of law warranting interference in the
present appeal. We are, therefore, not persuaded to take a view
different from the one taken by the learned Single Judge.
24. Accordingly, the present Letters Patent Appeal
stands dismissed. The judgment dated 30.08.2024 passed in
C.W.J.C. No. 18226 of 2013 is hereby affirmed.
25. Pending interlocutory applications, if any, also
Patna High Court L.P.A No.1185 of 2024(15) dt.06-11-2026
13/13
stand disposed of.
(Prabhat Kumar Singh, J)
( Rana Vikram Singh, J)
shashank/U
This page is for informational and research purposes only and does not constitute legal advice.
Consult a qualified advocate for advice specific to your situation.
Is your name in this judgment and should it be masked, or is something on this page wrong?
Request a review