Item No. - 10
IN THE HIGH COURT OF MANIPUR
AT IMPHAL
W.P.(C) No.597 of 2019
(Through Video Conference)
Shri Leishangthem Ghanashyam Singh, aged about 44 years, S/o (Late)
L. Krishna Singh of Uripok Polem Leikai, P.O> and P.S. Imphal, Imphal
West District, Manipur, Pin – 795001.
…. Petitioner/s
- Versus –
1. The State of Manipur, represented by the Commissioner/Secretary,
Public Health Engineering Department, Government of Manipur, P.O. and
P.S. Imphal, Manipur, Pin – 795001.
2.
The
Chief
Engineer,
Public
Health
Engineering
Department,
Government of Manipur, P.O. and P.S. Imphal, Manipur, Pin – 795001.
3. The Executive Engineer, Drainage and Sewerage Division, Public
Health Engineering Department, Government of Manipur, P.O. and P.S.
Imphal, Manipur, Pin – 795001.
.... Respondent/s
BEFORE
HON’BLE MR. JUSTICE MV MURALIDARAN
23.02.2022
Heard Mr.Ch. Bimolchandra, learned counsel for the petitioner and
Mrs.Ch. Sundari, learned Government Advocate for the respondents.
W.P.(C) No.597 of 2019
Page 1
2. This writ petition has been filed by the petitioner
seeking
direction on the respondents for payment of the undisputed bill amount for
the execution of different contract works to the petitioner amounting to
Rs.3,27,57,073/- within a stipulated period with interest of 18% per annum.
The petitioner also sought direction for payment of compensation to him
for causing monetary loss, injury and prejudice for failure of payment of the
undisputed bills entitled to him in time.
3. Brief facts which gave rise to the filing of the writ petition are as
follows:
The petitioner is a registered contractor and he had executed many
contract works of the Drainage and Sewerage Division of the Public
Health Engineering Department and other Departments. The petitioner has
been awarded with various contract works. The petitioner and the Executive
Engineer of the Public Health Engineering Department had entered into
different contract agreements for executing the works for the Drainage and
Sewerage Division for an amount of Rs.3,27,57,073/-.
3.1. The petitioner had completed the different contract
works
within the stipulated time to the satisfaction of the authorities concernedas
per the stipulated time given by the competent authority and also the
execution of the works were duly checked and verified by the concerned
authority. After completion of works, the petitioner submitted bills for
W.P.(C) No.597 of 2019
Page 2
payment. However, the bill amount of Rs.3,27,57,073/- payable to the
petitioner has been left out by the Department due to oversight. Despite
repeated requests made to the authority for payment of the undisputed bills,
the authority has not paid any heed to pay the outstanding bills. In fact, the
liability was duly admitted by the competent authority of the Public Health
Engineering Department, Government of Manipur.
3.2. Several contracts in connection with different works were
awarded to the other contractors and all those who have been awarded
contract have duly executed and concluded their supply order and also
paid with their respective bills. However, for the reasons best known to the
respondents, the petitioner has not been paid with his due till date.The
outstanding bills of the petitioner for the work executed have been duly
admitted by the Executive Engineer.
3.3. According to the petitioner, it is not in dispute that the
undisputed bills of the petitioner can be termed as a property of the
petitioner within the purview of Article 300-A of the Constitution of India and
the same cannot be forfeited from the petitioner without due process of law
after conclusion of the contract works executed by the petitioner. Further,
the question of attracting arbitration clause of the tender agreement does
not arise, once the undisputed bills become the property of the petitioner. In
W.P.(C) No.597 of 2019
Page 3
other words, after the conclusion of the different contract works, the
agreement clause of the relevant terms and agreement of the tenders are
not attracted at the time of payment of the final bill.
3.4. Since the respondents are statutory authorities within the
purview of Article 12 of the Constitution of India, their conducts areexpected
to be fair and reasonable. In the instant case, they are expected to make
immediate payment without any discrimination. Hence, being aggrieved
with the discriminatory and arbitrary acts of the respondents in not settling
the bills, the petitioner has filed the writ petition. Thus, a prayer is made
to direct the respondents to settled the undisputed bills to the tune of
Rs.3,27,57,073/- and also compensation for monetary loss and injury
suffered by him.
4. Resisting the writ petition, the first respondent filed affidavit-in-
opposition stating that the names of the work claimed by the petitioner are
not included in the approved work programme. As per rules, the
financial/budget system is yearly basis and works have to be executed as
per the yearly approved work programme and within the allocated budget of
that particular year. Accordingly, funds are also released as per the
approved budget on yearly basis. It is stated that the Department had
already released full amount against the budget provisions of the relevant
W.P.(C) No.597 of 2019
Page 4
years of the Drainage and Sewerage Division to the Division concerned.
Thus, it may be concluded that the responsibility of payment of any
outstanding bills owed to the petitioner, if any for the alleged completed
works lies with the Executive Engineer. The Department cannot take
responsibility of any works executed beyond the approved work programme
of the Department. Since the works executed by the petitioner are not
approved by the State Government, all liabilities cannot be borne by the
State Government.
5. The learned counsel for the petitioner submitted that the Public
Health Engineering Department issued work orders to the petitioner for
execution of various works and the same have been duly executed by the
petitioner within the stipulated time. He would submit that for the execution
of the different contract works, an amount of Rs.3,27,57,073/- is
outstanding to the petitioner and despite requests made by the petitioner,
the respondents are evading to settle the said amount.
6. The learned counsel further submitted that the respondents have
paid contract bills to several other contractors, however, the petitioner’s
undisputed bills have not been paid till date. Hence, the petitioner has filed
the instant writ petition seeking direction on the respondent to settle the
undisputed bills to the tune of Rs.3,27,57,073/- with interest and also
W.P.(C) No.597 of 2019
Page 5
compensation for causing monetary loss and hardship for failure of the
payment to the petitioner.
7. Per contra, the learned Government Advocate submitted that the
list of works executed by the petitioner has been studied and checked by he
authorities and on verification, it was found that some secondary sewer
line and manhole construction were executed by the petitioner, which were
part of the project sanction under secondary sewer network. The amount
relating to the list of works executed by the petitioner which are part of
primary and secondary sewerage network shall be paid from time to time
subject to the availability of fund and satisfactory completion of works. For
the remaining works claimed by the petitioner, the works are beyond the
scope of Imphal Sewerage Project Phase-I and the option of payment can
be considered only after re-examining the works. She would submit that
work orders have been issued by the then Executive Engineer and executed
by the contractor.
8. This Court considered the rival submissions of parties and also
perused the materials available on record.
9. The first respondent in his affidavit-in-opposition stated that the
names of the work claimed by the petitioner are not included in the
W.P.(C) No.597 of 2019
Page 6
approved work programme and as per rules the financial/budget system
is yearly basis and works have to be executed as per the yearly approved
work programme and within the allocated budget of that particular year. It
is stated that the Department had already released the full amount against
the budget provisions of the relevant years of the Drainage and Sewerage
Division to the Division concerned. Thus, the responsibility of payment of
any outstanding bills to the petitioner if any for the alleged completed
works lies with the Executive Engineer, Public Health Engineering
Department, Drainage and Sewerage Division and the Department cannot
take responsibility for any works executed beyond the approved work
programme of the Department.
10. It is also stated by the first respondent in the affidavit-in-
opposition that the works executed by the petitioner are not approved by the
State Government and therefore, all liabilities cannot be borne by the State
Government. Any liability, it must be admitted by the Chief Engineer and in
the present case, the outstanding due has not been admitted by the Chief
Engineer.
11. While it is the averments of the first respondent in the affidavit-
in-opposition, the respondents 1 to 3 in their reply to the rejoinder dated
18.02.2022 have categorically stated that the list of works executed by the
W.P.(C) No.597 of 2019
Page 7
petitioner has been studied and verified and found that some secondary
sewer line and manhole constructions which were executed by the
petitioner are part of the project sanction under the secondary sewer
network. That apart, the list of works executed by the petitioner, which are
part of primary and secondary sewerage network, has been annexed with
the reply, wherefrom, this Court finds that the petitioner had executed the
following works:
(i)
Construction of manhole 5m depth 200mm
thick at BD12 towards BD10 portion-I.
(ii)
Laying of lateral sewer line i/c construction of
collection
chamber
at
Thangal
Bazar
Southern Part-II.
(iii)
Laying of lateral sewer line i/c construction of
collection chamber at Paona Bazar Northern
Portion-II “01 to 07 & II “01 to 13.
(iv)
Laying of secondary line 200mm dia and
lateral sewer line 150mm dia at 1st MR
campus 1st and 2nd Leirak.
(v)
Laying of secondary line 200mm dia & lateral
sewer line 150mm dia. Across Keisamthong
Khul connecting to Manhole YY’10.
(vi)
Laying of secondary line 200mm dia and
lateral sewer line 150mm across Sougaijam
Leirak.
(vii)
Laying of secondary line 200mm dia and
lateral sewer line 150mm across 1st
rd
MR
th
Campus 3 & 4 leirak.
W.P.(C) No.597 of 2019
Page 8
(viii)
Demolition and relaying of RCC Primary
Sewer line 1000mm dia at Lamphel BRTF
Office for a length of.
(ix)
Demolition and relaying of RCC Primary
Sewer line 1000mm dia at Lamphel Police
Station opposite lane for a length of 80rm.
12. According to the respondents 1 to 3, the amount mentioned
against the Annexure-I to the reply shall be paid from time to time subject
to availability of fund and satisfactory completion of works. Further, in
respect of other works listed out in Annexure-II to the reply, it is the say of
the respondents 1 to 3 that the works are beyond the scope of Imphal
Sewerage Project Phase I and the option of payment can be considered
only after re-examining the works. Further, in paragraph 5 of the reply, the
respondents 1 to 3 stated that work orders have been issued by the then
Executive Engineer and executed by the contractor. Thus, according to the
respondents 1 to 3, works orders issued to the petitioner have been
executed by him and the works were completed. When such being the
plea of the respondents 1 to 3, this Court is of the view that there had been
outstanding bills due to the petitioner by the respondents.
13. Having issued work orders to the petitioner by the concerned
authority of the respondents 1 to 3 and executed by the petitioner and also
verified by the concerned authorities, failure on the part of the respondents
W.P.(C) No.597 of 2019
Page 9
to pay the respective undisputed bills would amount to failure on the part
of the respondents to discharge their duties.
In fact, the respondent
authorities are duty bound to settle the undisputed bills. The petitioner has
also listed out the liabilities in Annexure-I to the writ petition to the tune of
Rs.3,27,57,073/-.
14. The first respondent cannot contend that the
Department
cannot take responsibility for the works executed beyond the approved work
programme of the Department and some works executed by the petitioner
are not approved by the State Government. Merely because some of the
works were not approved by the State Government, it cannot be contended
that the State Government is not liable for the outstanding bills. Though the
first respondent
is
the Commissioner/Secretary
of Public Health
Engineering Department, the Chief Engineer of Public Health Engineering
Department and the Executive Engineer, Drainage and Sewerage Division,
Public Health Engineering Department have been impleaded as party
respondent and the petitioner has executed the work for the Public Health
Engineering Department. Therefore, all three respondents i.e. respondents
1 to 3 cannot deny the undisputed bills due to the petitioner and they are
duty bound to make payments to the work completed.
15. For the foregoing discussions and in view of the averments
made in paragraphs 4 and 5 of the reply affidavit dated 18.2.2022 filed
W.P.(C) No.597 of 2019
Page 10
by the respondents 1 to 3 to the rejoinder-affidavit, this Court is inclined to
dispose of the writ petition with following directions:
(i)
The writ petition is disposed of.
(ii)
The respondents 1 to 3 are directed to consider and pass
orders in the light of the averments made in paragraphs 4
and 5 of the reply affidavit dated 18.2.2022 and settle the
undisputed bill amounts in respect of the execution of
different contract works to the tune of Rs.3,27,57,073/-, in
accordance with law, within a period of eight weeks from
the date of receipt of a copy of this order.
(iii)
16.
No costs.
Registry is directed to issue copy of this order to both the
parties through their whatsapp/e-mail.
JUDGE
- Larson
W.P.(C) No.597 of 2019
Page 11
This page is for informational and research purposes only and does not constitute legal advice.