Full Judgment Text
Text read from the judgment PDF published on the High Court's eCourts portal, through the
Indian High Court Judgments open data set (Dattam Labs,
CC BY 4.0).
The court's own copy is the authoritative text.
CGHC010388682023
2026:CGHC:28798
NAFR
HIGH COURT OF CHHATTISGARH AT BILASPUR
WPC No. 4977 of 2023
Judgment Reserved On : 01.07.2026.
Judgment Delivered On : 10.07.2026.
1 - Krishna Kumar Kashyap S/o Late Shri Kunjram Kashyap Aged About 43 Years
R/o
Village
Ghivra,
Police
Station
Birra,
District
Sakti
(C.G.)
AVINASH
SHARMA
Digitally signed
by AVINASH
SHARMA
Date: 2026.07.10
18:16:04 +0530
2 - Smt. Shashi Kashyap W/o Ishwar Prasad Kashyap Aged About 48 Years R/o
Village
Ghivra,
Police
Station
Birra,
District
Sakti
(C.G.)
3 - Smt. Sarita Kashyap W/o Govindram Kashyap Aged About 36 Years R/o Village
Jamdi,
Police
Station
Hasaud,
District
Sakti
(C.G.)
4 - Smt. Ritu Kashyap W/o Sakhiram Kashyap Aged About 34 Years R/o Village
Singhul,
Police
Station
Sivrinarayan,
District
Janjgir-Champa
(C.G.)
5 - Hirdebai Wd/o Late Shri Kunjram Kashyap Aged About 70 Years R/o Village
Ghivra, Police Station Birra, District Sakti (C.G.)
... Petitioner(s)
versus
1 - State Of Chhattisgarh Through The Secretary, Department Of Water Resources,
Mantralaya
Mahanadi
Bhawan
New
Raipur
(C.G.)
2 - The Collector District Janjgir-Champa (C.G.)
3 - The Sdo(R) And Land Acquisition Officer Sakti District Sakti/janjgir, Champa
(C.G.)
4 - The Executive Engineer, Hasdev Canal Water Management Division, Janjgir,
District Janjgir-Champa (C.G.)
... Respondent(s)
For Petitioner(s)
:
Shri Avadhesh Mishra, Advocate.
For Respondent(s)
:
Shri Anadi Sharma, Panel Lawyer.
Hon’ble Mr. Justice Amitendra Kishore Prasad
C A V Order
1. The present Writ Petition has been filed for the following reliefs:-
10.1 That, this Hon'ble Court may kindly be pleased to issue
suitable writ for Respondent Authorities to release separately
or collectively the compensation of said acquired land
bearing Khasra no. 1846 situated at village Ghivra Patwari
Halka No. 27 Tahsil Jaijaipur (C.G.) to petitioners within
stipulated time.
10.2 That, any other relief which this Hon'ble Court may
deem fit and proper in the facts and circumstances of the
case including cost may also be allowed.
2. Gist of the facts is that the land of the petitioners was acquired by respondent
authorities for the construction of canal 35 years ago but when the
compensation had not been paid for a long time, the father/husband of
petitioners approached this Court vide WPC No. 1519/2019 in which, this
Court directed respondent no. 2/ Collector Janjgir Champa (C.G.) to decide
the representation of the petitioner in respect of land acquisition within a
period of 60 days. Ultimately, Collector Janjgir-Champa (C.G.) in compliance
of order of this Court called the record of acquired land of petitioner from the
office of The Executive Engineer Hasdev Canal Water Management Division
Janjgir Distt. Janjgir-Champa (C.G.) and thereafter registered the additional
land acquisition case of petitioner vide proceeding dated 25.04.2020. As per
said proceeding dated 25.4.2020, SDO (R) and Land Acquisition Officer Sakti
initiated the said case of petitioner vide order sheet dated 19.5.2020,
11.6.2020, 3.7.2020, 14.1.2021, 18.1.2021. Thereafter, when the respondent
in pursuant to aforesaid order of this Court could not decide the
representation of petitioner within 60 days, the respondents authorities filed
MCC no. 144/2021 on 16.2.2021 before this Court for extension of time for
compliance of the order dated 29.4.2019 passed by Court in WPC No.
1519/2019. The said MCC was disposed off on 05.05.2023. In the meanwhile
on 18.3.2021, the SDO (R) and Land Acquisition Officer Sakti issued the
calculation process of land in favour of father/husband of petitioner bearing
Khasra no. 1846 as total amount of Rs. 13,44,540/-. Thereafter on 27.3.2021
the respondent no. 2 issued a proposal dated 27.03.2021 for purchase of
land in favour of father/husband of petitioner vide Annexure P/7. On
02.05.2021, unfortunately the father/husband of petitioner died leaving
behind legal representative petitioner no. 1 to 5. On the basis of death of
father/husband of petitioner, all the revenue records of the petitioner
including above said Khasra no. 1846 was altered by lawful mutation in the
name of all his legal heirs i.e. petitioner no. 1 to 5. Thereafter again in the
name of legal representatives i.e. Petitioners nos. 1 to 5, the SDO (R) and
Land Acquisition Officer Sakti issued the calculation process of said acquired
land for further action of the Collector Janjgir-Champa vide order dated
25.9.2021. Thereafter, on 28.10.2021, Collector Janjgir Champa issued an
order and a proposal for purchase of land of petitioners vide Annexure P/11.
Thereafter, the SDO (R) and Land Acquisition Officer Sakti issued the order
sheet for issuing public notice to the Collector Janjgir-Champa vide its
revenue order sheet dated 28.12.2021 along with consent deed dated
29.11.2021. Thereafter, the respondent Collector Janjgir- Champa issued the
public notice in respects of purchasing of said land of petitioner no. 1 to 5
vide its letter dated 02.02.2022. Thereafter, the SDO (R) and Land
Acquisition Officer Sakti arbitrary once again called the record of the said
case from respondent the Collector Janjgir Champa even after issuing public
notice in respects of purchasing of said land and passed its illegal opinion
vide order sheet dated 20.5.2022 (Annexure P/1). After receiving of said
illegal opinion, the respondent learned Collector Janjgir- Champa dismissed
the said land acquisition proceeding improperly by returning such case to the
SDO (R) and Land Acquisition Officer Sakti vide its order dated 06.07.2022
(Annexure P/1) instead of releasing the compensation of said land.
3. Learned counsel for the petitioners submits that 0.28 acre land of petitioners
from Khasara No. 1846 total Rakba 0.33 acre was acquired by respondent
authorities 35 years ago, however, the same was acquired in two steps first
0.16 acre and thereafter 0.12 acre i.e. (0.16 + 0.12 = 0.28 acre) but the
compensation of the same separately or collectively has not yet been
released. He submits that as per the available record / impugned order
Annexure P-1, it has been stated by the concerned respondent authority that
only 0.16 acre of land of petitioners has been determined and award of
compensation of the same has been passed but compensation is not
released till date. It has been further stated by the impugned order that
remaining 0.12 acre acquired land of petitioners will be reported for
determination separately, however, the said process has not been done.
4. Learned counsel for the petitioners submits that it is crystal clear from the
record available that the said land of the petitioners (0.16 + 0.12 = 0.28 acre)
was acquired for the construction of canal and the compensation is
determined collectively and even the public notice for purchasing the said
land was issued but thereafter instead of releasing compensation,
respondent authority Collector Distt. Janjgir-Champa C.G. committed illegal
tactics by returning such case to respondent SDO (R) and Land Acquisition
Officer Sakti. Learned counsel further submits that no compensation of the
above acquired land of petitioners is given separately or collectively till date.
5. On the other hand, learned counsel for the State/respondent submits that
petitioners have come before this Court by way of this Petition seeking grant
of compensation with respect to Khasra No, 1846, however, it is submitted
that vide order dated 20.05.2022 and 06.07.2022, the revenue case of the
petitioners has been dismissed clearly observing therein that 0.16 acres out
of total .33 acres has been acquired by the respondents and on that acquired
. 16 acres, the Canal has been constructed. It has been further observed that
the remaining land out of total has not been used by the respondent
authorities and the same is being used by the petitioners for agricultural
purposes. Since, the respondents are not in need of the remaining land, the
same has not been acquired. Learned State counsel would place reliance on
the memorandum dated 03.03.2025 (Annexure R/2) issued by the SubDivisional Officer, Janjgir whereunder, it has been stated that for the
construction of Birra sub-distributor canal, 0.16 acre of land from Khasra No.
1846 of village Ghivra has been acquired in the year 1979-80 by passing an
order under mutual agreement and compensation of Rs. 264.00 (two
hundred sixty four rupees only) for Khasra No. 1846 area 0.16 acre is
registered in the name of landowner Nanki father Vishwanath.
6. Learned State counsel submits that it has been further stated that on
February 27, 2025, an on-site inspection of the above-mentioned land was
conducted. The Birra Sub-Distributor Canal has been constructed on 0.16
acres of land in Khasra No. 1846 of village Dhivara, Tehsil Hasaud. The
remaining land is being cultivated by the respective landowner/petitioners
herein. Therefore, the Birra sub-distributary canal has not been constructed
on an additional 0.12 acres of land from Khasra No. 1846 in village Ghivra,
Tehsil Hasaud. Hence, the proposed 0.12 acres of land from Khasra No.
1846 is not required to be acquired for the canal construction.
7. I have heard learned counsel for the parties and perused the documents
annexed with the petition carefully.
8. From the material available on record, it is evident that only 0.16 acre of land
out of Khasra No. 1846 was acquired for the construction of Birra SubDistributor Canal. The respondents have specifically stated that the canal has
been constructed only over the said acquired land and that the remaining .12
acre land continues to be in possession of the petitioners and is being used
for agricultural purposes. The memorandum dated 03.03.2025 and the spot
inspection report further support the stand of the respondents that no
additional area measuring 0.12 acre was acquired or utilized for canal
construction.
9. Further, in the memorandum dated 03.03.2025, it has been specifically
stated that for construction of Birra sub-distributor canal, 0.16 acre of land
from Khasra No. 1846 of village Ghivra has been acquired in the year 197980 by passing an order under mutual agreement and compensation of Rs.
264.00 (two hundred sixty four rupees only) for Khasra No. 1846 area 0.16
acre is registered in the name of landowner Nanki father Vishwanath. The
said memorandum has been passed by the revenue authorities based on
report dated 27.02.2025, which has not been disputed by the petitioner in any
way. Insofar as the acquired land measuring 0.16 acre is concerned, the
respondents have produced material indicating that compensation was
determined in the name of Nanki at the relevant time and has been received
by the petitioners.
10. For the foregoing, this Court, in exercise of its extraordinary jurisdiction under
Article 226 of the Constitution of India, does not find any arbitrariness,
illegality, or perversity in the impugned orders warranting interference. The
findings recorded by the competent authorities are based on the available
revenue records and the spot inspection, and no ground has been made out
to exercise writ jurisdiction.
11. Consequently, the writ petition, being devoid of merit, is hereby dismissed.
Sd/(Amitendra Kishore Prasad)
Judge
Avinash
The date when the
The date when the
The date when the judgment is
judgment is reserved
judgment is
uploaded on the website
pronounced
01.07.2026
10.07.2026
Operative
Full
------
10.07.2026
This page is for informational and research purposes only and does not constitute legal advice.